(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
06-29-2016 | On April 30, 2016, at 1804 hours0.0209 days <br />0.501 hours <br />0.00298 weeks <br />6.86422e-4 months <br />, during the plant startup following the 1M38 maintenance outage, a reactor SCRAM was manually inserted by the Control Room Operators during post maintenance testing following work on the 'D' Reactor Recirculation Pump ( RRP) mechanical seal. The SCRAM was initiated since leakage was discovered by a rising trend in drywell unidentified leakage during plant startup. The seal had been replaced during the maintenance outage. The SCRAM was selected as the preferred method of shutting down the reactor due to low decay heat conditions following the outage.
ENS 51895 was submitted on April 30, 2016, as required by 10 CFR 50.72 (b)(2)(iv)(B). This issue is reportable under 10 CFR 50.73(a)(2)(iv)(A), for any event or condition that resulted in manual or automatic actuation of any of the systems listed in paragraph 10 CFR 50.73(a)(2)(iv)(B). |
---|
|
---|
Category:Letter
MONTHYEARIR 07200015/20244012024-10-30030 October 2024 NRC Independent Spent Fuel Storage Installation Security Inspection Report No. 07200015/2024401 ML24303A2822024-10-29029 October 2024 License Termination Plan Supplemental Submittal for Technical Bases Documents ML24284A1972024-10-10010 October 2024 Cover Letter Oyster Creek, License Termination Plan Acceptance Review ML24269A0462024-10-0404 October 2024 Cover Letter for Oyster Creek Nuclear Generating Station, License Amendment Request, License Termination Plan, Acceptance Review Request for Additional Information ML24274A0822024-09-25025 September 2024 Independent Spent Fuel Storage Installation Security Plan, Training Qualification Plan, Safeguards Contingency Plan, Revisions 1 and 2 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000219/20240022024-09-0505 September 2024 – NRC Inspection Report 05000219/2024002 and 07200015/2024001 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24214A0372024-08-0101 August 2024 License Amendment Request to Revise Renewed Facility Operating License to Add License Condition 2.C.(18) to Include License Termination Plan Requirements ML24179A1842024-07-23023 July 2024 June 20, 2024, Clarification Call on Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000219/20240012024-05-14014 May 2024 Decommissioning Intl, LLC Oyster Creek Nuclear Generating Station - NRC Inspection Report No. 05000219/2024001 ML24120A0412024-04-29029 April 2024 Annual Radioactive Environmental Operating Report for 2023 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24120A0402024-04-29029 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24094A2142024-04-19019 April 2024 Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML24089A2492024-03-29029 March 2024 Reply to Notice of Violation EA-2024-024 ML24085A7902024-03-28028 March 2024 – Preapplication Readiness Assessment of the License Termination Plan ML24081A2882024-03-21021 March 2024 Request Preliminary Review and Feedback on Chapter 6 of the Draft License Termination Plan ML24046A1242024-02-29029 February 2024 – NRC Inspection Report 05000219/2023003 ML24033A3272024-02-0202 February 2024 Request Preliminary Review and Feedback on Chapter 5 of the Draft License Termination Plan ML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 – NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report – January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 – NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 – NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 – NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages 2024-09-05
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000219/LER-2022-001, Compensatory Measures Not Implemented Per Sites Physical Security Plan Due to Multiplexer (Mux) Power Supply Failure2022-01-21021 January 2022 Compensatory Measures Not Implemented Per Sites Physical Security Plan Due to Multiplexer (Mux) Power Supply Failure 05000219/LER-2017-0052018-01-0303 January 2018 1 OF 3, LER 17-005-00 for Oyster Creek Nuclear Generating Station Regarding Failure of the Emergency Diesel Generator #2 During Surveillance Testing Due to a Broken Electrical Connector 05000219/LER-2017-0032017-08-31031 August 2017 Automatic Scram while Suberitical due to Low Reactor Level, LER 17-003-00 for Oyster Creek Regarding Automatic Scram while Subcritical due to Low Reactor Level 05000219/LER-2017-0022017-08-31031 August 2017 Manual Reactor Scram due to Degrading Main Condenser Vacuum, LER 17-002-00 for Oyster Creek Regarding Manual Scram due to Degraded Main Condenser Vacuum 05000219/LER-2016-0022017-06-23023 June 2017 Control Rod Drive Cooling Water System Isolation Scram Time Testing Was Not Performed, LER 16-002-01 for Oyster Creek Regarding Control Rod Drive Cooling Water System Isolation Scram Time Testing Was Not Performed 05000219/LER-2017-0012017-05-0303 May 2017 Automatic SCRAM due to APRM High Flux during Turbine Valve Testing, LER 17-001-01 for Oyster Creek, Regarding Transfer of Automatic SCRAM due to APRM High Flux during Turbine Valve Testing ML17129A6032017-05-0303 May 2017 LER 16-S01-01 for Oyster Creek, Regarding Special Nuclear Material Discovered Outside of Material Access Area 05000219/LER-2016-0012017-01-24024 January 2017 1 OF 4, LER 16-001-01 for Oyster Creek Nuclear Generating Station Regarding Failure of the #1 Emergency Diesel Generator During Surveillance Testing due to a Cooling Water System Leak RA-16-107, LER 16-S01-00 for Oyster Creek Nuclear Generating Station Regarding Special Nuclear Material Discovered Outside of Material Access Area2016-12-0505 December 2016 LER 16-S01-00 for Oyster Creek Nuclear