MONTHYEARML24143A0612024-05-22022 May 2024 NRC Presentation Slides for Topical Reports to Support SLR (5-22-24 Public Meeting) V2 ML24100A8062024-04-0909 April 2024 Duke Energy Sites Annual Assessment Meeting Presentation Slides April 23, 2024 ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22007A2592022-02-0202 February 2022 Presubmittal Licensee Presentation for TS 3.5.3 PIV Testing LAR ML21167A0852021-06-24024 June 2021 Licensee Presentation for Robinson Pre-submittal Meeting TSTF-577 ML21174A3212021-06-24024 June 2021 Licensee Presentation for Robinson Presubmittal Meeting TSTF 577, Rev. 1 ML21105A7522021-04-15015 April 2021 2020 Robinson - EOC Presentation Slides ML19318F2912019-11-18018 November 2019 Duke Energy Presentation for the Pre-submittal Meeting on November 18, 2019, Regarding the RPV Stud Examination Relief Request ML19214A0562019-08-0707 August 2019 Presentation: Duke Energy Presubmittal Meeting - August 7, 2019 ML18144A0632018-05-24024 May 2018 Summary of Meeting Concerning Annual Assessment of H.B. Robinson Steam Electric Plant Unit 2 for Period of January 1, 2017 - December 31, 2017 ML17331A6272017-11-29029 November 2017 Duke Energy Pre-Submittal Meeting Presentation, Brunswick, Harris, and Robinson License Amendment Requests Regarding 10 CFR 50.69 ML17244A2272017-09-0707 September 2017 Duke Energy Presentation - H.B. Robinson 2017-09-07 Pre-sub Transmission Upgrade Meeting ML16112A2932016-05-0202 May 2016 05/02/2016 Presentation for Closed Pre-Submittal Meeting with Duke Energy Progress, Inc., to Discuss Fuel Reload Design Methodology Reports and Proposed LAR Re. H. B. Robinson And Shearon Harris Plants (CAC Nos. MF7443 And MF7444) RA-15-0041, Attachment 1, Affidavit and Attachment 3, Pre-Submittal Meeting Presentation Materials on DPC-NF-2010-A and DPC-NE-2011-P Methodologies (Redacted)2015-09-18018 September 2015 Attachment 1, Affidavit and Attachment 3, Pre-Submittal Meeting Presentation Materials on DPC-NF-2010-A and DPC-NE-2011-P Methodologies (Redacted) ML15231A6062015-08-19019 August 2015 Duke Energy Presentation - Robinson Nuclear Plant Transmission Upgrade Pre-submittal Meeting 08-26-2015 - MF6477 ML15125A4382015-05-0505 May 2015 Public Meeting Summary - 2014 Annual Assessment Public Meeting Regarding H.B. Robinson Steam Electric Plant ML15099A5872015-04-14014 April 2015 Duke Energy Slides for April 14 Meeting on NFPA-805 for Catawba, McGuire and Robinson ML14181A0782014-06-30030 June 2014 June 30 NRC Slides for Public Meeting with Duke - NTTF 2.1 - Seismic Reevaluation - GMRS ML14154A0932014-06-0303 June 2014 May 28, 2014, Summary of Category 1 Public Meeting - Annual Assessment of H.B. Robinson Steam Electric Plant ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13238A0542013-08-23023 August 2013 Meeting Summary - Category 1 Public Meeting Regulatory Conference, H.B. Robinson Steam Electric Plant, Docket No. 50-261 ML13127A0802013-04-18018 April 2013 Fleet Fire Protection Program NFPA 805 National Fire Protection Association NFPA 805 Pre-LAR Application for CNS, MNS, RNP ML12331A1782012-11-26026 November 2012 Meeting Slides Re GSI-191 Strainer Fiber Bypass Test Plan Slides for H. B. Robinson Unit 2 ML12206A3252012-08-0707 August 2012 G20120513/EDATS: OEDO-2012-0436 - Briefing Book for Meeting with Duke Energy on August 7, 2012 ML12188A0712012-07-11011 July 2012 G20120473/ EDATS: OEDO-2012-0404 - Briefing Book - Briefing Package for Meeting with Duke Energy on July 11, 2012 ML12107A3552012-04-16016 April 2012 4/11/2012 Summary of Category 1 Public Meeting - Annual Assessment of H.B. Robinson Steam Electric Plant ML1124200662011-08-30030 August 2011 Meeting Summary - Robinson - NRC Slides ML1124200682011-08-30030 August 2011 Meeting Summary - Robinson - Progress Energy Slides ML1123603572011-08-24024 August 