PNO-I-87-007:on 870129,licensee Began Normal Shutdown of Facility to Repair Leak in Steam Generator SG-1.Leak Caused by Tube Defect.Plant Will Remain Shut Down for 17 to 18 Days.State of CT Informed
ML20209A626
Person / Time
Site: Millstone Dominion icon.png
Issue date: 01/30/1987
From: Mccabe E, Rebelowski T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
References
PNO-I-87-007, PNO-I-87-7, NUDOCS 8702030405
Download: ML20209A626 (1)


. _. ._ __

~

DCS No: 50336870129 Date: January 30, 1987 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE--PNO-I-87-07 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or-public interest significance. The information is as initially received without vsrification or evaluation, and is basically all that is known by the Region I staff on this date.

Facility: Northeast Nuclear Energy Co. Licensee Emergency Classification:

Millstone Nuclear Sta. Notification of Unusual Event Unit 2 Alert Docket No. 50-336 Site Area Emergency Waterford, Connecticut General Emergency

__X_ Not Applicable

Subject:

SHUTDOWN IN EXCESS OF 48 HOURS At 5:30 p.m., January 29, the licensee began a normal shutdown of Millstone 2 to repair a primary to secondary leak of 0.2 gpm in Steam Generator SG-1. The plant is now shut down. A 17-18 day o,utage is expected.

The Technical Specification limit on primary to secondary SG leakage is 0.5 gpm per SG.

This shutdown was prompted by SG tube eddy current test (ECT) review after the leakage was identified. That review (of ECT data obtained in December 1986) identified a tube defcct in a tube that had not been plugged.

The licensee issued a press release describing the event and the planned outage length.

Tha State of Connecticut has been informed.

An ENS call was made at 5:39 p.m., January 29, to inform the NRC about the shutdown, and the resident inspector was informad at that time. Outage activities will be covered by resident and region-based specialist inspection.

CONTACT: T. Rebelowski E. McCabe 203-447-3179 215-337-5231 8-488-1231 4

DISTRIBUTION:

H. St. MNBB Phillips E/W Willste Mail: ADM:DMB Chairman Zech EDO NRR IE NMSS DOT:Trans only Comm. Bernthal PA OIA RES Comm. Roberts ELD AE00 NRC Ops Crt Comm. Asselstine Comm. Carr ACRS Air Right.; INP0----

SECY SP NSAC----

CA PDR Regional Offices TMI Resident Section RI Resident Office Licensee:

(Reactor Licensees)

R:gion I Form 83 l (Rav. July 1986) ,

g20gose70130 l PNO-i-87-oo7 pyg $ G_

. _ _ _ __ _ _ _ _ - _ _ _ _ _. _ . _ _ _ _ ._ _ _ _ _