LRA - NRC Pre-Submittal Meeting Slides
ML23172A209
Person / Time
Site: Clinton Constellation icon.png
Issue date: 06/28/2023
From: Tyree C
NRC/NRR/DNRL/NLRP
To:
References
Download: ML23172A209 (1)


Text

Clinton Power Station Unit 1 License Renewal Application (LRA)

Safety Pre-Application Meeting June 28, 2023 Chris Tyree Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation 1

Audio Issues

  • Call into bridgeline:

(301) 576-2978 Passcode:89874471#

Conference ID:898 744 71#

  • In Teams, check your devise settings:
1) Click More
2) Choose settings
3) Choose Device Settings 2

Meeting Agenda

  • Safety Review:

o Process Overview o Tentative Review Schedule for Dresden

  • NRC Contact Information
  • Conclusion / Questions 3

License Renewal Review Process Inspection Onsite Report(s)

Inspection(s) Issued**

License Renewal Application**

Submitted To NRC Advisory Committee on Safety Evaluation Reactor Safeguards ACRS Safety Evaluation Safety Evaluation Report with Open (ACRS) Full Committee Audit & Review Report Issued**

Item(s) Issued** Subcommittee Review**

Safety Review**

Review Safety Evaluation Audit & Review ACRS Letter Issued**

License Renewal Process &

Environmental AMP Scoping Audit NRC Decision Meetings AMR Hearings* On Application**

Review AMP Review Environmental Review Draft Final Supplement DSEIS Supplement Site Environmental To GEIS Public To GEIS Audit Issued** Meeting Issued**

Opportunities for Public Interaction

  • If a Request for Hearing is Granted
    • Available at www.nrc.gov 4

Safety Review:

Process Overview Acceptance Review In-Office Technical Review On-Site Audit Breakout Audit Audit Issue Safety Evaluation Report (SER) 5

Tentative Safety Review Schedule Note: The review schedule below is tentative and subject to change.

The schedule is only finalized once the application has been accepted forreview and is docketed.

Activity Estimated Time Application Submission Date February 2024 Acceptance Date (Project Start Date) March 2024 In-Office Technical Review Audit June 2024 On-Site Audit June 2024 Breakout Audit August 2024 Safety Evaluation Report May 2025 Advisory Committee on Reactor Safeguards July 2025 (ACRS) Sub-Committee Meeting ACRS Full Committee Meeting November 2025 Licensing Decision January 2026 6

NRC Contact Information Safety Project Manager

  • Chris Tyree (Christopher.Tyree@nrc.gov)

Safety Branch Chief

Environmental Project Manger

Environmental Branch Chief