Letter Sequence Draft RAI |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARRBG-47805, Response to License Renewal Application NRC Request for Additional Information Set 22017-12-12012 December 2017 Response to License Renewal Application NRC Request for Additional Information Set 2 Project stage: Request RBG-47807, Response to License Renewal Application NRC Requests for Additional Information Set 32018-01-10010 January 2018 Response to License Renewal Application NRC Requests for Additional Information Set 3 Project stage: Other RBG-47812, Response to License Renewal Application (LRA) NRC Request for Additional Information (RAI) Set 42018-01-24024 January 2018 Response to License Renewal Application (LRA) NRC Request for Additional Information (RAI) Set 4 Project stage: Request RBG-47813, Response to License Renewal Application (LRA) NRC Request for Additional Information Set 52018-01-24024 January 2018 Response to License Renewal Application (LRA) NRC Request for Additional Information Set 5 Project stage: Request RBG-47830, License Renewal Application Update - Neutron Absorbing Material Monitoring Program2018-02-15015 February 2018 License Renewal Application Update - Neutron Absorbing Material Monitoring Program Project stage: Other RBG-47828, Response to License Renewal Application NRC Request for Additional Information (RAI) Set 82018-02-20020 February 2018 Response to License Renewal Application NRC Request for Additional Information (RAI) Set 8 Project stage: Request RBG-47840, Request for Due Date Extension for License Renewal Application NRC Request for Additional Information from 30 Days to 45 Days2018-02-22022 February 2018 Request for Due Date Extension for License Renewal Application NRC Request for Additional Information from 30 Days to 45 Days Project stage: Request RBG-47819, Response to License Renewal Application NRC Request for Additional Information - Set 7 Supplement to RAI B.1.11-2a2018-02-26026 February 2018 Response to License Renewal Application NRC Request for Additional Information - Set 7 Supplement to RAI B.1.11-2a Project stage: Supplement RBG-47834, Response to License Renewal Application NRC Request for Additional Information (RAI) Set 92018-03-0808 March 2018 Response to License Renewal Application NRC Request for Additional Information (RAI) Set 9 Project stage: Request RBG-47842, Response to License Renewal Application NRC Request for Additional Information Set 5 Supplement2018-03-22022 March 2018 Response to License Renewal Application NRC Request for Additional Information Set 5 Supplement Project stage: Supplement RBG-47848, License Renewal Application Update - Neutron Absorbing Material Monitoring Program - Supplement2018-03-22022 March 2018 License Renewal Application Update - Neutron Absorbing Material Monitoring Program - Supplement Project stage: Supplement RBG-47835, Submittal of Response to License Renewal Application NRC Request for Additional Information Set 102018-03-26026 March 2018 Submittal of Response to License Renewal Application NRC Request for Additional Information Set 10 Project stage: Request RBG-47849, Response to License Renewal Application NRC Request for Additional Information Set 4 Supplement2018-03-27027 March 2018 Response to License Renewal Application NRC Request for Additional Information Set 4 Supplement Project stage: Supplement RBG-47846, Response to License Renewal Application NRC Request for Additional Information (RAI) Set 122018-04-0303 April 2018 Response to License Renewal Application NRC Request for Additional Information (RAI) Set 12 Project stage: Request RBG-47850, Response to License Renewal Application NRC Request for Additional Information Set 5 Supplement2018-04-0404 April 2018 Response to License Renewal Application NRC Request for Additional Information Set 5 Supplement Project stage: Supplement ML18099A2362018-04-0909 April 2018 Topics for the April 10, 2018 Public Call with Entergy on River Bend Station, Unit 1 License Renewal Application Project stage: Meeting ML18106A6152018-04-16016 April 2018 Topics for the April 18, 2018, Telephone Call - Rev 1 with Aaron'S Rewrite Project stage: Request ML18115A0612018-04-25025 April 2018 