MONTHYEARML15155A4592015-06-0303 June 2015 NRR E-mail Capture - Callaway ESEP Clarifications Questions Project stage: Request ML15281A0042015-10-0101 October 2015 NRR E-mail Capture - Callaway Plant - Technical Review Checklist Related to Interim ESEP Supporting Implementation of NTTF R2.1, Seismic Project stage: Other ML15282A0442015-10-14014 October 2015 Staff Review of Interim Evaluation Associated with Reevaluated Seismic Hazard Implementing Near-Term Task Force Recommendations 2.1 Project stage: Approval 2015-10-14
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24193A0362024-07-10010 July 2024 NRR E-mail Capture - LIC-109 Acceptance Email - Callaway Plant, Unit 1 - Application to Revise Technical Specifications to Adopt TSTF-569, Rev. 2, Revise Response Time Testing Definition - EPID L-2024-LLA-0076 ML23362A0572023-12-28028 December 2023 NRR E-mail Capture - Callaway Plant, Unit 1 - SUNSI Review of the Final Safety Analysis Report (FSAR) Revision OL-26 ML23338A0392023-12-0101 December 2023 NRR E-mail Capture - LIC-109 Acceptance Review - Unacceptable with Opportunity to Supplement - Callaway - RR from Requirements of ASME BPV Code, Section Xl, Subsect IWL-Exam & Test-Unbonded Post Tensioning System - EPID L-2023-LLR-0061 ML23208A1052023-07-27027 July 2023 NRR E-mail Capture - Callaway Plant, Unit No. 1 - Regulatory Audit Questions - LAR to Clarify Support System Requirements for the Residual Heat Removal & Control Room Air Conditioning Systems ML23200A2982023-07-19019 July 2023 NRR E-mail Capture - Callaway Plant, Unit 1 - Final Request for Additional Information (RAI) - Request for Approval of Oqam, Revision 36a - EPID L-2023-LLQ-0000 ML23121A0112023-04-28028 April 2023 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of License Amendment Request to Revise TS to Adopt TSTF-501-A Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control - EPID L-2023-LLA-0046 ML23114A2302023-04-24024 April 2023 NRR E-mail Capture - Regulatory Audit Question - Callaway LAR and Exemption for Fuel Transition to Framatome Gaia Fuel - EPIDs - L-2022-LLA-0150 and L-2022-LLE-0030 ML23107A1812023-04-17017 April 2023 NRR E-mail Capture - Regulatory Audit Questions - Callaway LAR and Exemption for Fuel Transition to Framatome Gaia Fuel - EPIDs - L-2022-LLA-0150 and L-2022-LLE-0030 ML23096A0072023-04-0505 April 2023 NRR E-mail Capture - Final Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request to Revise TS 5.5.16 for Permanent Extension of Integrated Leak Rate Testing - EPID L-2022-LLA-0165 ML23073A0262023-03-13013 March 2023 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - SG Inspection Report Review - EPID L-2022-LRO-0143 ML23037A7092023-02-0606 February 2023 April 2023 Emergency Preparedness Exercise Inspection - Request for Information ML23037A0022023-02-0303 February 2023 NRR E-mail Capture - Callaway - LAR to Adopt AST - EPID L-2021-LLA-0177 - Revised Schedule for Completion of the Project ML23026A0212023-01-24024 January 2023 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - LAR for Proposed Changes to TS for SFP - ML23010A2902023-01-10010 January 2023 NRR E-mail Capture - LIC-109 Acceptance Review - Callaway Plant, Unit 1 - License Amendment Request to Clarify Support System Requirements for the RHR & Crac Systems - ML22346A0132022-12-0909 December 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of LAR to Revise TS 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies - EPID L-2022-LLA-0165 ML22322A0062022-11-17017 November 2022 NRR E-mail Capture - Final - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) Callaway - LAR for Proposed Changes to TS and Exemption Request Use of Framatome Gaia Fuel - L-2022-LLA-0150 & L-2022-LLE-0030 ML22287A0952022-10-14014 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22280A1322022-10-0707 October 2022 NRR E-mail Capture - Final - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) - Callaway - License Amendment Request for Proposed Changes to Tech Spec Changes for Spent Fuel Pool Storage - EPID L-2022-LLA-0 ML22278A0122022-10-0404 October 2022 NRR E-mail Capture - Draft - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) - Callaway License Amendment Request for Proposed Changes to Tech Spec Changes for Spent Fuel Pool Storage - EPID L-2022-LLA-013 