Letter Sequence Approval |
---|
|
|
MONTHYEARDCL-13-057, License Amendment Request 13-01, Administrative Revisions to Technical Specifications 3.7.10 and 5.6.52013-06-0606 June 2013 License Amendment Request 13-01, Administrative Revisions to Technical Specifications 3.7.10 and 5.6.5 Project stage: Request ML13179A0262013-06-27027 June 2013 E-mail Diablo Canyon, Units 1 & 2 - Acceptance Review Email, License Amendment Request, Revise Technical Specification (TS) 3.7.10, Control Room Ventilation System (CRVS) and TS 5.6.5, Core Operating Limits Report (COLR) Project stage: Acceptance Review ML14042A1932014-02-27027 February 2014 Issuance of Amendment Nos. 217 and 219, Editorial and Clarifying Changes to Technical Specification (TS) 3.7.10, Control Room Ventilation System (CRVS) and TS 5.6.5, Core Operating Limits Report (COLR) (TAC MF1959-MF1960) Project stage: Approval 2013-06-06
[Table View] |
|
---|
Category:Letter
MONTHYEARML24302A2622024-11-0101 November 2024 Letter to CA SHPO Regarding DCPP Dseis ML24302A1922024-11-0101 November 2024 Ltr to G. Frausto Coastal Band of Chumash Indians Re DCPP Dseis ML24302A1952024-11-0101 November 2024 Ltr to M. Olivas Tucker Ytt Re DCPP Dseis ML24302A1912024-11-0101 November 2024 Ltr to C. Mcdarment Tule River Tribe Re DCPP Dseis ML24302A1942024-11-0101 November 2024 Ltr to K. Kahn Santa Ynez Band of Chumash Indians Re DCPP Dseis ML24302A1962024-11-0101 November 2024 Ltr to SLO County Chumash Indians Re DCPP Dseis ML24302A1932024-11-0101 November 2024 Letter to G. Pierce Salinan Tribe of Monterey, SLO Re DCPP Dseis ML24302A1972024-11-0101 November 2024 Letter to V. Sage Walker Northern Chumash Tribal Council Re DCPP Dseis ML24302A2612024-11-0101 November 2024 Letter to Achp Re DCPP Dseis ML24275A0622024-10-30030 October 2024 NRC to NMFS Request Initiate Formal Endangered Species Act Consultation and Abbreviated Essential Fish Habitat for Proposed License Renewal of DCP Plant Units 1, 2 IR 05000275/20240032024-10-30030 October 2024 Integrated Inspection Report 05000275/2024003 and 05000323/2024003 and Independent Spent Fuel Storage Installation Report 07200026/2024001 ML24269A0122024-10-29029 October 2024 OEDO-24-00083 2.206 Petition Diablo Canyon Seismic CDF - Response to Petitioner Letter ML24284A3122024-10-28028 October 2024 Ltr to P Ting, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants ML24284A3112024-10-28028 October 2024 Ltr to a Peck, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants IR 05000275/20240132024-10-28028 October 2024 – License Renewal Report 05000275/2024013 and 05000323/2024013 DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 ML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 ML24277A0292024-10-18018 October 2024 NRC to Fws Req. for Concurrence W. Endangered Species Act Determinations for Diablo Canyon Power Plant Units 1,2, ISFSI Proposed License Renewals in San Luis Obispo Co., CA DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application 2024-09-09
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23012A2172023-02-0909 February 2023 Issuance of Amendment Nos. 244 and 245 Revision to Technical Specifications to Adopt TSTF-569, Revision 2, Revise Response Time Testing Definition ML21242A2162022-12-21021 December 2022 Issuance of Amendment Nos. 243 and 244 Technical Specifications and Revised License Conditions for the Permanently Defueled Condition (EPID: L-2020-LLA-0261 ML22326A1632022-11-21021 November 2022 Licensee Comment Email on Post-Shutdown Emergency Plan Amendment ML22187A0252022-11-16016 November 2022 Issuance of Amendment Nos. 242 and 243 Revision to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML22221A1682022-09-0606 September 2022 Issuance of Amendment Nos. 241 and 242 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspection ML21160A1742021-09-0202 September 2021 Issuance of Amendment Nos. 239 and 240 Revising Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)), to Implement Methodology from WCAP-17661, Revision 1 ML21188A3452021-07-0808 July 2021 Issuance of Amendment No. 238 Revision to TS 3.7.8, Auxiliary Saltwater (Asw) System (Emergency Circumstances) ML20218A2762020-09-11011 September 2020 Issuance of Amendment Nos. 237 and 239 to Relocate Technical Specification 5.3, Unit Staff Qualifications, to Updated Final Safety Analysis Report ML20235R6352020-08-31031 August 2020 Issuance of Amendment Nos. 236 and 238 Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System, Exigent Circumstances ML20232C6482020-08-17017 August 2020 Lochbaum Public Comment 1 on Exigent LAR to Modify TS 3.7.5, Auxiliary Feedwater System ML19196A3092019-08-21021 August 2019 Issuance of Amendment Nos. 233 and 235 Regarding Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions ML17212A3792017-09-25025 September 2017 Diablo Canyon Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 231 and 233 Re: Emergency Action Level Scheme Change (CAC Nos. MF8528 and MF8529) ML17012A2462017-04-27027 April 2017 Issuance of Amendments Revise Licensing Bases to Adopt Alternative Source Term ML17018A3412017-02-23023 February 2017 Issuance of Amendments Revise Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System, ML16330A6722017-01-0505 January 2017 Issuance of Amendment Nos. 228 and 230, Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation ML16139A0082016-12-21021 December 2016 Issuance of Amendment Nos. 227 and 229, Digital Replacement of the Process Protection System Portion of the Reactor Protection System and Engineered Safety Features Actuation System DCL-16-061, Supplement to License Amendment Request 15-03, Application of Alternative Source Term.2016-06-0909 June 2016 Supplement to License Amendment Request 15-03, Application of Alternative Source Term. DCL-16-061, Diablo Canyon, Units 1 and 2 - Supplement to License Amendment Request 15-03, Application of Alternative Source Term.2016-06-0909 June 