MONTHYEARML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23172A2092023-06-28028 June 2023 LRA - NRC Pre-Submittal Meeting Slides ML23172A2102023-06-28028 June 2023 CPS Lr Pre-Submittal Meeting Presentation ML23165A0162023-06-14014 June 2023 June 27, 2023, Clinton Power Station License Renewal Environmental Pre-application Public Meeting - NRC Slides ML23145A1342023-06-14014 June 2023 June 27, 2023, Clinton Power Station License Renewal Environmental Pre-application Public Meeting - Constellation Slides ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21194A1582021-07-13013 July 2021 and Lasalle Nuclear Generating Stations 2020 Annual Assessment Meeting Slides ML21021A0652021-01-21021 January 2021 NRC Pre-Application Meeting - Clinton One-Time Extension of the Containment Type a Leak Rate Test Frequency (Meeting Handout) ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20238B8662020-08-25025 August 2020 Hq Online EOC Slides ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20175A8722020-06-23023 June 2020 Risk-Informed Inservice Inspection - U.S Nuclear Regulatory Commission (NRC) - Four Element Risk-Informed Approach ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML19318F9512019-11-20020 November 2019 Presentation Slides for November 20, 2019, Pre-Application Meeting - Request for Revision to Quality Assurance Program Internal Audit Frequency ML19317C9952019-11-12012 November 2019 In-Service Testing Supplemental Position Indication Relief Request NRC Pre-Application Meeting November 18, 2019 ML19161A2572019-06-0404 June 2019 BWR Fleet Msv/Srv - Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19151A6602019-05-31031 May 2019 BWR Fleet Mssv/Srv Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19022A2002019-01-23023 January 2019 Request for Use of ASME Code Case N-879 for Exelon Nuclear Power Plants ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas U-604453, Regulatory Conference Information2018-11-19019 November 2018 Regulatory Conference Information ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML17067A3722017-03-16016 March 2017 March 7, 2017, Summary of Public Pre-Submittal Teleconference Meeting with Exelon Generation Company, LLC to Discuss Proposed License Amendment Request Regarding Residual Heat Removal System Operability in Mode 3 at Clinton Power Station, U ML17067A3622017-03-0707 March 2017 License Amendment Request; Mode 3 Applicability - Lpci/Sdc; NRC Pre-Submittal Teleconference - March 7, 2017 ML16314E4812016-11-14014 November 2016 Part 37 Applicability to Reactor Vessels and Associated Structures, Systems, and Components While in Safstor Awaiting Active Decommissioning Activities - November 14, 2016 ML16189A4332016-07-12012 July 2016 July 12, 2016, Public Meeting with NRC - Exelon Decommissioning Licensing Action Submittal Plan ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations ML15342A3542015-12-0808 December 2015 License Amendment Request Extension of Secondary Containment - NRC Pre- Application Meeting December 9, 2015 ML15173A3812015-06-19019 June 2015 Regulatory Conference Supplemental Information ML14223A5742014-08-11011 August 2014 8/7/14 Clinton Power Station Annual Assessment Meeting Licensee Slides ML14220A2492014-08-0707 August 2014 8/7/2014 NRC Slides of Clinton Power Station Annual Assessment Meeting Cy 2013 ML14114A7402014-04-0909 April 2014 Application of GE Hitachi Simplified Stability Solution GS3 Pre-Submittal Presentation ML13184A3152013-07-0202 July 2013 EOC Public Meeting Presentation July 2, 2013 ML12111A1282012-04-19019 April 2012 End-of-Cycle Performance Assessment Meeting Presentation Slides ML1208701402012-03-27027 March 2012 Licensee Slides for Exelon Fleet Pre-Submittal Public Meeting 4-10-12 Licensed Operator Eligibility Requirements LAR ML1111905212011-04-28028 April 2011 Clinton Power Station Cy 2010 End-Of-Cycle Open House Presentation ML1111905312011-04-28028 April 2011 Clinton Power Station Cy 2010 End-of-Cycle Open House Presentation (Short) ML0919803632009-08-20020 August 2009 Summary of Licensing Counterparts Meeting with Exelon Generation Company, to Discuss Licensing Practices and Processes ML0914003322009-05-11011 May 2009 Slides Presented at the Clinton 2008 EOC Performance/Reactor Issue Open House ML0908904942009-03-30030 March 2009 Presentation Slides for 03/31/2009 Meeting with the NRC Staff Concerning Proposed CO-60 Production at Clinton Station ML0812007842008-06-0202 June 2008 Meeting Slides, Nrc/Exelon Licensing Counterparts Meeting. ML0411301702004-04-0808 April 2004 Public Meeting Slides, Clinton 2003 End-of-Cycle Assessment ML0409805242004-03-11011 March 2004 March 11, 2004 - RIC 2004 Presentation - T11 - Christopher Crane - Emergent Technical Topics 2024-01-30
