Category:INSPECTION REPORT
MONTHYEARIR 05000456/19990131999-09-17017 September 1999 Insp Repts 50-456/99-13 & 50-457/99-13 on 990706-0824. Violations Noted.Major Areas Inspected:C/As & Engineering Related Activities to Address Technical Concerns Identified During Design Insp Completed on 980424 IR 05000456/19990121999-09-0303 September 1999 Insp Repts 50-456/99-12 & 50-457/99-12 on 990707-0816.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site IR 05000456/19990111999-07-29029 July 1999 Insp Repts 50-456/99-11 & 50-457/99-11 on 990525-0706.Two Violations Occurred & Being Treated as Ncvs.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19990091999-07-20020 July 1999 Insp Repts 50-456/99-09 & 50-457/99-09 on 990517-0623.No Violations Noted.Major Areas Inspected:Licensee Radiation Protection Program.Circumstances Surrounding 990428, Gatehouse Monitor Exiting Incident Were Also Reviewed IR 05000456/19990071999-06-18018 June 1999 Insp Repts 50-456/99-07 & 50-457/99-07 on 990414-0524.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000457/19990081999-06-14014 June 1999 Insp Rept 50-457/99-08 on 990415-0518.No Violations Noted. Major Areas Inspected:Isi & SG Insp Program IR 05000456/19990051999-05-20020 May 1999 Insp Repts 50-456/99-05 & 50-457/99-05 on 990405-23.Non- Cited Violations Identified.Major Areas Inspected:Review of Engineering & Technical Support & Corrective Actions IR 05000456/19990061999-05-11011 May 1999 Insp Repts 50-456/99-06 & 50-457/99-06 on 990302-0413.One non-cited Violation Re Configuration Control Error Occurred. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000456/19990021999-03-23023 March 1999 Insp Repts 50-456/99-02 & 50-457/99-02 on 990120-0301.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19990041999-03-23023 March 1999 Insp Repts 50-456/99-04 & 50-457/99-04 on 990222-24 & 0303 Onsite & 0309 & 11 Region 3 Ofc.No Violations Noted.Major Areas Inspected:Physical Security Program IR 05000456/19980161999-02-11011 February 1999 Insp Rept 50-456/98-16 on 980916-990121.No Violations Noted. Major Areas Inspected:Containment Access Opening & Replacement Activities,Removal & Replacement of Sgs,Welding of SG Piping & Review of Quality Control Activities IR 05000456/19980201998-12-30030 December 1998 Insp Repts 50-456/98-20 & 50-457/98-20 on 981020-1207.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19980211998-12-10010 December 1998 Insp Repts 50-456/98-21 & 50-457/98-21 on 981110-24.No Violations Noted.Major Areas Inspected:Aspects of Corrective Actions & Engineering Involvement in Corrective Action Process IR 05000456/19980181998-12-0404 December 1998 Insp Rept 50-456/98-18 on 981015-23 & 1109-10.No Violations Noted.Major Areas Inspected:Four Areas Associated with Licensee SG Replacement Project IR 05000456/19980191998-11-25025 November 1998 Insp Repts 50-456/98-19 & 50-457/98-19 on 981027-30.No Violations Noted.Major Areas Inspected:Licensee Implementation of 10CFR50.65 Requirements for Monitoring Effectiveness of Maintenance at Nuclear Power Plants ML20195G3731998-11-17017 November 1998 Insp Repts 50-456/98-14 & 50-457/98-14 on 980909-1019. Violations Noted.Major Areas Inspected:Licensee Operations, Maint & Engineering IR 05000456/19980151998-11-13013 November 1998 Insp Repts 50-456/98-15 & 50-457/98-15 on 980915-1022. Violations Noted.Major Areas Inspected:Review of Radiation Protection Program Focusing on Radiological Controls for Unit 1 Outage Activities & SG Replacement Project IR 05000456/19980171998-11-10010 November 1998 Insp Repts 50-456/98-17 & 50-457/98-17 on 981013-19. Violations Noted.Major Areas Inspected:Security Measures Implemented to Support Steam Generator Replacement Project IR 05000456/19980121998-10-0505 October 1998 Insp Repts 50-456/98-12 & 50-457/98-12 on 980728-0908.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19980111998-09-25025 September 1998 Insp Rept 50-456/98-11 on 980707-09,15-16,0805-06,10-13 & 26-28.No Violations Noted.Major Areas Inspected:Review of SG Replacement Program.Insp Focused on Welding of SG Feedwater Piping & Preparation Activities for Replacing SGs IR 05000456/19980131998-08-28028 August 1998 Insp Repts 50-456/98-13 & 50-457/98-13 on 980810-14.No Violations Noted.Major Areas Inspected:Review of Chemistry & Radiation Protection Programs IR 05000456/19980091998-08-25025 August 1998 Insp Repts 50-456/98-09 & 50-457/98-09 on 980609-0727. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20236N0941998-07-0606 July 1998 Insp Repts 50-456/98-08 & 50-457/98-08 on 980421-0608. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19980101998-07-0202 July 1998 Insp Repts 50-456/98-10 & 50-457/98-10 on 980615-19.No Violations Noted.Major Areas Inspected:Physical Security Program.Details Withheld (Ref 10CFR73.21) IR 05000456/19980071998-06-18018 June 1998 Insp Repts 50-456/98-07 & 50-457/98-07 on 980519-22.No Violations Noted.Major Areas Inspected:Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000456/19982011998-06-0101 June 1998 Insp Rept 50-456/98-201 on 980316-20,0330-0410 & 0420-24. No Violations Noted.Major Areas Inspected.Team Selected & Reviewed Relevant Portions of Ufsar,Ts,Drawings, Calculations,Mod Packages & Procedures IR 05000456/19980051998-05-19019 May 1998 Insp Repts 50-456/98-05 & 50-457/98-05 on 980310-0420. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000456/19980061998-04-21021 April 1998 Insp Repts 50-456/98-06 & 50-457/98-06 on 980331-0407. Violations Noted.Major Areas Inspected:Announced Review Protection Program.Insp Focused on Liquid & Gaseous Effluent Radiation Monitoring Programs ML20216B0761998-04-0808 April 1998 Insp Repts 50-456/98-02 & 50-457/98-02 on 980127-0309. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000456/19980031998-03-16016 March 1998 Insp Repts 50-456/98-03 & 50-457/98-03 on 980128-30.No Violations Noted.Major Areas Inspected:Operations & Maint ML20203D9201998-02-20020 February 1998 Insp Repts 50-456/97-22 & 50-457/97-22 on 971216-980126. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000457/19970211998-02-11011 February 1998 Insp Rept 50-457/97-21 on 971112-21 & 980115.Violations Noted.Major Areas Inspected:Operations & Engineering ML20198G1231998-01-0707 January 1998 Partially Withheld Insp Repts 50-456/97-20 & 50-457/97-20 on 971117-21 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support Performance Involving Evaluation of Effectiveness of Physical Protection Program ML20202F1951998-01-0202 January 1998 Insp Repts 50-456/97-19 & 50-457/97-19 on 971104-1215. Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support ML20199A5781997-12-17017 December 1997 Insp Repts 50-456/97-16 & 50-457/97-16 on 970923-1103. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000456/19970151997-11-26026 November 1997 Insp Repts 50-456/97-15 & 50-457/97-15 on 970812-0922. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000456/19970171997-11-17017 November 1997 Insp Repts 50-456/97-17 & 50-457/97-17 on 971006-22. Violations Noted.Major Areas Inspected:Plant Support & Radiation Protection Program IR 05000456/19970121997-10-17017 October 1997 Insp Repts 50-456/97-12 & 50-457/97-12 on 970414-0815. Violations Noted.Major Areas Inspected:Maint & Engineering IR 05000456/19970131997-09-17017 September 1997 Insp Repts 50-456/97-13 & 50-457/97-13 on 970701-0811. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000456/19970141997-09-12012 September 1997 Insp Repts 50-456/97-14 & 50-457/97-14 on 970811-15.No Violations Noted.Major Areas Inspected:Ro & SRO Requalification Training Programs IR 05000456/19970091997-08-26026 August 1997 Insp Repts 50-456/97-09 & 50-457/97-09 on 970520-0630. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support ML20149J7051997-07-24024 July 1997 Insp Repts 50-456/97-11 & 50-457/97-11 on 970618-24.No Violations Noted.Major Areas Inspected:Plant Support Performance & Evaluation of Effectiveness of Radiation Protection Program IR 05000456/19970101997-06-26026 June 1997 Insp Rept 50-456/97-10 on 970403-0602.No Violations Noted. Major Areas Inspected:Maint ML20141E8371997-06-17017 June 1997 Insp Repts 50-456/97-07 & 50-457/97-07 on 970408-0520. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20141H4431997-05-19019 May 1997 Enforcement Conference Repts 50-456/96-16 & 50-457/96-16 on 970514 in Lisle,Il.Major Areas Discussed:Apparent Violations Identified During Inspection,Along W/Corrective Actions Taken or Planned by Licensee ML20141J9301997-05-19019 May 1997 Insp Repts 50-456/97-08 & 50-457/97-08 on 970417-30. Violations Noted.Major Areas Inspected:Plant Support Performance ML20141D7711997-05-0909 May 1997 Insp Repts 50-456/97-05 & 50-457/97-05 on 970222-0407. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19970061997-04-10010 April 1997 Partially Withheld Insp Repts 50-456/97-06 & 50-457/97-06 on 970310-14.No Violations Noted.Major Areas Inspected: Evaluation of Performance of Security Organization & Review of Previous Open Items IR 05000456/19970041997-04-0808 April 1997 Insp Repts 50-456/97-04 & 50-457/97-04 on 970303-07. Violations Noted.Major Areas Inspected:Review of Emergency Preparedness Program,Aspect of Plant Support 1999-09-03
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000456/19990131999-09-17017 September 1999 Insp Repts 50-456/99-13 & 50-457/99-13 on 990706-0824. Violations Noted.Major Areas Inspected:C/As & Engineering Related Activities to Address Technical Concerns Identified During Design Insp Completed on 980424 IR 05000456/19990121999-09-0303 September 1999 Insp Repts 50-456/99-12 & 50-457/99-12 on 990707-0816.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site IR 05000456/19990111999-07-29029 July 1999 Insp Repts 50-456/99-11 & 50-457/99-11 on 990525-0706.Two Violations Occurred & Being Treated as Ncvs.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19990091999-07-20020 July 1999 Insp Repts 50-456/99-09 & 50-457/99-09 on 990517-0623.No Violations Noted.Major Areas Inspected:Licensee Radiation Protection Program.Circumstances Surrounding 990428, Gatehouse Monitor Exiting Incident Were Also Reviewed IR 05000456/19990071999-06-18018 June 1999 Insp Repts 50-456/99-07 & 50-457/99-07 on 990414-0524.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000457/19990081999-06-14014 June 1999 Insp Rept 50-457/99-08 on 990415-0518.No Violations Noted. Major Areas Inspected:Isi & SG Insp Program IR 05000456/19990051999-05-20020 May 1999 Insp Repts 50-456/99-05 & 50-457/99-05 on 990405-23.Non- Cited Violations Identified.Major Areas Inspected:Review of Engineering & Technical Support & Corrective Actions IR 05000456/19990061999-05-11011 May 1999 Insp Repts 50-456/99-06 & 50-457/99-06 on 990302-0413.One non-cited Violation Re Configuration Control Error Occurred. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000456/19990021999-03-23023 March 1999 Insp Repts 50-456/99-02 & 50-457/99-02 on 990120-0301.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19990041999-03-23023 March 1999 Insp Repts 50-456/99-04 & 50-457/99-04 on 990222-24 & 0303 Onsite & 0309 & 11 Region 3 Ofc.No Violations Noted.Major Areas Inspected:Physical Security Program IR 05000456/19980161999-02-11011 February 1999 Insp Rept 50-456/98-16 on 980916-990121.No Violations Noted. Major Areas Inspected:Containment Access Opening & Replacement Activities,Removal & Replacement of Sgs,Welding of SG Piping & Review of Quality Control Activities IR 05000456/19980201998-12-30030 December 1998 Insp Repts 50-456/98-20 & 50-457/98-20 on 981020-1207.