2016 Diablo Canyon, Units 1 and 2 - Supplement to License Amendment Request 15-03, Application of Alternative Source Term. ML16117A2522016-05-19019 May 2016 Issuance of Amendment Nos. 226 and 228, Revise Minimum Flow Value Specified in Technical Specification 3.4.1, RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits ML16035A4412016-04-14014 April 2016 Issuance of Amendment Nos. 225 and 227, Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML16055A3592016-03-0909 March 2016 Issuance of Amendment Nos. 224 and 226, Revise Updated Final Safety Analysis Report for Beacon Power Distribution Monitoring System Methodology and TS 5.6.5 (COLR) Paragon and Nexus Methodologies ML16032A0062016-02-19019 February 2016 Redacted, Issuance of Amendment Nos. 223 and 225, Revise UFSAR Section 15.4.2.2 to Incorporate Pressurizer Filling Analysis for Major Rupture of a Main Feedwater Pipe Accident Into Licensing Basis ML15029A1732016-01-0505 January 2016 ISFSI - Issuance of Amendment Nos. 222, 224, and 4, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended (CAC MF2809, MF2810, and L24991) ML15281A1642015-12-0303 December 2015 Issuance of Amendment Nos. 221 and 223, Revise Updated Final Safety Analysis Report and Approval to Perform Fuel Assembly Structural Analyses That Considers Application of Leak Before Break ML15245A5422015-09-30030 September 2015 Issuance of Amendment Nos. 220 and 222, Request to Revise Operating License Condition Related to Cyber Security Plan Milestone H Full Implementation Date ML15204A2222015-08-27027 August 2015 Issuance of Amendment Nos. 219 and 221, Adopt Technical Specifications Task Force Traveler TSTF-432, Revision 1, Change in Technical Specification End States (WCAP-16294) ML15162A8822015-07-0101 July 2015 Issuance of Amendment Nos. 218 and 220, Revise Surveillance Requirements in TS 3.8.1, AC Sources, Related to Diesel Generator Testing ML14042A1932014-02-27027 February 2014 Issuance of Amendment Nos. 217 and 219, Editorial and Clarifying Changes to Technical Specification (TS) 3.7.10, Control Room Ventilation System (CRVS) and TS 5.6.5, Core Operating Limits Report (COLR) (TAC MF1959-MF1960) ML13178A0052013-09-0505 September 2013 Issuance of Amendment Nos. 216 and 218, Adoption of TSTF-421-A, Revision to RCP Flywheel Inspection Program (WCAP-15666), Using Consolidated Line Item Improvement Process ML12352A0672013-01-31031 January 2013 Issuance of Amendment Nos. 215 and 217, Revise Technical Specifications Related to Auxilary Feedwater System to Adopt TSTF-245, Rev. 1, TSTF-340, Rev. 3, TSTF-412, Rev. 3, and TSTF-439, Rev. 2 ML12345A3792013-01-0909 January 2013 Issuance of Amendment Nos. 214 and 216, Revise Final Safety Analysis Report Update Section 4.3.2.2 to Allow Use of Beacon Power Distribution Monitoring System ML12338A0202012-12-0404 December 2012 Issuance of Amendment Nos. 213 and 215, Revise Technical Specification 3.7.10, Control Room Ventilation System (Crvs), Required Action A.1 Completion Time (Emergency Circumstances) ML1207903382012-03-29029 March 2012 Issuance of Amendment Nos. 211 and 213, Revise Technical Specifications to Adopt TSTF-163, Rev. 2, Minimum Vs. Steady State Voltage and Frequency, and Final Safety Analysis Report Update ML1116402742011-07-15015 July 2011 Issuance of Amendment Nos. 210 and 212, License Amendment Request to Revise License Condition and Approve Cyber Security Plan and Associated Implementation Schedule ML1020100842011-01-24024 January 2011 Issuance of Amendment Nos. 209 and 211, Revise Technical Specification 3.4.15, RCS Leakage Detection Instrumentation, Operability Requirements and Actions ML1025304432010-09-29029 September 2010 Issuance of Amendment Nos. 208 and 210, Revise FSAR Update to Include Damping Values for Seismic Design/Analysis - Integrated Head Assembly ML1018901172010-07-30030 July 2010 Issuance of Amendment Nos. 207 and 209, Revise FSAR Update to Include Critical Damping Value for Structural Dynamic Qualification of Control Rod Drive Mechanism Pressure Housings ML0925405442009-09-17017 September 2009 Issuance of Amendment No. 208, Revise Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs) for Unit 2 Cycle 15 (Exigent Circumstances) ML0921203992009-08-19019 August 2009 Issuance of Amendment Nos. 206 and 207, Modify Technical Specifications to Adopt TSTF-511, Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 26 ML0907701812009-04-29029 April 2009 License Amendment, Issuance of Amendment Nos. 205 and 206, Revise TS 3.3.1, Reactor Trip System (RTS) Instrumentation, to Delete High-Negative Rate Trip Function ML0906308082009-03-30030 March 2009 Issuance of Amendment Nos. 204 and 205, Revise TS 3.7.5, Auxiliary Feedwater (AFW) System, and TS 3.7.6, Condensate Storage Tank (CST) and Fire Water Storage Tank (Fwst) ML0900803872009-01-15015 January 2009 Issuance of Amendment Nos. 203 and 204, Changes to Technical Specification 5.5.16, Containment Leakage Rate Testing Program ML0834601732008-12-31031 December 2008 Issuance of Amendment No. 202 and 203 Increase the Completion Times for Required Actions Related to Technical Specifications 3.5.2, the ECCS, and 3.6.6, CS & CS (Tac MD7512 & MD7513) ML0832906092008-12-23023 December 2008 Issuance of Amendment Nos. 201 and 202, Adoption of Changes to Standard Technical Specifications Under Technical Specifications Task Force (TSTF)-448 ML0824102622008-10-30030 October 2008 Issuance of Amendment Nos. 200 and 201, Technical Specifications Change to Relocate Surveillance Test Intervals to a Licensee-Controlled Program (Risk-Informed Initiative 5b) ML0732400062008-01-0808 January 2008 Units, 1 and 2, Issuance of Amendment Nos. 198 and 199, Revise Technical Specification (TS) 3.3.2, TS 5.5.9, and TS 5.6.10 to Support Replacement of Steam Generators ML0719102142007-07-11011 July 2007 License Amendments, Incorporated the Mitigation Strategies Required by Section B.5.b. of Commission Order EA-02-026 ML0713707312007-06-26026 June 2007 Issuance of License Amendment Nos. 197 and 198 TS 5.5.16, Containment Leakage Rate Testing Program, for Consistency with 10 CFR 50.55a(g)(4) 2024-05-29
