Letter Sequence Request |
|---|
|
|
MONTHYEARML0800804772008-01-0808 January 2008 Notice of Non-Public Meeting with Exelon to Discuss Plans to Transition Wackenhut Security Workforce to a Proprietary In-House Workforce Project stage: Request ML0817104702008-05-19019 May 2008 License Renewal Application, May 19, 2008 Draft Request for Additional Information, for Sections 4.2 and 4.4 Project stage: Draft RAI ML0817800062008-07-23023 July 2008 License Renewal Application, June 5, 2008 Conference Call Between USNRC and Amergen to Discuss Draft Requests for Additional Information for Sections 4.2 and 4.4 Project stage: Draft RAI ML0821700462008-08-20020 August 2008 Unit - 1, Request for Additional Information, License Renewal Application, Sections 4.2 and 4.4, TAC MD7701 Project stage: RAI ML0821804992008-08-20020 August 2008 Request for Additional Information, License Renewal Application, Sections 2.3.3 & 2.3.4 Project stage: RAI ML0821800062008-08-22022 August 2008 License Renewal Application, Summary of June 25, 2008 Conference Call with Amergen Energy Company LLC, to Discuss Draft Request for Additional Information for Sections 2.2, 2.3, 2.4, and 2.5 Project stage: Draft RAI ML0821907812008-08-22022 August 2008 Request for Additional Information, License Renewal Application, Section 2.1.5.2 Project stage: RAI ML0822000322008-08-22022 August 2008 Request for Additional Information, on License Renewal Application Sections 2.2, 2.3, 2.4 & 2.5 Project stage: RAI ML0823301922008-08-26026 August 2008 License Renewal Application, Enclosure 2 to Summary of June 25, 2008 Conference Call with Amergen Energy Company to Discuss Draft Request for Additional Information, Sections 2.2, 2.3, 2.4 & 2.5 Project stage: Draft RAI ML0825601782008-09-10010 September 2008 Response to NRC Request for Additional Information Related to Three Mile Island Nuclear Station, Unit 1, License Renewal Application Project stage: Response to RAI ML0826300302008-09-16016 September 2008 Response to NRC Request for Additional Information Related to Three Mile Island Nuclear Station, Unit 1, License Renewal Application Project stage: Response to RAI ML0826703592008-09-19019 September 2008 Response to Request for Additional Information Related to License Renewal Application Project stage: Response to RAI ML0824900892008-09-29029 September 2008 Unit - 1, Request for Additional Information, License Renewal Application, Appendix B, Aging Management Programs, Part 1 Project stage: RAI ML0825205732008-09-30030 September 2008 Unit - 1, Request for Additional Information, License Renewal Application, Time Limited Aging Analysis Project stage: RAI ML0825200202008-10-0707 October 2008 Request for Additional Information, License Renewal Application, Appendix B, Aging Management Programs, Part 2 Project stage: RAI ML0825206142008-10-16016 October 2008 Unit - 1, Request for Additional Information, License Renewal Application, Aging Management Review Results Project stage: RAI ML0825201222008-10-20020 October 2008 Request for Additional Information, License Renewal Application, Boral Neutron Absorbing Material in Spent Fuel Pool Racks Project stage: RAI ML0830204062008-10-23023 October 2008 Response to NRC Request for Additional Information on License Renewal Application Project stage: Response to RAI ML0830803762008-10-30030 October 2008 Response to NRC Request for Additional Information Related to Three Mile Island, Unit 1, License Renewal Application Project stage: Response to RAI ML0831900392008-11-12012 November 2008 Response to NRC Request for Additional Information Related to Three Mile Island Nuclear Station, Unit 1, License Renewal Application Project stage: Response to RAI ML0831900382008-11-12012 November 2008 Response to NRC Request for Additional Information on License Renewal Application Project stage: Response to RAI ML0830900532008-11-17017 November 2008 License Renewal Application, Summary of Conference Call with Amergen Energy Company Regarding Responses to Request for Additional Information for Sections 2.3.3 and 2.3.4 Project stage: RAI ML0831700382008-11-24024 