Clinton Annual Assessment M
ti 1
Meeting Reactor Oversight Process - 2010 Nuclear Regulatory Commission - Region III Lisle, IL April 28, 2011
Region III Organization Mark Satorius Regional Administrator Cindy Pederson Deputy Regional Administrator Steve West Director Division of Reactor Projects Steve Reynolds Director Division of Reactor Safety 2
Gary Shear Deputy Director Ken OBrien Deputy Director Mark Ring Branch Chief Regional Specialists Clinton Resident Inspectors Brian Kemker, SRI David Lords, RI Project Engineer Bob Orlikowski Reactor Engineer Jason Draper
National Summary of Plant Performance Status as of 12/31/2010 Licensee Response 89 Regulatory Response 9
Degraded Cornerstone 6
3 Degraded Cornerstone 6
Multiple/Repetitive Deg. Cornerstone 0
Unacceptable 0
Total 104
National Summary
- Performance Indicator Results for 2010*
- Green 7009
- White 23
- Yellow 0
Red 0
4
- Red 0
- PIs are counted per plant per quarter
- Total Inspection Findings in 2010
- Green 816
- White 9
- Yellow 2
- Red 0
Finding data current as of 3/3/2011
Clinton Assessment Results January 1 - December 31, 2010
- Clinton is in the Licensee Column of 5
the Action Matrix
- There were fifteen (15) Severity Level IV or Green findings or violations identified
NRC Inspection Findings Clinton
- Green - Exelon failed to adequately design the Auxiliary Building floor drain system such that a failure of a single pipe could drain the suppression 6
g p p pp pool below the required level
- Green - Exelon failed to obtain the required license amendment from the NRC prior to defining an Operation with the Potential to Drain the Reactor Vessel (OPDRV) as used in the Technical Specifications
Clinton Inspection Activities January 1 - December 31, 2010
- Over 1700 hours0.0197 days <br />0.472 hours <br />0.00281 weeks <br />6.4685e-4 months <br /> of direct inspection
- Two (2) resident inspectors on site 7
- Two (2) resident inspectors on site -
residents make four quarterly inspections per year and walk through the plant every day
- Clinton was shut down for a refueling outage for approximately 25 days starting January 11, 2010
Clinton Inspection Activities January 1 - December 31, 2010
- Eight (8) regional inspections 8
- One (1) major team inspection
-Component Design Basis Inspection
Clinton Annual Assessment Summary January 1 - December 31, 2010
- Exelon Generating Company, LLC, operated Clinton in a manner that preserved public health and safety 9
- All cornerstone objectives were met with all Green Findings and Performance Indicators
- No substantive cross-cutting issues identified
January 1 - December 31, 2010
- NRC plans baseline inspections at Clinton for 2011 Clinton Annual Assessment Summary 10
- A follow up inspection (IP 92723) has been performed in response to the 4 SLIV traditional enforcement violations that were identified between 3Q09 and 2Q10
Open to the Public
- The NRC places a high priority on keeping the public and stakeholders informed of its activities.
11
- At www.nrc.gov, you can:
- Find public meeting dates and transcripts;
- Read NRC testimony, speeches, press releases, and policy decisions; and
- Access the agencys Electronic Reading Room to find NRC publications and documents.
What Do You Think of the ROP???
The biennial ROP external survey is coming 3rd Quarter 2011, and we want to hear from you!
Email ROPsurvey@nrc.gov to be notified when the ROP survey is available.
For information on ROP stakeholder feedback, please visit our website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS
/program-evaluations.html#section3 12
Contacting the NRC
- Report an emergency
- (301) 816-5100 (call collect)
- Report a safety concern 13
- (800) 695-7403
- Allegation@nrc.gov
- General information or questions
- www.nrc.gov
- Select What We Do for Public Affairs
NRC Representatives Brian Kemker, Senior Resident Inspector
- (217) 935-9521 David Lords, Resident Inspector
- (217) 935-9521 Mark Ring, Branch Chief
- (630) 829-9703 14
(
)
Gloria Stauffer, Site Administrative Assistant
- (217) 935-9521 Viktoria Mitlyng, Senior Public Affairs Officer
- (630) 829-9662 Prema Chandrathil, Public Affairs Officer
- (630) 829-9663 NRC Region III Office Switchboard
- (630) 829-9500 (800) 522-3025
Reference Sources
- Reactor Oversight Process
- http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/in dex.html 15 Public Electronic Reading Room
- http://www.nrc.gov/reading-rm.html Public Document Room 800-397-4209 (Toll Free)