Category:Letter
MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23012A2172023-02-0909 February 2023 Issuance of Amendment Nos. 244 and 245 Revision to Technical Specifications to Adopt TSTF-569, Revision 2, Revise Response Time Testing Definition ML21242A2162022-12-21021 December 2022 Issuance of Amendment Nos. 243 and 244 Technical Specifications and Revised License Conditions for the Permanently Defueled Condition (EPID: L-2020-LLA-0261 ML22326A1632022-11-21021 November 2022 Licensee Comment Email on Post-Shutdown Emergency Plan Amendment ML22187A0252022-11-16016 November 2022 Issuance of Amendment Nos. 242 and 243 Revision to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML22221A1682022-09-0606 September 2022 Issuance of Amendment Nos. 241 and 242 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspection ML21160A1742021-09-0202 September 2021 Issuance of Amendment Nos. 239 and 240 Revising Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)), to Implement Methodology from WCAP-17661, Revision 1 ML21188A3452021-07-0808 July 2021 Issuance of Amendment No. 238 Revision to TS 3.7.8, Auxiliary Saltwater (Asw) System (Emergency Circumstances) ML20218A2762020-09-11011 September 2020 Issuance of Amendment Nos. 237 and 239 to Relocate Technical Specification 5.3, Unit Staff Qualifications, to Updated Final Safety Analysis Report ML20235R6352020-08-31031 August 2020 Issuance of Amendment Nos. 236 and 238 Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System, Exigent Circumstances ML20232C6482020-08-17017 August 2020 Lochbaum Public Comment 1 on Exigent LAR to Modify TS 3.7.5, Auxiliary Feedwater System ML19196A3092019-08-21021 August 2019 Issuance of Amendment Nos. 233 and 235 Regarding Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions ML17212A3792017-09-25025 September 2017 Diablo Canyon Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 231 and 233 Re: Emergency Action Level Scheme Change (CAC Nos. MF8528 and MF8529) ML17012A2462017-04-27027 April 2017 Issuance of Amendments Revise Licensing Bases to Adopt Alternative Source Term ML17018A3412017-02-23023 February 2017 Issuance of Amendments Revise Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System, ML16330A6722017-01-0505 January 2017 Issuance of Amendment Nos. 228 and 230, Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation ML16139A0082016-12-21021 December 2016 Issuance of Amendment Nos. 227 and 229, Digital Replacement of the Process Protection System Portion of the Reactor Protection System and Engineered Safety Features Actuation System DCL-16-061, Supplement to License Amendment Request 15-03, Application of Alternative Source Term.2016-06-0909 June 2016 Supplement to License Amendment Request 15-03, Application of Alternative Source Term. DCL-16-061, Diablo Canyon, Units 1 and 2 - Supplement to License Amendment Request 15-03, Application of Alternative Source Term.2016-06-0909 June 2016 Diablo Canyon, Units 1 and 2 - Supplement to License Amendment Request 15-03, Application of Alternative Source Term. ML16117A2522016-05-19019 May 2016 Issuance of Amendment Nos. 226 and 228, Revise Minimum Flow Value Specified in Technical Specification 3.4.1, RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits ML16035A4412016-04-14014 April 2016 Issuance of Amendment Nos. 225 and 227, Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML16055A3592016-03-0909 March 2016 Issuance of Amendment Nos. 224 and 226, Revise Updated Final Safety Analysis Report for Beacon Power Distribution Monitoring System Methodology and TS 5.6.5 (COLR) Paragon and Nexus Methodologies ML16032A0062016-02-19019 February 2016 Redacted, Issuance of Amendment Nos. 223 and 225, Revise UFSAR Section 15.4.2.2 to Incorporate Pressurizer Filling Analysis for Major Rupture of a Main Feedwater Pipe Accident Into Licensing Basis ML15029A1732016-01-0505 January 2016 ISFSI - Issuance of Amendment Nos. 222, 224, and 4, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended (CAC MF2809, MF2810, and L24991) ML15281A1642015-12-0303 December 2015 Issuance of Amendment Nos. 221 and 223, Revise Updated Final Safety Analysis Report and Approval to Perform Fuel Assembly Structural Analyses That Considers Application of Leak Before Break ML15245A5422015-09-30030 September 2015 Issuance of Amendment Nos. 220 and 222, Request to Revise Operating License Condition Related to Cyber Security Plan Milestone H Full Implementation Date ML15204A2222015-08-27027 August 