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19980211998-12-10010 December 1998 Insp Repts 50-456/98-21 & 50-457/98-21 on 981110-24.No Violations Noted.Major Areas Inspected:Aspects of Corrective Actions & Engineering Involvement in Corrective Action Process IR 05000456/19980181998-12-0404 December 1998 Insp Rept 50-456/98-18 on 981015-23 & 1109-10.No Violations Noted.Major Areas Inspected:Four Areas Associated with Licensee SG Replacement Project IR 05000456/19980191998-11-25025 November 1998 Insp Repts 50-456/98-19 & 50-457/98-19 on 981027-30.No Violations Noted.Major Areas Inspected:Licensee Implementation of 10CFR50.65 Requirements for Monitoring Effectiveness of Maintenance at Nuclear Power Plants ML20195G3731998-11-17017 November 1998 Insp Repts 50-456/98-14 & 50-457/98-14 on 980909-1019. Violations Noted.Major Areas Inspected:Licensee Operations, Maint & Engineering IR 05000456/19980151998-11-13013 November 1998 Insp Repts 50-456/98-15 & 50-457/98-15 on 980915-1022. Violations Noted.Major Areas Inspected:Review of Radiation Protection Program Focusing on Radiological Controls for Unit 1 Outage Activities & SG Replacement Project IR 05000456/19980171998-11-10010 November 1998 Insp Repts 50-456/98-17 & 50-457/98-17 on 981013-19. Violations Noted.Major Areas Inspected:Security Measures Implemented to Support Steam Generator Replacement Project IR 05000456/19980121998-10-0505 October 1998 Insp Repts 50-456/98-12 & 50-457/98-12 on 980728-0908.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19980111998-09-25025 September 1998 Insp Rept 50-456/98-11 on 980707-09,15-16,0805-06,10-13 & 26-28.No Violations Noted.Major Areas Inspected:Review of SG Replacement Program.Insp Focused on Welding of SG Feedwater Piping & Preparation Activities for Replacing SGs IR 05000456/19980131998-08-28028 August 1998 Insp Repts 50-456/98-13 & 50-457/98-13 on 980810-14.No Violations Noted.Major Areas Inspected:Review of Chemistry & Radiation Protection Programs IR 05000456/19980091998-08-25025 August 1998 Insp Repts 50-456/98-09 & 50-457/98-09 on 980609-0727. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20236N0941998-07-0606 July 1998 Insp Repts 50-456/98-08 & 50-457/98-08 on 980421-0608. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19980101998-07-0202 July 1998 Insp Repts 50-456/98-10 & 50-457/98-10 on 980615-19.No Violations Noted.Major Areas Inspected:Physical Security Program.Details Withheld (Ref 10CFR73.21) IR 05000456/19980071998-06-18018 June 1998 Insp Repts 50-456/98-07 & 50-457/98-07 on 980519-22.No Violations Noted.Major Areas Inspected:Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000456/19982011998-06-0101 June 1998 Insp Rept 50-456/98-201 on 980316-20,0330-0410 & 0420-24. No Violations Noted.Major Areas Inspected.Team Selected & Reviewed Relevant Portions of Ufsar,Ts,Drawings, Calculations,Mod Packages & Procedures IR 05000456/19980051998-05-19019 May 1998 Insp Repts 50-456/98-05 & 50-457/98-05 on 980310-0420. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000456/19980061998-04-21021 April 1998 Insp Repts 50-456/98-06 & 50-457/98-06 on 980331-0407. Violations Noted.Major Areas Inspected:Announced Review Protection Program.Insp Focused on Liquid & Gaseous Effluent Radiation Monitoring Programs ML20216B0761998-04-0808 April 1998 Insp Repts 50-456/98-02 & 50-457/98-02 on 980127-0309. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000456/19980031998-03-16016 March 1998 Insp Repts 50-456/98-03 & 50-457/98-03 on 980128-30.No Violations Noted.Major Areas Inspected:Operations & Maint ML20203D9201998-02-20020 February 1998 Insp Repts 50-456/97-22 & 50-457/97-22 on 971216-980126. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000457/19970211998-02-11011 February 1998 Insp Rept 50-457/97-21 on 971112-21 & 980115.Violations Noted.Major Areas Inspected:Operations & Engineering ML20198G1231998-01-0707 January 1998 Partially Withheld Insp Repts 50-456/97-20 & 50-457/97-20 on 971117-21 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support Performance Involving Evaluation of Effectiveness of Physical Protection Program ML20202F1951998-01-0202 January 1998 Insp Repts 50-456/97-19 & 50-457/97-19 on 971104-1215. Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support ML20199A5781997-12-17017 December 1997 Insp Repts 50-456/97-16 & 50-457/97-16 on 970923-1103. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000456/19970151997-11-26026 November 1997 Insp Repts 50-456/97-15 & 50-457/97-15 on 970812-0922. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000456/19970171997-11-17017 November 1997 Insp Repts 50-456/97-17 & 50-457/97-17 on 971006-22. Violations Noted.Major Areas Inspected:Plant Support & Radiation Protection Program IR 05000456/19970121997-10-17017 October 1997 Insp Repts 50-456/97-12 & 50-457/97-12 on 970414-0815. Violations Noted.Major Areas Inspected:Maint & Engineering IR 05000456/19970131997-09-17017 September 1997 Insp Repts 50-456/97-13 & 50-457/97-13 on 970701-0811. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000456/19970141997-09-12012 September 1997 Insp Repts 50-456/97-14 & 50-457/97-14 on 970811-15.No Violations Noted.Major Areas Inspected:Ro & SRO Requalification Training Programs IR 05000456/19970091997-08-26026 August 1997 Insp Repts 50-456/97-09 & 50-457/97-09 on 970520-0630. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support ML20149J7051997-07-24024 July 1997 Insp Repts 50-456/97-11 & 50-457/97-11 on 970618-24.No Violations Noted.Major Areas Inspected:Plant Support Performance & Evaluation of Effectiveness of Radiation Protection Program IR 05000456/19970101997-06-26026 June 1997 Insp Rept 50-456/97-10 on 970403-0602.No Violations Noted. Major Areas Inspected:Maint ML20141E8371997-06-17017 June 1997 Insp Repts 50-456/97-07 & 50-457/97-07 on 970408-0520. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20141H4431997-05-19019 May 1997 Enforcement Conference Repts 50-456/96-16 & 50-457/96-16 on 970514 in Lisle,Il.Major Areas Discussed:Apparent Violations Identified During Inspection,Along W/Corrective Actions Taken or Planned by Licensee ML20141J9301997-05-19019 May 1997 Insp Repts 50-456/97-08 & 50-457/97-08 on 970417-30. Violations Noted.Major Areas Inspected:Plant Support Performance ML20141D7711997-05-0909 May 1997 Insp Repts 50-456/97-05 & 50-457/97-05 on 970222-0407. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19970061997-04-10010 April 1997 Partially Withheld Insp Repts 50-456/97-06 & 50-457/97-06 on 970310-14.No Violations Noted.Major Areas Inspected: Evaluation of Performance of Security Organization & Review of Previous Open Items IR 05000456/19970041997-04-0808 April 1997 Insp Repts 50-456/97-04 & 50-457/97-04 on 970303-07. Violations Noted.Major Areas Inspected:Review of Emergency Preparedness Program,Aspect of Plant Support 1999-09-03
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000456/19990131999-09-17017 September 1999 Insp Repts 50-456/99-13 & 50-457/99-13 on 990706-0824. Violations Noted.Major Areas Inspected:C/As & Engineering Related Activities to Address Technical Concerns Identified During Design Insp Completed on 980424 IR 05000456/19990121999-09-0303 September 1999 Insp Repts 50-456/99-12 & 50-457/99-12 on 990707-0816.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site IR 05000456/19990111999-07-29029 July 1999 Insp Repts 50-456/99-11 & 50-457/99-11 on 990525-0706.Two Violations Occurred & Being Treated as Ncvs.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19990091999-07-20020 July 1999 Insp Repts 50-456/99-09 & 50-457/99-09 on 990517-0623.No Violations Noted.Major Areas Inspected:Licensee Radiation Protection Program.Circumstances Surrounding 990428, Gatehouse Monitor Exiting Incident Were Also Reviewed IR 05000456/19990071999-06-18018 June 1999 Insp Repts 50-456/99-07 & 50-457/99-07 on 990414-0524.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000457/19990081999-06-14014 June 1999 Insp Rept 50-457/99-08 on 990415-0518.No Violations Noted. Major Areas Inspected:Isi & SG Insp Program IR 05000456/19990051999-05-20020 May 1999 Insp Repts 50-456/99-05 & 50-457/99-05 on 990405-23.Non- Cited Violations Identified.Major Areas Inspected:Review of Engineering & Technical Support & Corrective Actions IR 05000456/19990061999-05-11011 May 1999 Insp Repts 50-456/99-06 & 50-457/99-06 on 990302-0413.One non-cited Violation Re Configuration Control Error Occurred. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000456/19990021999-03-23023 March 1999 Insp Repts 50-456/99-02 & 50-457/99-02 on 990120-0301.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19990041999-03-23023 March 1999 Insp Repts 50-456/99-04 & 50-457/99-04 on 990222-24 & 0303 Onsite & 0309 & 11 Region 3 Ofc.No Violations Noted.Major Areas Inspected:Physical Security Program IR 05000456/19980161999-02-11011 February 1999 Insp Rept 50-456/98-16 on 980916-990121.No Violations Noted. Major Areas Inspected:Containment Access Opening & Replacement Activities,Removal & Replacement of Sgs,Welding of SG Piping & Review of Quality Control Activities IR 05000456/19980201998-12-30030 December 1998 Insp Repts 50-456/98-20 & 50-457/98-20 on 981020-1207.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000456/19980211998-12-10010 December 1998 Insp Repts 50-456/98-21 & 50-457/98-21 on 981110-24.No Violations Noted.Major Areas Inspected:Aspects of Corrective Actions & Engineering Involvement in Corrective Action Process IR 05000456/19980181998-12-0404 December 1998 Insp Rept 50-456/98-18 on 981015-23 & 1109-10.No Violations Noted.Major Areas Inspected:Four Areas Associated with Licensee SG Replacement Project IR 05000456/19980191998-11-25025 November 1998 Insp Repts 50-456/98-19 & 50-457/98-19 on 981027-30.No Violations Noted.Major Areas Inspected:Licensee Implementation of 10CFR50.65 Requirements for Monitoring Effectiveness of Maintenance at Nuclear Power Plants ML20195G3731998-11-17017 November 1998 Insp Repts 50-456/98-14 & 50-457/98-14 on 980909-1019. Violations Noted.Major Areas Inspected:Licensee Operations, Maint & Engineering ML20195G3681998-11-17017 November 1998 Notice of Violation from Insp on 980909-1019.Violation Noted:As of 980818,licensee Failed to Initiate Measures to Determine Cause or Take Action to Preclude Recurrence of Loose Bolts on Two EDG Lubricating Oil Heat Exchanger Bells ML20195G3031998-11-13013 November 1998 Notice of Violation from Insp on 980915-1022.Violation Noted:On 981022,two Individuals Working Under RWP 984014 Removed Outer Rubber Gloves While Replacing Insulation in Containment IR 05000456/19980151998-11-13013 November 1998 Insp Repts 50-456/98-15 & 50-457/98-15 on 980915-1022. Violations Noted.Major Areas Inspected:Review of Radiation Protection Program Focusing on Radiological Controls for Unit 1 Outage Activities & SG Replacement Project IR 05000456/19980171998-11-10010 November 1998 Insp Repts 50-456/98-17 & 50-457/98-17 on 981013-19. Violations Noted.Major Areas Inspected:Security Measures Implemented to Support Steam Generator Replacement Project ML20196D9201998-11-10010 November 1998 Notice of Violation from Insp on 981013-19.Violation Noted: Licensee Security Staff Discovered That on Three Occasions Between 980826 & 1002,security Officers Were Found Asleep on Post IR 05000456/19983051998-11-0202 November 1998 Exam Repts 50-456/98-305 & 50-457/98-305 on 980914 with Telephoned Exam Results 981020.No Violations Noted.Exam Results:Applicant Passed Retake Exam & Was Issued Reactor Operator License IR 05000456/19980121998-10-0505 October 1998 Insp Repts 50-456/98-12 & 50-457/98-12 on 980728-0908.