ML22269A4312022-09-26026 September 2022 November 2022 Emergency Preparedness Program Inspection - Request for Information NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) ML22251A0122022-09-0707 September 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of License Amendment Request for Application to Revise TS to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections - EPID L-2022-LLA-0110 NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22216A0072022-07-0808 July 2022 NRR E-mail Capture - Callaway Plant, Unit No. 1 - Draft Acceptance Review (Unacceptable for Review with Opportunity to Supplement) for Framatome Fuel Transition LAR and Exemption - EPIDs L-2022-LLA-0083 and L-2022-LLE-0019) ML22167A0252022-06-15015 June 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - LAR for Proposed Revision to Radiological Emergency Response Plan Regarding Response & Notification Goals - EPID L-2022-LLA-0024 ML22157A0102022-06-0303 June 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood Ultimate Heat Sink Temporary Temperature Increase to 102.8 Degrees Fahrenheit ML22154A0122022-06-0202 June 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22151A0512022-05-27027 May 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22137A0292022-05-16016 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22096A0232022-04-0505 April 2022 NRR E-mail Capture - Callaway Plant - Final RAIs - License Amendment and Regulatory Exemptions for a Risk-Informed Approach to Address Generic Safety Issue - 191 and Respond to GL 2004-02 (EPIDs L-2021-LLA-0059 and L-2021-LLE-0021) ML22089A0222022-03-29029 March 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LAR to Adopt TSTF-505 and TSTF-439 - Follow Up Clarifications for the Audit Questions - EPID L-2021-LLA-0197 ML22087A4022022-03-28028 March 2022 NRR E-mail Capture - Callaway - Draft RAIs - License Amendment and Regulatory Exemptions for a Risk-Informed Approach to Address Generic Safety Issue - 191 and Respond to Generic Letter 2004-02 (EPIDs L-2021-LLA-0059 and L-2021-LLE-0021) ML22070A1362022-03-10010 March 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of License Amendment Request for Proposed Revision to Radiological Emergency Response Plan Regarding Response and Notification Goals - EPID L-2022-LLA-0024 ML22047A2312022-02-11011 February 2022 Email Between NRC NSIR and FEMA Regarding Callaway Sirens 021122 ML22003A0852022-01-0303 January 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of License Amendment Request to Adopt TSTF-529, Clarify Use and Application Rules - EPID L-2021-LLA-0225 ML21334A5172021-11-30030 November 2021 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of Requested Licensing Action - Application to Adopt TSTF-439 and TSTF-505 - EPID L-2021-LLA-0197 ML21335A0172021-11-30030 November 2021 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of Requested Licensing Action - Application to Adopt TSTF-439 and TSTF-505 - EPID L-2021-LLA-0197 ML21308A0692021-11-0404 November 2021 NRR E-mail Capture - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) - Callaway Unit 1 - License Amendment Request - Adoption of Alternate Source Term and Revision of TSs - ML21258A0382021-09-14014 September 2021 NRR E-mail Capture - Final - Request for Additional Information - Callaway, Unit 1 - LAR to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors- EPID L-2020-LLA-023 ML21195A0252021-07-13013 July 2021 Email 7-13-21 Request for Information - Callaway EP Exercise Inspection - Sept 2021 ML21125A0452021-05-0404 May 2021 NRR E-mail Capture - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) - Callaway Plant, Unit 1 - License Amendment Request - Final Resolution to Address Concerns of GSI-191 - EPID L-2021-LLA-0059 ML21007A1622021-01-0606 January 2021 NRR E-mail Capture - Final - Request for Additional Information - (COVID-19) Callaway Plant, Unit 1 - Additional Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs - EPID L-2021-LLE-0242 ML20342A1802020-12-0606 December 2020 NRR E-mail Capture - Callaway - LIC-109 Acceptance Requested Licensing Action - Application to Adopt 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors EPID L-2020-LLA-0235 ML20296A6332020-10-22022 October 2020 NRR E-mail Capture - Callaway Plant, Unit 1 - Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Section VI (EPID L 2020 Lle 0140 (Covid 19)) - Revised Completion Schedule ML20205L4252020-07-22022 July 2020 NRR E-mail Capture - Callaway Plant, Unit 1 - Acceptance of Requested Licensing Action Request for One-Time License Amendment to Defer Upcoming Steam Generator Inspection (EPID L-2020-LLA-0142)(COVID-19) ML20203M3682020-07-21021 July 2020 NRR E-mail Capture - Draft Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request - Revision to Technical Specification (TS) 5.3.1 and Deletion of TS 5.3.1.1 and 5.3.1.2 - EPID L-2020-LLA-0046 ML20162A1882020-06-10010 June 2020 Request for Supporting Information for the Callaway SPRA Audit Review - Draft Supplement ML20153A7902020-05-29029 May 2020 Emai: RFI for Callaway EP Program Inspection ML20133K6742020-05-11011 May 2020 05000483, Request for Information 2020-002 ML20099G2422020-04-0808 April 2020 NRR E-mail Capture - Acceptance Callaway Containment Tendon COVID-19 Relief Request 2024-07-10
[Table view] |
Text
NRR-PMDAPEm Resource From: Ptasznik, Elizabeth M [EPtasznik@ameren.com]
Sent: Wednesday, June 03, 2015 6:53 PM To: Wyman, Stephen
Subject:
RE: Callaway ESEP Clarifications Questions
- Stephen, A response to each of your questions are provided for the Callaway Plant below. We are asking for an extension on our response to Question 2.c until 06/25/2015.
- 1. The components in question were not included on the ESEL because of the exemption NSSS Components contained in the Augmented Approach Guidelines (Reference 1, Section 3.2). Without further definition provided, those components considered to be part of the Nuclear Steam Supply System (NSSS) were designated as the Reactor Coolant System (RCS) and connected systems up to the main steam isolation valves (MSIVs).
Therefore, the components questioned, steam generator atmospheric relief valves (ARVs), accumulators, accumulator isolation valves, and reactor head vent and pressurizer PORV were not included on the Callaway Expedited Seismic Evaluation List (ESEL). (Reference 1: EPRI Report, Seismic Evaluation Guidance Augmented Approach for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1 - Seismic)
- 2. Steam generator water level, steam generator pressure, RCS pressure and RCS temperature were not included on the ESEL because of the exemption NSSS Components contained in the Augmented Approach Guidelines (Reference 1, Section 3.2). Without further definition provided, those components considered to be part of the Nuclear Steam Supply System (NSSS) were designated as the Reactor Coolant System (RCS) and connected systems up to the main steam isolation valves (MSIVs). Therefore, steam generator water level, steam generator pressure, RCS pressure and RCS temperature were not included on the Callaway Expedited Seismic Evaluation List (ESEL). Containment pressure instrumentation was not included at the time of the ESEP as the containment function was not expected to be challenged per the OIP. Further investigation of the need for inclusion of containment pressure instrumentation on the ESEL is needed. (Reference 1: EPRI Report, Seismic Evaluation Guidance Augmented Approach for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1 - Seismic)
- 3. The new flow path will rely on the HCST. For surface-mounted structures, systems and components (SSC),
directly applying the GMRS for HCLPF determination is acceptable. Thus the RLGM for the HCST is the GMRS.
The HCST, when constructed, will achieve a HCLPF capacity at the level of the RLGM. Connected piping and pipe supports screen out of ESEP and will be designed to SSE. Per the current design, a new fail-open AOV will be installed between the HCST and the existing AFW system. This valve will be seismically analyzed to meet ESEP requirements.
- 4. The walkdowns were performed by structural engineers that were designated as Seismic Capability Engineers (SCE). Required for that designation, they have all completed the EPRI 5-day SQUG training. These engineers were also the same engineers that performed the NTTF 2.3 Seismic Walkdowns for this plant (their certificates were included in the 2.3 NRC submittals.)
If there is a need for further discussion, please contact me, and we can arrange a phone call with Callaway's project team.