[Table view] Category:Safety Evaluation
MONTHYEARML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) ML24270A1662024-10-0909 October 2024 Authorization and Safety Evaluation for Alternative Request No. REP-RHR-SWOL ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23199A3122023-07-20020 July 2023 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule ML22340A6752023-03-0606 March 2023 Approval of Certified Fuel Handler Training and Retraining Program ML23012A2172023-02-0909 February 2023 Issuance of Amendment Nos. 244 and 245 Revision to Technical Specifications to Adopt TSTF-569, Revision 2, Revise Response Time Testing Definition ML21242A2162022-12-21021 December 2022 Issuance of Amendment Nos. 243 and 244 Technical Specifications and Revised License Conditions for the Permanently Defueled Condition (EPID: L-2020-LLA-0261 ML22334A0822022-12-0101 December 2022 Correction to Issuance of Amendment Nos. 242 and 243 Revision to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML22187A0252022-11-16016 November 2022 Issuance of Amendment Nos. 242 and 243 Revision to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML22221A1682022-09-0606 September 2022 Issuance of Amendment Nos. 241 and 242 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspection ML21160A1742021-09-0202 September 2021 Issuance of Amendment Nos. 239 and 240 Revising Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)), to Implement Methodology from WCAP-17661, Revision 1 ML21188A3452021-07-0808 July 2021 Issuance of Amendment No. 238 Revision to TS 3.7.8, Auxiliary Saltwater (Asw) System (Emergency Circumstances) ML20249C8502020-10-22022 October 2020 Proposed Alternative NDE-RCS-SE-2R22 to the Requirements of the ASME Code ML20218A2762020-09-11011 September 2020 Issuance of Amendment Nos. 237 and 239 to Relocate Technical Specification 5.3, Unit Staff Qualifications, to Updated Final Safety Analysis Report ML20235R6352020-08-31031 August 2020 Issuance of Amendment Nos. 236 and 238 Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System, Exigent Circumstances ML19274B0822019-10-0707 October 2019 Correction to Issuance of Amendment Nos. 233 and 235 to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for ERO Positions ML19196A3092019-08-21021 August 2019 Issuance of Amendment Nos. 233 and 235 Regarding Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions ML19176A0082019-06-28028 June 2019 Request for Relief from the Inservice Inspection Program Requirements of ASME Code, Section XI, for Steam Generator and Pressurizer Nozzle Inside Radius Sections ML19023A0262019-01-25025 January 2019 Request for Alternative from Volumetric/Surface Examination Frequency Requirements of ASME Code Case N-729-4 ML17263A0592017-10-0606 October 2017 Diablo Canyon Power Plant, Unit 2 - Relief Requests to Allow Use of Proposed Alternatives to Implement Requirements of ASME Code, for Reactor Pressure Vessel Welds for the Third ISI Interval (CAC Nos. MF9386, MF9387, MF9388, MF9389, and MF9390) ML17212A3792017-09-25025 September 2017 Diablo Canyon Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 231 and 233 Re: Emergency Action Level Scheme Change (CAC Nos. MF8528 and MF8529) ML17132A2312017-05-16016 May 2017 Diablo Canyon Power Plant, Units 1 and 2 - Correction Letter Regarding Amendment Nos. 230 and 232 to Adopt Alternative Source Term (CAC Nos. MF6399 and MF6400) ML17012A2462017-04-27027 April 2017 Issuance of Amendments Revise Licensing Bases to Adopt Alternative Source Term ML17037D2672017-03-0909 March 2017 Relief Request NDE-RCS-SE-1R20 to Allow Use of Alternate Depth Sizing Criteria for the Fourth Inservice Inspection ML17018A3412017-02-23023 February 2017 Issuance of Amendments Revise Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System, ML16349A3862016-12-28028 December 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML16139A0082016-12-21021 December 2016 Issuance of Amendment Nos. 227 and 229, Digital Replacement of the Process Protection System Portion of the Reactor Protection System and Engineered Safety Features Actuation System ML16207A3972016-07-27027 July 2016 Relief Request NDE-SIF-U1, Allow Use of Alternate Examination Volume Coverage Requirements, Class 2 Seal Injection Welds, for the Third 10-Year Inservice Inspection Interval ML16117A2522016-05-19019 May 2016 Issuance of Amendment Nos. 226 and 228, Revise Minimum Flow Value Specified in Technical Specification 3.4.1, RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits ML16035A4412016-04-14014 April 2016 Issuance of Amendment Nos. 225 and 227, Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML16055A3592016-03-0909 March 2016 Issuance of Amendment Nos. 224 and 226, Revise Updated Final Safety Analysis Report for Beacon Power Distribution Monitoring System Methodology and TS 5.6.5 (COLR) Paragon and Nexus Methodologies ML16056A5132016-03-0707 March 2016 Relief Request FLIG-U1, Request to Extend Third 10-Year Inservice Inspection Interval for Reactor Vessel Stud Hole Ligament Examinations ML16055A2812016-02-26026 February 2016 Relief Request NDE-FWNS-U1/U2 to Allow Use of Alternate Examination Volume Coverage Requirements, Third 10-Year Inservice Inspection Interval ML16032A0062016-02-19019 February 2016 Redacted, Issuance of Amendment Nos. 223 and 225, Revise UFSAR Section 15.4.2.2 to Incorporate Pressurizer Filling Analysis for Major Rupture of a Main Feedwater Pipe Accident Into Licensing Basis ML16013A3402016-01-27027 January 2016 Relief Request NDE-PNS-U2A, ASME Code Section XI Requirements to Allow Use of Alternate Exam Volume Coverage Requirements, for the Third 10-year Inservice Inspection Interval ML15037A0062016-01-0505 January 2016 ISFSI - Safety Evaluation, Encl. 4, Amendment Nos. 222, 224, and 4 - Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended (CAC MF2809, MF2810, and L24991) ML15029A1732016-01-0505 January 2016 ISFSI - Issuance of Amendment Nos. 222, 224, and 4, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended (CAC MF2809, MF2810, and L24991) ML15337A0212015-12-0808 December 2015 Relief Request NDE-SG-MS-IR - Relief from Exam Requirements for Main Steam Nozzles in Replacement Steam Generators, Third 10-Year Inservice Inspection Interval ML15281A1642015-12-0303 December 2015 Issuance of Amendment Nos. 221 and 223, Revise Updated Final Safety Analysis Report and Approval to Perform Fuel Assembly Structural Analyses That Considers Application of Leak Before Break ML15299A0342015-11-0404 November 2015 Relief Request NDE-RCS-SE-2R19, Use of Alternate Sizing Qualification Criteria Through a Protective Clad Layer, Third 10-Year Inservice Inspection Interval ML15245A5422015-09-30030 September 2015 Issuance of Amendment Nos. 220 and 222, Request to Revise Operating License Condition Related to Cyber Security Plan Milestone H Full Implementation Date ML15261A0072015-09-18018 September 2015 Request for Relief PRS-3, Proposed Alternative to Requirements for System Leakage Testing Class 1 Piping Vent, Drain, and Test Isolation Devices, for the Third 10-year Inservice Inspection Interval (TAC MF6520-MF6521) ML15204A2222015-08-27027 August 2015 Issuance of Amendment Nos. 219 and 221, Adopt Technical Specifications Task Force Traveler TSTF-432, Revision 1, Change in Technical Specification End States (WCAP-16294) ML15187A0352015-07-15015 July 2015 Relief Request REP-SI, Revision 2, Proposed Alternative for Repair/Replacement Activities for Certain Safety Injection Pump Welded Attachments, Remaining Useful Life +20 Years ML15162A8822015-07-0101 July 2015 Issuance of Amendment Nos. 218 and 220, Revise Surveillance Requirements in TS 3.8.1, AC Sources, Related to Diesel Generator Testing ML15168A0242015-06-19019 June 2015 Request for Alternative RPV-U1 - Extension to Allow Use of Alternate Reactor Inspection Interval Requirements for the Third 10-Year Inservice Inspection Interval ML14251A4682014-09-16016 September 2014 Relief Request NDE-SFW-13, ASME Code Section XI, Request for Alternative to Allow Use of Alternate Examination Requirements, Third 10-Year Inservice Inspection Interval ML14196A0952014-08-0404 August 2014 Request for Relief from ASME Code Requirements for Mechanical Clamping Devices for Class 2 and 3 Piping Pressure Boundary ML14104B6132014-05-14014 May 2014 Relief Request NDE-PNS-U2, Requirements for Examination Coverage of ASME Class 1 Pressurizer Nozzle-to-Head Welds, Third 10-Year Inservice Inspection Interval ML14042A1932014-02-27027 February 2014 Issuance of Amendment Nos. 217 and 219, Editorial and Clarifying Changes to Technical Specification (TS) 3.7.10, Control Room Ventilation System (CRVS) and TS 5.6.5, Core Operating Limits Report (COLR) (TAC MF1959-MF1960) 2024-05-29
[Table view] Category:Technical Specifications
MONTHYEARDCL-24-018, License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2024-02-28028 February 2024 License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) ML23012A2172023-02-0909 February 2023 Issuance of Amendment Nos. 244 and 245 Revision to Technical Specifications to Adopt TSTF-569, Revision 2, Revise Response Time Testing Definition ML21242A2162022-12-21021 December 2022 Issuance of Amendment Nos. 243 and 244 Technical Specifications and Revised License Conditions for the Permanently Defueled Condition (EPID: L-2020-LLA-0261 DCL-22-059, License Amendment Request 22-03 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2022-07-26026 July 2022 License Amendment Request 22-03 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions ML21188A3452021-07-0808 July 2021 Issuance of Amendment No. 238 Revision to TS 3.7.8, Auxiliary Saltwater (Asw) System (Emergency Circumstances) ML21188A0372021-07-0707 July 2021 Attachment 1 TS_3_7_8 (Marked Up Pages) ML21188A0352021-07-0707 July 2021 Attachment 2 TS_3_7_8 (Retype Pages) ML21188A0342021-07-0707 July 2021 Attachment 3-TS Bases Section 3_7_8 (Marked-up Pages) DCL-19-094, License Amendment Request 19-02 to Relocate Technical Specification 5.3, Unit Staff Qualifications, to the Updated Final Safety Analysis Report2019-12-0505 December 2019 License Amendment Request 19-02 to Relocate Technical Specification 5.3, Unit Staff Qualifications, to the Updated Final Safety Analysis Report DCL-18-100, License Amendment Request 18-02 - License Amendment Request to Revise Technical Specification 5.6.5b1 Core Operating Limits Report (COLR) for Full Spectrum Loss-of-Coolant Accident Methodology2018-12-26026 December 2018 License Amendment Request 18-02 - License Amendment Request to Revise Technical Specification 5.6.5b1 Core Operating Limits Report (COLR) for Full Spectrum Loss-of-Coolant Accident Methodology ML16330A6722017-01-0505 January 2017 Issuance of Amendment Nos. 228 and 230, Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation ML16139A0082016-12-21021 December 2016 Issuance of Amendment Nos. 227 and 229, Digital Replacement of the Process Protection System Portion of the Reactor Protection System and Engineered Safety Features Actuation System ML16035A4412016-04-14014 April 2016 Issuance of Amendment Nos. 225 and 227, Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML16083A5642016-03-23023 March 2016 License Amendment Request 16-02, License Amendment Request to Revise Technical Specification 3.4.12., Low Temperature Overpressure Protection (Ltop) System. DCL-16-028, Technical Specifications B.4.17., Steam Generator (SG) Tube Integrity, LTOP Orifice-Key Design Features, and Additional Information2016-03-23023 March 2016 Technical Specifications B.4.17., Steam Generator (SG) Tube Integrity, LTOP Orifice-Key Design Features, and