Proposed Tech Specs 3.0 & 4.0 Incorporating Revs Endorsed by Generic Ltr 87-09
ML18096A189
Person / Time
Site: Salem  PSEG icon.png
Issue date: 07/30/1991
From:
Public Service Enterprise Group
To:
Shared Package
ML18096A187 List:
References
GL-87-09, GL-87-9, NLR-N91126, NUDOCS 9108080050
Download: ML18096A189 (5)


Text

ATTACHMENT 2 REVISED TECHNICAL SPECIFICATION PAGES GENERIC LETTER 87-09 CHANGES NLR-N91126 REVISION TO LCR 88-06 Page affected by revision:

Unit 1 Technical Specification Page 3/4 8-14 (New)

Insert Page 3 of 8 (Revised)

Insert Page 5 of 8 (Revised)

Insert Page 7 of 8 (Revised)

I-I INSERT F (continued)

Specification 3.0.2 establishes that noncompliance with a specification exists when the requirements of the Limiting Condition for Operation are not met and the associated ACTION requirements have not been implemented within the specified time interval. The purpose of this specification is to clarify that (1) implementation of the ACTION requirements within the specified time interval constitutes compliance with a specification and (2) completion of the remedial measures of the ACTION requirements is not required when compliance with a Limiting Condition of Operation is restored within the time interval specified in the associated ACTION requirements.

Specification 3.0.3 establishes the shutdown ACTION requirements that must be implemented when a Limiting Condition for Operation is not met and the condition is not specifically addressed by the associated ACTION requirements.

The purpose of this specification is to delineate the time limits for placing the unit in a safe shutdown MODE when plant operation cannot be maintained within the limits for safe operation defined by the Limiting Conditions for Operation and its ACTION requirements. It is not intended to be used as an operational convenience which permits (routine) voluntary removal of redundant systems or components from service in lieu of other alternatives that would not result in redundant systems or components being inoperable. One hour is allowed to prepare for an orderly shutdown before initiating a change in plant operation. This time permits the operator to coordinate the reduction in electrical generation with the load dispatcher to ensure the stability and availability of the electrical grid. The. time limits specified to reach lower MODES of operation permit the shutdown to proceed in a controlled and orderly manner that is well within the specified maximum cooldown rate and within the cooldown capabilities of the facility assuming only the minimum required equipment is OPERABLE. This reduces thermal stresses on components of the primary coolant system and the pote~tial for a plant upset that could challenge safety systems under conditions for which this specification applies.

If remedial measur~s permitting limited continued operation of the facility under the provisions of the ACTION requirements are completed, the shutdown may be terminated. The time limits of the ACTION requirements are applicable from the point in time there was a failure to meet a Limiting Condition for Operation. Therefore, the shutdown may be terminated if the ACTION requirements have been met or the time limits of the ACTION requirements have not expired, thus providing an allowance for the completion of the required actions.

The time limits of Specification 3.0.3 allow 37 hour4.282407e-4 days <br />0.0103 hours <br />6.117725e-5 weeks <br />1.40785e-5 months <br />s* for the plant to be in the COLD SHUTDOWN MODE when a shutdown is required during the POWER MODE of operation. If the plant is in a lower MODE of operation when a shutdown is required, the time limit for reaching the next lower MODE of operation applies. However, if a lower MODE of operation is reached in less time than allowed, the total allowable time to reach COLD SHUTDOWN, or other applicable MODE, is not reduced. For example, if HOT STANDBY is reached in 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, the time allowed to reach HOT SHUTDOWN is the next 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> because of the total time to reach HOT SHUTDOWN is not reduced from the allowable limit of 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br />. Therefore, if remedial measures are completed that would permit a return to POWER operation, a penalty is not incurred by having to reach a lower MODE of operation in less than the total time allowed.

Insert Page 3 of 8

INSERT G Specifications 4.0.1 through 4.0.5 establish the general requirements applicable to Surveillance Requirements. These requirements are based on the Surveillance Requirements stated in the Code of Federal Regulations, 10 CFR 50.36(c)(3):

"Surveillance requirements are requirements relating to test, calibration, or inspection to ensure that the necessary quality of systems and components is maintained, that facility operation will be within safety Limits, and that the Limiting conditions of operation will be met."