Liz
1
ELIZABETH PTASZNIK Engineer Regulatory Affairs - Licensing E eptasznik@ameren.com Please consider the environment before printing this e-mail.
From: Wyman, Stephen [1]
Sent: Tuesday, May 19, 2015 3:30 PM To: Elwood, Thomas B; Ptasznik, Elizabeth M Cc: Maglio, Scott A; Devlin-Gill, Stephanie
Subject:
Callaway ESEP Clarifications Questions Mr. Elwood, In follow-up to our phone conversation today, as part of the NRC review of the Callaway ESEP report, the staff would appreciate clarification on the following technical items:
The following clarification questions are raised in the context of the NRC evaluation of the ESEP submittals only and licensees responses will be reviewed by NRC staff only to the extent the use of this information affects the elements and outcomes of the ESEP evaluation. As many licensees have used information from their ongoing SPRA analyses, the current review will not evaluate methods or results as they pertain to the SPRA. They will be reviewed later at the time of SPRA review.
- 1) The following SSCs appear to meet the ESEP guidance, but were not included on the ESEL: steam generator atmospheric relief valves (ARVs), accumulators, accumulator isolation valves, and reactor head vent or pressurizer PORV. Please add these components to the ESEL with any associated support equipment and provide results per ESEP guidance (e.g., HCLPF analysis results) or provide a justification why they are not included on the ESEL.
- 2) All necessary instrumentation does not appear to be included on the ESEL. Clarify which SSCs are necessary to achieve the following indications and confirm they are included in or added to the ESEL.
- a. Steam generator water level
- b. Steam generator pressure
- c. Containment pressure
- d. RCS pressure
- e. RCS Temperature
- 3) The hardened CST (HCST) was not included in the ESEL. Confirm whether the new flow path will rely on the HCST and if so, whether the HCST when constructed will achieve a HCLPF capacity at the level of the RLGM. If the new flow path will rely on support equipment which falls within the scope of the ESEP, such as permanently installed equipment or FLEX connection points, confirm that these SSCs will achieve a HCLPF capacity at the level of the RLGM.
- 4) The licensee did not state whether the walkdown personnel were trained in seismic walkdown.
Please confirm that the walkdowns were conducted by trained personnel that successfully completed training specific for seismic, such as the Seismic Qualification Utility Group (SQUG)
Walkdown Screening and Seismic Evaluation Training Course.
An email response will likely be sufficient to support the ESEP report review, however, please be aware that your email response will be made publicly available in ADAMS. A response around June 3rd, if practicable, would be greatly appreciated to support the planned review schedule.
2
Please let me or Nick DiFrancesco (at 301-415-1115) know if you would like to schedule a clarification call or have any questions and concerns.
- Thanks, Steve Stephen M. Wyman USNRC/NRR/JLD/HMB Office: O-13G9 MS: O-13C5 301-415-3041 (Voice) 301-415-8333 (Fax)
Stephen.Wyman@nrc.gov The information contained in this message may be privileged and/or confidential and protected from disclosure.
If the reader of this message is not the intended recipient, or an employee or agent responsible for delivering this message to the intended recipient, you are hereby notified that any dissemination, distribution or copying of this communication is strictly prohibited. Note that any views or opinions presented in this message are solely those of the author and do not necessarily represent those of Ameren. All e-mails are subject to monitoring and archival. Finally, the recipient should check this message and any attachments for the presence of viruses.
Ameren accepts no liability for any damage caused by any virus transmitted by this e-mail. If you have received this in error, please notify the sender immediately by replying to the message and deleting the material from any computer. Ameren Corporation 3
Hearing Identifier: NRR_PMDA Email Number: 2134 Mail Envelope Properties (BE753406A3C6734B92286A3A848D9A3606C61139A1)
Subject:
RE: Callaway ESEP Clarifications Questions Sent Date: 6/3/2015 6:52:53 PM Received Date: 6/3/2015 6:53:06 PM From: Ptasznik, Elizabeth M Created By: EPtasznik@ameren.com Recipients:
"Wyman, Stephen" <Stephen.Wyman@nrc.gov>
Tracking Status: None Post Office: exchcal1.corp.dir.ameren.com Files Size Date & Time MESSAGE 7637 6/3/2015 6:53:06 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: