ML23206A041

From kanterella
Revision as of 20:56, 8 August 2023 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

SNC Slides - Public Pre-Submittal Meeting on Aug 02, 2023 - Request for 45-Day Limited Extension of Risk Informed Completion Time (Rict) Program Backstop for TS 3.7.1 & 3.7.2
ML23206A041
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 08/02/2023
From:
Southern Nuclear Operating Co
To: Dawnmathews Kalathiveettil
NRC/NRR/DORL/LPL2-1
Kalathiveettil, D
References
EPID L-2023-LRM-0046
Download: ML23206A041 (1)


Text

Edwin I. Hatch Nuclear Plant Request for Limited Extension of Risk Informed Completion Time (RICT) Program Backstop

Agenda 2

The picture can't be display ed.

Agenda

Purpose:

Engage NRC Staff on Southern Nuclears proposed change to extend the Risk Informed Completion Time (RICT) backstop for select residual heat removal service water (RHRSW) and plant service water (PSW) Technical Specification (TS)

Required Actions (A.1 - one pump inoperable)

- System Design

- Current TS Requirements

- Brief History

- Requested Changes

- Approach

- Questions 3

System Design

4

The picture can't be display ed.

System Design - RHRSW

  • Two independent subsystems

- Each subsystem has a suction source (river), two 50% (i.e., 4000 gpm) capacity pumps, header, valves, piping, and heat exchanger

- Pump approximately 12,000 lbs / 61 ft long; Motor approximately 7,600 lbs / 6 ft long

  • Safety analyses assume RHRSW supports cooling of the suppression pool following a loss of coolant accident (LOCA)

- Safety analyses assume that, with one subsystem with two pumps operating at 3750 gpm each and up to 5% of tubes plugged in RHR heat exchanger, the suppression pool temperature and primary containment pressure are limited 211.6°F (design 281°F) and 27.8 psig (maximum allowable 62 psig), respectively

  • PRA Success Criteria is one pump at 4000 gpm and one heat exchanger

[ML21300A153]

The picture can't be display ed.

System Design - PSW

  • Two independent subsystems

- Each subsystem has a suction source (river), two 8500 gpm capacity pumps, header, valves, piping, and heat exchanger

- Three pumps required for normal operation; one pump required for safety analysis

- Pump approximately 12,000 lbs / 61 ft long; Motor approximately 7,600 lbs / 6 ft long

  • Safety analyses assume system supplies cooling to safety equipment during emergency conditions

- The diesel generators and the longterm cooling capability of the RHR, core spray, and RHR service water pumps depend on the cooling provided by the PSW system. Either subsystem can provide adequate cooling with only one pump providing flow.

[ML21300A153]

The picture can't be display ed.

Plant service water pump 7

The picture can't be display ed.

RHRSW 8

The picture can't be display ed.

PSW 9

Current TS Requirements 10

The picture can't be display ed.

Current TS Requirements 11

Reason for Change 12

The picture can't be display ed.

Reason for Change

  • Pump replacement typically 710 days but:

- Replacement pump fails preservice test

- Need divers to inspect suction area [+1 day]

- Replace with 2nd replacement pump [+7 to 10 days]

- Additional discoveries made during pump replacement [+11 days]

- Problem during postmaintenance test requiring offsite motor refurbish [+7 to 10 days]

  • Preventive maintenance (PM) to replace a pump motor is 45 days but:

- Motor / pump alignment issue [+1 day]

- Replacement pump motor requires offsite services and reinstall [+16 days]

- Difficulties aligning discharge head with discharge check valve flange [+10 days]

The picture can't be display ed.

Reason for Change November 2019 Unit 1 RHRSW pump B was replaced and then failed during pre-service testing. SNC replaced that pump with another new pump, which also failed during pre-service testing. SNC submitted an emergency license amendment request a to allow a one-time extension to the TS 3.7.1 Required Action A.1 Completion Time from 30 days to 45 days. The license amendment request was withdrawn b after the pump was restored to operable status less than 3 days prior to the original 30-day Completion Time.

September 2021 Challenges encountered during repair and replacement activities to restore operability to Unit 1 PSW pump C led to the need for an emergency license amendment request c (and RAI response d). The approved emergency license amendment e allowed, with compensatory measures established, a one-time extension of the TS 3.7.2 Required Action A.1 Completion Time from 30 days to 45 days.

April 2022 Challenges encountered during repair and replacement activities to restore operability to Unit 1 PSW pump A led to SNC submitting an emergency license amendment request f to, with compensatory measures established, extend the TS 3.7.2 Required Action A.1 Completion Time from 30 days to 45 days. The license amendment request was withdrawn g after HNP personnel restored the pump to operable condition less than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> prior to the 30-day Completion Time.

a. ML19333B967 b. ML19336B596 c. ML21264A003 d. ML21266A004 e. ML21264A644 f. ML22120A087 g. ML22123A159 14

Requested Changes 15

The picture can't be display ed.

Requested Changes 16

The picture can't be display ed.

Requested Changes 17

Approach 18

The picture can't be display ed.

Approach - Justification (Technical / Risk Basis)

- The current 30day RICT backstop is administrative limit

>> Proposed extension is limited to CTs where need has been demonstrated (TS 3.7.1 and TS 3.7.2 RA A.1)

- The RICT program provides assurance that the plant is maintained at an acceptable risk level:

>> Configurationspecific Completion Times (will not automatically get 45 days)

>> Risk Management Actions

>> RICT Budget and SNC procedures encourage staying within the front stop when possible

- Safety analysis requires:

>> One PSW pump required to supply for safe shutdown, including RHR shutdown cooling system requirements

>> Two RHRSW pumps required to provide adequate heat removal capacity following a design basis LOCA.

- Would preclude need for an emergency amendment maintain plant focus on restoring operability

The picture can't be display ed.

Approach - Justification (Precedence)

- Completion Times greater than 30 days are not uncommon

>> Some Plant Technical Specifications Examples:

  • Hatch Unit 1 and Unit 2 TS 3.7.4 Main Control Room Environmental Control (MCREC) System Required Action B.3 has a 90day completion time.

- Consistent with NUREG1433, Current Hatch TS 3.7.1 and TS 3.7.2 allow calculation of a RICT for one pump inoperable in each subsystem

The picture can't be display ed.

Approach Format

  • Submittal will follow postTSTF505 Adoption [ML20324A070] and NEI 0602

- Attachments to be provided:

1. Description and Assessment
2. Proposed Technical Specification Changes (MarkUp)
3. Proposed Technical Specification Changes (CleanTyped)
4. Proposed Technical Specification Bases Changes (MarkUp) - For Information Only

- Enclosures intended to be provided:

1. List of Required Actions to Corresponding PRA Functions
2. Information Supporting Consistency with Regulatory Guide 1.200, Revision 2
4. Information Supporting Justification of Excluding Sources of Risk Not Addressed by the PRA Models
5. Baseline CDF and LERF
9. Key Assumptions and Sources of Uncertainty
12. Risk Management Action Examples

- Enclosures not intended to be provided:

3. Information Supporting Technical Adequacy of PRA Models Without PRA Standards Endorsed by Regulatory Guide 1.200, Revision 2
6. Justification of Application of AtPower PRA Modes to Shutdown Modes
7. PRA Model Update Process
8. Attributes of the RealTime Model
10. Program Implementation
11. Monitoring Program

Questions 22