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19980111998-09-25025 September 1998 Insp Rept 50-456/98-11 on 980707-09,15-16,0805-06,10-13 & 26-28.No Violations Noted.Major Areas Inspected:Review of SG Replacement Program.Insp Focused on Welding of SG Feedwater Piping & Preparation Activities for Replacing SGs IR 05000456/19980131998-08-28028 August 1998 Insp Repts 50-456/98-13 & 50-457/98-13 on 980810-14.No Violations Noted.Major Areas Inspected:Review of Chemistry & Radiation Protection Programs IR 05000456/19980091998-08-25025 August 1998 Insp Repts 50-456/98-09 & 50-457/98-09 on 980609-0727. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20236N0911998-07-0606 July 1998 Notice of Violations from Insp on 980421-0608.Violations Noted:On 980424,licensee Failed to Implement Specific Fire Protection Program Requirements in That Welding Machine Was Left Unattended & Energized in Fuel Handling Bldg ML20236N0941998-07-0606 July 1998 Insp Repts 50-456/98-08 & 50-457/98-08 on 980421-0608. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000456/19980101998-07-0202 July 1998 Insp Repts 50-456/98-10 & 50-457/98-10 on 980615-19.No Violations Noted.Major Areas Inspected:Physical Security Program.Details Withheld (Ref 10CFR73.21) IR 05000456/19980071998-06-18018 June 1998 Insp Repts 50-456/98-07 & 50-457/98-07 on 980519-22.No Violations Noted.Major Areas Inspected:Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000456/19982011998-06-0101 June 1998 Insp Rept 50-456/98-201 on 980316-20,0330-0410 & 0420-24. No Violations Noted.Major Areas Inspected.Team Selected & Reviewed Relevant Portions of Ufsar,Ts,Drawings, Calculations,Mod Packages & Procedures IR 05000456/19980051998-05-19019 May 1998 Insp Repts 50-456/98-05 & 50-457/98-05 on 980310-0420. Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20248D0821998-05-19019 May 1998 Notice of Violation from Insp on 980310-0420.Violation Noted:On 980303,licensee Failed to Implement Braidwood Administrative Procedure 2321-18T11,Step E.1,for Sf Pool Skimmer Strainer Level Control IR 05000456/19983041998-04-29029 April 1998 NRC Operator Licensing Exam Repts 50-456/98-304OL & 50-457/98-304OL (Including Completed & Graded Tests) Administered During Wk of 980413 ML20217F5281998-04-21021 April 1998 Notice of Violation from Insp on 980331-0407.Violation Noted:Licensee Failed to Check That SG Worker Dosimetry Was Present & Correctly Worn IR 05000456/19980061998-04-21021 April 1998 Insp Repts 50-456/98-06 & 50-457/98-06 on 980331-0407. Violations Noted.Major Areas Inspected:Announced Review Protection Program.Insp Focused on Liquid & Gaseous Effluent Radiation Monitoring Programs ML20216B0611998-04-0808 April 1998 Notice of Violation from Insp on 980127-0309.Violation Noted:On 971010,21,1219 & 980105,licensee Failed to Require Independent Verification of Proper Sys Alignment for safety-related Valves Repositioned in Steps F.1.4 & F.1.7 ML20216B0761998-04-0808 April 1998 Insp Repts 50-456/98-02 & 50-457/98-02 on 980127-0309. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000456/19980031998-03-16016 March 1998 Insp Repts 50-456/98-03 & 50-457/98-03 on 980128-30.No Violations Noted.Major Areas Inspected:Operations & Maint ML20203D9201998-02-20020 February 1998 Insp Repts 50-456/97-22 & 50-457/97-22 on 971216-980126. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20203D9151998-02-20020 February 1998 Notice of Violation from Insp on 971216-980126.Violation Noted:In Nov 1989,licensee Failed to Initiate Deviation Rept & Take Corrective Measures to Preclude Repetition of Mechanical Failure to All 4 Main Feedwater Check Valves ML20202F2321998-02-11011 February 1998 Notice of Violations from Insp on 971112-21 & 980115. Violations Noted:Licensee Failed to Follow NSWP-A-15 & Bwap 330-10 Requirements to Issue PIF for Tempering Line Snubber Considered Inoperable on 971110 IR 05000457/19970211998-02-11011 February 1998 Insp Rept 50-457/97-21 on 971112-21 & 980115.Violations Noted.Major Areas Inspected:Operations & Engineering PNO-III-98-013, on 980126,turbine Tripped Causing Subsequent Reactor Trip.Cause of Turbine Trip Remains Under Investigation.Appears Replacement Circuit Board Had Incorrect Electronic Configuration1998-01-29029 January 1998 PNO-III-98-013:on 980126,turbine Tripped Causing Subsequent Reactor Trip.Cause of Turbine Trip Remains Under Investigation.Appears Replacement Circuit Board Had Incorrect Electronic Configuration ML20198G1231998-01-0707 January 1998 Partially Withheld Insp Repts 50-456/97-20 & 50-457/97-20 on 971117-21 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support Performance Involving Evaluation of Effectiveness of Physical Protection Program ML20202F1951998-01-0202 January 1998 Insp Repts 50-456/97-19 & 50-457/97-19 on 971104-1215. Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 07100104/20120151998-01-0202 January 1998 Notice of Violation from Insp on 971104-1215.Violation Noted:On 971102,inspectors Identified That Licensee Had Failed to Fasten Covers on Incore Neutron Detector Drive Mechanism IR 05000456/19973101997-12-29029 December 1997 NRC Operator Licensing Exam Repts 50-456/97-310OL & 50-457/97-310OL for Tests Administered on 971006-1107.Three Senior Reactor Operators & One Reactor Operator Passed Exam. One Senior Reactor & One Reactor Operator Failed ML20199A5681997-12-17017 December 1997 Notice of Violation from Insp on 970923-1103.Violation Noted:On 971014,licensee Instrument Technician Made Error When Changing Setpoints on Unit 2 Containment Area Radiation Monitor 2AR11J.Error Resulted in High Radiation Alarm 1999-09-03
[Table view] |
Text
-. __ _ _ . - . _ . . _ - . . __ - _ _ _ _ . _ _ _ _ _ _ ._ _ __ _ . _ _ _ _ _ _ _ . .