2015 Issuance of Amendment Nos. 219 and 221, Adopt Technical Specifications Task Force Traveler TSTF-432, Revision 1, Change in Technical Specification End States (WCAP-16294) ML15162A8822015-07-0101 July 2015 Issuance of Amendment Nos. 218 and 220, Revise Surveillance Requirements in TS 3.8.1, AC Sources, Related to Diesel Generator Testing ML14042A1932014-02-27027 February 2014 Issuance of Amendment Nos. 217 and 219, Editorial and Clarifying Changes to Technical Specification (TS) 3.7.10, Control Room Ventilation System (CRVS) and TS 5.6.5, Core Operating Limits Report (COLR) (TAC MF1959-MF1960) ML13178A0052013-09-0505 September 2013 Issuance of Amendment Nos. 216 and 218, Adoption of TSTF-421-A, Revision to RCP Flywheel Inspection Program (WCAP-15666), Using Consolidated Line Item Improvement Process ML12352A0672013-01-31031 January 2013 Issuance of Amendment Nos. 215 and 217, Revise Technical Specifications Related to Auxilary Feedwater System to Adopt TSTF-245, Rev. 1, TSTF-340, Rev. 3, TSTF-412, Rev. 3, and TSTF-439, Rev. 2 ML12345A3792013-01-0909 January 2013 Issuance of Amendment Nos. 214 and 216, Revise Final Safety Analysis Report Update Section 4.3.2.2 to Allow Use of Beacon Power Distribution Monitoring System ML12338A0202012-12-0404 December 2012 Issuance of Amendment Nos. 213 and 215, Revise Technical Specification 3.7.10, Control Room Ventilation System (Crvs), Required Action A.1 Completion Time (Emergency Circumstances) ML1207903382012-03-29029 March 2012 Issuance of Amendment Nos. 211 and 213, Revise Technical Specifications to Adopt TSTF-163, Rev. 2, Minimum Vs. Steady State Voltage and Frequency, and Final Safety Analysis Report Update ML1116402742011-07-15015 July 2011 Issuance of Amendment Nos. 210 and 212, License Amendment Request to Revise License Condition and Approve Cyber Security Plan and Associated Implementation Schedule ML1020100842011-01-24024 January 2011 Issuance of Amendment Nos. 209 and 211, Revise Technical Specification 3.4.15, RCS Leakage Detection Instrumentation, Operability Requirements and Actions ML1025304432010-09-29029 September 2010 Issuance of Amendment Nos. 208 and 210, Revise FSAR Update to Include Damping Values for Seismic Design/Analysis - Integrated Head Assembly ML1018901172010-07-30030 July 2010 Issuance of Amendment Nos. 207 and 209, Revise FSAR Update to Include Critical Damping Value for Structural Dynamic Qualification of Control Rod Drive Mechanism Pressure Housings ML0925405442009-09-17017 September 2009 Issuance of Amendment No. 208, Revise Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs) for Unit 2 Cycle 15 (Exigent Circumstances) ML0921203992009-08-19019 August 2009 Issuance of Amendment Nos. 206 and 207, Modify Technical Specifications to Adopt TSTF-511, Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 26 ML0907701812009-04-29029 April 2009 License Amendment, Issuance of Amendment Nos. 205 and 206, Revise TS 3.3.1, Reactor Trip System (RTS) Instrumentation, to Delete High-Negative Rate Trip Function ML0906308082009-03-30030 March 2009 Issuance of Amendment Nos. 204 and 205, Revise TS 3.7.5, Auxiliary Feedwater (AFW) System, and TS 3.7.6, Condensate Storage Tank (CST) and Fire Water Storage Tank (Fwst) ML0900803872009-01-15015 January 2009 Issuance of Amendment Nos. 203 and 204, Changes to Technical Specification 5.5.16, Containment Leakage Rate Testing Program ML0834601732008-12-31031 December 2008 Issuance of Amendment No. 202 and 203 Increase the Completion Times for Required Actions Related to Technical Specifications 3.5.2, the ECCS, and 3.6.6, CS & CS (Tac MD7512 & MD7513) ML0832906092008-12-23023 December 2008 Issuance of Amendment Nos. 201 and 202, Adoption of Changes to Standard Technical Specifications Under Technical Specifications Task Force (TSTF)-448 ML0824102622008-10-30030 October 2008 Issuance of Amendment Nos. 200 and 201, Technical Specifications Change to Relocate Surveillance Test Intervals to a Licensee-Controlled Program (Risk-Informed Initiative 5b) ML0732400062008-01-0808 January 2008 Units, 1 and 2, Issuance of Amendment Nos. 198 and 199, Revise Technical Specification (TS) 3.3.2, TS 5.5.9, and TS 5.6.10 to Support Replacement of Steam Generators ML0719102142007-07-11011 July 2007 License Amendments, Incorporated the Mitigation Strategies Required by Section B.5.b. of Commission Order EA-02-026 ML0713707312007-06-26026 June 2007 Issuance of License Amendment Nos. 197 and 198 TS 5.5.16, Containment Leakage Rate Testing Program, for Consistency with 10 CFR 50.55a(g)(4) ML0703500512007-04-17017 April 2007 Issuance of Amendment Nos. 195 and 196 TS 3.4.1 Reactor Coolant System Pressure, Temperature, & Flow Departure from Nucleate Boiling Limits & TS 5.6.5 Core Operating Limits Report. ML0704405032007-03-19019 March 2007 License Amendment, Deletion of License Condition Section 2.G in Facility Operating License (CLIIP Item) 2023-02-09
