(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
|
---|
Category:Preliminary Safety Analysis Report (PSAR)
MONTHYEARML24144A0922024-05-23023 May 2024 Enclosure 1: Hermes 2 Preliminary Safety Analysis Report ML24144A0942024-05-23023 May 2024 Enclosure 3: KP-TR-022-NP Hermes 2 Postulated Event Methodology Revision 1 ML24138A2132024-05-16016 May 2024 Enclosure 1: Changes to Hermes 2 PSAR Chapters 3, 5 and 13 (non-proprietary) ML24136A2552024-05-15015 May 2024 Enclosure 1: Changes to Hermes 2 PSAR Chapter 9 ML24073A3192024-03-13013 March 2024 Enclosure 1: Changes to Hermes 2 PSAR Chapter 13 ML24072A2992024-03-12012 March 2024 Enclosure 1 - Changes to Hermes 2 PSAR Chapter 7 ML24039A1912024-02-0808 February 2024 Kairos Power LLC, Changes to Hermes 2 PSAR Chapter 2 ML24031A1392024-01-30030 January 2024 Kairos Power LLC, Changes to Hermes 2 Preliminary Safety Analysis Report (PSAR) Chapter 3 ML24026A3012024-01-26026 January 2024 Kairos Power, LLC, Changes to Hermes 2 Preliminary Safety Analysis Report (PSAR) Chapter 7 ML24025C6872024-01-24024 January 2024 Kairos Power LLC, Changes to PSAR Chapter 3 and 9 ML24011A2922024-01-11011 January 2024 Kairos Power LLC, Preliminary Safety Analysis Report, Chapter 9 ML24009A2492024-01-0909 January 2024 Kairos Power LLC, Changes to Hermes 2 Preliminary Safety Analysis Report (PSAR) Chapter 9 ML24003A7672024-01-0303 January 2024 Kairos Power LLC, Changes to Hermes 2 Construction Permit Application (PSAR) Chapters 4, 5, 7, and 13 ML23356A0802023-12-22022 December 2023 Enclosure 1: Kairos Power, LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapter 13 ML23355A1632023-12-21021 December 2023 Enclosure 1: Changes to Hermes 2 PSAR Chapter 4 ML23355A1942023-12-21021 December 2023 Kairos Power LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapter 3 and Chapter 5 ML23349A1492023-12-15015 December 2023 Kairos Power LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapter 2 ML23151A7452023-05-31031 May 2023 Enclosure 1 - Preliminary Safety Analysis Report ML23115A3952023-04-25025 April 2023 Kairos Power, LLC - Enclosure 1, Changes to Hermes PSAR Chapters 2, 3, 4, 7, 8, 9, 13, and 14 ML23034A2142023-02-0303 February 2023 Kairos Power LLC, Changes to Preliminary Safety Analysis Report (Psar), Revision 1, Chapter 2 ML22353A6252022-12-19019 December 2022 Kairos Power LLC, Transmittal of Changes to Preliminary Safety Analysis Report Chapter 6 and Response to NRC Question on Dhrs Testing ML22286A2432022-10-13013 October 2022 Kairos Power, LLC - Preliminary Safety Analysis Report ML22285A2292022-10-12012 October 2022 Enclosure 1: Changes to PSAR Chapter 4 ML22284A1532022-10-11011 October 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report Chapter 13 ML22284A1562022-10-11011 October 2022 Enclosure 1: Changes to Hermes PSAR Chapters 3, 4, 6, and 14 ML22279B0642022-10-0606 October 2022 Enclosure 1: Changes to Hermes PSAR Chapters 3 and 7 ML22272A5952022-09-29029 September 2022 Enclosure 1: HER-PSAR-001, Preliminary Safety Analysis Report, Rev. 1 ML22263A0352022-09-19019 September 2022 Kairos Power, LLC - Transmittal of Changes to Construction Permit Application - Exemptions Enclosure, PSAR Chapter 1, PSAR Chapter 3, and PSAR Chapter 14S ML22263A0342022-09-19019 September 2022 Enclosure 2 - Changes to PSAR Chapter 15 (Non-Proprietary) ML22259A1412022-09-16016 September 2022 Kairos Power, LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapters 3 and 4 ML22256A3012022-09-13013 September 2022 Enclosure 1: