Forwards Amends 125 & 119 to Licenses NPF-2 & NPF-8, Respectively & Se.Amends Revises TS to Incorporate Latest Revised Topical Repts Governing Installation of Laser Welded Steam Generator Tube Sleeves
ML20137E276
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 03/24/1997
From: Jacob Zimmerman
NRC (Affiliation Not Assigned)
To: Dennis Morey
SOUTHERN NUCLEAR OPERATING CO.
Shared Package
ML20137E281 List:
References
TAC-M97699, TAC-M97700, NUDOCS 9703270139
Download: ML20137E276 (4)


Text

H . D! N. Moray March 24,1997 V ce Presid:nt - Farley Project-Southern Nuclear Operating Company, Inc.

Post Office Box 1295 Birmingham, Alabama 35201-1295

SUBJECT:

ISSUANCE OF AMENDMENTS - JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 (TAC NOS. M97699 and M97700) l

Dear Mr. Morey:

The Nuclear Regulatory Commission has issued the enclosed Amendment No.125 i to Facility Operating Licensa No. NPF-2 and Amendment No.119 to Facility I Operating License No. NPF-8 for the Joseph M. Farley Nuclear Plant, Units 1 and 2. The amendments change the Technical Specifications (TS) in response to your submittal dated January 10, 1997, as supplemented by letter dated February 24, 1997.

The amendments revise the TS to incorporate the latest revised topical reports '

governing the installation of laser welded steam generator tube sleeves. In addition, an administrative change for Unit 2 revises the TS by deleting the reference to a one-cycle implementation of L*, which expired at the last  !

Unit 2 outage.  ;

A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commission's biweekly Federal Reaister notico.

l Sincerely, ORIGINAL SIGNED BY:

Jacob I. Zimmerman, Project Manager '

Project Directorate II-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364

Enclosures:

1. Amer.dment No.125 to NPF-2 I
2. Amendment No.119 to NPF-8
3. Safety Evaluation I }

cc w/encls: See next page DISTRIBUTION:

-2 a G. Hill (4) ACRS C. Grimes,TSB OGC J. Johnson,RII P. Skinner,RII e-mail TLH3 SE only DOCUMENT NAME: G:\FARLEY\M97699.AMD p#lH s@M , . .e OFFICE P0ll 2/h PDI!-2/LAh EMCB b OGC[k r PD22/D NAME J N:en L. BERRY -

TSULLIVAN i II Th(*] H. BERK 0W / c/

l DATE I 97/ /97 10 /97 /2 0 /97 3fIA /97 COPY YES No $\ No YES h) YES h~

YES(No)

~

0FFICIAL RECORD COPY 7ggg-PDR ADOCK 05000348 P PDR

,Nr. D, N. Mo.ey March 24, 1997 l Vice Presid:nt - Farley Project l S:uthern Nuclear Operating Company, Inc.

Post Office Box 1295 Birmingham, Alabama 35201-1295

SUBJECT:

. ISSUANCE OF AMENDMENTS - JOSEPH M. FARLEY NUCLEAR PLANT,

UNITS 1 AND 2 (TAC NOS. M97699 and M97700)

I

Dear Mr. Morey:

The Nu: lear Regulatory Commission has issued the enclosed Amendment No.125 to Facility Operating License No. NPF-2 and Amndment No.119 to Facility Operating License No. NPF-8 for the Joseph M. Farley Nuclear Plant, Units 1 1 and 2. The amendments change the Technical Specifications (TS) in response to  :

your submittal dated January 10, 1997, as supplemented by letter dated j February 24, 1997. '

The amendments revise the TS to incorporate the latest revised topical reports governing the installation of laser welded steam generator tube sleeves. In ,

addition, an administrative change for Unit 2 revises the TS by deleting the

. reference to a one-cycle implementation of L*, which expired at the last Unit 2 outage.

l A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commission's biweekly Federal Reaister i notice.

Sincerely, ORIGINAL SIGNED BY:

Jacob I. Zimmerman, Project Manager i Project Directorate 11-2 Division of Reactor Projects - I/II i Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364 J

Enclosures:

1. Amendment No.125 to NPF-2 3 2. Amendment No.119 to NPF-8 j 3. Safety Evaluation
cc w/encls: See next page

! DISTRIBUTION:

Docket File PUBLIC PDII-2 RF S.Varga G. Hill (4) ACRS C. Grimes,TSB OGC J. Johnson,RII P. Skinner,RII e-mail TLH3 SE only DOCUMENT NAME: G:\FARLEY\M97699.AMD f)f/N 9'/O 3 , ,f' o m es een reder non-rite (s siscs 6 dWTO "o22io . ,d p

me 4 M uren t.seur M inutum M /d%v4 n.sr uow % i om 4D i,r  % i,r M ,o i,r v&a o 'i,r 3Ia ,,r co,, vs. o Ga ,,o vs. s; 've, e u. C

- ~

OFFICIAL RECORD COPY

I e

W "4 4 UNITED STATES

< E NUCLEAR REGULATORY COMMISSION f WASHINGTON, D.C. 20066-0001

% , , , g +* March 24, 1997 Mr. D. N. Morey Vice President - Farley Project Southern Nuclear Operating Company, Inc.

Post Office Box 1295 Birmingham, Alabama 35201-1295

SUBJECT:

ISSUANCE OF AMENDMENTS - JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 (TAC NOS. M97699 and M97700)

Dear Mr. Morey:

The Nuclear Regulatory Commission has issued the enclosed Amendment No.125 to Facility Operating License No. NPF-2 and Amendment No.119 to Facility Operating License ho. NPF-8 for the Joseph M. Farley Nuclear Plant, Units 1 and 2. The amendments change the Technical Specifications (TS) in response to your submittal dated January 10, 1997, as supplemented by letter dated February 24, 1997.

The amendments revise the TS to incorporate the latest revised topical reports governing the installation of laser welded steem generator tube sleeves. In addition, an administrative change for Unit 2 revises the TS by deleting the reference to a one-cycle implementation of L*, which expired at the last Unit 2 outage.

A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commission's biweekly Federal Reaister notice.

Sincerely,

_ Jacob Wl

/ I. Zimmerman, Project Manager Project Directorate II-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364

Enclosures:

1. Amendment No.125 to NPF-2
2. Amendment No.119 to NPF-8
3. Safety Evaluation cc w/encls: See next page

Southern Nuclear Operating Company Joseph M. Farley Nuclear Plant cc:

Mr. R. D. Hill, Jr.

General Manager -

Southern Nuclear Operating Company  !

Post Office Box 470 l Ashford, Alabama 36312 )

l Mr. Mark Ajlunt, Licensing Manager  !

l Southern Nuclear Operating Company l Post Office Box 1295 i Birmingham, Alabama 35201-1295 '

Mr. M. Stanford Blanton Balch and Bingham Law Firm j Post Office Box 306 l 1710 Sixth Avenue North l Birmingham, Alabama 35201 Mr. J. D. Woodard Executive Vice President Southern Nuclear Operating Company l Post Office Box 1295 Birmingham, Alabama 35201  !

State Health Officer Alabama Department of Public Health l 434 Monroe Street Montgomery, Alabama 36130-1701 Chairman Houston County Commission Post Office Box 6406 Dothan, Alabama 36302 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, NW., Suite 2900 i Atlanta, Georgia 30323 i Resident Inspector U.S. Nuclear Regulatory Commission 7388 N. State Highway 95 Columbia, Alabama 36319 l

l