Additional Information ML16055A3592016-03-0909 March 2016 Issuance of Amendment Nos. 224 and 226, Revise Updated Final Safety Analysis Report for Beacon Power Distribution Monitoring System Methodology and TS 5.6.5 (COLR) Paragon and Nexus Methodologies ML16032A0062016-02-19019 February 2016 Redacted, Issuance of Amendment Nos. 223 and 225, Revise UFSAR Section 15.4.2.2 to Incorporate Pressurizer Filling Analysis for Major Rupture of a Main Feedwater Pipe Accident Into Licensing Basis ML15245A5422015-09-30030 September 2015 Issuance of Amendment Nos. 220 and 222, Request to Revise Operating License Condition Related to Cyber Security Plan Milestone H Full Implementation Date ML15204A2222015-08-27027 August 2015 Issuance of Amendment Nos. 219 and 221, Adopt Technical Specifications Task Force Traveler TSTF-432, Revision 1, Change in Technical Specification End States (WCAP-16294) ML15162A8822015-07-0101 July 2015 Issuance of Amendment Nos. 218 and 220, Revise Surveillance Requirements in TS 3.8.1, AC Sources, Related to Diesel Generator Testing DCL-15-052, Response to NRC Request for Additional Information Regarding License Amendment Request 14-01, Revision to Technical Specification 3.8.1, AC Sources - Operating.2015-04-29029 April 2015 Response to NRC Request for Additional Information Regarding License Amendment Request 14-01, Revision to Technical Specification 3.8.1, AC Sources - Operating. ML14042A1932014-02-27027 February 2014 Issuance of Amendment Nos. 217 and 219, Editorial and Clarifying Changes to Technical Specification (TS) 3.7.10, Control Room Ventilation System (CRVS) and TS 5.6.5, Core Operating Limits Report (COLR) (TAC MF1959-MF1960) ML13130A2252013-05-10010 May 2013 Technical Specification 3.5.2 Safety Injection Pump 2-1 Issue Information ML13267A1352013-01-31031 January 2013 Attachment 6 to DCL-13-016, LTR-RAM-1-13-002 NP-Attachment, Revision 0, Justification for the Application of Technical Specifications Changes in WCAP-14333 and WCAP-15376 to the Tricon/Als Process Protection System at the Diablo Canyon Powe DCL-12-107, Supplement to PG&E Letter DCL-11-059, License Amendment Request 11-04, Revision to Technical Specification (TS) 3.6.6, 'Containment Spray and Cooling Systems,' TS 3.7.5, 'Auxiliary Feedwater (AFW) System,' TS 3.8.1, 'Ac.....2012-11-0101 November 2012 Supplement to PG&E Letter DCL-11-059, License Amendment Request 11-04, Revision to Technical Specification (TS) 3.6.6, 'Containment Spray and Cooling Systems,' TS 3.7.5, 'Auxiliary Feedwater (AFW) System,' TS 3.8.1, 'Ac..... DCL-12-057, Supplement to PG&E Letter DCL-12-017, Response to NRC Request for Additional Information: NRC Question 12012-05-31031 May 2012 Supplement to PG&E Letter DCL-12-017, Response to NRC Request for Additional Information: NRC Question 1 DCL-11-097, License Amendment Request 11-05, Evaluation Process for New Seismic Information and Clarifying the Diablo Canyon Power Plant Safe Shutdown Earthquake2011-10-20020 October 2011 License Amendment Request 11-05, Evaluation Process for New Seismic Information and Clarifying the Diablo Canyon Power Plant Safe Shutdown Earthquake DCL-11-059, Diablo Canyon Units 1 & 2, License Amendment Request 11-04, Revision to Technical Specification 3.6.6, Containment Spray and Cooling Systems, TS 3.7.5, Auxiliary Feedwater System, TS 3.8.1, AC Sources-Operating, TS 3.8.9, Distribution Sys2011-06-0101 June 2011 Diablo Canyon Units 1 & 2, License Amendment Request 11-04, Revision to Technical Specification 3.6.6, Containment Spray and Cooling Systems, TS 3.7.5, Auxiliary Feedwater System, TS 3.8.1, AC Sources-Operating, TS 3.8.9, Distribution Syste DCL-11-055, Supplement to License Amendment Request 11-02, Revision to Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs).2011-04-21021 April 2011 Supplement to License Amendment Request 11-02, Revision to Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs). DCL-11-018, License Amendment Request 11-02, Revision to Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs)2011-02-17017 February 2011 License Amendment Request 11-02, Revision to Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs) DCL-10-028, Emergency License Amendment Request 10-02, One Time Revision to Technical Specification 3.8.1, AC Sources - Operating.2010-03-11011 March 2010 Emergency License Amendment Request 10-02, One Time Revision to Technical Specification 3.8.1, AC Sources - Operating. DCL-10-028, Diablo Canyon, Units 1 and 2, Emergency License Amendment Request 10-02, One Time Revision to Technical Specification 3.8.1, AC Sources - Operating.2010-03-11011 March 2010 Diablo Canyon, Units 1 and 2, Emergency License Amendment Request 10-02, One Time Revision to Technical Specification 3.8.1, AC Sources - Operating. DCL-10-018, License Amendment Request 10-01, Revision to Technical Specification 3.8.1, AC Sources - Operating.2010-02-24024 February 2010 License Amendment Request 10-01, Revision to Technical Specification 3.8.1, AC Sources - Operating. DCL-09-062, Emergency License Amendment Request 09-04 Revision to Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs) for Unit 2 Cycle 15.2009-09-0303 September 2009 Emergency License Amendment Request 09-04 Revision to Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs) for Unit 2 Cycle 15. ML0919601772009-07-0303 July 2009 License Amendment Request 09-02, Revision to Technical Specification 3.4.15, RCS Leakage Detection Instrumentation, Operability Requirements and Actions for RCS Leakage Detection Instrumentation DCL-09-009, License Amendment Request 09-01 - Revision to Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, Deletion of the High Negative Rate Trip Function2009-02-24024 February 2009 License Amendment Request 09-01 - Revision to Technical Specification 3.3.1, Reactor Trip System (RTS) Instrumentation, Deletion of the High Negative Rate Trip Function DCL-08-100, Supplement to