ML20096D719

From kanterella
Jump to navigation Jump to search
Forwards Dp Hall Requesting Extension of CP Until 861001,for Info of ASLB & Parties.Related Correspondence
ML20096D719
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/29/1984
From: Fox C
ILLINOIS POWER CO., SCHIFF, HARDIN & WAITE
To: Clark H, Ferguson G, Paris O
Atomic Safety and Licensing Board Panel
References
OL, NUDOCS 8409060260
Download: ML20096D719 (5)


Text

'BO A . . .

0,J t- SCHIFF'HARDIN & WAITE -

.c ' ~ m~72 ,,

WA$HiNGTON OFFICE:

-i . ~ 7200 SearsTower. Chicago.Ilhnois 80606 1101 Connecticut Avenue.N W.. Washington D.C 20036 Telephone (312) 8761000 Twa 910 2212463 Telephone (2021857-0600 Telen SHW64590 August 29,-1984

.w nq.

~Mr. Hugh K. Clark, Esq., Chairman-P.O.< Box 127A .L,

, Kennedyville, Maryland .

21645 Sr., 4 Pd :54

Dr. George A. Ferguson School,of Engineering '

s.

Howard University. ~

2300 Sixth Street, N.W.

Washington, D.C. 20059 Dr. Oscar H. Paris Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission

' Washington, D.C. 20555 Re s . Illinois Power Company -- Clinton Power Station Docket No. 50-461 OL Gentlemen

' Attached is a copy of a letter, dated August 22, 1984, from Donald P. Hall, Vice President, Illinois Power Company

to Dr. Harold R. Denton, Director, Office of Nuclear Reactor Regulation,.USNRC, requesting an extension of the construction permit for the Clinton Power Station to October 1, 1986. We are providing this to you, and to the other parties in the licensing proceeding, as part of our effort to keep you informed of all significant developments which may.' affect licensing. .

Please do not hesitate to contact me if.you have any questions' .

with respect to'this. i very truly yours, i

Charles D. Fox IV CDF:ja cc w/ encl.: Secretary of the Commission #

Executive Legal Director ,

Allen J. Samelson, Illinois Assistant Attorney General t Jean Foy, Prairie Alliance j Richard L. Goddard, Office of the Executive Legal Director Fred'W. Christiansen, USNRC Resident Office Atomic Safety and Licensing Board Panel l Atomic Safety and Licensing Appeal Board Panel e  ; .bEOS 4

~

, b728 L20-84 ( 08-22)<-L 0982-L

/LLIN0/S POWER COMPANY CLINToN Powtft 51AtioN. P.o. 80s 678 CLINToN. tLLINol$ (1727 August 22, 1984 Docket No. 50-461 -

Dr. Harold R. Denton, Director 54 50 Office of Nuclear Reactor Regulation -4 Edl34, ,

U. S. Nuclear Regulatory Commission Washington, D.C. 20555 e .v ; .

Subject:

Clinton Power Station Unit 1 Extension of Construction Permit No. CPPR-137

Dear Dr. Denton:

In letters U-0286, dated August 31, 1981, and U-0467, dated April 23, 1982, Illinois Power Company (IP) requested that the latest date for completion of construction of Clinton Power Station (CPS), as specified in Construction Permit No. CPPR-137, be extended from October 1, 1981 to October 1, 1984. The Nuclear Regulatory Commission (NRC) granted this request on June 7, 1982. (See 47 Fed. Reg. 28185, June 29, 1962.) IP, on behalf of itself and as agent for Soyland Power Cooperative Inc.,

and Western Illinois Power Cooperative, Inc., hereby requests that the latest date for completion of construction of CPS be further extended to October 1, 1986.

10 CFR 50.55(a) of the Commission's regulations states that each constructor shall state the earliest and latest date for completion of construction. As we informed you in letter 0982-L dated May 24, 1983, IP has revised its fuel load date from January 1984 to January 1986.