November 2008 License Renewal Application, Request for Additional Information, Sections 2.3 & 2.4 Project stage: RAI ML0828800032008-11-24024 November 2008 Unit - 1, License Renewal Application, Aging Management Programs, Audit Summary Report Project stage: Other ML0832402452008-12-0303 December 2008 License Renewal Application Regarding Scoping and Screening Audit Summary Project stage: Other ML0834400582008-12-0505 December 2008 Response to NRC Request for Additional Information Related to License Renewal Application, Sections 2.3 & 2.4 Project stage: Response to RAI ML0835100402009-01-0505 January 2009 Unit - 1, License Renewal Application, Request for Additional Information Project stage: RAI ML0907106042009-03-31031 March 2009 Safety Evaluation Report with Open Items Related to the License Renewal of Three Mile Island Nuclear Station, Unit 1 Project stage: Approval ML0913200422009-06-30030 June 2009 Safety Evaluation Report Related to the License Renewal of Three Mile Island, Unit 1 Project stage: Approval ML0916604702009-06-30030 June 2009 Safety Evaluation Report Related to the License Renewal of Three Mile Island, Unit 1 Project stage: Approval 2008-05-19
[Table View] |
Text
January 8, 2008 NOTICE OF SIGNIFICANT LICENSEE MEETING THIS MEETING IS NOT OPEN TO PUBLIC ATTENDANCE Name of Licensee:
Exelon Generation Company, LLC Name of Facilities/Docket Nos:
Region III Braidwood 456; 50-457 Quad Cities 254; 50-265 LaSalle 373; 50-374 Clinton 461 Dresden 237; 50-249 Byron 454, 50-455 Region I Peach Bottom 277; 50-278 Three Mile Island 289 Oyster Creek 219 Limerick 352; 50-353 Date and Time of Meeting:
Friday, January 11, 2008 at 10:30 CST Location of Meeting:
U.S. NRC Region III 2443 Warrenville Road, Suite 210 Lisle, Illinois, 60532 Video Conference Location:
Headquarters Operations Center Region I Purpose of Meeting:
To discuss Exelon=s plans to transition the Wackenhut security workforce to a proprietary in-house workforce.
Category:
This meeting will be closed to the public because the staff has determined that the information is security-sensitive in nature.
NRC Attendees:
R. Correia, Deputy Director for Security Oversight, NSIR S. West, Director, DRS, Region III A. Boland, Deputy Director, DRS, Region III F. Peduzzi, Team Leader, NSIR M. Gamberoni, Director, DRS, Region I D. Roberts, Deputy Director, DRS, Region I J. Trapp, Plant Support Branch Chief, Region I E. Duncan, Plant Support Branch Chief, Region III Licensee Attendees:
G. Kaegi, Exelon J. Achterberg, Exelon D. Evans, Exelon D. Benyak, Exelon M. Carney, Exelon
Notice of Significant Licensee Meeting Note: Attendance at this meeting by NRC personnel, other than those listed above, should be made known to Eric Duncan at (630) 829-9757 by COB Thursday, January 10, 2007.
The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript or other information from the meeting in another format (e.g. Braille, large print), please notify the NRC=s meeting coordinator.
Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
Approved by: _______/RA/______________
Eric Duncan Chief, Plant Support Branch Division of Reactor Safety Distribution:
D. Jackson, (DEJ1), Region III Coordinator, OEDO T. McGinty (TJM1), Deputy Director, Division of Operating Reactor Licensing (DORL), NRR J. Lubinski (JWL), Deputy Director, Division of Operating Reactor Licensing (DORL), NRR R. Correia, Deputy Director for Security Oversight, NSIR F. Peduzzi, Team Leader, NSIR M. Gamberoni, Director, DRS, Region I D. Roberts, Deputy Director, DRS, Region I J. Trapp, Plant Support Branch Chief, Region I C. Pederson (CDP1), Director, Division of Reactor Projects, RIII G. Shear (GLS), Deputy Director, Division of Reactor Projects, RIII S. West (KSW), Director, Division of Reactor Safety, RIII A. Boland (ATB), Deputy Director, Division of Reactor Safety, RIII E. Duncan (ERD), Branch Chief, Plant Support, Division of Reactor Safety, RIII DRP Branch Chiefs (MAR, KXR, RAS)
R. M. Lickus (RML2), Regional State Liaison Officer, RIII RIII Public Affairs (VTM, PSC1)
T. Tomczak (TXN), ORA P. Buckley (PLB1), ORA S. Sarna (SLS), DRP