[Table view] Category:Safety Evaluation
MONTHYEARML23199A3122023-07-20020 July 2023 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule ML22340A6752023-03-0606 March 2023 Approval of Certified Fuel Handler Training and Retraining Program ML23012A2172023-02-0909 February 2023 Issuance of Amendment Nos. 244 and 245 Revision to Technical Specifications to Adopt TSTF-569, Revision 2, Revise Response Time Testing Definition ML21242A2162022-12-21021 December 2022 Issuance of Amendment Nos. 243 and 244 Technical Specifications and Revised License Conditions for the Permanently Defueled Condition (EPID: L-2020-LLA-0261 ML22334A0822022-12-0101 December 2022 Correction to Issuance of Amendment Nos. 242 and 243 Revision to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML22187A0252022-11-16016 November 2022 Issuance of Amendment Nos. 242 and 243 Revision to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML22221A1682022-09-0606 September 2022 Issuance of Amendment Nos. 241 and 242 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspection ML21160A1742021-09-0202 September 2021 Issuance of Amendment Nos. 239 and 240 Revising Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)), to Implement Methodology from WCAP-17661, Revision 1 ML21188A3452021-07-0808 July 2021 Issuance of Amendment No. 238 Revision to TS 3.7.8, Auxiliary Saltwater (Asw) System (Emergency Circumstances) ML20249C8502020-10-22022 October 2020 Proposed Alternative NDE-RCS-SE-2R22 to the Requirements of the ASME Code ML20218A2762020-09-11011 September 2020 Issuance of Amendment Nos. 237 and 239 to Relocate Technical Specification 5.3, Unit Staff Qualifications, to Updated Final Safety Analysis Report ML20235R6352020-08-31031 August 2020 Issuance of Amendment Nos. 236 and 238 Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System, Exigent Circumstances ML19274B0822019-10-0707 October 2019 Correction to Issuance of Amendment Nos. 233 and 235 to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for ERO Positions ML19196A3092019-08-21021 August 2019 Issuance of Amendment Nos. 233 and 235 Regarding Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions ML19176A0082019-06-28028 June 2019 Request for Relief from the Inservice Inspection Program Requirements of ASME Code, Section XI, for Steam Generator and Pressurizer Nozzle Inside Radius Sections ML19023A0262019-01-25025 January 2019 Request for Alternative from Volumetric/Surface Examination Frequency Requirements of ASME Code Case N-729-4 ML17263A0592017-10-0606 October 2017 Diablo Canyon Power Plant, Unit 2 - Relief Requests to Allow Use of Proposed Alternatives to Implement Requirements of ASME Code, for Reactor Pressure Vessel Welds for the Third ISI Interval (CAC Nos. MF9386, MF9387, MF9388, MF9389, and MF9390) ML17212A3792017-09-25025 September 2017 Diablo Canyon Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 231 and 233 Re: Emergency Action Level Scheme Change (CAC Nos. MF8528 and MF8529) ML17132A2312017-05-16016 May 2017 Diablo Canyon Power Plant, Units 1 and 2 - Correction Letter Regarding Amendment Nos. 230 and 232 to Adopt Alternative Source Term (CAC Nos. MF6399 and MF6400) ML17012A2462017-04-27027 April 2017 Issuance of Amendments Revise Licensing Bases to Adopt Alternative Source Term ML17037D2672017-03-0909 March 2017 Relief Request NDE-RCS-SE-1R20 to Allow Use of Alternate Depth Sizing Criteria for the Fourth Inservice Inspection ML17018A3412017-02-23023 February 2017 Issuance of Amendments Revise Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System, ML16349A3862016-12-28028 December 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML16139A0082016-12-21021 December 2016 Issuance of Amendment Nos. 227 and 229, Digital Replacement of the Process Protection System Portion of the Reactor Protection System and Engineered Safety Features Actuation System ML16207A3972016-07-27027 July 2016 Relief Request NDE-SIF-U1, Allow Use of Alternate Examination Volume Coverage Requirements, Class 2 Seal Injection Welds, for the Third 10-Year