Forwards 831014 Press Release, Officially Announcing Cancellation of Facility.Util Will Meet W/Nrc to Discuss Impact of Cancellation of Unit 2 on Licensing of Unit 1
ML20113D096
Person / Time
Site: Clinton  Constellation icon.png
Issue date: 10/18/1983
From: Fox C
SCHIFF, HARDIN & WAITE
To: Clark H, Ferguson G, Paris O
Atomic Safety and Licensing Board Panel
Shared Package
ML20113D074 List:
References
OL, NUDOCS 8504120261
Download: ML20113D096 (2)


Text

,

SCHIFF HARDIN 0WAITE A PwwerwNo kuS*g N caperskre

  • ei$MINGTON OFDCE:

7200 SearsTower. Chicago.ittinois 60606 1101 Conne cticut Ave nue. N.W We shington. D.C. 20036 Telephone (312) 8761000 Twx 910-2212463 Telephone (202)857 0600 Telex SHW64590 October 18, 1983 FEDERAL EXPRESS .

Hugh K. Clark, Esq., Chairman Administrative Judge P. O. Box 127A Kennedyville, Maryland 21645 Dr. George A. Ferguson Administrative Judge School of Engineering Howard University 2300 Sixth Street, N.W.

Washington, D.C. '20059 Dr. Oscar H. Paris Administrative Judge Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Wash'ington, D.C. 20555 Re: Illinois Power Company -

Clinton Power Station, Unit 1 50-461 OL

Dear Judge Clark,

Judge Ferguson, and Judge Paris:

Enclosed is a copy of a Press Release of October 14, 1983 in which Illinois Power Company officially announced the cancellation of Unit 2 of the Clinton Power Station. Illinois Power Company will meet with the Nuclear Regulatory Commission Staff in the near future to discuss the impact of the cancella-tion of Unit 2 on the licensing of Unit 1.

Please do not hesitate to contact me if you have any questions. We will, of course, keep the Board fully informed on all future developments with respect to the cancellation of Unit 2.

L Very truly yours, Charles D. Fox IV CDF:kb -

Enclosure I cc: Prairie Alliance Jean Foy

! Richard J. Goddard Philip L. Willman Willie.m F. Patterson, Jr. Allen Samelson 8504120261 G50409

$DR ADOCK 05000462 PDR

,. =

ILUN0lB FOR IMMEDIATE RELEASE I NEWS RELEASE For further information contact:

Al Adams (217) 424-6400 POWER DECATUR, IL., October 14, 1983 -- Illinois Power Company today officially announced the cancellation of Unit 2 at the Clinton nuclear power station.

The company has not perform'ed any additional work toward completion of Clinton 2 since 1977. Negotiations are now underway to cancel contracts pertaining to completion of Unit 2.

The present investment in work completed, plus cancellation costs for Unit 2, on a net after-tax cost to Illinois Power Company is estimated to be between $16 million and S22 million. The company intends to seek approval to amortize these costs over a period of years.

In announcing the cancellation the company cited the fact that its projected sales of electricity indicate that no replacement or additional generating unit's will be needed after Clinton Unit 1 comes on line until sometime in the 1990s.

Clinton Unit 1 is now 81 percent complete with commercial operation scheduled for 1986.