Turkey Point Inspection / Activity Plan 09/01/2007 - 03/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/31/2007 10:51:57 Report 22 2
EB3-ISI
- U3 INSERVICE INSPECTION Baseline Inspections 09/10/2007 09/14/2007 3
7111108P IP Inservice Inspection Activities - PWR 3
PSB1-RP
- RP OCCUPATIONAL BASELINE INSP WK1 Baseline Inspections 09/10/2007 09/14/2007 3, 4 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 09/10/2007 09/14/2007 3, 4 7112102 IP ALARA Planning and Controls Baseline Inspections 09/10/2007 09/14/2007 3, 4 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 09/10/2007 09/14/2007 3, 4 71151 IP Performance Indicator Verification 2
EB3SGISI
- U3 STEAM GENERATOR ISI Baseline Inspections 09/17/2007 09/21/2007 3
7111108P IP Inservice Inspection Activities - PWR 2
EB1-SUMP
- PWR CONTAINMENT SUMP BLOCKAGE TI (U-3)
Safety Issues 09/24/2007 09/28/2007 3
2515/166 IP Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02]
2 PSB1-RP
- RP OCCUPATIONAL BASELINE INSP WK2 Baseline Inspections 09/24/2007 09/28/2007 3, 4 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 09/24/2007 09/28/2007 3, 4 7112102 IP ALARA Planning and Controls Baseline Inspections 09/24/2007 09/28/2007 3, 4 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 09/24/2007 09/28/2007 3, 4 71151 IP Performance Indicator Verification 4
PIR-FU
- PROBELM IDENTIFICATION & RESOLUTION FU Baseline Inspections 12/10/2007 12/14/2007 3, 4 71152 IP Identification and Resolution of Problems 1
PSB1-RP
- RADIATION PROTECTION PREINSPECTION VISIT Baseline Inspections 01/07/2008 01/09/2008 3, 4 7112101 IP Access Control to Radiologically Significant Areas 3
- REQUALIFICATION INSPECTION Baseline Inspections 01/14/2008 01/18/2008 3, 4 7111111B IP Licensed Operator Requalification Program 4
PSB1-RP
- RADIATION PROTECTION PUBLIC BASELINE Baseline Inspections 01/28/2008 02/01/2008 3, 4 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 01/28/2008 02/01/2008 3, 4 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 01/28/2008 02/01/2008 3, 4 7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems Baseline Inspections 01/28/2008 02/01/2008 3, 4 7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P Baseline Inspections 01/28/2008 02/01/2008 3, 4 71151-OR01 IP Occupational Exposure Control Effectiveness Baseline Inspections 01/28/2008 02/01/2008 3, 4 71151-PR01 IP RETS/ODCM Radiological Effluent 1
PSB1-EP
- EP INSP Baseline Inspections 02/25/2008 02/29/2008 3, 4 7111402 IP Alert and Notification System Testing Baseline Inspections 02/25/2008 02/29/2008 3, 4 7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 02/25/2008 02/29/2008 3, 4 7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 02/25/2008 02/29/2008 3, 4 7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 02/25/2008 02/29/2008 3, 4 71151-EP01 IP Drill/Exercise Performance This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Turkey Point Inspection / Activity Plan 09/01/2007 - 03/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/31/2007 10:51:57 Report 22 1
PSB1-EP
- EP INSP Baseline Inspections 02/25/2008 02/29/2008 3, 4 71151-EP02 IP ERO Drill Participation Baseline Inspections 02/25/2008 02/29/2008 3, 4 71151-EP03 IP Alert & Notification System 1
EB1-SUMP
- TI 2515/166 CONTAINMENT SUMP INSPECTION Safety Issues 05/05/2008 05/09/2008 4
2515/166 IP Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02]
1 EB3-ISI
- U4 INSERVICE INSPECTION Baseline Inspections 05/05/2008 05/09/2008 4
7111108P IP Inservice Inspection Activities - PWR 1
EB3SGISI
- U4 SG ISI Baseline Inspections 05/12/2008 05/16/2008 4
7111108P IP Inservice Inspection Activities - PWR 9
EB1-CDBI
- COMPONENT DESIGN BASIS INSPECTION Baseline Inspections 08/25/2008 08/29/2008 3, 4 7111121 IP Component Design Bases Inspection Baseline Inspections 09/08/2008 09/12/2008 3, 4 7111121 IP Component Design Bases Inspection Baseline Inspections 09/22/2008 09/26/2008 3, 4 7111121 IP Component Design Bases Inspection Baseline Inspections 09/29/2008 10/03/2008 3, 4 7111121 IP Component Design Bases Inspection 1
- PREP TRIP-PROBLEM ID AND RESOL Baseline Inspections 09/22/2008 09/26/2008 3, 4 71152B IP Identification and Resolution of Problems 4
- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 11/03/2008 11/07/2008 3, 4 71152B IP Identification and Resolution of Problems Baseline Inspections 11/17/2008 11/21/2008 3, 4 71152B IP Identification and Resolution of Problems 4
EB1-MODS
- MODIFICATIONS - 10CFR50.59 Baseline Inspections 01/12/2009 01/16/2009 3, 4 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 01/12/2009 01/16/2009 3, 4 7111117B IP Permanent Plant Modifications 3
OL EXAM
- INITIAL EXAM PREP Not Applicable 02/09/2009 02/13/2009 3
V23299 TURKEY POINT/FEBRUARY 2009 EXAM AT POWER FACILITIES 3
PSB1-EP
- EP EXERCISE Baseline Inspections 02/16/2009 02/20/2009 3, 4 7111401 IP Exercise Evaluation Baseline Inspections 02/16/2009 02/20/2009 3, 4 7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 02/16/2009 02/20/2009 3, 4 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 02/16/2009 02/20/2009 3, 4 71151-EP02 IP ERO Drill Participation Baseline Inspections 02/16/2009 02/20/2009 3, 4 71151-EP03 IP Alert & Notification System 3
OL EXAM
- INITIAL EXAM Not Applicable 02/23/2009 03/06/2009 3
V23299 TURKEY POINT/FEBRUARY 2009 EXAM AT POWER FACILITIES This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.