Letter Sequence Draft RAI |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement
Results
Other: ML17156A098, ML17346A732, ML17347A383, ML17348B142, ML18078A747, ML18107A504, ML18120A135, ML18124A190, ML18127A034, ML18129A356, ML18143B396, ML18151A082, ML18155A550, RBG-47807, Response to License Renewal Application NRC Requests for Additional Information Set 3
|
MONTHYEARML17156A0982017-06-19019 June 2017 Receipt and Availability FRN - License Renewal Application for River Bend, Unit 1 Project stage: Other RBG-47773, Supplement to License Renewal Application2017-08-0101 August 2017 Supplement to License Renewal Application Project stage: Supplement ML17320B0992017-11-16016 November 2017 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application Project stage: RAI ML17335A0982017-11-29029 November 2017 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application Project stage: RAI ML17347B4322017-12-13013 December 2017 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 5 Project stage: RAI ML17347B4242017-12-13013 December 2017 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 4 Project stage: RAI ML17361A3962017-12-27027 December 2017 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 6 Project stage: RAI ML17348B1422018-01-0808 January 2018 RBS Scoping and Screening Audit Report Project stage: Other ML17347A3832018-01-0808 January 2018 RBS Ope Audit Report Project stage: Other ML18009A9092018-01-0909 January 2018 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 7 Project stage: RAI RBG-47807, Response to License Renewal Application NRC Requests for Additional Information Set 32018-01-10010 January 2018 Response to License Renewal Application NRC Requests for Additional Information Set 3 Project stage: Other ML18022A9412018-01-22022 January 2018 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 8 Project stage: RAI RBG-47813, Response to License Renewal Application (LRA) NRC Request for Additional Information Set 52018-01-24024 January 2018 Response to License Renewal Application (LRA) NRC Request for Additional Information Set 5 Project stage: Request RBG-47812, Response to License Renewal Application (LRA) NRC Request for Additional Information (RAI) Set 42018-01-24024 January 2018 Response to License Renewal Application (LRA) NRC Request for Additional Information (RAI) Set 4 Project stage: Request ML17346A7322018-01-29029 January 2018 Aging Management Programs Audit Report Regarding River Bend Station, Unit 1 License Renewal Application Review Project stage: Other RBG-47818, Response to License Renewal Application NRC Request for Additional Information - Set 72018-02-0707 February 2018 Response to License Renewal Application NRC Request for Additional Information - Set 7 Project stage: Request ML18043A0082018-02-0808 February 2018 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 10 Project stage: RAI ML18043A3512018-02-12012 February 2018 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 11 Project stage: RAI ML18051A0922018-02-20020 February 2018 Single Positive Test Form Collected on 01/09/2017 Project stage: Request RBG-47828, Response to License Renewal Application NRC Request for Additional Information (RAI) Set 82018-02-20020 February 2018 Response to License Renewal Application NRC Request for Additional Information (RAI) Set 8 Project stage: Request RBG-47840, Request for Due Date Extension for License Renewal Application NRC Request for Additional Information from 30 Days to 45 Days2018-02-22022 February 2018 Request for Due Date Extension for License Renewal Application NRC Request for Additional Information from 30 Days to 45 Days Project stage: Request ML18065A2132018-03-0606 March 2018 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 12 Project stage: RAI ML18078A7472018-03-0606 March 2018 Highland Mining Company, NRC Form 591 Part 1, Inspection Report 03036608/2018001 Project stage: Other ML18057A4532018-03-0707 March 2018 Summary of Telephone Conference Call Held on February 20, 2018 Between the U.S. Nuclear Regulatory Commission and Energy Regarding RAI Pertaining to the River Bend Station, Unit 1 License Renewal Application Review Project stage: RAI ML18059A8222018-03-0808 March 2018 Summary of Public Telephone Conference Call Held on February 27, 2018 Between the U.S. Nuclear Regulatory Commission and Entergy Regarding Requests for Additional Information Pertaining to the River Bend Station Unit 1 Project stage: RAI RBG-47834, Response to License Renewal Application NRC Request for Additional Information (RAI) Set 92018-03-0808 March 2018 Response to License Renewal Application NRC Request for Additional Information (RAI) Set 9 Project stage: Request ML18068A1872018-03-0909 March 2018 NRR E-mail Capture - Revision of Final Request for Additional