Public Meeting - NRC Slides - Perry CAL Follow-up Inspection - Performance Improvement Initiative
ML053490405
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 12/14/2005
From:
NRC/RGN-III
To:
References
Download: ML053490405 (17)


Text

Perry Nuclear Power Plant Perry CAL Followup Inspection -

Performance Improvement Initiative Nuclear Regulatory Commission - Region III Lisle, Illinois December 14, 2005

Purpose of Todays Meeting z Provide a public forum for the discussion of Perry Nuclear Power Plant performance z NRC to discuss the results of our review of the revised Perry Performance Improvement Initiative z Perry management will respond to the information presented z Receive comments and questions from the public www.nrc.gov

Agenda z Introduction z Discussion of Perry Nuclear Power Plant Performance z Overview of Confirmatory Action Letter (CAL) z Overview of CAL Inspection Activities z Revised Perry Performance Improvement Initiative -

Inspection Scope and Results z Licensee Response and Remarks z Adjourn NRC meeting with FENOC

<Break>

z Public Comments and Questions of NRC z Adjourn Meeting www.nrc.gov

Review of Perry Performance

  • August 2004 - Perry enters Multiple/Repetitive Degraded Cornerstone of NRC Action Matrix
  • January-May 2005 - IP 95003 Inspection Conducted
  • May 2005 - Public Exit Meeting for IP 95003
  • July 2005 - IP 95003 Inspection Report Issued
  • September 2005 - NRC Issues CAL
  • November 2005 - NRC Reviews Revised PII www.nrc.gov

Confirmatory Action Letter (CAL)

FENOC Committed to Sustained Improvement in:

  • Corrective Action Program Effectiveness
  • Human Performance

Perry CAL Inspection Activities Planned NRC Inspection Activities:

  • Review Licensees Assessment Activities and Corrective Action Development
  • Review Corrective Action Implementation
  • Review Corrective Action Effectiveness www.nrc.gov

Inspection Scope - Revised Perry Performance Improvement Initiative Perry Phase 2 PII Scope

  • Corrective Action Program Implementation Improvement
  • Excellence in Human Performance
  • Training to Improve Performance
  • Effective Work Management
  • Employee Engagement and Job Satisfaction
  • Operational Focused Organization www.nrc.gov

Inspection Scope - Revised Perry Performance Improvement Initiative Inspection Scope

  • Phase 1 PII Item Dispositioning
  • Commitments and Action Items to Address IP 95003 Issues
  • Processes and Procedures
  • Phase 2 PII Performance Indicators
  • Phase 2 PII to Resolve Performance Issues www.nrc.gov

Inspection Results - Revised Perry Performance Improvement Initiative Inspection Results

  • Phase 1 PII Item Dispositioning - Adequate
  • Open Phase 1 Items Properly Categorized
  • Completed Phase 1 Items Not Reviewed
  • Commitments and Action Items to Address IP 95003 Issues
  • Issues Not Specifically Addressed in PII
  • Flexible Actions Required Implementation Rigor
  • Issues Addressed Outside of PII www.nrc.gov

Inspection Results - Revised Perry Performance Improvement Initiative Inspection Results

  • Processes and Procedures
  • Processes and Procedures Adequate
  • Performance Improvement Initiative Process Procedure Developed
  • Phase 2 PII Performance Indicators
  • Some Performance Indicators in Development
  • Existing Performance Indicators Appear Adequate www.nrc.gov

Inspection Results - Revised Perry Performance Improvement Initiative Inspection Results

  • Phase 2 PII to Resolve Performance Issues
  • Adequate Dispositioning of Phase 1 Items
  • Adequate Scope
  • Adequate Process and Procedures
  • Adequate Performance Indicators Conclusion - Phase 2 PII Adequate www.nrc.gov

Summary Perry is Being Operated Safely Challenge Areas:

- Corrective Action Program Implementation

- Human Performance Continued Supplementary Oversight www.nrc.gov

Perry Nuclear Power Plant Upcoming NRC Activities Corrective Action Implementation Reviews z IP 95002 Action Item Review z Corrective Action Program Action Item Review z Emergency Preparedness Action Item Review z Human Performance Action Item Review www.nrc.gov

Contacts for Additional Information Regional Public Affairs Officer

  • Phone: (630) 829-9663 or (630) 829-9662 Perry Resident Inspector Office
  • Ray Powell, Senior Resident Inspector
  • Phone: (440) 259-3610 www.nrc.gov

Reference Sources z Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html z Public Electronic Reading Room http://www.nrc.gov/reading-rm.html z Public Document Room 1-800-397-4209 (Toll Free) www.nrc.gov

Summary Perry is Being Operated Safely Challenge Areas:

- Corrective Action Program Implementation

- Human Performance Continued Supplementary Oversight www.nrc.gov

Questions and Comments From the Public www.nrc.gov