-
.
,
U. S. NUCLEAR REGULATORY COMMISSION REGIONlli Docket Nos: 50-456;50-457 License Nos: NPF-72; NPF-77 l
l Report Nos: 50-456/98017(DRS); 50-457/98017(DRS) !
l Licensee: Commonwealth Edison Company l
l Facility: Braidwood Nuclear Generating Plant, Units 1 and 2 l l
Location: RR #1, Box 84 i Braceville,IL 60407 !
Dates: October 13-19,1998 ,
inspector: G. Pirtle, Physical Security inspector Approved by: James R. Creed, Chief, Plant Support Branch 1 (
Division of Reactor Safety )
l i
l
.
!
"
9812O20356 981110 PDR ADOCK 05000456 G PDR _
. ..
- . . . - . - . - ~ . - . _ . . _ .
-
.
L EXECUTIVE SUMMARY l Braidwood Nuclear Generation Plant i NRC Inspection Reports 50-456/98017; 50-457/98017 This inspection included a review of the security measures implemented to support the Steam
' Generator Replacement Project. It was an announced inspection conducted by a regional ,
i physical security specialis l
General security support for the Steam Generator Replacement Project was very goo Overtime demands for the security force were challenging but effectively monitored by the L security staff. Compensatory measures, except as noted below, were properly implemented.
l , Loggable security events were not excessive, and the general workforce demonstrated a good understanding and compliance with security responsibilities.
! A violation was identified for three occasions between August 26 and October 2,1998, when security officers were determined to be inattentive to duty (asleep) (Section S4.b.1).
An unresolved item was identified pertaining to the adequacy of compensatory measures implemented for a section of the vehicle barrier system (Section S3.b.1).
An Inspection Followup Item was identified pertaining to possible altering of fitness-for-duty test specimens by some individuals (Section S8). !
Security equipment observed during the inspection functioned as designed (Section S2).
Security procedures reviewed were generally well written. Records reviewed were accurate and complete (Section S3).
Security force members observed on post were knowledgeable of post requirements and performed their duties in an adequate manner. Security force support was well managed, and the plant population demonstrated a high level of awareness and compliance with security requirements (Section S4).
.
k ( 2
!
- - . - . . - , . . , ,- .. -
.__ _ __ =_ . _ - . .. _.. __.__.__ _ . __ _ _ .__ _ _ . - _ _
.
Report Details
,
IV. Plant Support S2 Status of Security Facilities and Equipment Insoection Scope (81700)
The inspector reviewed the condition of security equipment and facilities required by the security plan. The equipment observed included, but was not limited to, search equipment, intrusion alarm equipment, alarm assessment equipment, and equipment
,
within the secondary alarm station (SAS) and Main Access Facility (MAF). Observations and Findinas Search equipment at the MAF and equipment at the SAS functioned as designe Security force personnel evaluated had the required communication equipment and weapons, if necessar c. Conclusions Security equipment observed during the inspection functioned as designe S3 Security and Safeguards Procedures and Documentation Inspection Scooe (50001 and 81064)
'
The inspector reviewed selected procedures pertaining to the areas inspected and also reviewed appropriate logs, records, and other documents pertaining to security support for the Steam Generator Replacement Project. Emphasis was on security considerations associated with vital and protected area barriers that may be affected during the steam generator replacement projec Observations and Findinas Procedures reviewed were generally well written. Records reviewed sere complete and accurate. An unresolved item was identified while reviewing security procedures and documentatio b.1 Section 5.2.1.1 of the Braidwood Station Security Plan states that the vehicle barrier system (VBS) meets the requirements of 10 CFR 73.55(c)(7) and (8), and also commits to compensatory measures for degraded portions of the VBS equivalent to those identified in Nuclear Energy Institute (NEI) Document 96-01 " Guidelines For Operational '
Planning and Maintaining Integrity of Vehicle Barrier Systems (VBS)", dated February 199 The inspector's review of documentation of compensatory measures and interviews disclosed that adequate compensatory measures may not have been implemented
-
- _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _
when a portion of the VBS was degraded to allow protected area entry and exit of the steam generators. In both cases, the jersey barriers that make up part of the VBS were unpinned and left in that condition for periods up to four days. The licensee's Corporate Security Procedure (CNSG No. 4, Revision 1, " Operational Planning and Maintaining Integrity of Vehicle Barrier Systems", dated August 1996), allowed unpinned jersey barriers to be used for compensatory measure The jersey barriers in question were initially anchored (and an adequate VBS) and then unanchored for up to four days (which may have caused an inadequaie VBS) solely because of the licensee's actions (removing the anchor pins). The licensee's initial analysis of the VBS when installed concluded that the jersey barriers had to be anchored to be an effective VBS. While the jersey barriers were unanchored, the two fences and alarm system were in place and operational. Additionally, adequate security measures were implemented for the short period of time when the two perimeter gates were opened. Our concern is only the period of time there were no security officers present at the degraded portions of the VBS. The licensee's security staff believed the unpinned jersey barriers met compensatory measure guidance provided in NEl Document 96-01 as well as their own procedure We are unsure if the compensatory measures implemented are adequate, although they did comply with the licensee's procedure. It appears that adequate compensatory measures would have required more substantial barriers. Section 73.55(g)(1) of 10 CFR Part 73 requires that compensatory measures not reduce the effectiveness of the security system. Unanchored Jersey barriers may reduce the effectiveness of the VBS below the standard required by 10 CFR 73.55(c)(7).
The unresolved item is whether compensatory measures were required if the VBS degradation was the result of licensee preplanned actions which resulted in the VBS not meeting the criteria of 10 CFR 73.55(c)( 7), and an analysis showed that the barriers
, had to be anchored to be effective. This issue will be forwarded to NRC Headquarters for review, and resolution of the issue will be addressed by separate correspondence (URI 50-456/ 98017-01(DRS); 50-457/98017-01(DRS)). This issue is of safety significance because if inadequate compensatory measures were implemented, the VBS would have been ineffective in countering the design basis vehicle threat described in 10 CFR 73.1(a)(1)(iii). Conclusions Security proct duros reviewed were generally well written. Records reviewed were accurate and complete. An unresolved item was noted re!ating to the adequacy of I compensatory measures implemented for a section of the VB I S4 Security and Safeguards Staff Knowledge and Performance l a. -Inspection Scope (50001 and 81700)
The inspector toured various security posts, including the secondary alarm station and Main Access Facility, and the compensatory post for the Steam Generator Replacement
. .. .. ..