Draft Response on RAI B1.21-1 Flow Accelerated Corrosion Project stage: Request ML18115A0722018-04-25025 April 2018 Draft Response on RAI B.1.25-1(Internal Surfaces in Miscellaneous Piping and Ducting Components) Project stage: Request ML18115A1632018-04-25025 April 2018 Draft Response on RBS LRA RAI B.1.21-2 Flow Accelerated Corrosion Project stage: Request RBG-47853, Response to License Renewal Application NRC Request for Additional Information Supplement to B.1.35-12018-04-26026 April 2018 Response to License Renewal Application NRC Request for Additional Information Supplement to B.1.35-1 Project stage: Supplement ML18121A3022018-05-0101 May 2018 Draft Response to NRC Request for Additional Information (RAI) 4.6-2a Generated from Staff'S Review on the River Bend License Renewal Application Project stage: Draft RAI ML18121A2942018-05-0101 May 2018 Draft Response to NRC Request for Additional Information (RAI) 4.6-1a Generated from Staffs Review on the River Bend License Renewal Application Project stage: Draft RAI ML18122A1262018-05-0202 May 2018 RAI B.1.17-1 Revised - w- header-footer-watermark Project stage: Request ML18122A2312018-05-0202 May 2018 Draft Response to NRC Request for Additional Information (RAI) B.1.40-5 Service Water Integrity Generated from Staffs Review on the River Bend Station, Unit 1 License Renewal Application Project stage: Draft RAI RBG-47852, Response to License Renewal Application NRC Request for Additional Information Set 132018-05-10010 May 2018 Response to License Renewal Application NRC Request for Additional Information Set 13 Project stage: Request RBG-47860, Response to License Renewal Application NRC Request for Supplemental Information2018-05-10010 May 2018 Response to License Renewal Application NRC Request for Supplemental Information Project stage: Supplement ML18131A2412018-05-11011 May 2018 RBS 012 Item 158a Response (RAI 3.2.2.3.2-1a) Revised - Received on 05/10/2018 Project stage: Request ML18135A1072018-05-15015 May 2018 RBS Draft Response (RAI 4.3.1-2a_Class 1 Fatigue w-header-footer-watermark_received on 051318 Project stage: Request ML18136A8212018-05-16016 May 2018 Draft Response to RAI 3.6.2.2.2.2-1a High Voltage Insulators - RBS LRA Review Project stage: Request ML18136A7052018-05-16016 May 2018 RBS Draft Response to LRA Review RAI 4.7.3-1a Fluence Effects for Rv Internals Project stage: Request RBG-47867, Response to License Renewal Application NRC Request for Additional Information RAI 3.2.2.2-1a Supplement2018-05-16016 May 2018 Response to License Renewal Application NRC Request for Additional Information RAI 3.2.2.2-1a Supplement Project stage: Supplement ML18141A4882018-05-21021 May 2018 Draft Response (RAI 3.6.2.2.2.2-1a) from LRA Review Revised After the May 17, 2018 Call Project stage: Request ML18143B6862018-05-24024 May 2018 RBS Draft Response (Operating Experience) to Draft RAI 3-0-5 Received 052318 Project stage: Request RBG-47861, Response to License Renewal Application NRC Request for Additional Information Sets 14,15 and Operating Experience Review Clarification2018-05-29029 May 2018 Response to License Renewal Application NRC Request for Additional Information Sets 14,15 and Operating Experience Review Clarification Project stage: Request ML18143B7362018-05-31031 May 2018 NUREG-1437, Dfc, Supplement 58, Generic Environmental Impact Statement for License Renewal of Nuclear Plants - Supplement 58 - Regarding River Bend Station, Unit 1. Project stage: Acceptance Review RBG-47870, License Renewal Application, Revised Updated Safety Analysis Report Supplement, Appendix a, Section A.4, License Renewal Commitment List2018-06-0606 June 2018 License Renewal Application, Revised Updated Safety Analysis Report Supplement, Appendix a, Section A.4, License Renewal Commitment List Project stage: Supplement RBG-47873, License Renewal Application, Revised Updated Safety Analysis Report Supplement, Appendix a, Section A.4, License Renewal Commitment List, Revised Commitment 52018-06-13013 June 2018 License Renewal Application, Revised Updated Safety Analysis Report Supplement, Appendix a, Section A.4, License Renewal Commitment List, Revised Commitment 5 Project stage: Supplement ML18212A1512018-07-31031 July 2018 License Renewal Safety Evaluation Report Project stage: Approval RBG-47883, Amendment 1 to License Renewal Application2018-08-0202 August 2018 Amendment 1 to License Renewal Application Project stage: Other ML18138A3552018-08-16016 August 2018 Safety Evaluation Report Related to the License Renewal of River Bend Station, Unit 1 Project stage: Approval ML18283A0822018-10-0909 October 2018 Supplemental Information Related to License Renewal Application NRC Request for Additional Information to Clarify Response to RAI 2.3.3.16-1 Set 11 Project stage: Response to RAI ML18346A6442018-10-19019 October 2018 Revision to River Bend SER - ML18212A151 - Section 2-3-3-16 Plant Drains Project stage: Other 2018-04-03
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24255A1192024-09-16016 September 2024 Notification of NRC Follow Up Inspection for One Severity Level (SL) III and Two SL IV or Three or More SL IV Violations and Request for Additional Information ML24106A0432024-04-11011 April 2024 June 2024 Emergency Preparedness Exercise Inspection Request for Information ML24088A0092024-03-27027 March 2024 NRR E-mail Capture - Entergy Fleet - Final Request for Confirmation of Information (RCI) Re Alternative Request EN-RR-22-001 Concerning ASME Code Case N-752 (L-2022-LLR-0054) ML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23311A4322023-11-0909 November 2023 Notification of NRC Supplemental Inspection (95001) and Request for Information ML23195A0692023-07-24024 July 2023 2023 River Bend Station Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ML23116A1462023-04-26026 April 2023 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Final RAI for Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23081A4602023-03-22022 March 2023 RFI River Bend CETI 2023012 Drr ML23004A0422023-01-0404 January 2023 License Renewal Phase 1 Request for Information ML22354A0812022-12-20020 December 2022 Inservice Inspection Request for Information ML22235A1082022-08-19019 August 2022 RBS Emergency Preparedness (EP) Exercise Inspection October 2022 RFI ML22180A0612022-06-29029 June 2022 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000458/2022010) and Request for Information ML20350B8112020-12-11011 December 2020 2021 RBS PIR Request for Information ML20337A4452020-12-0202 December 2020 Riverbend Station Inservice Inspection Request for Information ML20255A1892020-09-0909 September 2020 Email 09Sept2020 - RFI for RBS EP Exercise Inspection ML20260H4422020-09-0808 September 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Official RAIs for RR Associated with Updating ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20162A1122020-06-10010 June 2020 Notification of Inspection (NRC Inspection Report 05000458/2020003) and Request for Information ML20126G3922020-05-0101 May 2020 Request for Information, May 01, 2020, River Bend Station Special Inspection, NRC Inspection Report 2020050 ML20038A2092020-02-0404 February 2020 05000458 Request for Information IR2020-001 Occupational Radiation Safety ML19102A0722019-04-11011 April 2019 NRR E-mail Capture - River Bend Station, Unit 1 - Final Request for Additional Information Relief Request RBS-ISI-021 ML18250A3112018-09-0404 September 2018 NRR E-mail Capture - Final RAI - RBS EAL Scheme Change LAR (L-2018-LLA-0130) ML18229A0082018-08-16016 August 2018 NRR E-mail Capture - Final Request for Additional Information for P-T Curves - NON-PROPRIETARY Version ML18250A3102018-08-0101 August 2018 NRR E-mail Capture - Draft RAI - RBS EP EAL Scheme Change LAR (L-2018-LLA-0130) ML18151A0822018-05-30030 May 2018 Summary of a Telephone Conference Call Held on May 21, 2018, Between NRC and Entergy Regarding the Need for Additional Information to Support the River Bend Station License Renewal Application RBG-47861, Response to License Renewal Application NRC Request for Additional Information Sets 14,15 and Operating Experience Review Clarification2018-05-29029 May 2018 Response to License Renewal Application NRC Request for Additional Information Sets 14,15 and Operating Experience Review Clarification ML18149A2882018-05-24024 May 2018 NRR E-mail Capture - River