License Amendment Request 07-03, Revision to Technical Specification 3.7.10, Control Room Ventilation System (CRVS)2008-11-25025 November 2008 Supplement to License Amendment Request 07-03, Revision to Technical Specification 3.7.10, Control Room Ventilation System (CRVS) ML0824102622008-10-30030 October 2008 Issuance of Amendment Nos. 200 and 201, Technical Specifications Change to Relocate Surveillance Test Intervals to a Licensee-Controlled Program (Risk-Informed Initiative 5b) DCL-07-097, License Amendment Request 07-04, Proposed Technical Specifications Change to Relocate Surveillance Test Intervals to a Licensee-Controlled Program (Risk Informed Technical Specifications Initiative 5b)2007-10-15015 October 2007 License Amendment Request 07-04, Proposed Technical Specifications Change to Relocate Surveillance Test Intervals to a Licensee-Controlled Program (Risk Informed Technical Specifications Initiative 5b) DCL-07-075, Supplement to License Amendment Request 07-01, Revision to Technical Specifications to Support Steam Generator Replacement, and Response to Request for Additional Information2007-08-0909 August 2007 Supplement to License Amendment Request 07-01, Revision to Technical Specifications to Support Steam Generator Replacement, and Response to Request for Additional Information ML0713707332007-06-26026 June 2007 Tech Spec Pages for Amendment Nos. 197 and 198 TS 5.5.16, Containment Leakage Rate Testing Program, for Consistency with 10 CFR 50.55a(g)(4) ML0709900742007-06-25025 June 2007 Units, 1 and 2, Tech Spec Page for Amendments 196 and 197 Administrative Changes to the Technical Specification 5.5.8, Inservice Testing Program. ML0703500522007-04-17017 April 2007 Tech Spec Pages for Amendment Nos. 195 and 196 TS 3.4.1 Reactor Coolant System Pressure, Temperature, & Flow Departure from Nucleate Boiling Limits & TS 5.6.5 Core Operating Limits Report. ML0704404942007-03-21021 March 2007 Tech Spec Pages for Amendments 194 and 195 Regarding Steam Generator Tube Integrity Technical Specifications ML0701902142007-01-19019 January 2007 Units, 1 and 2 - Tech Spec Pages for Amendments 192 and 193 Technical Specification 1.1 Definitions and Technical Specification 3.4.16 Reactor Coolant System Specific Activity DCL-06-143, License Amendment Request 06-10 Revision to Technical Specification 5.5.8, Inservice Testing Program2006-12-29029 December 2006 License Amendment Request 06-10 Revision to Technical Specification 5.5.8, Inservice Testing Program DCL-06-136, License Amendment Request 06-05 Revision to Technical Specification 3.4.1, Reactor Coolant System Pressure, Temperature, and Flow Departure from Nucleate Boiling Limits, and Technical Specification 5.6.5, Core Operating....2006-12-29029 December 2006 License Amendment Request 06-05 Revision to Technical Specification 3.4.1, Reactor Coolant System Pressure, Temperature, and Flow Departure from Nucleate Boiling Limits, and Technical Specification 5.6.5, Core Operating.... DCL-06-142, License Amendment Request 06-09, Revision to Technical Specification 5.5.16, Containment Leakage Rate Testing Program (TSTF-343)2006-12-29029 December 2006 License Amendment Request 06-09, Revision to Technical Specification 5.5.16, Containment Leakage Rate Testing Program (TSTF-343) ML0635500312006-12-20020 December 2006 Tech Spec Pages for Amendment 192 Regarding TS 5.6.5, Core Operating Limits Report. DCL-06-129, Special Report 06-03 - 180 Day Report for Steam Generator Technical Specification Task Force 449, Thirteenth Refueling Outage2006-11-17017 November 2006 Special Report 06-03 - 180 Day Report for Steam Generator Technical Specification Task Force 449, Thirteenth Refueling Outage 2024-02-28
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 27, 2014 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 - ISSUANCE OF AMENDMENTS RE: EDITORIAL REVISIONS TO TECHNICAL SPECIFICATIONS 3.7.10 AND 5.6.5 (TAC NOS. MF1959 AND MF1960)
Dear Mr. Halpin:
The U.S. Nuclear Regulatory Commission (the Commission) has issued the enclosed Amendment No. 217 to Facility Operating License No. DPR-80 and Amendment No. 219 to Facility Operating License No. DPR-82 for the Diablo Canyon Power Plant, Unit Nos. 1 and 2, respectively. The amendments consist of changes to the Technical Specifications (TSs) in response to your application dated June 6, 2013.
The amendments revise Technical Specification (TS) 3.7.10, "Control Room Ventilation System (CRVS)," and TS 5.6.5, "Core Operating Limits Report (COLR)," to incorporate editorial changes. Specifically, the amendments delete footnote (1) from the TS 3.7.10 Condition A Completion Time, and revise inconsistent wording in TS 5.6.5a.4, TS 5.6.5a.5, and TS 5.6.5a.9.
E. Halpin A copy of the related Safety Evaluation is enclosed. The Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice.
Sincerely, James Kim, Project Manager Plant Licensing IV-2 and Decommissioning Transition Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosures:
- 1. Amendment No. 217 to DPR-80
- 2. Amendment No. 219 to DPR-82
- 3. Safety Evaluation cc w/enclosures: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 PACIFIC GAS AND ELECTRIC COMPANY DOCKET NO. 50-275 DIABLO CANYON NUCLEAR POWER PLANT, UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 217 License No. DPR-80
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Pacific Gas and Electric Company (the licensee), dated June 6, 2013, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Enclosure 1
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and Paragraph 2.C.(2) of Facility Operating License No. DPR-80 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 217, are hereby incorporated in the license. Pacific Gas & Electric Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan, except where otherwise stated in specific license conditions.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days.