Inservice Inspection Interval ML16117A2522016-05-19019 May 2016 Issuance of Amendment Nos. 226 and 228, Revise Minimum Flow Value Specified in Technical Specification 3.4.1, RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits ML16035A4412016-04-14014 April 2016 Issuance of Amendment Nos. 225 and 227, Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML16055A3592016-03-0909 March 2016 Issuance of Amendment Nos. 224 and 226, Revise Updated Final Safety Analysis Report for Beacon Power Distribution Monitoring System Methodology and TS 5.6.5 (COLR) Paragon and Nexus Methodologies ML16056A5132016-03-0707 March 2016 Relief Request FLIG-U1, Request to Extend Third 10-Year Inservice Inspection Interval for Reactor Vessel Stud Hole Ligament Examinations ML16055A2812016-02-26026 February 2016 Relief Request NDE-FWNS-U1/U2 to Allow Use of Alternate Examination Volume Coverage Requirements, Third 10-Year Inservice Inspection Interval ML16032A0062016-02-19019 February 2016 Redacted, Issuance of Amendment Nos. 223 and 225, Revise UFSAR Section 15.4.2.2 to Incorporate Pressurizer Filling Analysis for Major Rupture of a Main Feedwater Pipe Accident Into Licensing Basis ML16013A3402016-01-27027 January 2016 Relief Request NDE-PNS-U2A, ASME Code Section XI Requirements to Allow Use of Alternate Exam Volume Coverage Requirements, for the Third 10-year Inservice Inspection Interval ML15037A0062016-01-0505 January 2016 ISFSI - Safety Evaluation, Encl. 4, Amendment Nos. 222, 224, and 4 - Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended (CAC MF2809, MF2810, and L24991) ML15029A1732016-01-0505 January 2016 ISFSI - Issuance of Amendment Nos. 222, 224, and 4, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended (CAC MF2809, MF2810, and L24991) ML15337A0212015-12-0808 December 2015 Relief Request NDE-SG-MS-IR - Relief from Exam Requirements for Main Steam Nozzles in Replacement Steam Generators, Third 10-Year Inservice Inspection Interval ML15281A1642015-12-0303 December 2015 Issuance of Amendment Nos. 221 and 223, Revise Updated Final Safety Analysis Report and Approval to Perform Fuel Assembly Structural Analyses That Considers Application of Leak Before Break ML15299A0342015-11-0404 November 2015 Relief Request NDE-RCS-SE-2R19, Use of Alternate Sizing Qualification Criteria Through a Protective Clad Layer, Third 10-Year Inservice Inspection Interval ML15245A5422015-09-30030 September 2015 Issuance of Amendment Nos. 220 and 222, Request to Revise Operating License Condition Related to Cyber Security Plan Milestone H Full Implementation Date ML15261A0072015-09-18018 September 2015 Request for Relief PRS-3, Proposed Alternative to Requirements for System Leakage Testing Class 1 Piping Vent, Drain, and Test Isolation Devices, for the Third 10-year Inservice Inspection Interval (TAC MF6520-MF6521) ML15204A2222015-08-27027 August 2015 Issuance of Amendment Nos. 219 and 221, Adopt Technical Specifications Task Force Traveler TSTF-432, Revision 1, Change in Technical Specification End States (WCAP-16294) ML15187A0352015-07-15015 July 2015 Relief Request REP-SI, Revision 2, Proposed Alternative for Repair/Replacement Activities for Certain Safety Injection Pump Welded Attachments, Remaining Useful Life +20 Years ML15162A8822015-07-0101 July 2015 Issuance of Amendment Nos. 218 and 220, Revise Surveillance Requirements in TS 3.8.1, AC Sources, Related to Diesel Generator Testing ML15168A0242015-06-19019 June 2015 Request for Alternative RPV-U1 - Extension to Allow Use of Alternate Reactor Inspection Interval Requirements for the Third 10-Year Inservice Inspection Interval ML14251A4682014-09-16016 September 2014 Relief Request NDE-SFW-13, ASME Code Section XI, Request for Alternative to Allow Use of Alternate Examination Requirements, Third 10-Year Inservice Inspection Interval ML14196A0952014-08-0404 August 2014 Request for Relief from ASME Code Requirements for Mechanical Clamping Devices for Class 2 and 3 Piping Pressure Boundary ML14104B6132014-05-14014 May 2014 Relief Request NDE-PNS-U2, Requirements for Examination Coverage of ASME Class 1 Pressurizer Nozzle-to-Head Welds, Third 10-Year Inservice Inspection Interval ML14042A1932014-02-27027 February 2014 Issuance of Amendment Nos. 217 and 219, Editorial and Clarifying Changes to Technical Specification (TS) 3.7.10, Control Room Ventilation System (CRVS) and TS 5.6.5, Core Operating Limits Report (COLR) (TAC MF1959-MF1960) ML13192A3542013-09-12012 September 2013 Relief Request RVFLNG-INT3 - Alternative to ASME Code Pressure Test Requirements for Class 1 Reactor Vessel Flange Leakoff Lines, Third 10-Year Inservice Inspection Interval (TAC MF0408-MF0409) ML13178A0052013-09-0505 September 2013 Issuance of Amendment Nos. 216 and 218, Adoption of TSTF-421-A, Revision to RCP Flywheel Inspection Program (WCAP-15666), Using Consolidated Line Item Improvement Process ML13232A3082013-08-28028 August 2013 Relief Request REP-1 U2, Revision 2, Alternative to Code Requirements for Pressurizer Structural Weld Overlays, for the Third 10-Year Inservice Inspection Interval 2023-07-20