Bend Station Request for Additional Information - Reactor Core Isolation Cooling Piping Modification (L-2018-LLA-0029) ML18141A4882018-05-21021 May 2018 Draft Response (RAI 3.6.2.2.2.2-1a) from LRA Review Revised After the May 17, 2018 Call ML18141A3172018-05-21021 May 2018 OE Draft RAI 3-0-5 Rogers ML18131A2412018-05-11011 May 2018 RBS 012 Item 158a Response (RAI 3.2.2.3.2-1a) Revised - Received on 05/10/2018 ML18124A0092018-05-0303 May 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 15 ML18122A2312018-05-0202 May 2018 Draft Response to NRC Request for Additional Information (RAI) B.1.40-5 Service Water Integrity Generated from Staffs Review on the River Bend Station, Unit 1 License Renewal Application ML18122A1262018-05-0202 May 2018 RAI B.1.17-1 Revised - w- header-footer-watermark ML18121A3022018-05-0101 May 2018 Draft Response to NRC Request for Additional Information (RAI) 4.6-2a Generated from Staff'S Review on the River Bend License Renewal Application ML18121A0292018-04-30030 April 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 14 ML18115A1632018-04-25025 April 2018 Draft Response on RBS LRA RAI B.1.21-2 Flow Accelerated Corrosion ML18113A3322018-04-23023 April 2018 035 RB Buried Pipe 3rd Round RAI - Allik Holston ML18103A0152018-04-12012 April 2018 NRR E-mail Capture - Summary of Public Telephone Conference Call Held on March 27, 2018, Between the U.S. Nuclear Regulatory Commission and Entergy and Final Requests for Additional Information for the Safety Review of the River Bend Statio ML18073A0912018-03-14014 March 2018 NRC and Energy Public Meeting on Fatigue Analysis Related to River Bend License Renewal ML18068A1872018-03-0909 March 2018 Revision of Final Request for Additional Information (RAI 2.3.3.17-2) for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 11 RBG-47834, Response to License Renewal Application NRC Request for Additional Information (RAI) Set 92018-03-0808 March 2018 Response to License Renewal Application NRC Request for Additional Information (RAI) Set 9 ML18065A2132018-03-0606 March 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 12 ML18060A1532018-03-0101 March 2018 NRR E-mail Capture - River Bend Station: Request for Additional Information Concerning New Technical Specification for Control Building Air Conditioning (L-2017-LLA-0291) ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update) ML18043A3512018-02-12012 February 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 11 ML18043A0082018-02-0808 February 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 10 ML18038B4702018-02-0707 February 2018 NRR E-mail Capture - Fyi_River Bend Station RAIs Set 9 ML18022A9412018-01-22022 January 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 8 ML18011A0462018-01-10010 January 2018 Notification of Cyber Security Inspection (NRC Inspection Report 05000458/2018406) and Request for Information IR 05000458/20184062018-01-10010 January 2018 River Bend Station - Notification of Cyber Security Inspection (NRC Inspection Report 05000458/2018406) and Request for Information ML18009A9092018-01-0909 January 2018 Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 7 2024-09-16
[Table view] |
Text
DRAFT - UNCERTIFIED INFORMATION Question RAI 4.6-2a
Background
Section 4.6 of the SRP LR states that if a plants code of record requires a fatigue parameter evaluation (fatigue analysis or fatigue waiver), then this analysis may be a time limited aging analyses (TLAA) and must be evaluated in accordance with 10 CFR 54.21(c) (1) to ensure that the effects of aging on the intended functions are adequately managed for the period of extended operation.
The current licensing basis may include fatigue waiver evaluations that preclude the need for performing CUF analyses of structural components. The ASME Code Section III rules for performing fatigue waiver evaluations for structural components are analogous to those in the Code for performing fatigue waiver evaluations of mechanical components. ASME Code NE-3222.4(d) Analysis for Cyclic Operations, Vessels Not Requiring Analysis for Cyclic Operation, provides for a waiver from fatigue analysis when certain cyclic loading criteria are met.