Generating Station Regarding Special Nuclear Material Discovered Outside of Material Access Area 05000219/LER-2016-0052016-11-17017 November 2016 Technical Specification Prohibited Condition Caused by One Electromatic Relief Valve Inoperable for Greater than Allowed Outage Time, LER 16-005-00 for Oyster Creek Nuclear Generating Station Regarding Technical Specification Prohibited Condition Caused by One Electromatic Relief Valve Inoperable for Greater than Allowed Outage Time 05000219/LER-2016-0032016-06-29029 June 2016 Manual SCRAM Inserted due to Leakage from the D' Reactor Recirculation Pump Seal, LER 16-003-00 for Oyster Creek, Unit 1, Regarding Manual SCRAM Inserted due to Leakage from the 'D' Reactor Recirculation Pump Seal RA-16-001, Special Report for Inoperability of the Turbine Building High Range Radioactive Noble Gas Monitor2016-01-15015 January 2016 Special Report for Inoperability of the Turbine Building High Range Radioactive Noble Gas Monitor ML1015505702009-08-26026 August 2009 Event Notification for Oyster Creek on Offsite Notification Due to a Water Leak Containing Tritium ML0932006252009-07-24024 July 2009 NRC Operations Center Event Report - Oyster Creek ML1015505672009-04-15015 April 2009 Event Notification for Oyster Creek on Offsite Notification Due to Potential Release of Tritium ML0506107132005-02-16016 February 2005 LER 04-03-001 Oyster Creek, Unit 1, Regarding Actuation of Reactor Protection System Due to Spurious Hi-Hi Trip Signals on Intermediate Range Monitors Caused by Electromagnetic Interference 2022-01-21
[Table view] |
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
2. DOCKET
2015 002 00
Description of Event
On April 30, 2016, during the plant startup from 1M38 at approximately 1422 hours0.0165 days <br />0.395 hours <br />0.00235 weeks <br />5.41071e-4 months <br />, the station identified a rise in Unidentified Leak Rate (UILR). UILR rose from 0.21 gpm to 1.62 gpm at 1545 hours0.0179 days <br />0.429 hours <br />0.00255 weeks <br />5.878725e-4 months <br />. During this time reactor pressure was increased from 335 psi to 450 psi. As part of the troubleshooting for the unexpected rise in UILR, inspections in the drywell were performed and identified primary coolant leaking from the pump shaft of the D' Reactor Recirculation pump (RRP). At 1804 hours0.0209 days <br />0.501 hours <br />0.00298 weeks <br />6.86422e-4 months <br />, Control Room Operators initiated a manual SCRAM of the reactor to place the plant in a safe condition due to the leakage on the 'D' RRP.
Assessment of Safety Consequences
Following the manual SCRAM actuation, all systems responded as expected; therefore, this event is of low safety significance.
Cause of Event
In mid- 2015, unidentified drywell leak rate along with temperature and pressure trends on the 'D' RRP indicated degradation of the pump seal. The leakage was monitored for several months and remained within the limitations delineated by the Station's Technical Specifications (TS). In order to ensure that the condition did not degrade further, a maintenance outage (1M38) was scheduled to commence on April 25, 2016, with the replacement of the 'D' RRP seal as the main focus of the scope of work.
During 1M38 on April 27, 2016, the old 'D' RRP seal was removed and the new replacement seal was installed.
During the installation, the technicians discovered that the pump coupling could not be installed because it was too tall to fit onto the seal. The pump vendor then recommended machining the coupling and that minor machining is part of the normal fit-up process when installing new seal components. Additionally, the pump installation procedure specifically states that machining of up to 0.060" is permitted. Engineering prepared, approved and issued a technical evaluation to maintenance to machine the coupling to 0.060". The backing ring functions as a keeper for the 0-ring on, the shaft sleeve. Following this machining, the coupling fit and reassembly of the pump was completed.
Following completion of the maintenance work on the 'D' RRP and during the startup from 1M38, Control Room Operators identified a rising trend in UILR. UILR rose from 0.21 gpm to 1.62 gpm as reactor pressure was increased from 335 psi to 450 psi. Inspections conducted inside the drywell, identified primary coolant leaking from around the pump shaft of the 'D' RRP. At 1804 hours0.0209 days <br />0.501 hours <br />0.00298 weeks <br />6.86422e-4 months <br />, a manual SCRAM of the reactor was initiated to place the plant in a safe condition due to the leakage on the `D' RRP.
Following the SCRAM and during the disassembly of the 'D' RRP, when removing the pump half coupling keys the shaft sleeve 0-ring was found extruding on top of the back-up ring. Upon further disassembly the 0-ring was found to be cut, and an approximately one-inch piece of the 0-ring was found sitting on top of the back-up ring, which lead to the leakage from the seal cavity.
The Root Cause of the event was determined to be that the seal rebuild procedure was not properly revised in 2012 to prevent this failure from occurring.
Corrective Actions
- A Failure Mode analysis was conducted and implemented to determine the cause of the failure.
- The failed seal was replaced and tested satisfactorily.
- A Root Cause Evaluation was conducted.
- RRP seal replacement procedures will be revised to include critical dimension specifications with verifications and signoffs.
- Lessons learned have been communicated to Station Supervision.
Previous Occurrences
There were no previous occurrences of seal leakage resulting in manual SCRAM at Oyster Creek although several similar issues have been identified throughout the industry.