Letter Sequence Meeting |
---|
|
Results
Other: ML17156A098, ML17347A383, ML17348B142, ML18078A747, ML18107A504, ML18120A135, ML18124A190, ML18127A034, ML18129A356, ML18143B396, ML18151A082, ML18155A550, ML18241A321
|
MONTHYEARML17156A0982017-06-19019 June 2017 Receipt and Availability FRN - License Renewal Application for River Bend, Unit 1 Project stage: Other RBG-47773, Supplement to License Renewal Application2017-08-0101 August 2017 Supplement to License Renewal Application Project stage: Supplement ML17320B0992017-11-16016 November 2017 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application Project stage: RAI ML17335A0982017-11-29029 November 2017 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application Project stage: RAI ML17347B4242017-12-13013 December 2017 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 4 Project stage: RAI ML17347B4322017-12-13013 December 2017 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 5 Project stage: RAI ML17361A3962017-12-27027 December 2017 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 6 Project stage: RAI ML17348B1422018-01-0808 January 2018 RBS Scoping and Screening Audit Report Project stage: Other ML17347A3832018-01-0808 January 2018 RBS Ope Audit Report Project stage: Other ML18009A9092018-01-0909 January 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 7 Project stage: RAI ML18022A9412018-01-22022 January 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 8 Project stage: RAI ML17346A7322018-01-29029 January 2018 Aging Management Programs Audit Report Regarding River Bend Station, Unit 1 License Renewal Application Review Project stage: Acceptance Review RBG-47818, Response to License Renewal Application NRC Request for Additional Information - Set 72018-02-0707 February 2018 Response to License Renewal Application NRC Request for Additional Information - Set 7 Project stage: Request ML18043A0082018-02-0808 February 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 10 Project stage: RAI ML18043A3512018-02-12012 February 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 11 Project stage: RAI ML18078A7472018-03-0606 March 2018 Highland Mining Company, NRC Form 591 Part 1, Inspection Report 03036608/2018001 Project stage: Other ML18065A2132018-03-0606 March 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 12 Project stage: RAI ML18057A4532018-03-0707 March 2018 Summary of Telephone Conference Call Held on February 20, 2018 Between the U.S. Nuclear Regulatory Commission and Energy Regarding RAI Pertaining to the River Bend Station, Unit 1 License Renewal Application Review Project stage: RAI ML18059A8222018-03-0808 March 2018 Summary of Public Telephone Conference Call Held on February 27, 2018 Between the U.S. Nuclear Regulatory Commission and Entergy Regarding Requests for Additional Information Pertaining to the River Bend Station Unit 1 Project stage: RAI ML18068A1872018-03-0909 March 2018 Revision of Final Request for Additional Information (RAI 2.3.3.17-2) for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 11 Project stage: RAI ML18073A0912018-03-14014 March 2018 NRC and Energy Public Meeting on Fatigue Analysis Related to River Bend License Renewal Project stage: Meeting ML18073A0482018-03-19019 March 2018 License Renewal Application Review Response to Request for Due Date Extension for Request for Additional Information Set 10 Project stage: RAI ML18078A7552018-03-28028 March 2018 Telephone Call Summary on Applicant'S Response to RAI B1.4-1 & B.1.4-2 (Set 5) on 030618 Rev 2 - All Edits Incorp Project stage: RAI ML18078A7482018-03-29029 March 2018 Uranium One Public Meeting Feb. 22, 2018 Project stage: Meeting ML18071A0182018-03-29029 March 2018 Telephone Call Summary RAI 3.2.2.3.2-1a Generic Filtration on 27FEB2018 v1_RBS Edits incorp._030618 Project stage: RAI ML18089A0762018-04-12012 April 2018 03/13/2018 Summary of Public Telephone Conference Call Held on Between the U.S. Nuclear Regulatory Commission and Entergy Regarding Requests for Additional Information Pertaining to the River Bend Station, Unit 1 License Renewal Application Project stage: RAI ML18107A5042018-04-24024 April 2018 03/29/2018 Summary of Public Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML18121A0292018-04-30030 April 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 14 Project stage: RAI RBG-47863, Annual Radioactive Effluent Release Report for 20172018-05-0101 May 2018 Annual Radioactive Effluent Release Report for 2017 Project stage: Request RBG-47862, Annual Radiological Environmental Operating Report for 20172018-05-0101 May 2018 Annual Radiological Environmental Operating Report for 2017 Project stage: Request ML18124A0092018-05-0303 May 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 15 Project stage: RAI ML18120A1352018-05-10010 May 2018 Call Summary - Fuel Oil, Ext.-Int. Surf. Monitoring, FAC & Others 041018, Rev2 Project stage: Other ML18127A0342018-05-25025 May 2018 Summary of Public Telephone Conference Call Held on April 18, 2018, Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the RBS Unit 1 License Renewal Application Review Project stage: Other ML18124A1902018-05-25025 May 2018 Summary of a Telephone Conference Call Held on April 25, 2018, Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the River Bend Station, Unit 1 License Renewal Application Re Project stage: Other ML18129A3562018-05-29029 May 2018 April 26, 2018 Summary of a Telephone Conference Call Between NRC and Entergy Regarding the Need for Additional Information to Support the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML18151A0822018-05-30030 May 2018 Summary of a Telephone Conference Call Held on May 21, 2018, Between NRC and Entergy Regarding the Need for Additional Information to Support the River Bend Station License Renewal Application Project stage: Other ML18143B3962018-06-0404 June 2018 05/03/2018 Summary Telephone Conference with Entergy Regarding the Need for Additional Information to Support the River Bend Station Unit 1 License Renewal Application Review. Project stage: Other ML18155A5502018-06-14014 June 2018 Summary of a Telephone Conference Call Held on May 17, 2018, Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the River Bend Station Unit 1 License Renewal Application Revie Project stage: Other RBG-47879, Comments on Plant-Specific Supplement 58 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding River Bend Station, Unit 1, Draft Report for Comment2018-07-12012 July 2018 Comments on Plant-Specific Supplement 58 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding River Bend Station, Unit 1, Draft Report for Comment NRC-2017-0141, Comment (4) of Anonymous Individual on Entergy Operations, Inc.; River Bend Station, Unit 1 Renewal2018-07-23023 July 2018 Comment (4) of Anonymous Individual on Entergy Operations, Inc.; River Bend Station, Unit 1 Renewal Project stage: Request ML18206A4532018-07-23023 July 2018 Comment (3) of Anonymous Individual Opposing to Entergy Operations, Inc.; River Bend Station, Unit 1 Renewal Project stage: Request ML18206A4512018-07-23023 July 2018 Comment (2) from Anonymous on Entergy Operations, Inc.; River Bend Station, Unit 1 Project stage: Request ML18206A4502018-07-23023 July 2018 Comment (1) of Edward Festner Opposing to Entergy Operations, Inc.; River Bend Station, Unit 1 Renewal Project stage: Request ML18212A1792018-07-31031 July 2018, 16 August 2018 Safety Evaulation Report Related to the License Renewal of River Bend Station, Unit 1, Docket No. 50-458, Entergy Operations, Inc. and Entergy Louisiana, LLC Project stage: Request ML18241A3212018-08-29029 August 2018 Fws to NRC, Concurrence with the Nrc'S Determination That River Bend License Renewal Is Not Likely to Adversely Affect the Pallid Sturgeon Project stage: Other ML18291B1472018-10-18018 October 2018 Revision of the River Bend License Renewal Safety Evaluation Report Project stage: Approval ML18310A0722018-11-30030 November 2018 NUREG-1437, Supplement 58, Generic Environment Impact Statement for License Renewal of Nuclear Plants Supplement 58 Regarding River Bend Station, Unit 1, Final Report Project stage: Acceptance Review ML18277A2872018-12-20020 December 2018 Issuance of Renewed Facility Operating License No. NPF-47 for River Bend Station, Unit 1 Project stage: Approval 2018-03-29
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24255A1192024-09-16016 September 2024 Notification of NRC Follow Up Inspection for One Severity Level (SL) III and Two SL IV or Three or More SL IV Violations and Request for Additional Information ML24106A0432024-04-11011 April 2024 June 2024 Emergency Preparedness Exercise Inspection Request for Information ML24088A0092024-03-27027 March 2024 NRR E-mail Capture - Entergy Fleet - Final Request for Confirmation of Information (RCI) Re Alternative Request EN-RR-22-001 Concerning ASME Code Case N-752 (L-2022-LLR-0054) ML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23311A4322023-11-0909 November 2023 Notification of NRC Supplemental Inspection (95001) and Request for Information ML23195A0692023-07-24024 July 2023 2023 River Bend Station Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ML23116A1462023-04-26026 April 2023 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Final RAI for Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23081A4602023-03-22022 March 2023 RFI River Bend CETI 2023012 Drr ML23004A0422023-01-0404 January 2023 License Renewal Phase 1 Request for Information ML22354A0812022-12-20020 December 2022 Inservice Inspection Request for Information ML22235A1082022-08-19019 August 2022 RBS Emergency Preparedness (EP) Exercise Inspection October 2022 RFI ML22180A0612022-06-29029 June 2022 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000458/2022010) and Request for Information ML20350B8112020-12-11011 December 2020 2021 RBS PIR Request for Information ML20337A4452020-12-0202 December 2020 Riverbend Station Inservice Inspection Request for Information ML20255A1892020-09-0909 September 2020 Email 09Sept2020 - RFI for RBS EP Exercise Inspection ML20260H4422020-09-0808 September 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Official RAIs for RR Associated with Updating ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20162A1122020-06-10010 June 2020 Notification of Inspection (NRC Inspection Report 05000458/2020003) and Request for Information ML20126G3922020-05-0101 May 2020 Request for Information, May 01, 2020, River Bend Station Special Inspection, NRC Inspection Report 2020050 ML20038A2092020-02-0404 February 2020 05000458 Request for Information IR2020-001 Occupational Radiation Safety ML19102A0722019-04-11011 April 2019 NRR E-mail Capture - River Bend Station, Unit 1 - Final Request for Additional Information Relief Request RBS-ISI-021 ML18250A3112018-09-0404 September 2018 NRR E-mail Capture - Final RAI - RBS EAL Scheme Change LAR (L-2018-LLA-0130) ML18229A0082018-08-16016 August 2018 NRR E-mail Capture - Final Request for Additional Information for P-T Curves - NON-PROPRIETARY Version ML18250A3102018-08-0101 August 2018 NRR E-mail Capture - Draft RAI - RBS EP EAL Scheme Change LAR (L-2018-LLA-0130) ML18151A0822018-05-30030 May 2018 Summary of a Telephone Conference Call Held on May 21, 2018, Between NRC and Entergy Regarding the Need for Additional Information to Support the River Bend Station License Renewal Application RBG-47861, Response to License Renewal Application NRC Request for Additional Information Sets 14,15 and Operating Experience Review Clarification2018-05-29029 May 2018 Response to License Renewal Application NRC Request for Additional Information Sets 14,15 and Operating Experience Review Clarification ML18149A2882018-05-24024 May 2018 NRR E-mail Capture - River Bend Station Request for Additional Information - Reactor Core Isolation Cooling Piping Modification (L-2018-LLA-0029) ML18141A4882018-05-21021 May 2018 Draft Response (RAI 3.6.2.2.2.2-1a) from LRA Review Revised After the May 17, 2018 Call ML18141A3172018-05-21021 May 2018 OE Draft RAI 3-0-5 Rogers ML18131A2412018-05-11011 May 2018 RBS 012 Item 158a Response (RAI 3.2.2.3.2-1a) Revised - Received on 05/10/2018 ML18124A0092018-05-0303 May 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 15 ML18122A2312018-05-0202 May 2018 Draft Response to NRC Request for Additional Information (RAI) B.1.40-5 Service Water Integrity Generated from Staffs Review on the River Bend Station, Unit 1 License Renewal Application ML18122A1262018-05-0202 May 2018 RAI B.1.17-1 Revised - w- header-footer-watermark ML18121A3022018-05-0101 May 2018 Draft Response to NRC Request for Additional Information (RAI) 4.6-2a Generated from Staff'S Review on the River Bend License Renewal Application ML18121A0292018-04-30030 April 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 14 ML18115A1632018-04-25025 April 2018 Draft Response on RBS LRA RAI B.1.21-2 Flow Accelerated Corrosion ML18113A3322018-04-23023 April 2018 035 RB Buried Pipe 3rd Round RAI - Allik Holston ML18103A0152018-04-12012 April 2018 NRR E-mail Capture - Summary of Public Telephone Conference Call Held on March 27, 2018, Between the U.S. Nuclear Regulatory Commission and Entergy and Final Requests for Additional Information for the Safety Review of the River Bend Statio ML18073A0912018-03-14014 March 2018 NRC and Energy Public Meeting on Fatigue Analysis Related to River Bend License Renewal ML18068A1872018-03-0909 March 2018 Revision of Final Request for Additional Information (RAI 2.3.3.17-2) for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 11 RBG-47834, Response to License Renewal Application NRC Request for Additional Information (RAI) Set 92018-03-0808 March 2018 Response to License Renewal Application NRC Request for Additional Information (RAI) Set 9 ML18065A2132018-03-0606 March 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 12 ML18060A1532018-03-0101 March 2018 NRR E-mail Capture - River Bend Station: Request for Additional Information Concerning New Technical Specification for Control Building Air Conditioning (L-2017-LLA-0291) ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update) ML18043A3512018-02-12012 February 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 11 ML18043A0082018-02-0808 February 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 10 ML18038B4702018-02-0707 February 2018 NRR E-mail Capture - Fyi_River Bend Station RAIs Set 9 ML18022A9412018-01-22022 January 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 8 ML18011A0462018-01-10010 January 2018 Notification of Cyber Security Inspection (NRC Inspection Report 05000458/2018406) and Request for Information IR 05000458/20184062018-01-10010 January 2018 River Bend Station - Notification of Cyber Security Inspection (NRC Inspection Report 05000458/2018406) and Request for Information ML18009A9092018-01-0909 January 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 7 2024-09-16
[Table view] |
Text
NRC Staff Technical Concerns to Fatigue Analysis RAI Responses Related to RAI 4.6-1 Response
Background
Section 4.6 of the SRP-LR states that if a plants code of record requires a fatigue parameter evaluation (fatigue analysis or fatigue waiver), then this analysis may be a time-limited aging analyses (TLAA) and must be evaluated in accordance with 10 CFR 54.21(c)(1) to ensure that the effects of aging on the intended functions are adequately managed for the period of extended operation.
The current licensing basis may include fatigue waiver evaluations that preclude the need for performing CUF analyses of structural components. The ASME Code Section III rules for performing fatigue waiver evaluations for structural components are analogous to those in the Code for performing fatigue waiver evaluations of mechanical components. ASME Code NE-3222.4(d) Analysis for Cyclic Operations, Vessels Not Requiring Analysis for Cyclic Operation, provides for a waiver from fatigue analysis when certain cyclic loading criteria are met.
RBS USAR Section 3.8.2.4.1 states: Fatigue analysis requirements for the steel containment cylinder and dome are evaluated in accordance with the requirements of ASME Boiler and Pressure Vessel Code Section III, Division I, Subsection NE.
In its response to RAI 4.6-1, dated February 6, 2018, the applicant stated, in part, the following:
[USAR] Table 3.8-1 indicates that fatigue is considered for operating conditions I(b) , II , III(b) and IV. The free standing SCV cylinder and dome analysis reviews the operating conditions identified in USAR Table 3.8-1 and concludes that fatigue during operating conditions I(b) , II ,
III(b) and IV does not occur because the containment vessel is free to expand, thereby preventing cyclic loading. Therefore, the freestanding containment vessel and dome were not analyzed for fatigue and there are no cycle limits or cumulative usage factors.
