|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML23335A0822023-12-0707 December 2023 NRC -Crystal River LTP Public Mtg Slide Deck Final ML23335A0832023-12-0707 December 2023 ADPCR3 - Crystal River LTP Public Mtg Slide Deck Final ML23341A1522023-12-0707 December 2023 December 11, 2023 Public Meeting - RIPE Exemption Request - Licensee Slides ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22153A3842022-06-0606 June 2022 Duke Energy Presentation Material for June 6, 2022 Public Meeting on GSI-191 Closeout ML22091A1332022-04-0101 April 2022 Bru Har Combined 2021 Assessment Meeting Slides ML22007A2592022-02-0202 February 2022 Presubmittal Licensee Presentation for TS 3.5.3 PIV Testing LAR ML21167A0852021-06-24024 June 2021 Licensee Presentation for Robinson Pre-submittal Meeting TSTF-577 ML21174A3212021-06-24024 June 2021 Licensee Presentation for Robinson Presubmittal Meeting TSTF 577, Rev. 1 ML21105A7522021-04-15015 April 2021 2020 Robinson - EOC Presentation Slides ML21041A4532021-02-17017 February 2021 Brunswick/Nrc Pre-submittal Meeting: LAR to Adopt TSTF-505, Rev. 2 (Risk-Informed Completion Times) Presentation ML21011A0822021-01-12012 January 2021 Pre-Submittal Meeting January 12, 2021, Revision to VRR-01, Full Stroke Testing of Safety/Relief Valves - Presentation Material ML20100G6342020-04-0909 April 2020 Revised- Bru 2019 Annual Assessment Meeting Slides ML20034F2842020-02-0303 February 2020 Implementation of TSTF-564 - NRC Conference Call - February 5, 2020 ML20022A0262020-01-22022 January 2020 NEI Presentation Status Update for Ropte Short Term Action Plan: Removed Planned Unavailability for Mitigating Systems Performance Index ML19318F2912019-11-18018 November 2019 Duke Energy Presentation for the Pre-submittal Meeting on November 18, 2019, Regarding the RPV Stud Examination Relief Request ML19214A0562019-08-0707 August 2019 Presentation: Duke Energy Presubmittal Meeting - August 7, 2019 ML19077A3672019-03-14014 March 2019 March 14, 2019 Pre-submittal Meeting TS DNBR Safety Limit Change LAR Meeting Slides ML18351A1342018-12-20020 December 2018 December 20, 2018 Pre-submittal Meeting Slides for Escw Risk-Informed LAR ML18333A1822018-11-0808 November 2018 Pre-Submittal Meeting - November 8, 2018 - License Amendment Request for Shearon Harris Nuclear Power Plant Emergency Plan Revision ML18255A0102018-09-12012 September 2018 NRC Slides for Target Rock Public Meeting ML18255A0142018-09-12012 September 2018 BWROG Presentation Slides for Public Meeting Sept 12 2018 ML18144A0632018-05-24024 May 2018 Summary of Meeting Concerning Annual Assessment of H.B. Robinson Steam Electric Plant Unit 2 for Period of January 1, 2017 - December 31, 2017 ML17331A6272017-11-29029 November 2017 Duke Energy Pre-Submittal Meeting Presentation, Brunswick, Harris, and Robinson License Amendment Requests Regarding 10 CFR 50.69 ML17297B7892017-10-26026 October 2017 Meeting Slide for Partially Closed Pre-submittal Public Meeting with Duke Energy for License Amendment Request to Adopt Areva'S XM-11 Fuel Methodology for Brunswick Steam Electric Plant ML17244A2272017-09-0707 September 2017 Duke Energy Presentation - H.B. Robinson 2017-09-07 Pre-sub Transmission Upgrade Meeting ML17250B2382017-08-30030 August 2017 TMRE Presubmittal NRC ML17229B2942017-08-22022 August 2017 Meeting Slide Regarding Partially Closed Pre-submittal Public Meeting