FOR THE NUCLEAR REGULATORY COMMISSION Michael T. Markley, Chief Plant Licensing IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Facility Operating License No. DPR-80 and Technical Specifications Date of Issuance: February 27, 2014
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 PACIFIC GAS AND ELECTRIC COMPANY DOCKET NO. 50-323 DIABLO CANYON NUCLEAR POWER PLANT. UNIT NO. 2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 219 License No. DPR-82
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Pacific Gas and Electric Company (the licensee), dated June 6, 2013, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Enclosure 2
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and Paragraph 2.C.(2) of Facility Operating License No. DPR-82 is hereby amended to read as follows:
(2) Technical Specifications (SSER 32. Section 8)* and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 219, are hereby incorporated in the license. Pacific Gas & Electric Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan, except where otherwise stated in specific license conditions.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days.
FOR THE NUCLEAR REGULATORY COMMISSION Michael T. Markley, Chief Plant Licensing IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Facility Operating License No. DPR-82 and Technical Specifications Date of Issuance: February 27, 2014
ATTACHMENT TO LICENSE AMENDMENT NO. 217 TO FACILITY OPERATING LICENSE NO. DPR-80 AND AMENDMENT NO. 219 TO FACILITY OPERATING LICENSE NO. DPR-82 DOCKET NOS. 50-275 AND 50-323 Replace the following pages of the Facility Operating License Nos. DPR-80 and DPR-82, and Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Facility Operating License Nos. DPR-80 and DPR-82 REMOVE INSERT Technical Specifications REMOVE INSERT 3.7-18 3.7-18 5.0-19 5.0-19
(4) Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5) Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C. This License shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1) Maximum Power Level The Pacific Gas and Electric Company is authorized to operate the facility at reactor core power levels not in excess of 3411 megawatts thermal (100% rated power) in accordance with the conditions specified herein.
(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix 8, as revised through Amendment No. 217, are hereby incorporated in the license.
Pacific Gas & Electric Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan, except where otherwise stated in specific license conditions.
(3) Initial Test Program The Pacific Gas and Electric Company shall conduct the post-fuel-loading initial test program (set forth in Section 14 of Pacific Gas and Electric Company's Final Safety Analysis Report, as amended), without making any major modifications of this program unless modifications have been identified and have received prior NRC approval. Major modifications are defined as:
- a. Elimination of any test identified in Section 14 of PG&E's Final Safety Analysis Report as amended as being essential; Amendment No. 217
(4) Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5) Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C. This License shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1) Maximum Power Level The Pacific Gas and Electric Company is authorized to operate the facility at reactor core power levels not in excess of 3411 megawatts thermal (100% rated power) in accordance with the conditions specified herein.
(2) Technical Specifications (SSER 32. Section 8)* and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix 8, as revised through Amendment No. 219, are hereby incorporated in the license.
Pacific Gas & Electric Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan, except where otherwise stated in specific license conditions.
(3) Initial Test Program (SSER 31, Section 4.4.1)
Any changes to the Initial Test Program described in Section 14 of the FSAR made in accordance with the provisions of 10 CFR 50.59 shall be reported in accordance with 50.59(b) within one month of such change.
- The parenthetical notation following the title of many license conditions denotes the section of the Safety Evaluation Report and/or its supplements wherein the license condition is discussed.
Amendment No. 219
CRVS 3.7.10 3.7 PLANT SYSTEMS 3.7.10 Control Room Ventilation System (CRVS)
LCO 3.7.10 Two CRVS trains shall be OPERABLE.
N0 TE-------------------------------------------------------------
The control room envelope (CRE) boundary may be opened intermittently under administrative controls.
APPLICABILITY: MODES 1, 2, 3, 4, 5, and 6.
During movement of recently irradiated fuel assemblies.
ACTIONS
NOTE---------------------------------------------------------
ACTIONS apply simultaneously to both units.
CONDITION REQUIRED ACTION COMPLETION TIME A. One CRVS train inoperable A.1 Restore CRVS train to 7 days for reasons other than OPERABLE status.
Condition B.
B. One or more CRVS trains B.1 Initiate action to Immediately inoperable due to implement mitigating inoperable CRE boundary actions.
in MODE 1, 2, 3, or 4. AND B.2 Verify mitigating actions 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ensure CRE occupant exposures to radiological hazards will not exceed limits, and CRE occupants are protected from smoke and chemical hazards.
AND B.3 Restore CRE boundary 90 days to OPERABLE status.
(continued)
DIABLO CANYON- UNITS 1 & 2 3.7-18 Unit 1- Amendment No. ~.~.-:t-84,w.t, 24-J, 217 Unit 2- Amendment No.~.-+%.~.~.~. 219
Reporting Requirements 5.6 5.6 Reporting Requirements (continued) 5.6.3 Radioactive Effluent Release Report
NOTE--------------------------------------------------------
A single submittal may be made for a multiple unit station. The submittal shall combine sections common to all units at the station; however, for units with separate radwaste systems, the submittal shall specify the releases of radioactive material from each unit.
The Radioactive Effluent Release Report covering the operation of the unit during the previous year shall be submitted prior to May 1 of each year in accordance with 10 CFR 50.36a. The report shall include a summary of the quantities of radioactive liquid and gaseous effluents and solid waste released from the unit. The material provided shall be consistent with the objectives outlined in the ODCM and Process Control Program and in conformance with 10 CFR 50.36a and 10 CFR 50, Appendix I, Section IV.B.1.