Specification 4.0.1 establishes the requirement that surveillances must be performed during the OPERATIONAL MODES or other conditions for which the requirements of the Limiting Conditions for Operation apply unless otherwise stated in an individual Surveillance Requirement. The purpose of this specification is to ensure that surveillances are performed to verify the operational status of systems and components and that parameters are within specified Limits to ensure safe operation of the facility when the plant is in a MODE or other specified condition for which the associated Limiting Conditions for Operation are applicable. surveillance Requirements do not have to be performed when the facility is in an OPERATIONAL MODE for which the requirements of the associated Limiting Condition for Operation do not apply unless otherwise specified. The Surveillance Requirements associated with a Special Test Exception are only applicable when the Special Test Exception is used as an allowable exception to the requirements of a specification.

Insert Page 5 of 8

~

INSERT H (continued) surveillance is terminated. If a surveillance test is to be performed when certain conditions exist and the provisions of Specification 4.0.4 are not applicable for entry into the mode at which those conditions ~ould be achieved, the time interval, whether it be the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> allowance or the allowed outage time of the action statement, begins when the plant reaches the conditions necessary to perform the test.

Surveillance Requirements do not have to be performed on inoperable equipment because the ACTION requirements define the remedial measures that apply.

However, the Surveillance Requirements have to be met to demonstrate that inoperable equipment has been restored to OPERABLE status.

Specification 4.0.4 establishes the requirement that all applicable surveillances must be met before entry into an OPERATIONAL MODE or other condition of operation specified in the Applicability statement. The purpose of this specification is to ensure that system and component OPERABILITY requirements or parameter limits are met before entry into a MODE or condition for which these systems and components ensure safe operation of the facility.

This provision applies to changes in OPERATIONAL MODES or other specified conditions associated with plant shutdown as well as startup.

Under the provisions of this specification, the applicable Surveillance Requirements must be performed within the specified surveillance interval to ensure that the Limiting Conditions for Operation are met during initial plant startup or following a plant outage.

When a shutdown is required to comply with ACTION requirements, the provisions of Specification 4.0.4 do not apply because this could delay placing the facility in a low~r ,MODE of operation.

Specification 4.0.5 establishes the requirement that inservice inspection of ASME Code Class 1, 2, and 3 components and inservice testing of ASME Code Class 1, 2, and 3 pumps and valves shall be performed in accordance with a periodically updated version of Section XI of th~ ASME Boiler and Pressure Vessel Code and Addenda as required by 10 CFR 50.55a. These requirements apply except when relief has been provided in writing by the Commission.

This specification includes a clarification of the frequencies for performing the inservice inspection and testing activities required by Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda. This clarification is provided to ensure consistency in surveillance intervals throughout the Technical Specifications and to remove any ambiguities relative to the frequencies for performing the required inservice inspection and testing activities.

Insert Page 7 of 8

.. ELECTRICAL El"R SYSTEMS e 3/4.8.3 ELECTRICAL EQUIPMENT PROTECTIVE DEVICES LIMITING CONDITION FOR OPERATION 3.8.3.l All containment penetration conductor overcurrent protective devices" required to provide thermal protection of penetrations shall be OPERABLE.

APPLICA.B!LITY: MODES 1, 2, 3 and*4.

ACTION:

With one or more of the required containment penetration conductor 6vercurrent p=otective device(s) inoperable:

a. Restore the protective device(s) to OPERABLE status or de-energize the circuit(s) by tripping either the primary or backup protective device, or racking out or removing the primary or backup device within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, declare the affected system or component inoperable, and verify the primary or backup protective device to be /

tripped, or the primary or backup device rackad out or removed at ~

least once per 7 days t~reaftar;ltho P***i*i*~ ef ipee~fiea*i**

13 *9 * " *** *** app l i ul> lo ** *"*<<w*nnt 4oni CH In c hew~** . vA <cR l:aa*:a tl:l.ai.r pri.ma:y or back11p protective dauic;i trippild, or wA3.c:h l:l.a\*e tl:le pwiaal'y or bac:k1.1p deuJ.c:* rac:kad 01.1t QI' l'MKiP.ted, or I !

b. Be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIREMENTS

4. 8. 3. l All required containment penetration conductor overcurrent protect i*Je devices shall be demon~trated OPERABLE:
a. At least once per LB months:
l. For at least ona 4.16 KV reactor coolant pump circuit, such that all reactor coolant pump circuits are demonstrated OPERABLE at least once per 72 months, by performance of:

(a)_ A. CHANNEL CALIBRATION of the associated protective relays, and (b) An integrated system functional test which includes simulated automatic actuation of tha system and verifying that each relay and associatad circuit breakers and control circuits function as d~signed

  • SALEM - UNIT 1 3/4 8-14 Amendment No. 105