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 January 15, 2009 Mr. John 1. Conway Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 3, Mail Code 104/6/601 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 - ISSUANCE OF AMENDMENTS RE: REVISION TO TECHNICAL SPECIFICATION 5.5.16, "CONTAINMENT LEAKAGE RATE TESTING PROGRAM," (TAC NOS. MD8042 AND MD8043)
Dear Mr. Conway:
The U.S. Nuclear Regulatory Commission (the Commission) has issued the enclosed Amendment No. 203 to Facility Operating License No. DPR-80 and Amendment No. 204 to Facility Operating License No. DPR-82 for the Diablo Canyon Power Plant (DCPP), Unit Nos. 1 and 2, respectively. The amendments consist of changes to the Technical Specifications (TSs) in response to your application dated February 1, 2008, as supplemented by letter dated August 20, 2008.
The amendments revise TS 5.5.16.b, "Containment Leakage Rate Testing Program," to specify a lower peak calculated containment internal pressure following a large-break loss-of-coolant accident and the containment design pressure at the DCPP, Units 1 and 2. By letter dated August 20, 2008, the licensee withdrew its request to use the guidance in American National Standards Institute/American Nuclear Society (ANSI/ANS) 56.8-2002, "Containment System Leakage Testing," in lieu of the 1994 Edition.
J. Conway -2 A copy of the related Safety Evaluation is enclosed. The Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice.
Sincerely,
()1t,y\\J Cuu \
Alan B. Wang, ProjeJManager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosures:
- 1. Amendment No. 203 to DPR-80
- 2. Amendment No. 204 to DPR-82
- 3. Safety Evaluation cc w/encls: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 PACIFIC GAS AND ELECTRIC COMPANY DOCKET NO. 50-275 DIABLO CANYON NUCLEAR POWER PLANT, UNIT NO.1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 203 License No. DPR-80
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Pacific Gas and Electric Company (the licensee), dated February 1, 2008, as supplemented by letter dated August 20, 2008, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Enclosure 1
-2
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and Paragraph 2.C.(2) of Facility Operating License No. DPR-80 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 203, are hereby incorporated in the license. Pacific Gas & Electric Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan, except where otherwise stated in specific license conditions.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 120 days.
FOR THE NUCLEAR REGULATORY COMMISSION AL)~ /t~
Michael T. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Facility Operating License No. DPR-80 and Technical Specifications Date of Issuance: January 15, 2009
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 PACIFIC GAS AND ELECTRIC COMPANY DOCKET NO. 50-323 DIABLO CANYON NUCLEAR POWER PLANT, UNIT NO.2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 204 License No. DPR-82
- 1. The Nuclear RegUlatory Commission (the Commission) has found that:
A. The application for amendment by Pacific Gas and Electric Company (the licensee), dated February 1, 2008, as supplemented by letter dated August 20, 2008, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regUlations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Enclosure 2
-2
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and Paragraph 2.C.(2) of Facility Operating License No. DPR-82 is hereby amended to read as follows:
(2) Technical Specifications (SSER 32, Section 8)* and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 204, are hereby incorporated in the license. Pacific Gas & Electric Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan, except where otherwise stated in specific license conditions.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 120 days.