Nevertheless, to allow for unexpected contingencies. IP is requesting that the latest completion date be extended to October 1, 1986 pursuant to 10 CFR 50.55(b).

The following factors constitute the basis for extension of the latest completion date:

1. In 1982 IP initiated a series of stop work orders and recovery programs to implement corrective action and improve ,

construction programs for several areas of construction.

2. In1982,IPalsoinitiatedanOverinspectionPro$ramand Record Verification Program to verify the quality of construction of large portions of CPS.

The time required to lift the stop work orders and complete the recovery programs, Overinspection Program, and the Record Verification Program was not accounted for in IP's previous request for an extension of the l

]

-0728 b

  • L20-84(08-22)-L construction permit for CPS to October 1, 1984. Since the purpose of

- these programs is to' ensure the protection of the public health and safety, these programs constitute good cause for the extension of the latest completion date to October 1 1986.

As required by 10 CFR 170.21, our check for $150 is enclosed to cover the filing fee for this application for amendment to the

- construction permit for CPS.

Finally..IP notes that the.NRC has not acted on proposed amendments to Section 3E of Construction ~ Permit No. CPPR-137 which were requested in the aforementioned letter U-0286, as modified by letter U-0445, dated March 29, 1982, from IP to the NRC. Your prompt consideration of this request would be appreciated.

y a relv yours, D. P. Hall Vice President -

SPF/lm Attachment - Notarization ec: See Attached Distribution List

u

- -0728 L20-84(08-22)-L STATE OF ILLINOIS -

COUNTY OF De Witt DONALD P. HALL, Being first duly sworn, deposes and says:

That he is Vice President of Illinois Power Company; that the foregoing request for an extension of the latest completion date has been prepared under his supervision and direction; that he knows the contents thereof; and that to the best of his knowledge and belief said request and the facts contained therein are true and correct.

d DATED: This alI2 a day of August, 1984 Signed:

Donald P. Hall Subscribed and sworn to before me this m%A day of August, 1984.

e4 U[r'. LL [ -/S*M n_

Notary Public My c'omnission expires:

l'otdei t 19 SL-

~

.~ .

. 0728 L20-84(08-22)-L

.r 0982-L Distribution List c

.e.,.

Dr. Harold R. Denton, Director A. Samelson, Esq.

Office of Nuclear Reactor Regulation Assistant Attorney dsderalp g U. S. Nuclear Regulatory Commission ~ Environmental Control Divlsion E A !54 Washington, D.C. 20555 Southern Region 500 South Second Street ec: J. G. Kappler Springfield.. Illinois 61(0}6 En Regional. Administrator Region III J. Foy U. S. Nuclear Regulatory Commission Spokesperson, Prairie Alliance 799 Roosevelt Road 511 W. Nevada Glen Ellyn, Illinois 60137 Urbana, Illinois 61801 B. L. Siegel H. K. Clark, Esq.

Clinton Licensing Project Manager Chairman, Atomic Safety and Mail Code 416 Licensing Board U. S. Nuclear Regulatory Commission P. O. Box 127A Washington, D.C. 20555 Kennedyville, Maryland 21645 F. Christianson Dr. O. H. Paris Mail Code V-690 Atomic Safety and Licensing Board NRC Resident _ Office U. S. Nuclear Regulatory Commission Clinton Power Station Washington, D.C. 20555 R. R. #3, Box 228 Clinton, Illinois 61727 Dr. G. A. Ferguson Atonic Safety and Licensing Board Dr. D. Etchison School of Engineering Director, Illinois Department Howard University of Nuclear Safety 2300 Sixth Street, N.W.

1035 Outer _ Park Drive Washington, D.C. 2005C Springfield, Illinois 62704 R. J. Goddard,<Esq.

Office of the Legal Director U. S. Nuclear Regulatory Commission Washington, D.C. 20555

)

.