[Table view] |
Text
Clinton Annual Assessment M ti Meeting Reactor Oversight Process - 2010 Nuclear Regulatory Commission - Region III Lisle, IL April 28, 2011 1
Region III Organization Mark Satorius Regional Administrator Cindy Pederson Deputy Regional Administrator Steve West Steve Reynolds Director Division of Reactor Projects Director Division of Reactor Safety Gary Shear Ken OBrien Deputy Director Deputy Director Mark Ring Regional Specialists Branch Chief Clinton Project Engineer Resident Inspectors Bob Orlikowski Brian Kemker, SRI David Lords, RI Reactor Engineer Jason Draper 2
National Summary of Plant Performance Status as of 12/31/2010 Licensee Response 89 Regulatory Response 9 Degraded Cornerstone 6 Multiple/Repetitive Deg. Cornerstone 0 Unacceptable 0 Total 104 3
National Summary
- Performance Indicator Results for 2010*
- Green 7009
- White 23
- Yellow 0
- Red 0
- PIs are counted per plant per quarter
- Total Inspection Findings in 2010
- Green 816
- White 9
- Yellow 2
- Red 0 Finding data current as of 3/3/2011 4
Clinton Assessment Results January 1 - December 31, 2010
- Clinton is in the Licensee Column of the Action Matrix
- There were fifteen (15) Severity Level IV or Green findings or violations identified 5
NRC Inspection Findings Clinton
- Green - Exelon failed to adequately design the Auxiliary Building floor drain system such that a g pipe failure of a single p p could drain the suppression pp pool below the required level
- Green - Exelon failed to obtain the required license amendment from the NRC prior to defining an Operation with the Potential to Drain the Reactor Vessel (OPDRV) as used in the Technical Specifications 6
Clinton Inspection Activities January 1 - December 31, 2010
- Over 1700 hours0.0197 days <br />0.472 hours <br />0.00281 weeks <br />6.4685e-4 months <br /> of direct inspection
- Two (2) resident inspectors on site -
residents make four quarterly inspections per year and walk through the plant every day
- Clinton was shut down for a refueling outage for approximately 25 days starting January 11, 2010 7
Clinton Inspection Activities January 1 - December 31, 2010
- Eight (8) regional inspections
- One (1) major team inspection
- Component Design Basis Inspection 8
Clinton Annual Assessment Summary January 1 - December 31, 2010
- Exelon Generating Company, LLC, operated Clinton in a manner that preserved public health and safety
- All cornerstone objectives were met with all Green Findings and Performance Indicators
- No substantive cross-cutting issues identified 9
Clinton Annual Assessment Summary January 1 - December 31, 2010
- NRC plans baseline inspections at Clinton for 2011
- A follow up inspection (IP 92723) has been performed in response to the 4 SLIV traditional enforcement violations that were identified between 3Q09 and 2Q10 10
Open to the Public
- The NRC places a high priority on keeping the public and stakeholders informed of its activities.
- Find public meeting dates and transcripts;
- Read NRC testimony, speeches, press releases, and policy decisions; and
- Access the agencys Electronic Reading Room to find NRC publications and documents.
11
What Do You Think of the ROP???
The biennial ROP external survey is coming 3rd Quarter 2011, and we want to hear from you!
Email ROPsurvey@nrc.gov to be notified when the ROP survey is available.
For information on ROP stakeholder feedback, please visit our website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS
/program-evaluations.html#section3 12
Contacting the NRC
- (301) 816-5100 (call collect)
- (800) 695-7403
- Allegation@nrc.gov
- General information or questions
- www.nrc.gov
- Select What We Do for Public Affairs 13
NRC Representatives
- (217) 935-9521
- David Lords, Resident Inspector
- (217) 935-9521
- ((630)) 829-9703
- Gloria Stauffer, Site Administrative Assistant
- (217) 935-9521
- (630) 829-9662
- (630) 829-9663
- NRC Region III Office Switchboard
- (630) 829-9500 (800) 522-3025 14
Reference Sources
- Reactor Oversight Process
- http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/in dex.html
- Public Electronic Reading Room
- http://www.nrc.gov/reading-rm.html
- Public Document Room 800-397-4209 (Toll Free) 15