FOR THE NUCLEAR REGULATORY COMMISSION Michael T. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Facility Operating License No. DPR-82 and Technical Specifications Date of Issuance: January 15, 2009
ATTACHMENT TO LICENSE AMENDMENT NO. 203 TO FACILITY OPERATING LICENSE NO. DPR-80 AND AMENDMENT NO. 204 TO FACILITY OPERATING LICENSE NO. DPR-82 DOCKET NOS. 50-275 AND 50-323 Replace the following pages of the Facility Operating License Nos. DPR-80 and DPR-82, and Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Facility Operating License Nos. DPR-80 and DPR-82 REMOVE INSERT
-3 -3 Technical Specifications REMOVE INSERT 5.0-16 5.0-16
-3 (4) Pursuant to the Act and 10 CFR Parts 30,40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5) Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C. This License shall be deemed to contain and is subject to the conditions specified in the Commission's regUlations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is SUbject to the additional conditions specified or incorporated below:
(1) Maximum Power Level The Pacific Gas and Electric Company is authorized to operate the facility at reactor core power levels not in excess of 3411 megawatts thermal (100% rated power) in accordance with the conditions specified herein.
(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix S, as revised through Amendment No. 203, are hereby incorporated in the license.
Pacific Gas & Electric Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan, except where otherwise stated in specific license conditions.
(3) Initial Test Program The Pacific Gas and Electric Company shall conduct the post-fuel-loading initial test program (set forth in Section 14 of Pacific Gas and Electric Company's Final Safety Analysis Report, as amended), without making any major modifications of this program unless modifications have been identified and have received prior NRC approval. Major modifications are defined as:
- a. Elimination of any test identified in Section 14 of PG&E's Final Safety Analysis Report as amended as being essential; Amendment No. 203
-3 (4) Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5) Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C. This License shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1) Maximum Power Level The Pacific Gas and Electric Company is authorized to operate the facility at reactor core power levels not in excess of 3411 megawatts thermal (100% rated power) in accordance with the conditions specified herein.
(2) Technical Specifications (SSER 32, Section 8)* and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix S, as revised through Amendment No. 204, are hereby incorporated in the license.
Pacific Gas & Electric Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan, except where otherwise stated in specific license conditions.
(3) Initial Test Program (SSER 31! Section 4.4.1)
Any changes to the Initial Test Program described in Section 14 of the FSAR made in accordance with the provisions of 10 CFR 50.59 shall be reported in accordance with 50.59(b) within one month of such change.
- The parenthetical notation following the title of many license conditions denotes the section of the Safety Evaluation Report and/or its supplements wherein the license condition is discussed.
Amendment No. 204
Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.15 Safety Function Determination Program (SFDP) (continued)
- b. A required system redundant to the system(s) in turn supported by the inoperable supported system is also inoperable; or
- c. A required system redundant to the support system(s) for the supported systems (a) and (b) above is also inoperable.
The SFDP identifies where a loss of safety function exists. If a loss of safety function is determined to exist by this program, the appropriate Conditions and Required Actions of the LCO in which the loss of safety function exists are required to be entered.
5.5.16 Containment Leakage Rate Testing Program
- a. A program shall be established to implement the leakage rate testing of the containment as required by 10 CFR 50.54(0) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program," dated September 1995, as modified by the following exceptions:
- 1. The visual examination of containment concrete surfaces intended to fulfill the requirements of 10 CFR 50, Appendix J, Option B testing, will be performed in accordance with the requirements of and frequency specified by ASME Section XI Code, Subsection IWL, except where relief has been authorized by the NRC.
- 2. The visual examination of the steel liner plate inside containment intended to fulfill the requirements of 10 CFR 50, Appendix J, Option B, will be performed in accordance with the requirements of and frequency specified by ASME Section XI code, Subsection IWE, except where relief has been authorized by the NRC.
- 3. The ten-year interval between performance of the integrated leakage rate (Type A) test, beginning May 4, 1994, for Unit 1 and April 30, 1993, for Unit 2, has been extended to 15 years.
- b. The peak calculated containment internal pressure for the design basis loss of coolant accident, Pa, is 43.5 psig. The containment design pressure is 47 psig.
- c. The maximum allowable containment leakage rate, La, at Pa, shall be 0.10% of containment air weight per day.
