ML062970074

From kanterella
Revision as of 00:37, 23 March 2020 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

NRC Generic Letter 2006-01, Steam Generator Tube Integrity and Associated Technical Specifications
ML062970074
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 11/14/2006
From: Kalyanam N
NRC/NRR/ADRO/DORL/LPLIV
To: Rosenblum R
Southern California Edison Co
Kalynanam N, NRR/DORL/LP4, 415-1480
References
GL-06-001, TAC MD0107, TAC MD0108
Download: ML062970074 (5)


Text

November 14, 2006 Mr. Richard M. Rosenblum Senior Vice President and Chief Nuclear Officer Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128

SUBJECT:

SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 -

U.S. NUCLEAR REGULATORY COMMISSION GENERIC LETTER 2006-01, STEAM GENERATOR TUBE INTEGRITY AND ASSOCIATED TECHNICAL SPECIFICATIONS (TAC NOS. MD0107 AND MD0108)

Dear Mr. Rosenblum:

On January 20, 2006, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2006-01, Steam Generator [SG] Tube Integrity and Associated Technical Specifications

[TSs] (Agencywide Document Access and Management System (ADAMS) Accession No. ML060200385). This GL requested that addressees either submit a description of their program for ensuring SG tube integrity for the interval between inspections or adopt alternative TS requirements for ensuring SG tube integrity.

By letter dated February 3, 2006 (ADAMS Accession No. ML060380266), Southern California Edison, the licensee for San Onofre Nuclear Generating Station, Units 2 and 3 (SONGS 2 and 3), submitted a response to GL 2006-01. This response stated that by application to the NRC dated November 30, 2005, the licensee requested changes to the TSs for SONGS 2 and 3 to adopt the alternative TS requirements for ensuring SG tube integrity (ADAMS Accession No. ML053390294). The new TSs were modeled after Technical Specification Task Force (TSTF) Traveler, TSTF-449, Steam Generator Tube Integrity (ADAMS Accession No. ML051090200). The original application was supplemented by a letter dated May 30, 2006 (ADAMS Accession No. ML061530259). On September 19, 2006, the NRC staff issued Amendment No. 204 and Amendment No. 196 for SONGS 2 and 3, respectively, (ADAMS Accession No. ML062620367).

R. Rosenblum The NRC staff finds the licensees adoption of new SG TSs modeled after TSTF-449 to be an acceptable and complete response to GL 2006-01. This completes the NRC staffs efforts on TAC Nos. MD0107 and MD0108. If you have any questions regarding this letter, please contact me at 301-415-1480.

Sincerely,

/RA/

N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-361 and 50-362 cc: See next page

R. Rosenblum The NRC staff finds the licensees adoption of new SG TSs modeled after TSTF-449 to be an acceptable and complete response to GL 2006-01. This completes the NRC staffs efforts on TAC Nos. MD0107 and MD0108. If you have any questions regarding this letter, please contact me at 301-415-1480.

Sincerely,

/RA/

N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-361 and 50-362 cc: See next page DISTRIBUTION:

PUBLIC LPLIV r/f RidsNrrDorlLpl4 RidsNrrPMNKalyanam RidsNrrLALFeizollahi RidsNrrDciCfeb RidsAcrsAcnwMailCenter RidsOgcRp RidsRgn4MailCenter (TPruett) RidsNrrDciCsgb (AHiser)

ADAMS ACCESSION NO: ML062970074

  • See prior concurrence dated 11/02/06 OFFICE NRR/LPL4/PM NRR/LPL4/LA NRR/CSGB/BC* NRR/LPL4/BC NAME NKalyanam LFeizollahi Allen Hiser DTerao DATE 11/6/06 11/8/06 11/2/06 11/14/06 OFFICIAL RECORD COPY

San Onofre Nuclear Generating Station Units 2 and 3 cc:

Mr. Daniel P. Breig Director, Radiologic Health Branch Southern California Edison Company State Department of Health Services San Onofre Nuclear Generating Station P.O. Box 997414, MS 7610 P. O. Box 128 Sacramento, CA 95899-7414 San Clemente, CA 92674-0128 Resident Inspector/San Onofre NPS Mr. Douglas K. Porter, Esquire c/o U.S. Nuclear Regulatory Commission Southern California Edison Company Post Office Box 4329 2244 Walnut Grove Avenue San Clemente, CA 92674 Rosemead, CA 91770 Mayor Mr. David Spath, Chief City of San Clemente Division of Drinking Water and 100 Avenida Presidio Environmental Management San Clemente, CA 92672 P. O. Box 942732 Sacramento, CA 94234-7320 Mr. James T. Reilly Southern California Edison Company Chairman, Board of Supervisors San Onofre Nuclear Generating Station County of San Diego P.O. Box 128 1600 Pacific Highway, Room 335 San Clemente, CA 92674-0128 San Diego, CA 92101 Mr. James D. Boyd, Commissioner Mark L. Parsons California Energy Commission Deputy City Attorney 1516 Ninth Street (MS 31)

City of Riverside Sacramento, CA 95814 3900 Main Street Riverside, CA 92522 Mr. Ray Waldo, Vice President Southern California Edison Company Mr. Gary L. Nolff San Onofre Nuclear Generating Station Assistant Director - Resources P.O. Box 128 City of Riverside San Clemente, CA 92764-0128 3900 Main Street Riverside, CA 92522 Mr. Brian Katz Southern California Edison Company Regional Administrator, Region IV San Onofre Nuclear Generating Station U.S. Nuclear Regulatory Commission P.O. Box 128 611 Ryan Plaza Drive, Suite 400 San Clemente, CA 92764-0128 Arlington, TX 76011-8064 Mr. Michael R. Olson San Diego Gas & Electric Company 8315 Century Park Ct. CP21G San Diego, CA 92123-1548 March 2006

San Onofre Nuclear Generating Station Units 2 and 3 cc:

Mr. Steve Hsu Department of Health Services Radiologic Health Branch MS 7610, P.O. Box 997414 Sacramento, CA 95899 Mr. A. Edward Scherer Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128 March 2006