with Duke Energy for a License Amendment Request for Brunswick Steam Electric Plant ML17044A0892017-03-0202 March 2017 EDG SR Presubmittal Meeting March 2, 2017 ML16267A0292016-09-29029 September 2016 SFP Pre-Submittal Meeting Slides - BWR Storage Rack Inserts, Updated NCS Analysis at Harris Nuclear Plant ML16231A1322016-08-18018 August 2016 Materials for 8/18/16 Pre-Application Meeting Brunswick Mellla+ LAR ML16210A5152016-07-28028 July 2016 Bnp Commercial Grade Dedication Issue (Printable) ML16134A1742016-05-12012 May 2016 Summary of Public Meeting - 2015 Annual Assessment Regarding Brunswick, Units 1 and 2 ML16112A2932016-05-0202 May 2016 05/02/2016 Presentation for Closed Pre-Submittal Meeting with Duke Energy Progress, Inc., to Discuss Fuel Reload Design Methodology Reports and Proposed LAR Re. H. B. Robinson And Shearon Harris Plants (CAC Nos. MF7443 And MF7444) ML17227A2362016-02-18018 February 2016 Presentation Slides from February 18, 2016, Meeting with Duke Energy Regarding Crystal River Unit 3, Cyber Security Plan Implementation Schedule Milestone 8 RA-15-0041, Attachment 1, Affidavit and Attachment 3, Pre-Submittal Meeting Presentation Materials on DPC-NF-2010-A and DPC-NE-2011-P Methodologies (Redacted)2015-09-18018 September 2015 Attachment 1, Affidavit and Attachment 3, Pre-Submittal Meeting Presentation Materials on DPC-NF-2010-A and DPC-NE-2011-P Methodologies (Redacted) ML15231A6062015-08-19019 August 2015 Duke Energy Presentation - Robinson Nuclear Plant Transmission Upgrade Pre-submittal Meeting 08-26-2015 - MF6477 ML15125A4382015-05-0505 May 2015 Public Meeting Summary - 2014 Annual Assessment Public Meeting Regarding H.B. Robinson Steam Electric Plant ML15125A4602015-05-0505 May 2015 Summary of Public Meeting to Discuss the Annual Assessment of the Brunswick Steam Electric Plant with the Public for the Period of January 1, 2014, Through December 31, 2014 ML15099A5872015-04-14014 April 2015 Duke Energy Slides for April 14 Meeting on NFPA-805 for Catawba, McGuire and Robinson ML14181A0782014-06-30030 June 2014 June 30 NRC Slides for Public Meeting with Duke - NTTF 2.1 - Seismic Reevaluation - GMRS ML14154A0932014-06-0303 June 2014 May 28, 2014, Summary of Category 1 Public Meeting - Annual Assessment of H.B. Robinson Steam Electric Plant ML14140A1882014-05-19019 May 2014 Summary of Public Meeting - 2013 Annual Assessment Regrading Brunswick Steam Electric Plant ML14129A3352014-05-0909 May 2014 Summary of Category 1 Public Meeting - Annual Assessment of Shearon Harris Nuclear Plant ML14024A2632014-01-16016 January 2014 Handouts for Post-Shutdown Decommissioning Activities Report Public Meeting, January 16, 2014 ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13277A0382013-09-24024 September 2013 GEH Presentation on Methods Applicability to Areva Atrium 10XM Fuel ML13238A3072013-08-29029 August 2013 Slide for 08/29/13 Meeting CR-3 Decommissioning Submittals ML13238A0542013-08-23023 August 2013 Meeting Summary - Category 1 Public Meeting Regulatory Conference, H.B. Robinson Steam Electric Plant, Docket No. 50-261 2023-12-07
[Table view] |
Text
Fire Protection Initiatives NRC Meeting December 9, 2004 Brunswick (BNP)
Crystal River 3 (CR3)
Harris (HNP)
Robinson (RNP)
Nuclear Generation Group a3 Progress Energy No commitments are made or implied by this presentation.
Information is presented to stimulate dialogue.
