NRR E-mail Capture - Final RAI - RBS EAL Scheme Change LAR (L-2018-LLA-0130)
ML18250A311
Person / Time
Site: River Bend Entergy icon.png
Issue date: 09/04/2018
From: Lisa Regner
Plant Licensing Branch IV
To: Schenk T
Entergy Nuclear Operations
References
L-2018-LLA-0130
Download: ML18250A311 (2)


Text

NRR-DMPSPEm Resource From: Regner, Lisa Sent: Tuesday, September 4, 2018 11:16 AM To: FOLDS, TITUS; SCHENK, TIM Cc: Regner, Lisa

Subject:

FINAL RAI - RBS EAL Scheme Change LAR (L-2018-LLA-0130)

Attachments: DRAFT RAI - RBS EP EAL Scheme Change LAR (L-2018-LLA-0130)

Final Request for Additional Information (L-2018-LLA-0116)

On August 2, 2018, the U.S. Nuclear Regulatory Commission (NRC) staff sent Entergy Operations, Inc. (the licensee, Entergy) a draft Request for Additional Information (RAI) as provided in the attached document. These RAI questions relate to a license amendment request (LAR) that proposes to update an emergency action level (EAL) scheme change for River Bend Station (RBS).

Entergy informed the NRC staff that a clarification call was needed, and this call was held on August 30, 2018.

Subsequently, Entergy informed the NRC staff that the questions were understood and Mr. Titus Folds agreed to provide a response to this final RAI on or before October 19, 2018. If Entergy does not respond by this date, the requested completion date for the EAL scheme change decision may not be met by the NRC.

The NRC staff also informed the licensee that a publicly available version of this final RAI would be placed in the NRCs Agencywide Documents Access and Management System (ADAMS).

By letter dated April 30, 2018 (ADAMS package Accession No. ML18128A044), the licensee requested an amendment to the Operating License for RBS. The proposed amendment requests an EAL scheme change to update to the Nuclear Energy Institute (NEI) 99-01, Revision 6. The NRC staff requires additional information to complete its review of this request as detailed in the attached document.

Lisa Regner Sr. Project Manager NRR/DORL/LPL4 301-415-1906 O9D14 1

Hearing Identifier: NRR_DMPS Email Number: 549 Mail Envelope Properties (BN6PR09MB149116016BC5B8B215DC0883E5030)

Subject:

FINAL RAI - RBS EAL Scheme Change LAR (L-2018-LLA-0130)

Sent Date: 9/4/2018 11:16:09 AM Received Date: 9/4/2018 11:16:11 AM From: Regner, Lisa Created By: Lisa.Regner@nrc.gov Recipients:

"Regner, Lisa" <Lisa.Regner@nrc.gov>

Tracking Status: None "FOLDS, TITUS" <TFOLDS@entergy.com>

Tracking Status: None "SCHENK, TIM" <tschenk@entergy.com>

Tracking Status: None Post Office: BN6PR09MB1491.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 1557 9/4/2018 11:16:11 AM DRAFT RAI - RBS EP EAL Scheme Change LAR (L-2018-LLA-0130) 22793 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: