MONTHYEARIR 05000335/20230102024-01-26026 January 2024 NRC Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000335/2023010 and 05000389/2023010 IR 05000335/20230042024-01-24024 January 2024 Integrated Inspection Report 05000335/2023004 and 05000389/2023004 IR 05000335/20230032023-11-0606 November 2023 Integrated Inspection Report 05000335/2023003 and 05000389/2023003 IR 05000335/20233012023-09-20020 September 2023 NRC Operator License Examination Report 05000335/2023301 and 05000389/2023301 IR 05000335/20230022023-08-0707 August 2023 Integrated Inspection Report 05000335/2023002 and 05000389/2023002 IR 05000335/20234032023-06-29029 June 2023 Security Inspection Report 05000335/2023403 and 05000389/2023403 IR 05000335/20234022023-06-20020 June 2023 Security Baseline Inspection Report 05000335/2023402 and 05000389/2023402 IR 05000335/20234012023-05-16016 May 2023 Cyber Security Inspection Report 05000335/2023401 and 05000389/2023401 (Cover Letter) IR 05000335/20230012023-05-0909 May 2023 Integrated Inspection Report 05000335/2023001 and 05000389/2023001 IR 05000335/20234202023-03-21021 March 2023 Security Baseline Inspection Report 05000335/2023420 and 05000389/2023420 IR 05000335/20220062023-03-0101 March 2023 Annual Assessment Letter for St. Lucie Units 1 & 2 (Report 05000335/2022006 and 05000389/2022006) IR 05000335/20220042023-02-10010 February 2023 Integrated Inspection Report 05000335/2022004 and 05000389/2022004 IR 05000335/20220112022-12-27027 December 2022 Triennial Fire Protection Inspection Report 05000335/2022011 and 05000389/2022011 IR 05000335/20220032022-11-0404 November 2022 Integrated Inspection Report 05000335/2022003 and 05000389/2022003 ML22208A1762022-08-0404 August 2022 Review of the Fall 2021 Steam Generator Tube Inspection Report IR 05000335/20220022022-08-0101 August 2022 Integrated Inspection Report 05000335/2022002 and 05000389/2022002 ML22210A0782022-07-22022 July 2022 Stl 2022003 Document Request IR 05000335/20220122022-06-29029 June 2022 Biennial Problem Identification and Resolution Inspection Report 05000335 2022012 and 05000389 2022012 IR 05000335/20224012022-05-20020 May 2022 Security Baseline Inspection Report 05000335/2022401 and 05000389/2022401 IR 05000335/20220012022-05-12012 May 2022 Integrated Inspection Report 05000335/2022001 and 05000389/2022001 IR 05000335/20220102022-04-27027 April 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000335/2022010 and 05000389/2022010 IR 05000335/20214022022-04-0404 April 2022 Material Control and Accounting Program Inspection Report 05000335/2021402 and 05000389/2021402 - Public IR 05000335/20210062022-03-0202 March 2022 Annual Assessment Letter for St. Lucie, Units 1 & 2 (Report No. 05000335/2021006 and 05000389/2021006) IR 05000335/20210042022-02-14014 February 2022 Integrated Inspection Report 05000335/2021004 and 05000389/2021004 IR 05000335/20214032021-12-14014 December 2021 Security Baseline Inspection Report 05000335/2021403 and 05000389/2021403 IR 05000335/20210102021-12-0707 December 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000335/2021010 and 05000389/2021010 IR 05000335/20210032021-11-0303 November 2021 Integrated Inspection Report 05000335/2021003 and 05000389/2021003 IR 05000335/20210052021-08-25025 August 2021 Updated Inspection Plan for St. Lucie Plant Units 1 & 2 (Report 05000335/2021005 and 05000389/2021005) IR 05000335/20210022021-08-10010 August 2021 Integrated Inspection Report 05000335/2021002 and 05000389/2021002 IR 05000335/20214012021-06-23023 June 2021 Security Baseline Inspection Report 05000335/2021401 and 05000389/2021401 IR 05000335/20213012021-06-21021 June 2021 NRC Examination Report 05000335/2021301 and 05000389/2021301 IR 05000335/20210012021-05-12012 May 2021 Integrated Inspection Report 05000335/2021001 and 05000389/2021001 IR 05000335/20200062021-03-0303 March 2021 Annual Assessment Letter for St. Lucie Nuclear Plant, Unit 1 and Unit 2 Report 05000335/2020006 and 05000389/2020006 IR 05000335/20203012021-02-16016 February 2021 NRC Operator License Examination Report 05000335/2020301 and 05000389/2020301 IR 05000335/20200042021-02-0808 February 2021 Integrated Inspection Report 05000335/2020004 and 05000389/2020004 and Independent Spent Fuel Storage Installation (ISFSI) Inspection 07200061/2020002 IR 05000335/20204012021-01-0505 January 2021 Security Baseline Inspection Report 05000335/2020401 and 05000389/2020401 IR 05000335/20200112020-12-16016 December 2020 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000335/2020011 and 05000389/2020011 IR 05000335/20200032020-10-30030 October 2020 Integrated Inspection Report 05000335/2020003 and 05000389/2020003 ML20296A3732020-10-22022 October 2020 Security Inspection Report IR 05000335/20200052020-08-24024 August 2020 Updated Inspection Plan for St. Lucie Plant, Unit 1 and 2 (Report 05000335/2020005 and 05000389/2020005) IR 