.
..
- - _ _ ____ __ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _
'
t Project. The inspector also observed performance of duties to determine if the security officers were knowledgeable of post requirements. Security event logs and other records pertaining to security force performance were also reviewe Observations and Findinas The overall security support for the steam generator replacement project was very goo Compensatory measures, except as noted earlier, were properly implemented. Four compensatory measures (three for containment access and one for outage related duties) were routinely used to support the SGRP. The support was provided without having to change shift schedules, or cancel scheduled vacations. The overtime (approximately 15%) for the security force was demanding, but managed well. There were only two occasions when a security officer exceeded 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in a seven day period, and both occasions were for only one hour. Five overtime deviations were approved for working more that 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in a 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> period (maximum period was 28 in 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />). Overtime deviations were dowmented. Security personnelinterviewed stated that they were not normally called in on scheduled days off for overtime. In spite of the demands, the security training section was able to fulfill training requirements for nine newly hired security officers and annual Appendix B (job task related)
requalification training for security personnel was able to be continue Loggable security events were not excessive, considering the number of contractors processed for the outage (2,300), which was indicative of a workforce aware of their security responsibilities. Inspector review of security events between September 5 and October 10,1998, showed approximately 26 unsecured door incidents, and 29 uncontrolled or lost security badge incident During observation of site ingress practices on October 15-16,1998, it was very evident that personnel entering the site were thoroughly familiar with ingress procedures, and security personnel adequately controlled the ingress process. Required physical searches of personnel were completed in an adequate manner. Hand carried items were searched when appropriate. Vehicle authorizations, escorts, and searches upon entering the protected area were completed in a controlled and thorough manne Interviews with the Station Security Administrator and contract security force manager disclosed that approximately 2,300 personnel were processed for unescorted access in preparation for the SGRP, and well over a hundred vehicle entries and exits were completed. During the week of the inspection approximately 1,600 personnel a day processed through the entry search equipment for protected area entry. All of these functions were completed in a relatively error-free manner. Security staffing levels for support of the SGRP were reviewed and determined to be adequate. The turnover rate for the past three months averaged about five security officer losses per mont Security officers checked on post had proper post orders and were knowledgeable of post responsibilities. Documentation reviewed was complete and accurat b.1 A violation was identified pertaining to three occasion between August 26 and October 2,1998, when security officers were determined by the licensee to be inattentive to duty (asleep) as described below:
_ _ _ _ .
__
.
Section 7.3.3 of the Braidwood Station Security Plan describes the compensatory measures to be implemented for an unlocked or unalarmed vital area door (Details are Safeguards Information).
!
Section 11.1 of the Braidwood Station Security Plan describes the number of guards that must be immediately available at all times for immediate response to security 1 contingencies (Details are Safeguards Information).
Contrary to the above, the licensee security staff discovered that on three occasions between August 26 and October 2,1998, security officers were found asleep on their post. On August 26,1998, compensatory measures required by Section 7.3.3 of the security plan for a vital area door were not effective because the security officer used for the compensatory measures was found asleep. On September 17,1998, the minimum number of guards required by Section 11.1 of the security plan to be available for immediate response for security contingencies was not available because a member of the armed response force was found asleep. On October 2,1998, compensatory measures for an opening in the recdor containment liner was not effective because the security officer posted to control access was found asleep (VIO 50-456/98017-02(DRS);
50-457/98017-02(DRS)). The security officers involved in the incidents had their employment terminate The inspector's review of the circumstances of the incidents concluded that excessive hours worked preceding the sleeping incidents was not a common factor. Interviews with the contract security force manager who conducted the followup investigations indicated that all of the personnel involved knew they were tired and thought if they could just set down and rest they would be able to continue their shift. The common thread between the three incidents was the individuals failure to use the assistance that they knew was availabl As a result of a similar violation cited in inspection Reports 50-456/97020; 50-457/
97020, dated January 7,1998, the licensee implemented a program called the " Stand and Call" program. The program in essence consisted of encouraging security officers to " stand" and " call" their supervisors if they felt fatigued. Once advised, the supervisor assumed the responsibility to assist the individual, in whatever way possible and necessary, to be able to finish the tour of duty, or be relieved from the security post or tour of duty. All of the personnelinvolved in the three sleeping incidents had signed an i attendance sheet that they had been trained on the " Stand and Call" progra I interviews with the contract security force manager also disclosed that on 21 occasions in 1998, security officers had used the program and assistance was provided to j personnel to include relieving them from duty in some cases and allowing them to sleep, '
providing transportation to their off site residence, supervisors remaining on post with the person, changing post assignment, and other actions the supervisors felt were necessary. Penalties or discipline were not imposed for actions taken under the " Stand and Call" program. The " Stand and Call" program was publicized on some bulletin boards in the security area. Every security officer questioned about the program by the i inspector knew the elements of the program and believed that they would get assistance l if they used the program. The officero also stated that they would use the program if ;
'
I
'
.
they felt the need for assistance to remain awake, particularly since the three security officers employment was terminated for sleeping on pos After the second incident of inattentive duty (steeping) by a security officer, the licensee security staff and contract security force manager conducted meetings on September 17 and 18,1998, to re-emphasize the elements of the " Stand and Call" program and commit their support to the program to eliminate incidents of inattentivenes The " Stand and Call" program implemented by security management can prevent further occurrence of sleeping on duty if the security personnel use the assistance availabl In the inspector's judgement, the licensee security staff and contract security manager are committed to the program and the program has been used 21 times by security force members. Therefore, additional corrective actions for this violation do not appear necessar Conclusions A violation was identified for three occasions when security officers were determined by the licensee security staff to be inattentive to duty (asleep). Security force members observed on post were knowledgeable of post requirements and performed their duties in an adequate manner. Security force support was well managed and, based upon the number of security reportable events, the plant population demonstrated a high level of awareness and compliance with security requirement S8 Miscellaneous Security and Safeguards issues The Nuclear Generation Group Corporate Security (NGGCS) Fitness-For-Duty (FFD) l staff advised NRC Region lli that they suspected that some contractor personnel were i adulterating their FFD test specimens to mask the presence of prohibited substance l This suspicion was based on an analysis of presumptive positive tests that subsequently were reported to be negative by the laboratory that completed followup testing. The NGGCS staff was continuing their inquiry into the matter. Because of the sensitive nature of the issue, and the fact that an ongoing investigation is in progress, other information such as the method of adulteration, and methods of detection and actions will not be addressed in detail in this report. NRC Region Ill will monitor the licensee's investigation conclusions and corrective actions implemented as a result of the investigation (IFl 50-456/98017-03(DRS); 50-457/98017-03(DRS)).