Information (RAI 2.3.3.17-2) for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 11 Project stage: RAI ML18073A0482018-03-19019 March 2018 License Renewal Application Review Response to Request for Due Date Extension for Request for Additional Information Set 10 Project stage: RAI RBG-47835, Submittal of Response to License Renewal Application NRC Request for Additional Information Set 102018-03-26026 March 2018 Submittal of Response to License Renewal Application NRC Request for Additional Information Set 10 Project stage: Request RBG-47849, Response to License Renewal Application NRC Request for Additional Information Set 4 Supplement2018-03-27027 March 2018 Response to License Renewal Application NRC Request for Additional Information Set 4 Supplement Project stage: Supplement ML18078A7552018-03-28028 March 2018 Telephone Call Summary on Applicants Response to RAI B1.4-1 & B.1.4-2 (Set 5) on 030618 Rev 2 - All Edits Incorp Project stage: RAI ML18078A7482018-03-29029 March 2018 Uranium One Public Meeting Feb. 22, 2018 Project stage: Meeting ML18071A0182018-03-29029 March 2018 Telephone Call Summary RAI 3.2.2.3.2-1a Generic Filtration on 27FEB2018 v1_RBS Edits incorp._030618 Project stage: RAI RBG-47846, Response to License Renewal Application NRC Request for Additional Information (RAI) Set 122018-04-0303 April 2018 Response to License Renewal Application NRC Request for Additional Information (RAI) Set 12 Project stage: Request RBG-47850, Response to License Renewal Application NRC Request for Additional Information Set 5 Supplement2018-04-0404 April 2018 Response to License Renewal Application NRC Request for Additional Information Set 5 Supplement Project stage: Supplement ML18089A0762018-04-12012 April 2018 Summary of Public Telephone Conference Call Held on Between the U.S. Nuclear Regulatory Commission and Entergy Regarding Requests for Additional Information Pertaining to the River Bend Station, Unit 1 License Renewal Application Review Project stage: RAI ML18107A5042018-04-24024 April 2018 Summary of Public Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Regarding the Need for Additional Information to Support the River Bend Station, Unit 1 License Renewal Application Review Project stage: Other ML18115A0612018-04-25025 April 2018 Draft Response on RAI B1.21-1 Flow Accelerated Corrosion Project stage: Request ML18115A1632018-04-25025 April 2018 Draft Response on RBS LRA RAI B.1.21-2 Flow Accelerated Corrosion Project stage: Request ML18115A0722018-04-25025 April 2018 Draft Response on RAI B.1.25-1(Internal Surfaces in Miscellaneous Piping and Ducting Components) Project stage: Request ML18121A0292018-04-30030 April 2018 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 14 Project stage: RAI ML18121A2942018-05-0101 May 2018 Draft Response to NRC Request for Additional Information (RAI) 4.6-1a Generated from Staffs Review on the River Bend License Renewal Application Project stage: Draft RAI ML18121A3022018-05-0101 May 2018 Draft Response to NRC Request for Additional Information (RAI) 4.6-2a Generated from Staffs Review on the River Bend License Renewal Application Project stage: Draft RAI ML18122A2312018-05-0202 May 2018 Draft Response to NRC Request for Additional Information (RAI) B.1.40-5 Service Water Integrity Generated from Staffs Review on the River Bend Station, Unit 1 License Renewal Application Project stage: Draft RAI ML18122A1262018-05-0202 May 2018 RAI B.1.17-1 Revised - w- header-footer-watermark Project stage: Request ML18124A0092018-05-0303 May 2018 NRR E-mail Capture - Final Requests for Additional Information for the Safety Review of the River Bend Station License Renewal Application (CAC No. MF9757) - Set 15 Project stage: RAI ML18120A1352018-05-10010 May 2018 Call Summary - Fuel Oil, Ext.-Int. Surf. Monitoring, FAC & Others 041018, Rev2 Project stage: Other ML18135A1072018-05-15015 May 2018 RBS Draft Response (RAI 4.3.1-2a_Class 1 Fatigue w-header-footer-watermark_received on 051318 Project stage: Request ML18136A7052018-05-16016 May 2018 RBS Draft Response to LRA Review RAI 4.7.3-1a Fluence Effects for Rv Internals Project stage: Request ML18136A8212018-05-16016 May 2018 Draft Response to RAI 3.6.2.2.2.2-1a High Voltage Insulators - RBS LRA Review Project stage: Request 2018-03-26
[Table View] |
Text
DRAFT - UNCERTIFIED INFORMATION DRAFT - UNCERTIFIED INFORMATION Question RAI 4.6-2a
Background
Section 4.6 of the SRP LR states that if a plants code of record requires a fatigue parameter evaluation (fatigue analysis or fatigue waiver), then this analysis may be a time limited aging analyses (TLAA) and must be evaluated in accordance with 10 CFR 54.21(c) (1) to ensure that the effects of aging on the intended functions are adequately managed for the period of extended operation.