05000335/20200022020-07-29029 July 2020 St.Lucie Units 1 & 2 Integrated Inspection Report 05000335/2020002, 05000389/2020002, and Independent Spent Fuel Storage Installation Inspection (Lsfsi) 07200061/2020001 IR 05000335/20200102020-07-16016 July 2020 Biennial Problem Identification and Resolution Inspection Report 05000335/2020010 and 05000389/2020010 IR 05000335/20200012020-05-0505 May 2020 Integrated Inspection Report 05000335/2020001 and 05000389/2020001 and Exercise of Enforcement Discretion IR 05000335/20190062020-03-0303 March 2020 Annual Assessment Letter for St. Lucie Nuclear Plant, Units 1 and 2 NRC Report 05000335/2019006 and 05000389/2019006 IR 05000335/20190032019-11-14014 November 2019 Integrated Inspection Report 05000335/2019003 and 05000389/2019003 IR 05000335/20193022019-10-18018 October 2019 NRC Examination Report 05000335/2019302 and 05000389/2019302 IR 05000335/20194112019-10-0707 October 2019 NRC Security Inspection Report 05000335/2019411 and 05000389/2019411 IR 05000335/20194012019-09-0909 September 2019 Cyber Security Inspection Report 05000335/2019401 and 05000389/2019401 (Public) IR 05000335/20190052019-08-27027 August 2019 Updated Inspection Plan for St. Lucie Plant, Unit 1 and Unit 2 - (Report 05000335/2019005 and 05000389/2019005) IR 05000335/20190112019-08-20020 August 2019 Triennial Fire Protection Inspection Report 05000335/2019011 and 05000389/2019011 2024-01-26
[Table view] |
Text
U.S. NUCLEAR REGULATORY COMMISSION (NRC)
OFFICE OF NUCLEAR SECURITY AND INCIDENT RESPONSE (NSIR)
INSPECTION REPORT Docket Numbers: 05000335 and 05000389 License Numbers: DPR-67 and NPF-16 Report Number: 05000335/2020420 and 05000389/2020420 Enterprise Identifier: I-2020-420-0016 Licensee: Florida Power & Light Company Facility: St. Lucie Nuclear Power Plant, Units 1 and 2 Location: Jensen Beach, Florida Inspection Dates: September 28, 2020 to October 02, 2020 Inspectors: T. Barry, Security Specialist D. Bradfield, Team Leader R. Patterson, Senior Physical Security Inspector R. Stone, Security Specialist A. Woyansky, Security Specialist Approved By: Dante C. Johnson, Chief Security Performance Evaluation Br Division of Security Operations Enclosure
SUMMARY
The NRC continued monitoring the licensees performance by conducting a security inspection at St. Lucie Nuclear Power Plant, Units 1 and 2, in accordance with Inspection Manual Chapter (IMC) 2201, Appendix C, Generic, Special, and Infrequent Inspections. IMC 2201 Appendix C inspections for the security inspection program are designed to support the NRC goals of maintaining safety, enhancing public confidence, improving the effectiveness, efficiency and realism of the regulatory process, reducing unnecessary regulatory burden, and promoting the common defense and security.
List of Findings and Violations No findings or violations of more than minor significance were identified.
Additional Tracking Items None.
2
INSPECTION SCOPES Unless otherwise noted, security inspections were conducted in accordance with the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Publicly available IPs are located at:
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 92707 - Security Inspection of Facilities Impacted by a Local, State, or Federal Emergency Where the NRCs Ability to Conduct Triennial Force On-Force Exercises is Limited (1 Sample)
(1) The NRC inspectors completed this inspection by gathering sufficient information to develop a scenario that can be segmented into limited scope tactical response drills that allows for a limited assessment of the ability of licensees physical security systems and security organization to meet the general performance objective of Title 10 of the Code of Federal Regulations (10 CFR) 73.55(b) and to ensure changes made to the physical protection program in response to a local, State, or Federal emergency (e.g., state of emergency, disaster, or public health emergency) have not adversely impacted the licensees implementation of their protective strategy.
REPORT ATTACHMENTS Supplemental Information for the report is considered Safeguards Information and is located separately within the NRCs Safeguards Information Local Area Network and Electronic Safe database (SLES), under NS125678.
INSPECTION RESULTS No findings were identified.
EXIT MEETINGS AND DEBRIEFS The inspectors verified no proprietary information was retained or documented in this report.
- On October 7, 2020, the inspectors presented the security inspection results to Mr. Dan DeBoer and other members of the licensee staff.
3
DOCUMENTS REVIEWED Inspection Type Designation Description or Title Revision or Procedure Date 92707 Corrective AR02370421 Action Documents Resulting from Inspection Miscellaneous FPL St. Lucie St. Lucie Physical Security Revision 21 PSP Plan SFI 2415 St. Lucie Plant Target Sets Revision 13, Dated 03/11/2020 4