In its response to RAI 4.6 2, dated February 6, 2018, the applicant stated, in part, the following:
- For the personnel airlock, drywell airlock, drywell combination door/hatch assembly components: The evaluation concluded that analysis for cyclic operation was not necessary. No cumulative usage factors were calculated. The evaluation assumed 120 plant startup cycles. LRA Table 4.3-1 has a limiting value of 168 for plant startups, but because the allowable number of cycles for this ASME Section NE 3222.4(d) criterion was 2,800 cycles, the increase in cycles shown in LRA Table 4.3-1 does not impact the conclusion that a fatigue analysis is unnecessary.
- For the equipment hatch component: The equipment hatch calculation determined a fatigue analysis was not necessary after considering loads from OBE, SSE, LOCA, SRV lifts and heatups because the loads were very low. Cumulative usage factors were not calculated, and
- For the drywell head component: The drywell head calculation determined the alternating stresses from earthquakes and SRV loads were so low that the allowable number of cycles were infinite (CUF- 0).
Issue It is not clear if the evaluation performed under ASME Section NE 3222.4(d) criterion for the personnel airlock, drywell airlock, and the drywell combination door/hatch assembly constitutes a fatigue waiver that relies on time dependent cycles, and whether they were evaluated and dispositioned in accordance with 10 CFR 54.21(c) (1). The staff notes that the current licensing basis may include fatigue waiver evaluations that preclude the need for performing CUF analyses of structural components which may be a TLAA and must be evaluated.
Additionally, it is not clear if the equipment hatch and the drywell head were evaluated in accordance with the requirements of ASME Code Section III, Division I, Subsection NE-3222.4(d) to waive the requirements of a fatigue analysis, and what the disposition is in accordance with 10 CFR 54.21(c) (1) for the evaluations.
Request
- 1. State the disposition, in accordance with 10 CFR 54.21(c) (1), for the personnel airlock, drywell airlock, and the drywell combination door/hatch assembly evaluations.
DRAFT - UNCERTIFIED INFORMATION
DRAFT - UNCERTIFIED INFORMATION
- 2. Clarify if an evaluation was performed in accordance with ASME Code,Section III, Subsection NE 3222.4(d) to evaluate the fatigue analysis requirements for the equipment hatch and the drywell head.
A. If an evaluation was performed state the assumed number of cycles and limits. Otherwise, clarify what requirements of the ASME Code were followed to evaluate the fatigue analysis requirements for the equipment hatch and the drywell head, and clarify whether these evaluations are based on time dependent cycles.
B. State the disposition, in accordance with 10 CFR 54.21(c) (1), for the equipment hatch and drywell head evaluations.
Response
- 1. The personnel airlock, drywell airlock, and drywell combination door/hatch assembly fatigue waiver evaluations are considered time-limited aging analyses due to the cycle assumptions in the evaluations.
The Fatigue Monitoring Program in accordance with 10 CFR 54.21(c)(1)(iii) will ensure the numbers of cycles remain within the values allowed in the fatigue waiver criteria of ASME Code,Section III, Subsection NE 3222.4(d).
- 2. A. The equipment hatch calculation includes a fatigue waiver evaluation for the hatch cover and a fatigue calculation specific to the hatch bolting. The calculation evaluates the hatch bolting for 50,000 cycles of SRV lifts.
The drywell head calculation determined the alternating stresses were low and that the allowable number of cycles is infinite. The fatigue usage factor was zero. The cycles specified were 120 heatups, 5 operating basis earthquakes of 30 cycles each, 1 safe shutdown earthquake of 20 cycles, 50,000 SRV cycles and 350 loss-of-coolant induced cycles.
B. The Fatigue Monitoring Program in accordance with 10 CFR 54.21(c)(1)(iii) will ensure that the numbers of transient cycles remain within the values assumed for the fatigue analyses and fatigue waiver evaluations.
DRAFT - UNCERTIFIED INFORMATION