Issue It is not clear if the evaluation performed for the freestanding containment vessel and dome components constitutes a fatigue waiver that relies on time dependent cycles, and whether they were evaluated and dispositioned in accordance with 10 CFR 54.21(c)(1). The staff notes that the current licensing basis may include fatigue waiver evaluations that preclude the need for performing CUF analyses of structural components which may be a TLAA and must be evaluated. The staff also notes that the statement containment vessel is free to expand, thereby preventing cyclic loading does not appear consistent with regard to fatigue or fatigue waiver considerations of the ASME code, Subsection NE, and cannot be concluded from USAR Table 3.8-1.
Request Clarify if the evaluation performed for the freestanding containment vessel and dome constitutes a fatigue waiver analysis in accordance with the ASME code that relies on time dependent cycles, and state the disposition in accordance with 10 CFR 54.21(c)(1) with the technical basis.
1lPage
Related to RAI 4.6-2 Response
Background
Section 4.6 of the SRP-LR states that if a plants code of record requires a fatigue parameter evaluation (fatigue analysis or fatigue waiver), then this analysis may be a time-limited aging analyses (TLAA) and must be evaluated in accordance with 10 CFR 54.21(c)(1) to ensure that the effects of aging on the intended functions are adequately managed for the period of extended operation.
The current licensing basis may include fatigue waiver evaluations that preclude the need for performing CUF analyses of structural components. The ASME Code Section III rules for performing fatigue waiver evaluations for structural components are analogous to those in the Code for performing fatigue waiver evaluations of mechanical components. ASME Code NE-3222.4(d) Analysis for Cyclic Operations, Vessels Not Requiring Analysis for Cyclic Operation, provides for a waiver from fatigue analysis when certain cyclic loading criteria are met.
In its response to RAI 4.6-2, dated February 6, 2018, the applicant stated, in part, the following:
- For the personnel airlock, drywell airlock, drywell combination door/hatch assembly components: The evaluation concluded that analysis for cyclic operation was not necessary. No cumulative usage factors were calculated. The evaluation assumed 120 plant startup cycles. LRA Table 4.3-1 has a limiting value of 168 for plant startups, but because the allowable number of cycles for this ASME Section NE 3222.4(d) criterion was 2,800 cycles, the increase in cycles shown in LRA Table 4.3-1 does not impact the conclusion that a fatigue analysis is unnecessary.
- For the equipment hatch component: The equipment hatch calculation determined a fatigue analysis was not necessary after considering loads from OBE, SSE, LOCA, SRV lifts and heatups because the loads were very low. Cumulative usage factors were not calculated, and
- For the drywell head component: The drywell head calculation determined the alternating stresses from earthquakes and SRV loads were so low that the allowable number of cycles were infinite (CUF- O).
Issue It is not clear if the evaluation performed under ASME Section NE 3222.4(d) criterion for the personnel airlock, drywell airlock, drywell combination door/hatch assembly components and the equipment hatch constitutes a fatigue waiver that relies on time dependent cycles, and whether they were evaluated and dispositioned in accordance with 10 CFR 54.21(c)(1). The staff notes that the current licensing basis may include fatigue waiver evaluations that preclude the need for performing CUF analyses of structural components which may be a TLAA and must be evaluated.
Additionally, it is not clear what is the disposition in accordance with 10 CFR 54.21(c)(1) for the drywell head calculation.
Request
- 1. Clarify if the evaluation performed under ASME Section NE 3222.4(d) criterion for the personnel airlock, drywell airlock, drywell combination door/hatch assembly components and the equipment hatch constitutes a fatigue waiver that relies on time dependent cycles, and state the disposition, in accordance with 10 CFR 54.21(c)(1), for each component evaluation.
- 2. Clarify the disposition, in accordance with 10 CFR 54.21(c)(1), for the drywell head fatigue analysis.