MONTHYEARML0329500082003-10-30030 October 2003 Letter, Request for Withholding Information from Public Disclosure. TAC No MB9888 and MB9889 Project stage: Withholding Request Acceptance ML0331002372003-11-10010 November 2003 Ltr, Request for Additional Information Core Operating Limits Report Project stage: RAI ML0334303912004-01-0909 January 2004 Issuance of License Amendments Core Operating Limits Report, (TAC Nos. MB9888 and MB9889). Non-Proprietary Project stage: Approval ML0401302782004-01-14014 January 2004 Letter, Correction Letter for Amendments 164/150 Project stage: Other 2003-11-10
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 ML23286A2602023-11-0808 November 2023 Issuance of Amendment Nos. 260 and 245 to Renewed Facility Operating Licenses Relocation of Pressure and Temperature Limit Curves to the Pressure Temperature Report IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212A9012023-08-0303 August 2023 Regulatory Audit Report to Support the Review of the Amendments to Relocation of the Pressure Temperature Limit Curves to the Pressure and Temperature Limits Report IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 ML23208A3182023-07-27027 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-07-24024 July 2023 Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis ML23192A5272023-07-12012 July 2023 NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 ML23186A2062023-07-0606 July 2023 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000374/2023010 ML23181A1502023-06-30030 June 2023 Combined Response to Request for Additional Information and Supplemental Information in Support of LAR to Relocate Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167A0352023-06-16016 June 2023 Registration of Use of Cask to Store Spent Fuel ML23171A9562023-06-12012 June 2023 Post Exam Ltr RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 ML23123A2202023-05-0303 May 2023 Relief Request I4R-14 for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23121A1612023-05-0101 May 2023 Information Meeting (Open House) with a Question-and-Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of LaSalle County Station, Units 1 and 2 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23107A1822023-04-18018 April 2023 Operator Licensing Examination Approval Lasalle County Station, May 2023 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23073A2182023-03-22022 March 2023 Issuance of Amendment No. 258 to Renewed Facility Operating Licenses Exigent Amendment to Revise Design Basis Related to Seismic Requirements RS-23-048, Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements2023-03-0707 March 2023 Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-037, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station2023-02-22022 February 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station ML23024A1372023-02-0303 February 2023 Request for Withholding Information from Public Disclosure for LaSalle County Station, Unit Nos. 1 and 2 ML23031A1972023-01-31031 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information, Inspection Report Nos. 05000373/2023011 and 05000374/2023011 IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 2024-01-05
[Table view] |
Text
January 14, 2004 Mr. John L. Skolds, President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LASALLE COUNTY STATION, UNITS 1 AND 2 - CORRECTION TO ISSUANCE OF AMENDMENTS (TAC NOS. MB9888 AND MB9889)
Dear Mr. Skolds:
On January 9, 2004, the Nuclear Regulatory Commission (Commission) issued Amendment No. 164 to Facility Operating License No. NPF-11 and Amendment No. 150 to Facility Operating License No. NPF-18 for the LaSalle County Station, Units 1 and 2, (LaSalle) respectively. The amendments consisted of changes to the Technical Specifications (TS) in response to your application dated July 1, 2003, as supplemented by letter dated December 10, 2003.
Based on discussions between your staff and the Commission staff on January 12, 2004, we are reissuing a corrected copy of page 5 of the Safety Evaluation dated January 9, 2004. The lower end of the Inlet Sub-Cooling range and the lower end of the R-Factor were incorrectly listed as 0.1 Btu/lbm and 1.03, respectively. These values should be 6 and 1.02, consistent with your supplemental letter dated December 10, 2003. The third paragraph is also corrected to reference the use of additional data provided in the December 10 letter to support these values rather than the use of extrapolated data.
We apologize for any inconvenience this may have caused.
Sincerely,
/RA/
William A. Macon, Jr., Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos.: 50-373 and 50-374
Enclosure:
As stated cc w/encl: See next page
January 14, 2004 Mr. John L. Skolds, President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LASALLE COUNTY STATION, UNITS 1 AND 2 - CORRECTION TO ISSUANCE OF AMENDMENTS (TAC NOS. MB9888 AND MB9889)
On January 9, 2004, the Nuclear Regulatory Commission (Commission) issued Amendment No. 164 to Facility Operating License No. NPF-11 and Amendment No. 150 to Facility Operating License No. NPF-18 for the LaSalle County Station, Units 1 and 2, (LaSalle) respectively. The amendments consisted of changes to the Technical Specifications (TS) in response to your application dated July 1, 2003, as supplemented by letter dated December 10, 2003.
Based on discussions between your staff and the Commission staff on January 12, 2004, we are reissuing a corrected copy of page 5 of the Safety Evaluation dated January 9, 2004. The lower end of the Inlet Sub-Cooling range and the lower end of the R-Factor were incorrectly listed as 0.1 Btu/lbm and 1.03, respectively. These values should be 6 and 1.02, consistent with your supplemental letter dated December 10, 2003. The third paragraph is also corrected to reference the use of additional data provided in the December 10 letter to support these values rather than the use of extrapolated data.
We apologize for any inconvenience this may have caused.
