IR 05000244/2022403

From kanterella
Revision as of 04:46, 10 June 2022 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
R. E. Ginna Nuclear Power Plant, LLC - Cyber Security Inspection Report 05000244/2022403 (Cover Letter Only)
ML22144A206
Person / Time
Site: Ginna Constellation icon.png
Issue date: 05/24/2022
From: Glenn Dentel
NRC/RGN-I/DORS
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
Dentel G
References
IR 2022403
Download: ML22144A206 (3)


Text

May 24, 2022

SUBJECT:

R. E. GINNA NUCLEAR POWER PLANT, LLC - CYBER SECURITY INSPECTION REPORT 05000244/2022403

Dear Mr. Rhoades:

On April 29, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at R. E. Ginna Nuclear Power Plant, LLC and discussed the results of this inspection with Mr. Paul Swift, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low security significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at R. E. Ginna Nuclear Power Plant, LLC.

The following cross-cutting aspect was assigned to the finding using Inspection Manual Chapter 0310, Aspects Within Cross Cutting Areas: [H.12] - Avoid Complacency.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at R. E. Ginna Nuclear Power Plant, LLC. This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).

Sincerely, Digitally signed by Glenn Glenn T. T. Dentel Date: 2022.05.24 Dentel 16:26:04 -04'00'

Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket No. 05000244 License No. DPR-18 Enclosure:

As stated cc w/o encl: Distribution via LISTSERV cc w/encl:

R. Null, Manager Security Operations A. Peterson, State Liaison Office Designee, NY State Energy, Research & Development Authority B. Wright, NYS Division of Homeland Security and Emergency Services ML22144A201 (Cover letter w/ enclosure(s))

ADAMS ACCESSION NUMBER: ML22144A206 (Cover letter)

Entire Report: Non-Sensitive Publicly Available X SUNSI Review X Sensitive X Non-Publicly Available Cover Letter Only: X Non-Sensitive X Publicly Available X SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DORS RI/DORS RI/DORS RI/DORS NAME BPinson DWerkheiser ECarfang GDentel DATE 5/23/22 5/24/22 5/23/22 5/23/22