2011 Meeting Slides ML1123601792011-08-24024 August 2011 8/25/2011- Robinson Nuclear Plant Regulatory Performance Meeting Slides ML12083A0492011-07-20020 July 2011 Meeting Slides - Meeting with Carolina Power & Light Company to Discuss the H. B. Robinson Steam Electric Plant, Unit 2 Performance Improvement Plant and New Management ML1113703442011-05-11011 May 2011 05/11/2011 Meeting Slides Regarding Strategic Plan ML1108909072011-03-30030 March 2011 Slides of Meeting Regarding H.B. Robinson Annual Assessment Meeting ML1108908992011-03-30030 March 2011 Attendance List of 03/24/11 Meeting Regarding Annual Assessment of H.B. Robinson Steam Electric Plant ML1013904942010-05-12012 May 2010 Event Review for Robinson - Slides ML1011703342010-04-27027 April 2010 Summary of Category 1 Public Meeting with Carolina Power and Light Company Regarding NRC Reactor Oversight Process Annual Assessment H.B. Robinson Steam Electric Plant, Unit 2 ML1006203162010-03-10010 March 2010 Summary of Meeting with Progress Energy Carolina, Inc. to Discuss Issues Identified During NRC Staff'S Review of H. B. Robinson Steam Electric Plant, Unit 2, Generic Letter 2004-02 Supplemental Responses ML0912706522009-05-0606 May 2009 Summary of Category 1 Public Meeting Discussed NRC Reactor Oversight Process Annual Assessment of H. B. Robinson, Unit 2 ML0830800052008-10-31031 October 2008 Meeting Slides, Progress Energy Public Meeting, NRC Region II Visit ML0813706302008-05-0707 May 2008 Slides from H. B. Robinson Meeting Re. Robinson Steam Electric Plant Annual Assessment Meeting Reactor Oversight Program - Cy 2007 ML0722100412007-07-26026 July 2007 Meeting Slides NRC Region Meeting Robinson Nuclear Plant. ML0716505352007-05-21021 May 2007 Enclosure - Slides for NRC CY2006 Annual Assessment Meeting ML0611402602006-04-0404 April 2006 Public Meeting Slides - Category One Management Meeting H. B. Robinson, Unit 2 ML0615301932006-03-27027 March 2006 NFPA 805 Pilot Observation Visit Trip Report - March 2006 - Handouts ML0523604402005-08-11011 August 2005 Attachment 4 - Progress Energy Slides ML0511004362005-03-24024 March 2005 NRC CY2004 Annual Assessment Meeting - Robinson - Hartsville, South Carolina, March 24, 2005 ML0436402692004-12-0909 December 2004 Progress Energy, Meeting Briefing of 12/9/04, Fire Protection Program ML0901504242004-08-25025 August 2004 Progress Energy Carolinas, Inc., Handouts for the Brunswick and H.B. Robinson NPP Tours During the Shearon Harris Scol Environmental Site Audit of Alternative Sites ML0410600042004-03-30030 March 2004 Presentation of NRC CY2003 Annual Assessment Meeting for H.B. Robinson 2024-05-22
[Table view] |
Text
NRC CY2004 Annual Assessment Meeting ROBINSON Hartsville, South Carolina March 24, 2005
Purpose of Todays Meeting A public forum for discussion of Robinson performance NRC will address Robinson performance issues identified in the annual assessment letter Robinson management will be given the opportunity to respond to the information in the letter and inform the NRC of new or existing programs to maintain or improve their performance
Agenda Introduction Review of Reactor Oversight Process National Summary of Plant Performance Discussion of Robinson Plant Performance Results Robinson Management Response and Remarks NRC Closing Remarks Break NRC Available to Address Public Questions
William Travers Regional Administrator Loren Plisco Deputy Regional Administrator Victor McCree Charles Casto Director Division of Reactor Projects Director Division of Reactor Safety Leonard Wert Harold Christensen Deputy Director Deputy Director Paul Fredrickson Regional Specialists Branch Chief Robinson Project Engineers Resident Inspectors George MacDonald Robert Hagar James Polickoski David Jones
