Notice of Annual Assessment Meeting with Exelon Generation Company, LLC, Regarding the Safety Performance of the Three Mile Island Power Station
ML090780385
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 03/19/2009
From: Bellamy R
NRC/RGN-I/DRP/PB6
To:
BELLAMY RR
References
Download: ML090780385 (4)


Text

MN No.09-008 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF SIGNIFICANT LICENSEE MEETING March 19, 2009 Licensee: Exelon Generation Company, LLC Facilities: Three Mile Island Power Station, Unit 1 Docket No(s). 50-289 Time and Date: April 2, 2009, 7:00 - 9:00 pm Location: Londonderry Town Hall 738 South Geyers Church Road Middletown, PA 17057

Purpose:

The NRC requested an Annual Assessment Meeting with Exelon management to discuss NRCs assessment of the safety performance of the Three Mile Island Power Station for calendar year 2008, as described in the Annual Assessment Letter dated March 4, 2009. Exelon management will be given the opportunity to respond to the information in the letter and inform the NRC of new or existing programs to maintain or improve their performance. The NRC will also be available to engage interested stakeholders on performance of the plant and our role in ensuring safe plant operations.

NRC Attendees: R. Bellamy, Chief, Projects Branch 6, Region I D. Kern, Senior Resident Inspector, Three Mile Island J. Brand, Resident Inspector, Three Mile Island Licensee Attendees: B. Noll, Three Mile Island Site Vice President, Exelon T. Dougherty, Three Mile Island Plant Manager, Exelon B. Carsky, Three Mile Island Operations Director, Exelon S. Queen, Three Mile Island Engineering Director, Exelon Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

Meeting

Contact:

Dr. Ronald R. Bellamy, Chief, Projects Branch 6 610-337-5200 E-mail: ronald.bellamy@nrc.gov.

2 The NRCs Annual Assessment Letter for Three Mile Island Unit 1 can be located in ADAMS with Accession Number ML090620783. This meeting notice with the enclosed agenda can be located in ADAMS with Accession Number ML090780385. The NRC slides for the meeting can be located in ADAMS with Accession Number ML090750834. ADAMS is accessible from the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html.

Additional information relative to the NRCs Annual Assessment process and the safety performance of the Three Mile Island Power Station can be found on the NRCs web site at:

http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. The NRC=s Policy Statement, AEnhancing Public Participation in NRC Meetings,@ effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, http://www.nrc.gov/reading-rm/doc-collections/commission/policy/67fr36920.html and contains information regarding visitors and security.

Handicapped persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting, to provide the NRC staff adequate notice to determine whether the request can be accommodated. Attendance by NRC personnel at this meeting should be made known by March 24, 2009, via telephone to the NRC meeting contact.

Approved by: ____/RA/ _______________

Ronald R. Bellamy, Ph.D., Chief Projects Branch 6 Division of Reactor Projects Distribution:

C. Crane, President and Chief Operating Officer, Exelon Corporation M. Pacilio, Chief Operating Officer, Exelon Nuclear W. Noll, Site Vice President, TMI Unit 1, Exelon Nuclear T. Dougherty, Plant Manager, TMI, Unit 1, Exelon Nuclear Manager, Regulatory Assurance, TMI, Unit 1, Exelon Nuclear Senior Vice President, Nuclear Services, Exelon Nuclear Senior Vice President, Mid-Atlantic Operations, Exelon Nuclear Senior Vice President, Operations Support, Exelon Nuclear Vice President, Licensing and Regulatory Affairs, Exelon Nuclear P. Cowan, Director, Licensing, Exelon Nuclear D. Helker, Licensing, Exelon Generation J. Fewell, Esq., Associate General Counsel, Exelon Correspondence Control Desk, Exelon Nuclear Chairman, Board of County Commissioners of Dauphin County Chairman, Board of Supervisors of Londonderry Township R. Janati, Director, Bureau of Radiation Protection, State of PA D. Allard, Director, PA DEP J. Johnsrud, National Energy Committee E. Epstein, TMI-Alert (TMIA)

J. Powers, Director, PA Office of Homeland Security R. French, Director, PA Emergency Management Agency

3 Three Mile Island Nuclear Power Station, Unit 1 Annual Assessment Meeting Agenda:

April 2, 2009

  • Introduction and NRC Organization
  • Review of NRC Reactor Oversight Process
  • Regulatory Summary of National Plant Performance
  • NRC Assessment of Plant Performance Results
  • Exelon Response and Remarks
  • NRC Closing Remarks
  • Break
  • NRC Available to Address Public Questions

4 Distribution w/encl: (VIA E-MAIL)

Executive Director for Operations, OEDO (RIDSEDOMAILCENTER RESOURCE)

Deputy Executive Director for Reactor Programs,OEDO (RIDSEDOMAILCENTER RESOURCE)

Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD)

Associate Director, Office of Operating Reactor Oversight and Licensing, NRR/ADRO (RIDSNRRADRO)

Director, Division of Inspection and Regional Support, NRR/DIRS (RIDSNRRDIRS)

Director, Division of Operating Reactor Licensing, NRR/DORL (RIDSNRRDORL)

Project Directorate I-1 (PD1/2), NRR (RIDSNRRDORILPI 1-2)

Asst. General Counsel Materials Litigation and Enforcement, OGC (RIDSOGCMAILCENTER)

S. Collins, RA R. Bellamy, DRP M. Dapas, DRA S. Barber, DRP D. Roberts, DRS S. Campbell, RI, OEDO E. Cobey, DRS C. Newport, DRP E. Miller, NRR D. Kern, DRP - Senior Resident Inspector J. Lubinski, NRR J. Brand, DRP - Resident Inspector H. Chernoff, NRR C. LaRegina, DRP, OA P. Bamford, PM, NRR N. McNamara, SLO K. Farrar, Regional Counsel DRP Division Secretary, RI D. Screnci, Senior PAO DRS Division Secretary, RI N. Sheehan, Field PAO G. Matakas, ORA, Secretary D. Lew, DRP PMNS J. Clifford, DRP Region I Docket Room (with concurrences)

J. Thompson, NRR Accession Number ML090780385 SUNSI REVIEW COMPLETE: __RRR____ (Reviewers Initials)

DOC NAME: G:\DRP\BRANCH6\ROP Assessment Folders\ROP 9\AA Meeting Notices and slides\TMI AA Meeting Notice 2008.doc After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE: RI/DRP RI/DRP NAME: SBarber/SB RBellamy/RRR DATE: 03/18/09 03/19 /09 OFFICIAL RECORD COPY