'Fire Protection Initiatives Progress Energy Participants P Paul Gaffney, Corporate - Chief Elect/l&C Engineer P Jeff Ertman, Corporate - Fire Protection Engineer o Frank Dola, CR3 - Operations o Steve Hardy, BNP - SSA Project Manager o John Kunzmann, HNP - SSA Engineer
- Frank Modlin, RNP - Appendix R Engineer o Chuck Baucom, RNP - Licensing Supervisor o Ken Heffner, Corporate - Licensing P Additional personnel by phone
- Tony Maness, HNP - FP Project Manager lNuclear Progress Energl i
Group Page 2 0
Fire Protection Initiatives Outline
- Areas of Continuing or Future Interest
- Provide additional results and insights using examples
- Closing Summary reneraton NeaG~ Page 3 Progress Energj
=
Background===
- What Progress Energy is doing:
o Safe Shutdown Analysis (SSA) Validation o Revised Manual Action Feasibility Evaluations
o Address specific site issues o Incorporate latest industry information into the SSA NcGeneration Gru u Pager4 Progress Energy
=
Background===
Fire Protection SSA Goals
- Safety P Compliance - Current Design Methodology (CDM)
- Appendix R/NUREG 800 (HNP) o Add New Criteria - Revised Design Methodology (RDM) based on new data
- Consistent Approach at all PE Sites
- Forward Looking Tools P Use Computer Aided Fault Tree Analysis (CAFTA) tool for logic development d(
Nucear U
w Generation Group Page 5 Progress Energj
=
Background===
PE SSA Methiodology Overview d bGroup Nuclear Generation Page 6 Progress Energl
=
Background===
SSA Revised Design Methodology
- Examples - RDM Criteria added SSA:
o Multiple circuit failures per circuit - for
'enhanced' cable selection
- Multiple components with in a single cable o Up to two concurrent spurious actuations
- Examples - Enhanced Manual Actions Criteria:
- Define higher complexity areas P Add timeline definition p
GuceaGeneration Pageruc Progress Energl
=
Background===
SSA Methodology Development Some of the
References:
P EPRI cable test data P February 2003 NRC Fire Induced Cable Failure workshop results P Revised IP71111.05 P RIS 2004-03 P NRC Federal Register Notice on Manual actions late 2003 P NEI 00-01, NEI 04-06 Nudear Generaton Page 8 Group W Progress Energj
=
Background===
PE FP SSA Project Problem Resolution
, ib Nudear
,Group Generabon Page 9 Progress EnergI
Status SSA Validation Project
- Established design guidelines from available published information - some details previously provided
- Various stages of Project implementation at each site
- HNP current target complete in 2005
- BNP, RNP, CR3 current target complete analysis by end of 2006
- Recognize PE will need to address final NRC criteria in the future
- Problem resolution and modifications not included in this project schedule Nudear E
if -
^
Generation Page 10fi rgesE rg Pg 1
Status SSA Validation Project The PE SSA Validation Project meets the intent of NEI 04-06 Self Assessment guidance PE views our Validation Project as meeting the self assessment requirement for applicability of NRC proposed enforcement discretion for circuit failure findings
( ~ Nuclear ag
( ~Generation Page IIU PoresEeg
Status Revised Manual Action Feasibility
- Used NRC Criteria from the late 2003 Federal Register notice - not a major change from previous PE criteria
- Demonstrate that the time to complete manual operator actions is bounded by the time to reach an unrecoverable condition
- CR3 and RNP completed in 2004; BNP scheduled in early 2005; HNP in mid 2005 1 Recognize PE will need to address final NRC criteria in the future l Nuclear
( Gue Group arGeneration Page 12 0 Progress EnergI
Results to Date SSA Current Design Methodology
- Majority of the existing analysis has been demonstrated effective
- Have identified some cables that are not protected
- Improved Fire SSD Procedures
- Added system's for increased flexibility such as off site power Nuclear d
Generation Group Page 13 Progress Energl
Results to Date SSA Revised Design Methodology
P Boundary Valves in series
- Scope of Cables Selected o For SSEL components, typically did not result in more cables pulled into the analysis o More cables were evaluated as spurious
- Multiple spurious actuations being systematically addressed l Nuclear PrgesE rg Po d Generation Page 14 Gru rgesEeg
Areas of Continuing or Future Interest
- Progress Energy Internal Initiatives o Addition of RDM criteria into SSA P Use of PB/RI tools to address multiple cable failures and resulting spurious actuations
- Credit offsite power for non-lIl.G.3 Fire Areas P Change Fire Area resolution strategy from llI.G.3 to shutdown from the control room P Use of available off site power in addition to on site emergency power supplies for selected Il.G.3 Fire Areas (Nudear Group Page 15 3 Progress Energy
Areas of Continuing or Future Interest F*ire Rated Cable to Meet Il.G.2 (or NUREG-0800 Equivalent)
Requirements
- Resolution of Manual Actions P Manual actions not previously approved in accordance with Il.G.2 o Suppression in Fire Areas with manual actions P Alternative means of establishing manual action time line
( Nuclear Group Page 16 0 Progress Ei rerg
Additional Discussion of Results and Insights Discuss Examples Answer Questions
,[ Nuclear Generation Page 17 d Group Progress Energy
Summary
. All sites current engaged in SSA Validation
. Waiting for completion of staff guidance on some aspects of the initiatives
/ b Nuclear Generation Page 18 Progress Energj I Group