(continued)
DIABLO CANYON - UNITS 1 & 2 5.0-16 Unit 1 - Amendment No.~,~,~,.w+, 4-98,203 Unit 2 - Amendment No. ~, ~, 74, 4-98, 4W, 204
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 203 TO FACILITY OPERATING LICENSE NO. DPR-80 AND AMENDMENT NO. 204 TO FACILITY OPERATING LICENSE NO. DPR-82 PACIFIC GAS AND ELECTRIC COMPANY DIABLO CANYON POWER PLANT, UNITS 1 AND 2 DOCKET NOS. 50-275 AND 50-323
1.0 INTRODUCTION
By application dated February 1, 2008, as supplemented by letter dated August 20, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession Nos.
ML080390454 and ML082410418, respectively), Pacific Gas and Electric Company (PG&E, the licensee) requested changes to the Technical Specifications (TS) for the Diablo Canyon Power Plant (DCPP), Units 1 and 2. The supplemental letter dated August 20, 2008, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the staffs original proposed no significant hazards consideration determination as published in the Federal Register on March 25, 2008 (73 FR 15787).
The proposed amendments will revise TS 5.5.16.b, "Containment Leakage Rate Testing Program," to specify a lower peak calculated containment internal pressure following a large-break loss-of-coolant accident (LOCA) and the containment design pressure at the DCPP, Units 1 and 2. By letter dated August 20, 2008, the licensee withdrew its request to use the guidance in American National Standards Institute/American Nuclear Society (ANSI/ANS) 56.8-2002, "Containment System Leakage Testing," in lieu of the 1994 Edition.
2.0 REGULATORY EVALUATION
Section 50.54(0) of Title 10 of the Code of Federal Regulations (10 CFR) requires primary reactor containments for water-cooled power reactors to be subject to the requirements of Appendix J, "Leakage Rate Testing of Containment of Water Cooled Nuclear Power Plants," to 10 CFR Part 50. Appendix J specifies containment leakage testing requirements, including the types of tests required to ensure the leak-tight integrity of the primary reactor containment and systems and components which penetrate the containment. In addition, Appendix J discusses leakage rate acceptance criteria, test methodology, frequency of testing, and reporting requirements for each type of test.
Enclosure 3
-2 10 CFR 50 Appendix A, General Design Criterion (GOC) 50, Containment design basis, requires that the containment, shall be designed to accommodate, without exceeding the design leakage rate and with sufficient margin, the calculated conditions from any LOCA.
10 CFR 50 Appendix A, GOC 16, Containment design, requires that reactor containment and associated systems shall be provided to establish an essentially leak-tight barrier against the uncontrolled release of radioactivity to the environment, and to assure that the containment design conditions important to safety are not exceeded for as long as the postulated accident conditions require.
NUREG-1431, "Standard Technical Specifications [STS], Westinghouse Plants Specifications,"
Volume 1, Revision 3, dated June 2004, is the latest approved version of STS available for use.
3.0 TECHNICAL EVALUATION
The current OCPP TS 5.5.16.b states that the peak calculated containment internal pressure for the design-basis LOCA, Pa , is 47 pounds per square inch gauge (psig), which is the containment design pressure value. The current Final Safety Analysis Report Update (FSARU) analysis of record for the peak containment internal pressure following the design-basis LOCA with the original Model 51 steam generators (SGs) is contained in Appendix 6.2C of the OCPP FSARU. Using the COCO digital computer code, the peak containment internal pressure was calculated to be 41.53 psig. The use of the containment design pressure of 47 psig as Pain TS 5.5.16.b is conservative since it results in containment leak-rate testing being performed at a pressure well above the current peak calculated containment internal pressure of 41.53 psig following the design-basis LOCA. In accordance with Section 3.2.11 of ANSI/ANS 56.8-1994, compliance with the current TS for an integrated leak-rate test (ILRT) requires that the ILRT test pressure shall not be less than 0.96 Pa (47 psig) or 45.12 psig nor exceed P-design (47 psig).
Current TS 5.5.16.b states:
The peak calculated containment internal pressure for the design basis loss of coolant accident, Pa , is 47 psig.
The proposed change to TS 5.5.16.b would state:
The peak calculated containment internal pressure for the design basis loss of coolant accident, Pa, is 43.5 psig. The containment design pressure is 47 psig.
The licensee performed a new containment integrity analysis as part of the OCPP replacement SG program. The reanalysis was performed to reevaluate the bounding peak pressure and temperature of design-basis LOCA inside containment and to demonstrate the ability of the containment heat removal systems to mitigate accidents. Calculation of the containment response following a postulated LOCA was analyzed by use of the digital computer code GOTHIC Version 7.2. This code version was used to take advantage of the diffusion layer model heat transfer option.