X1 Exit Meeting Summary The inspector presented the onsite inspection results to members of the licensee management on October 19,1998. The licensee management representatives acknowledged the findings presented. The inspector asked the licensee if any inspection findings discussed during the exit meeting should be considered as proprietary or safeguards information. No proprietary or safeguards information was identifie PARTIAL LIST OF PERSONS CONTACTED Licensee:
T. Tulon, Site Vice President ;
G. Baker, Station Security Administrator '
M. Cassidy, NRC Coordinator D. Cecchett, Lead Licensing Engineer )
R. Davis, Training Coordinator, Burns International Security Services, Ins (BISSI)
G. Groth, SGRP Project Manager i T. Hakey, Security Shift Supervisor, BISSI l J. Lamb, Trainer, BISSI '
R. Lane, Nuclear Generation Group Security Director l J. Nalewajka, Assessment Manager M. Riegel, Nuclear Oversight Manager ,
D. Turner, Assistant Station Security Administrator l D. Walker, Security Force Manager, BISSI H. Walker, Administration coordinator, BISSI K. Zohner, Administration Assistant, BISSI NRC C. Phillips, Senior Resident inspector INSPECTION PROCEDURES USED IP 50001 Steam Generator Replacement inspection IP 81064 Compensatory Measures IP 81700 Physical Security Program For Power Reactors ITEMS OPENED AND CLOSED Opened 50-456/98017-01 URI Compensatory Measures For a Degraded Portion of The Vehicle Barrier System 50-457/98017-01 URI Compensatory Measures For a Degraded Portion of The Vehicle Barrier System 50-456/98017-02 VIO Security Officers Were Determined to Be Asleep on Three Occasions Between August 26 and October 2,1998 50-457/98017-02 VIO Security Officers Were Determined to Be Asleep on Three Occasions Between August 26 and October 2,1998 50-456/98017-03 IFl Fitness-For-Duty Test Specimens May Have Been Altered
- . .. - - _ _ _ _ _ _ _ - _ _ - _ _ - _ - _ - _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ - _ _ _ - _ _ _ _ _ _
~ -
..
50-457/98017-03 IFl Fitness-For-Duty Test Specimens May Have Been Altered Closed 50-456/98017-02 VIO Security Officers Were Determined to Be Asleep on Three Occasions Between August 26 and October 2,1998 50-457/98017-02 VIO Security Officers Were Determined to Be Asleep on Three Occasions Between August 26 and October 2,1998
9
'
_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ .
. - _ , _ . . _ . . . . _ . ~ . _ _ . _ . _. ..- . _ _ _ _ . _ . . - _ ..__. _ .-.. ,
!
l
..
E LIST OF ACRONYMS USED ,
BISSI Burns international Security Services, In .
CNSG Corporate Nuclear Security Guidelines FFD Fitness For Duty IFl inspection Followup Item MAF Main Access Facility ' i URI Unresolved item :
'
SAS Secondary Alarm Station SGRP Steam Generator Replacement Project VIO Violation VBS Vehicle Barrier System
i
!
)
i
l l
10
<
'
-
m ,
,
PARTIAL LISTING OF DOCUMENTS REVIEWED Procedure CNSG 100, "X-Ray Searches" Revision 3, October 1997 Procedure CNSG 102, " Personnel Search / ingress", Revision 4, October 1998 Procedure CNSG 107, " Maintaining Search Integrity Between Stations", Revision 1, March 1998
,
Procedure CNSG 4, " Operational Planning and Maintaining Integrity of Vehicle Barrier Systems
'
(VBS)", Revision 2, Ncvember 199 Training Files for Nine Recently Hired Security Officers Braidwood Security Investigation Report No. SEP/98/02 (Security Officer inattentive issue) i Braidwood Security Investigation Report No. AUG/98/02 (Security Officer Inattentive issue)
Contractor Security Reports From July 1998 to September 1998 ;
Comed Nuclear Generating Group Contract Security Turnover Ratio For Braidwood From !
January Through September 1998 Problem Identification Form A1998-0551, " Alleged Inattentiveness to Duty", dated October 2, 1998
- Attention to Duty- Stand and Call" Handout, dated December 1997 l
BISSI incident Report No. 036498, " inattentive Concern", dated October 2,1998 l l
BISSI " Weekly Hours" From September 3,1998 through October 8,1998 Procedure BwAP 100-7, " Overtime Guidelines For Station Personnel", Revision 7
" Overtime Deviation Authorizations" For Security Between September 1 and October 2,1998 Four " Security Special Area Posting" for Four SGRP Security Posts Braidwood Station Security Event Log For Period Between July 1 and September 30,1998 Self Assessment Report, " Security's Ingress Search Process", July 6-14,1998 )
> .
i i
11 *
,, O. Kingsley -3-
'
Distribution:
SAR (E-Mail)
RPC (E-Mail)
Project Mgr., NRR w/encls ;
J. Caldwell, Rlli w/encls ,
C. Pederson, Rlli w/encls -
B. Clayton, Rill w/encis ,
SRI Braidwood w/encls ,
DRP w/encls
. TSS w/encls DRS (2) w/encls Rill PRR w/encls ,
O PUBLIC IE-01 w/encis ;
Docket File w/encls l GREENS :
IEO (E-Mail)
DOCDESK (E-Mail)
, l
i 4
, .
t
.
l .-
!
,
P W
E i
! !
'
l
.
I i
- l c .
I i
l
! ; ,
,