The current licensing basis may include fatigue waiver evaluations that preclude the need for performing CUF analyses of structural components. The ASME Code Section III rules for performing fatigue waiver evaluations for structural components are analogous to those in the Code for performing fatigue waiver evaluations of mechanical components. ASME Code NE-3222.4(d) Analysis for Cyclic Operations, Vessels Not Requiring Analysis for Cyclic Operation, provides for a waiver from fatigue analysis when certain cyclic loading criteria are met.
In its response to RAI 4.6 2, dated February 6, 2018, the applicant stated, in part, the following:
- For the personnel airlock, drywell airlock, drywell combination door/hatch assembly components: The evaluation concluded that analysis for cyclic operation was not necessary. No cumulative usage factors were calculated. The evaluation assumed 120 plant startup cycles. LRA Table 4.3-1 has a limiting value of 168 for plant startups, but because the allowable number of cycles for this ASME Section NE 3222.4(d) criterion was 2,800 cycles, the increase in cycles shown in LRA Table 4.3-1 does not impact the conclusion that a fatigue analysis is unnecessary.
- For the equipment hatch component: The equipment hatch calculation determined a fatigue analysis was not necessary after considering loads from OBE, SSE, LOCA, SRV lifts and heatups because the loads were very low. Cumulative usage factors were not calculated, and
- For the drywell head component: The drywell head calculation determined the alternating stresses from earthquakes and SRV loads were so low that the allowable number of cycles were infinite (CUF- 0).
Issue It is not clear if the evaluation performed under ASME Section NE 3222.4(d) criterion for the personnel airlock, drywell airlock, and the drywell combination door/hatch assembly constitutes a fatigue waiver that relies on time dependent cycles, and whether they were evaluated and dispositioned in accordance with 10 CFR 54.21(c) (1). The staff notes that the current licensing basis may include fatigue waiver evaluations that preclude the need for performing CUF analyses of structural components which may be a TLAA and must be evaluated.
Additionally, it is not clear if the equipment hatch and the drywell head were evaluated in accordance with the requirements of ASME Code Section III, Division I, Subsection NE-3222.4(d) to waive the requirements of a fatigue analysis, and what the disposition is in accordance with 10 CFR 54.21(c) (1) for the evaluations.
Request 1.
State the disposition, in accordance with 10 CFR 54.21(c) (1), for the personnel airlock, drywell airlock, and the drywell combination door/hatch assembly evaluations.
DRAFT - UNCERTIFIED INFORMATION DRAFT - UNCERTIFIED INFORMATION 2.
Clarify if an evaluation was performed in accordance with ASME Code,Section III, Subsection NE 3222.4(d) to evaluate the fatigue analysis requirements for the equipment hatch and the drywell head.
A.
If an evaluation was performed state the assumed number of cycles and limits. Otherwise, clarify what requirements of the ASME Code were followed to evaluate the fatigue analysis requirements for the equipment hatch and the drywell head, and clarify whether these evaluations are based on time dependent cycles.
B.
State the disposition, in accordance with 10 CFR 54.21(c) (1), for the equipment hatch and drywell head evaluations.
Response
- 1. The personnel airlock, drywell airlock, and drywell combination door/hatch assembly fatigue waiver evaluations are considered time-limited aging analyses due to the cycle assumptions in the evaluations.
The Fatigue Monitoring Program in accordance with 10 CFR 54.21(c)(1)(iii) will ensure the numbers of cycles remain within the values allowed in the fatigue waiver criteria of ASME Code,Section III, Subsection NE 3222.4(d).
- 2. A. The equipment hatch calculation includes a fatigue waiver evaluation for the hatch cover and a fatigue calculation specific to the hatch bolting. The calculation evaluates the hatch bolting for 50,000 cycles of SRV lifts.
The drywell head calculation determined the alternating stresses were low and that the allowable number of cycles is infinite. The fatigue usage factor was zero. The cycles specified were 120 heatups, 5 operating basis earthquakes of 30 cycles each, 1 safe shutdown earthquake of 20 cycles, 50,000 SRV cycles and 350 loss-of-coolant induced cycles.
B. The Fatigue Monitoring Program in accordance with 10 CFR 54.21(c)(1)(iii) will ensure that the numbers of transient cycles remain within the values assumed for the fatigue analyses and fatigue waiver evaluations.