Changes to Hermes PSAR Chapters 3, 4, and 6 ML22250A6802022-09-0707 September 2022 Enclosure 1: Changes to PSAR Chapters 4 and 5 ML22242A1682022-08-30030 August 2022 Kairos Power LLC, Changes to Construction Permit Application - PSAR Chapters 3, 4, 8, and 13 ML22237A3262022-08-25025 August 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report Chapters 3, 4, 5, 9 and 14 ML22236A5952022-08-24024 August 2022 Kairos Power, LLC, Preliminary Safety Analysis Report, Chapter 6 ML22231B0302022-08-19019 August 2022 Enclosure 1: Change to Hermes PSAR Chapter 14 ML22230D0492022-08-18018 August 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapter 4.2 ML22252A2592022-08-18018 August 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report Table 4.2-5 ML22230D0532022-08-18018 August 2022 Enclosure 1 - Changes to PSAR Table 4.2-5 ML22224A2022022-08-12012 August 2022 Enclosure 2: Changes to Preliminary Safety Analysis Report Chapter 13 ML22210A3192022-07-29029 July 2022 Enclosure 1: Changes to PSAR Chapter 4 and Chapter 6 ML22209A1392022-07-27027 July 2022 Enclosure 1: Change to Hermes PSAR Chapter 5 ML22181B0562022-06-30030 June 2022 Enclosure 1: Changes to PSAR Chapter 7 ML22181B1592022-06-30030 June 2022 Enclosure 1 - Changes to PSAR Chapters 3, 4, and 6 (Non-Proprietary) ML22181B1762022-06-30030 June 2022 Enclosure 1 - Changes to PSAR Chapter 4.2 ML22181B1132022-06-27027 June 2022 Enclosure 1: Changes to PSAR Chapter 3 ML22178A2382022-06-27027 June 2022 Enclosure 1: Changes to PSAR Chapter 9 ML22171A0172022-06-20020 June 2022 Kairos Power, LLC Preliminary Safety Analysis Report ML22167A1922022-06-16016 June 2022 Kairos Power LLC, Changes to Construction Permit Application - PSAR Chapter 14 ML22161B0142022-06-10010 June 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report Chapter 7 2024-05-23
[Table view] |
Text
KP-NRC-2208-008 Enclosure 1 Change to Hermes PSAR Chapter 14 (Non-Proprietary)
Preliminary Safety Analysis Report Technical Specifications Section Section Name LCO or Condition Basis Inlet gas system pressure is The objective is to limit the maintained within an upper quantity and pressure of bound limit. spilled Flibe or cover gas to ensure a postulated event does not exceed limits.
Argon purity in the cover gas is The objective is to limit maintained within an upper radionuclides in the Flibe bound limit. below solubility limits where solutesolute interactions can be neglected.
The quantity of materials at risk The objective is to limit the in the gas space of the primary quantity of materials at risk heat transport system and the in the cover gas to ensure a primary heat rejection system is postulated event does not maintained within an upper exceed limits.
bound limit.
3.4 Engineered Safety Decay heat removal system The objective is to specify the Features operability requirement to have an operable decay heat removal system to ensure that the safety limits will not be exceeded.
Reactor vessel integrity The objective is to specify a design operating temperature limit to ensure the safety limit is not exceeded for postulated events.
3.5 Ventilation Systems N/A N/A 3.6 Emergency Power N/A N/A 3.7 Radiation Monitoring Radiation monitoring system is Radiation in plant effluents is Systems and Effluents designed to be available during measured against applicable normal operating conditions as limits.
well as during postulated events.
3.8 Experiments N/A N/A 3.9 Facility Specific LCOs N/A N/A Kairos Power Hermes Reactor 145 Revision 0