The GOTHIC modeling for OCPP is consistent with the NRC-approved Kewaunee Power Station evaluation model. Kewaunee and OCPP both have large dry containment designs with
-3 similar active heat removal capabilities. The heat transfer option was approved by the Nuclear Regulatory Commission (NRC) for use in the Kewaunee analyses with the condition that the effect of mist be excluded from what was earlier termed as the mist diffusion layer model. The GOTHIC containment modeling for DCPP has followed the conditions of acceptance placed on the Kewaunee evaluation model.
The NRC staff reviewed the input parameters and assumptions used for the DCPP GOTHIC model for containment integrity analysis for a large-break LOCA. The NRC staff found the input parameters and assumptions to be conservative and consistent with the input parameters and assumptions used for the NRC-approved Kewaunee evaluation model. The differences in GOTHIC code versions are documented in Appendix A of the GOTHIC User Manual Release Notes. Version 7.2 of GOTHIC is used consistently with the restrictions identified in the NRC approved evaluation model and none of the user-controlled enhancements added to Version 7.2 were implemented in the DCPP containment model.
According to the licensee's analysis, the actual peak calculated containment internal pressure is 41.2 and 41.4 psig, for DCPP, Units 1 and 2, respectively. The licensee has proposed to use a conservative value of 43.5 psig as the peak calculated containment internal pressure in TS 5.5.16.b for DCPP. This ensures that the value specified in TS 5.5.16.b contains adequate margin to the FSARU containment internal pressure analysis values of 41.2 and 41.4 psig for the DCPP, Units 1 and 2, respectively. The containments for DCPP, Units 1 and 2, are designed and constructed to withstand a maximum internal pressure of 47 psig, which is specified as the containment design pressure in the proposed TS 5.5.16.b. Therefore, the licensee proposes to change TS 5.5.16.b, to specify the peak calculated containment internal pressure, Pa , as 43.5 psig following a LOCA and to specify the containment design pressure as 47 psig. The revised TS 5.5.16.b will allow Type A, B, and C leak-rate tests at the DCPP to be performed at a lower pressure and provide a wider acceptable pressure test range for containment ILRTs without exceeding the containment design pressure.
As noted above, the current TS is conservative as it uses the containment maximum design pressure of 47 psig for Pa , the peak calculated containment internal pressure for the design basis loss-of-coolant accident. As allowed by NUREG-1431, Revision 3, STS 5.5.16.b, Option B, the licensee has proposed that the TS 5.5.16.b Pa value (43.5 psig) be based on the FSARU containment internal pressure analysis calculated pressure with margin included.
DCPP converted to the NUREG-1431, STS and did not adopt STS 5.5.16.b, Option B change at the time of conversion. This change brings the DCPP TS into conformance with NUREG-1431, Revision 3, STS 5.5.16.b, Option B. The value of 43.5 psig is bounding for both units. The containment design pressure has not changed. Based on the above, the NRC staff concludes that the licensee's proposed change is acceptable.
- 4
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the California State official was notified of the proposed issuance of the amendments. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
The amendments change a requirement with respect to the installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendments involve no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration and there has been no public comment on such finding published in the Federal Register on March 25, 2008 (73 FR 15787). Accordingly, the amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9).
Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with .the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: B. Lee Date: January 15, 2009
January 15, 2009 J. Conway -2 A copy of the related Safety Evaluation is enclosed. The Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice.
Sincerely, I RAJ Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosures:
- 1. Amendment No. 203 to DPR-80
- 2. Amendment No. 204 to DPR-82
- 3. Safety Evaluation cc w/encls: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrLAJBurkhardt Resource LPLIV Reading RidsNrrPMDiabloCanyon Resource RidsAcrsAcnw_MailCTR Resource RidsOgcRp Resource RidsNrrDirsltsb Resource RidsRgn4MailCenter Resource RidsNrrDorlDpr Resource B.Lee, NRR/DSS/SCVB RidsNrrDorlLpl4 Resource ASallman, NRR/DSS/SCVB RidsNrrDssScvb Resource ADAM s Accession No: ML090080387 *SE*In ut memo OFFICE NRRlLPL4/PM NRRlLPL4/LA DIRS/ITSB/BC DSS/SCVB/BC OGC NRRlLPL4/BC NRRlLPL4/PM AWang MTM NAME AWang ,IBurkhardl RElliolt RDennig' EWiliiams MMarkley for DATE 1/12/09 1/9109 1/13/09 1/6109 1/13/09 1/15/09 1/15/09 OFFICIAL RECORD COPY