NRC Performance Goals PRIMARY GOALS Ensure protection of the public health and safety and the environment Ensure the secure use and management of radioactive materials OTHER GOALS
- Ensure openness in NRC regulatory process
- Ensure that NRC actions are effective, efficient, realistic, and timely
- Ensure excellence in NRC management to carry out the NRCs strategic objective
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response
Examples of Baseline Inspections Equipment Alignment ~92 hrs/yr Triennial Fire Protection ~200 hrs every 3 yrs Operator Response ~125 hrs/yr Emergency Preparedness ~80 hrs/yr Rad Release Controls ~100 hrs every 2 yrs Worker Radiation Protection ~100 hrs/yr Corrective Action Program ~250 hrs every 2 yrs Corrective Action Case Reviews ~60 hrs/yr
Performance Thresholds Safety Significance Green: Very low safety issue White: Low-to-moderate safety issue Yellow: Substantial safety issue Red: High safety issue NRC Inspection Efforts Green: Only Baseline Inspections White: May increase NRC oversight Yellow: Increased NRC oversight Red: Increased NRC oversight and other NRC actions
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone ncreasing Safety Significance ncreasing NRC Inspection Efforts ncreasing NRC/Licensee Management Involvement ncreasing Regulatory Actions
National Summary of Plant Performance Status at End of CY 2004 icensee Response 78 egulatory Response 21 egraded Cornerstone 0 ultiple/Repetitive Degraded Cornerstone 3 nacceptable 0 Total 102*
Davis-Besse under a special inspection process
Robinson CY2004 Inspection Activities
- 4300 hours0.0498 days <br />1.194 hours <br />0.00711 weeks <br />0.00164 months <br /> of inspection related activities
- Radiation protection inspection
- Spent fuel storage construction and operations inspection
- Reactor vessel upper and lower head inspection
- Reactor containment sump blockage inspection
- Problem identification and resolution inspection
- Fire protection inspection
- Reactor operator initial exam
- Supplemental Inspection on reactor coolant leakage White performance indicator
Robinson CY2004 Assessment Results Performance was within the Licensee Response Column of the NRCs Action Matrix for the first three quarters Performance was within the Regulatory Response Column in the fourth quarter One Performance Indicator was classified in the fourth quarter as requiring additional NRC oversight (White)
All inspection findings were classified as very low safety significance (Green)
White Performance Indicator Reactor coolant system identified-leakage PI crossed the Green/White threshold in the fourth quarter A relatively large (7gpm) valve packing leak occurred on October 12, 2004 Unit was expeditiously shutdown and valve was repaired Supplemental inspection indicated corrective action was adequate
Robinson Annual Assessment Summary Progress Energy operated Robinson in a manner that preserved public health and safety All cornerstone objectives were met NRC plans baseline inspections at Robinson for the remainder of CY 2005
Robinson CY2005 Inspection Activities
- Resident inspector daily inspections
- Radiation protection inspections
- Spent fuel storage operations and construction inspections (Dry Run)
- Reactor head replacement inspection
- Safety system design and performance inspection
- Licensed operator requalification inspection
NRC CY2004 Annual Assessment Meeting ROBINSON Hartsville, South Carolina March 24, 2005
Contacting the NRC Report an emergency (301) 816-5100 (call collect)
Report a safety concern:
(800) 695-7403 Allegation@nrc.gov General information or questions www.nrc.gov Select What We Do for Public Affairs
Reference Sources Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html Public Electronic Reading Room http://www.nrc.gov/reading-rm.html Public Document Room 1-800-397-4209 (Toll Free)