5.6.4 Not Used 5.6.5 CORE OPERATING LIMITS REPORT (COLR)
- a. Core operating limits shall be established prior to each reload cycle, or prior to any remaining portion of a reload cycle, and shall be documented in the COLR for the following:
- 1. Shutdown Bank Insertion Limits for Specification 3.1.5,
- 2. Control Bank Insertion Limits for Specification 3.1.6,
- 3. Axial Flux Difference for Specification 3.2.3,
- 4. Heat Flux Hot Channel Factor (F 0 (z)) for Specification 3.2.1,
- 5. Nuclear Enthalpy Rise Hot Channel Factor ( F~H) for Specification 3.2.2,
- 6. SHUTDOWN MARGIN values in Specifications 3.1.1, 3.1.4, 3.1.5, 3.1.6, and 3.1.8,
- 7. Moderator Temperature Coefficient limits in Specification 3.1.3,
- 8. Refueling Boron Concentration limits in Specification 3. 9.1, and
- 9. RCS Pressure, Temperature, and Flow DNB Limits in Specification 3.4.1.
(continued)
DIABLO CANYON - UNITS 1 & 2 5.0-19 Unit 1- Amendment No. ~.+SG,ct-9§, +00, 217 Unit 2- Amendment No. ~.~.4-00 . .:t-99, 219
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 217 TO FACILITY OPERATING LICENSE NO. DPR-80 AND AMENDMENT NO. 219 TO FACILITY OPERATING LICENSE NO. DPR-82 PACIFIC GAS AND ELECTRIC COMPANY DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-275 AND 50-323
1.0 INTRODUCTION
By application dated June 6, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13158A137), Pacific Gas and Electric Company (the licensee) requested changes to the Technical Specifications (Appendix A to Facility Operating License Nos. DPR-80 and DPR-82) for the Diablo Canyon Power Plant, Unit Nos. 1 and 2.
Specifically, the proposed changes would revise Technical Specification (TS) 3. 7.1 0, "Control Room Ventilation System (CRVS)," and TS 5.6.5, "Core Operating Limits Report (COLR)," to incorporate editorial changes.
2.0 REGULATORY EVALUATION
In Section 50. 36, "Technical specifications," of Title 10 of the Code of Federal Regulations
( 10 CFR), the Commission established its regulatory requirements related to the content of TS.
Pursuant to 10 CFR 50.36, TS are required to include items in the following five specific categories related to station operation: (1) safety limits, limiting safety system settings, and limiting control settings; (2) limiting conditions for operation; (3) surveillance requirements; (4) design features; and (5) administrative controls. The rule does not specify the particular requirements to be included in a plant's TS.
Enclosure 3
3.0 TECHNICAL EVALUATION
3.1 Proposed TS Changes 3.1.1 TS3.7.10 Current footnote (1) to the TS 3.7.10 Condition A Completion Time states:
(1) The Completion Time that one CRVS train can be inoperable as specified by Required Action A.1 may be extended beyond the 7 day completion time up to 13 days to support repair and restoration of the CRVS actuation instrumentation which required TS 3.7.10 Condition A entry per TS 3.3.7 Required Action 8.1.2.
Upon completion of the repair and restoration, this footnote is no longer applicable and will expire at 20:38 PST on December 10, 2012.
The amendment would delete the above footnote.
3.1.2 TS 5.6.5a.4 Current TS 5.6.5a.4 states:
Heat Flux Hot Channel Factor, K(Z) and W(Z)- F0 (z)(FaRTP Specification 3.2.1),
Revised TS 5.6.5a.4 would state:
Heat Flux Hot Channel Factor (F 0 (Z)) for Specification 3.2.1, 3.1.3 TS 5.6.5a.5 Current TS 5.6.5a.5 states:
RCS Flow Rate and Nuclear Enthalpy Rise Hot Channel Factor- FNAH(FRTPAH and PF AH for Specification 3.2.2),
Revised TS 5.6.5a.5 would state:
Nuclear Enthalpy Rise Hot Channel Factor (FNAH) for Specification 3.2.2, 3.1.4 TS 5.6.5a.9 Current TS 5.6.5a.9 states:
RCS pressure and temperature DNB limits in Specification 3.4.1, Revised TS 5.6.5a.9 would state:
RCS Pressure Temperature, and Flow DNB Limits in Specification 3.4.1.
3.2 NRC Staff Evaluation The NRC staff has reviewed the licensee's regulatory and technical analyses in support of its proposed license amendment, which are described in Sections 2 and 3 of the licensee's submittal. The NRC staff's evaluation is provided below:
3.2.1 Changes toTS 3.7.10 The proposed change to TS 3. 7.10 deletes a footnote that was included in a license amendment under emergency circumstances dated December 4, 2012 (ADAMS Accession No. ML12338A020). The footnote was only valid until December 10, 2012. Therefore, deletion of footnote ( 1) to the TS 3. 7.1 0 Condition A Completion Time is editorial in nature and, therefore, the change is acceptable.
3.2.2 Changes toTS 5.6.5 TS 5.6.5a specifies the limits that shall be documented in the Core Operating Limits Report (COLR). It also references specific TS section(s) for each required limit. The proposed changes correct inconsistent wording between the referenced TSs in 5.6.5a.4, 5.6.5a.5, and 5.6.5a.9, and the TS section titles. The changes are considered to be of an editorial and clarifying nature and are not material, such that the current intent of the requirement is unchanged. The NRC staff concludes that these changes are acceptable.
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the California State official was notified of the proposed issuance of the amendments. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
The amendments change a requirement with respect to the installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendments involve no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration and there has been no public comment on such finding published in the Federal Register on August 6, 2013 (78 FR 47791 ). Accordingly, the amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(1 O)(v). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) there is reasonable assurance that such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: Jennivine K. Rankin D~e: February 27, 2014
ML14042A193 *via Email OFFICE NRR/DORLILPL4-2/PM NRR/DORLILPL4-2/LA NRR/DSS/SCVB/BC* NRR/DSS/STSB/BC*
NAME JKim JBurkhardt RDennig REIIiott DATE 2/18/14 2/14/14 1/30/14 1/30/14 OFFICE NRR/DSS/SRXB/BC OGC/NLO with comments NRR/DORLILPL4-1/BC NRR/DORLILPL4-2/PM NAME CJackson SUttal MMarkley (Flyon for) JKim DATE 2/24/14 2/26/14 2/27/14 2/27/14