(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
|
---|
Category:Letter
MONTHYEARIR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 IR 05000482/20244202024-10-31031 October 2024 Security Baseline Inspection Report 05000482/2024420 05000482/LER-2024-001-01, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-10-22022 October 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing ML24296B1902024-10-22022 October 2024 10 CFR 50.55a Requests for the Fifth Ten-Year Interval Inservice Testing Program 05000482/LER-2024-002, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-10-21021 October 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information ML24281A1012024-10-0707 October 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24199A1712024-09-17017 September 2024 Issuance of Amendment No. 241 Revise Ventilation Filter Testing Program Criteria and Administrative Correction of Absorber in Technical Specification 5.5.11 ML24260A0712024-09-12012 September 2024 License Amendment Request for a Risk-Informed Resolution to GSI-191 IR 05000482/20240102024-09-10010 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000482/2024010 (Public) ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24221A2582024-09-0606 September 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 05000277/LER-2024-003, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum2024-09-0505 September 2024 Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum ML24248A2492024-09-0404 September 2024 Inservice Inspection Program Fourth Interval, Third Period, Refueling Outage 26 Owner’S Activity Report ML24248A0762024-09-0404 September 2024 Containment Inservice Inspection Program Third Interval, Second Period, Refueling Outage 26 Owner’S Activity Report ML24241A2212024-08-29029 August 2024 Notice of Enforcement Discretion for Wolf Creek Generating Station IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) ML24240A2642024-08-27027 August 2024 Corporation - Request for Notice of Enforcement Discretion Regarding Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24235A0342024-08-23023 August 2024 U.S. Nuclear Regulatory Commission’S Analysis of Constellation Energy Generation’S Decommissioning Funding Status Report IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 IR 05000277/20240022024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24227A5562024-08-14014 August 2024 Application to Revise Technical Specifications to Adopt TSTF-569-A, Revision 2, Revision of Response Time Testing Definitions ML24225A1692024-08-12012 August 2024 10 CFR 50.46 Annual Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24214A3232024-08-0101 August 2024 Response to Request for Additional Information - Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24213A3352024-07-31031 July 2024 License Amendment Request to Revise Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)) (Fq Methodology), to Implement the Methodology from WCAP-17661-P-A, Revision 1. ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) IR 05000482/20240022024-07-18018 July 2024 Integrated Inspection Report 05000482/2024002 ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report IR 05000482/20244012024-07-0202 July 2024 Security Baseline Inspection Report 05000482/2024401 05000482/LER-2024-001, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-07-0202 July 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML24166A1172024-06-20020 June 2024 Regulatory Audit Summary Regarding Proposed Alternative Schedule to Complete Decommissioning Beyond 60 Years RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24150A2722024-05-29029 May 2024 Annual Radiological Environmental Operating Report 81, January 1, 2023 Through December 31, 2023 ML24150A0562024-05-29029 May 2024 Foreign Ownership, Control or Influence (FOCI) Information – Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement 2024-09-06
[Table view] |
Text
Dustin T. Hamman Director Nuclear and Regulatory Affairs October 10, 2024 000654
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Docket Nos. 50-482 and 72-79: Revision of One Form that Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS)
Commissioners and Staff:
In accordance with 10 CFR 50.54(q)(5) and 10 CFR 72.44(f), WCGS is submitting a change to the emergency plan. Specifically, one form that implements the WCGS RERP has been revised. The revised document is identified below:
Form Effective Date APF 06-002-02, Rev. 2A September 25, 2024
The attached summary of the changes to the implementing form explains these changes do not reduce the effectiveness of the WCGS RERP.
This letter contains no commitments. If you have any questions concerning this matter, please contact me at (620) 364-4204.
Sincerely,
Dustin T. Hamman
DTH/ jkt
Attachment:
Summary of Changes to One Form that Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS)
cc: M. R. Bloodgood (NRC), w/a S. S. Lee (NRC), w/a J. D. Monninger, (NRC), w/a Director of Division of Fuel Management (NRC), w/a Senior Emergency Preparedness Inspector (NRC), w/a Senior Resident Inspector (NRC), w/a WC Licensing CorrespondenceRA 24 -000654, w/a
P.O. Box 411 l Burlington, KS 66839 l 620-364-8831
Attachment to 000654 Page 1 of 1
Summary of Changes to One Form that Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS)
- 1. Form APF 06-0 02-02, EMERGENCY ACTION LEVELS TECHNICAL BASES, Rev. 2A
Form APF 06-0 02-02 has been revised. This document provides an explanation and rationale for each Emergency Action Level (EAL) included in the EAL Upgrade Project for Wolf Creek Generating Station (WCGS).The changes are editorial in nature.
On page 20, the revision bar on DSC - Dry Shielded Canister was removed. This revision bar was added for Revision 1 of the form. Removal was missed when Revision 2 was implemented.
On page 120, in the second bullet, there was a typographical error in the Identified LEAKAGE definition.The phrase "either not to" has been changed to "to not." The definition now reads, "Leakage into the containment atmosphere from sources that are both specifically located and known to not interfere with the operation of leakage detection systems; or."
These changes do not reduce the effectiveness of the Wolf Creek Radiological Emergency Response Plan.