Inspection/Activity Plan for 03/01/2003 - 03/30/2004
ML030660199
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/03/2003
From: Joel Munday
NRC/RGN-II/DRP/RPB3
To: Stall J
Florida Power & Light Co
Shared Package
ML030660199 List:
References
IR-03-001
Download: ML030660199 (3)


Text

Page 1 of 3 Turkey Point 02/20/2003 14:51:42 Inspection / Activity Plan Report 22 03/01/2003 - 03/30/2004 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB2-ISI - INSERVICE INSPECTION-U3 1 3 IP 7111108P Inservice Inspection Activities - PWR 03/03/2003 03/07/2003 Baseline Inspections Comments:

2515/150 - 2515/150 REV 1 UNIT 3 1 3 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-0 03/05/2003 03/07/2003 Safety Issues Comments:

S/G-ISI - S/G INSERVICE INSPECTION-U3 1 3 IP 7111108P Inservice Inspection Activities - PWR 03/10/2003 03/12/2003 Baseline Inspections Comments:

PS-SEC - SECURITY - TI/ICM 3 3, 4 IP 2515/148 Inspection of Nuclear Reactor Safeguards - Interim Compensatory Measures 03/31/2003 04/04/2003 Safety Issues Comments:

PS-RP - RADIATION PROTECTION 3 3, 4 IP 7112101 Access Control to Radiologically Significant Areas 10/06/2003 10/10/2003 Baseline Inspections 3, 4 IP 7112102 ALARA Planning and Controls 10/06/2003 10/10/2003 Baseline Inspections 3, 4 IP 7112202 Radioactive Material Processing and Transportation 10/06/2003 10/10/2003 Baseline Inspections 3, 4 IP 71151 Performance Indicator Verification 10/06/2003 10/10/2003 Baseline Inspections Comments:

EB2-ISI - INSERVICE INSPECTION-U4 1 4 IP 7111108P Inservice Inspection Activities - PWR 10/13/2003 10/17/2003 Baseline Inspections Comments:

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 3 Turkey Point 02/20/2003 14:51:42 Inspection / Activity Plan Report 22 03/01/2003 - 03/30/2004 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 2515/150 - 2515/150 REV 1 UNIT 4 1 4 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-0 10/13/2003 10/17/2003 Safety Issues Comments:

S/G-ISI - S/G INSERVICE INSPECTION-U4 1 4 IP 7111108P Inservice Inspection Activities - PWR 10/20/2003 10/22/2003 Baseline Inspections Comments:

PS-RP - RADIATION PROTECTION 2 3, 4 IP 7112101 Access Control to Radiologically Significant Areas 10/20/2003 10/24/2003 Baseline Inspections 3, 4 IP 7112102 ALARA Planning and Controls 10/20/2003 10/24/2003 Baseline Inspections 3, 4 IP 7112202 Radioactive Material Processing and Transportation 10/20/2003 10/24/2003 Baseline Inspections 3, 4 IP 71151 Performance Indicator Verification 10/20/2003 10/24/2003 Baseline Inspections Comments:

OL PREP - INITIAL EXAM PREP 2 3 V23209 TURKEY POINT/EXAMS AT POWER FACILITIES 11/03/2003 11/07/2003 Not Applicable Comments:

EB2-HS - HEAT SINK 1 3, 4 IP 7111107B Heat Sink Performance 12/08/2003 12/12/2003 Baseline Inspections Comments:

OL EXAM - INITIAL EXAM 2 3 V23209 TURKEY POINT/EXAMS AT POWER FACILITIES 12/08/2003 12/19/2003 Not Applicable Comments:

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 3 of 3 Turkey Point 02/20/2003 14:51:42 Inspection / Activity Plan Report 22 03/01/2003 - 03/30/2004 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB1FP - TFP PRE-INSPECTION VISIT 4 3, 4 IP 7111105T Fire Protection 01/04/2004 01/09/2004 Baseline Inspections Comments:

OL EP - EP INSPECTION 2 3, 4 IP 7111402 Alert and Notification System Testing 01/26/2004 01/30/2004 Baseline Inspections 3, 4 IP 7111403 Emergency Response Organization Augmentation Testing 01/26/2004 01/30/2004 Baseline Inspections 3, 4 IP 7111404 Emergency Action Level and Emergency Plan Changes 01/26/2004 01/30/2004 Baseline Inspections 3, 4 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 01/26/2004 01/30/2004 Baseline Inspections 3, 4 IP 71151 Performance Indicator Verification 01/26/2004 01/30/2004 Baseline Inspections Comments:

OL RQ - REQUAL INSPECTION 2 3, 4 IP 7111111B Licensed Operator Requalification 01/26/2004 01/30/2004 Baseline Inspections Comments:

EB1-FP - TRIENNIAL FIRE PROTECTION 4 3, 4 IP 7111105T Fire Protection 01/26/2004 01/30/2004 Baseline Inspections 3, 4 IP 7111105T Fire Protection 02/09/2004 02/13/2004 Baseline Inspections Comments:

EB2-MR - MAINTENANCE RULE 1 3, 4 IP 7111112B Maintenance Effectiveness 02/23/2004 02/27/2004 Baseline Inspections Comments:

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.