Sincerely,
/RA/
William A. Macon, Jr., Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos.: 50-373 and 50-374
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION:
PUBLIC PD3-2 r/f OGC GHill (4)
WBeckner ACRS DHills, RIII FAkstulewicz AAttard EKendrick ADAMS Accession Number: ML040130278 OFFICE PM:LPD3-2 LA:LPD3-2 SC:SRXB-A SC:LPD3-2 NAME WMacon PCoates FAkstulewicz AMendiola DATE 1/13/04 1/13/04 1/13/04 1/14/04 OFFICIAL RECORD COPY
LaSalle County Station Units 1 and 2 cc:
Site Vice President - LaSalle County Station Robert Cushing, Chief, Public Utilities Division Exelon Generation Company, LLC Illinois Attorney Generals Office 2601 North 21st Road 100 W. Randolph Street Marseilles, IL 61341-9757 Chicago, IL 60601 LaSalle County Station Plant Manager Regional Administrator Exelon Generation Company, LLC U.S. NRC, Region III 2601 North 21st Road 801 Warrenville Road Marseilles, IL 61341-9757 Lisle, IL 60532-4351 Regulatory Assurance Manager - LaSalle Illinois Emergency Management Exelon Generation Company, LLC Agency 2601 North 21st Road Division of Disaster Assistance &
Marseilles, IL 61341-9757 Preparedness 110 East Adams Street U.S. Nuclear Regulatory Commission Springfield, IL 62701-1109 LaSalle Resident Inspectors Office 2605 North 21st Road Document Control Desk - Licensing Marseilles, IL 61341-9756 Exelon Generation Company, LLC 4300 Winfield Road Phillip P. Steptoe, Esquire Warrenville, IL 60555 Sidley and Austin One First National Plaza Senior Vice President - Nuclear Services Chicago, IL 60603 Exelon Generation Company, LLC 4300 Winfield Road Assistant Attorney General Warrenville, IL 60555 100 W. Randolph St. Suite 12 Chicago, IL 60601 Vice President - Operations Support Exelon Generation Company, LLC Chairman 4300 Winfield Road LaSalle County Board Warrenville, IL 60555 707 Etna Road Ottawa, IL 61350 Chief Operating Officer Exelon Generation Company, LLC Attorney General 4300 Winfield Road 500 S. Second Street Warrenville, IL 60555 Springfield, IL 62701 Vice President - Licensing and Regulatory Chairman Affairs Illinois Commerce Commission Exelon Generation Company, LLC 527 E. Capitol Avenue, Leland Building 4300 Winfield Road Springfield, IL 62706 Warrenville, IL 60555
LaSalle County Station Units 1 and 2 Director Licensing Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Counsel, Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Manager Licensing - Clinton and LaSalle Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
(d) A final set of additive constants are determined by adjusting the preliminary additive constants, subject to minimizing the difference between the R-Factors.
The range of application for the GEXL97 correlation is the same as the range of the hypothetical database from which the correlation is derived. The applicable ranges are presented below:
i) Pressure: 800 to 1300 psia ii) Mass Flux: 0.1x106 to 1.5x106 lb/hr-ft2 iii) Inlet Sub-cooling: 6 to 100 Btu/lbm iv) R-Factor: 1.02 -- 1.20 This application range covers the complete range of expected operation of the ATRIUM-10 fuel during normal steady state and transient conditions in the LSCS BWR reload cores.
The lower end of the Inlet Sub-cooling range differs slightly from that presented in the licensees original submittal dated July 1, 2003. In that document, the lower end of the range was extrapolated from 10 down to zero for the Inlet Sub-cooling and the R-Factor range was also extrapolated from 1.03 down to 1.02. Following discussions with the NRC staff (documented in Ref. 2), the licensee and GNF acquired additional subcooling and R-Factor data to justify the desired ranges within the limits of the development database of the GEXL97 correlation.
With respect to the ranges stated above, GNF provided the results of analysis of the reference loading pattern for the LaSalle Unit 1, Cycle 11 mixed core reload, which has core operating characteristics that are representative of the conditions that will be encountered during this cycle. The CPR was extracted for all the ATRIUM-10 fuel throughout the entire cycle.
In summary, the NRC staff reviewed the analyses and results presented in NEDC-33106P, "GEXL97 Correlation for ATRIUM-10 Fuel," and determined that the analyses and results are in accordance with the guidance and limitations of 10 CFR 50.34, and the applicable sections of NUREG-0800, "Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants." In addition, the staff concludes that the analysis presented in NEDC-33106P is acceptable because:
(a) The total uncertainty in the correlations critical power predictions appropriately takes into account the fact that the uncertainty in the new correlations fit to the hypothetical database and the uncertainty in the hypothetical database with respect to the underlying experimental data are appropriately treated; (b) Generating the hypothetical database using the approved SPCB correlation encoded in the Framatome subchannel code XCOBRA-T is a reasonable engineering approach to dealing with mixed reload core fuel, where the experimental database and critical power correlation for the previous vendors fuel is not available to the new fuel vendor; (c) GNF intends to utilize the new GEXL97 correlation within the limits of the hypothetical data base, without extrapolation outside the approved limits of the data base, as specified in this safety evaluation (SE); and