MONTHYEARIR 05000458/20240102024-10-31031 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2024010 IR 05000458/20240032024-10-31031 October 2024 Integrated Inspection Report 05000458/2024003 RBG-48315, Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement2024-09-24024 September 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement RBG-48306, Report of Changes and Errors to 10CFR50.462024-09-24024 September 2024 Report of Changes and Errors to 10CFR50.46 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24255A1192024-09-16016 September 2024 Notification of NRC Follow Up Inspection for One Severity Level (SL) III and Two SL IV or Three or More SL IV Violations and Request for Additional Information RBG-48311, Reply to a Notice of Violation, NRC Inspection Report 05000458/20240022024-08-28028 August 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2024002 IR 05000458/20240052024-08-22022 August 2024 Updated Inspection Plan for River Bend Station (Report 05000458/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24214A2752024-08-0202 August 2024 Acknowledgement of Readiness for Supplemental Inspection RBG-48308, Notification of Readiness for Supplemental Inspection2024-07-31031 July 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20240022024-07-30030 July 2024 Integrated Inspection Report 05000458/2024002 and Notice of Violation ML24164A0862024-06-12012 June 2024 Notification of Commercial Grade Dedication Inspection (05000458/2024010) and Request for Information 05000458/LER-2023-005-01, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-06-0404 June 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 ML24081A0072024-05-16016 May 2024 Issuance of Amendment No. 213 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b ML24093A0892024-05-16016 May 2024 Issuance of Amendment No. 214 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors IR 05000458/20240012024-05-14014 May 2024 Integrated Inspection Report 05000458/2024001 ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions ML24102A2842024-05-0707 May 2024 Summary of Regulatory Audit in Support of LARs to Revise Technical Specifications to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 RBG-48276, 2023 Annual Radioactive Effluent Release Report2024-04-23023 April 2024 2023 Annual Radioactive Effluent Release Report RBG-48288, Louisiana Pollutant Discharge Elimination System Permit Renewal2024-04-15015 April 2024 Louisiana Pollutant Discharge Elimination System Permit Renewal IR 05000458/20244022024-04-15015 April 2024 Security Baseline Inspection Report 05000458/2024402 (Full Report) ML24106A0432024-04-11011 April 2024 June 2024 Emergency Preparedness Exercise Inspection Request for Information ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair RBG-48277, 2023 Annual Radiological Environmental Operating Report2024-04-10010 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000458/20243012024-04-0202 April 2024 Notification of NRC Initial Operator Licensing Examination 05000458/2024301 ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) IR 05000458/20240402024-03-15015 March 2024 – 95001 Supplemental Inspection Report 05000458/2024040 and Follow-Up Assessment ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24066A1802024-03-0707 March 2024 Notification of NRC Follow-Up Inspection for Any Severity Level I or II Traditional Enforcement Violation IR 05000458/20230062024-02-28028 February 2024 Annual Assessment Letter for River Bend Station - Report 05000458/2023006 RBG-48278, 2023 Spent Fuel Storage Radioactive Effluent Release Report2024-02-27027 February 2024 2023 Spent Fuel Storage Radioactive Effluent Release Report RBG-48286, Revision to Owners Activity Report Form (OAR) for Cycle 222024-02-27027 February 2024 Revision to Owners Activity Report Form (OAR) for Cycle 22 ML24031A0042024-02-21021 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0052 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000458/LER-2023-006, Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard2024-02-0808 February 2024 Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard RBG-48274, Notification of Readiness for Supplemental Inspection2024-02-0505 February 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20230042024-01-30030 January 2024 Integrated Inspection Report 05000458/2023004 IR 05000458/20230402024-01-18018 January 2024 – 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter 05000458/LER-2023-005, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-01-16016 January 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 – Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) 05000458/LER-2023-004, Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure2023-12-28028 December 2023 Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment 2024-09-24
[Table view] |
Text
ber 30, 2013
SUBJECT:
RIVER BEND STATION - TEMPORARY INSTRUCTION 2515/186, "INSPECTION OF PROCEDURES AND PROCESS FOR RESPONDING TO POTENTIAL AIRCRAFT THREATS," INSPECTION REPORT NUMBER 05000458/2013406
Dear Mr. Olson:
On September 5, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Waterford Steam Electric Station, Unit 3, using Temporary Instruction 2515/186, "Inspection of Procedures and Processes for Responding to Potential Aircraft Threats." The enclosed inspection report documents the results of the inspection, which were preliminarily discussed on June 5, 2013, with you and other members of your staff. After discussing the results with the Office of Nuclear Security and Incident Response (NSIR) and the Office of Nuclear Reactor Regulation (NRR),
an exit meeting was conducted via telephone on September 5, 2013.
The objective of this inspection was to assess the implementation procedures and processes of River Bend Station, that are required by Title 10 of the Code of Federal Regulations (CFR) 50.54(hh)(1), which provides the requirements for responding to a potential aircraft threat. The results from this inspection, along with the results from this inspection performed at other operating commercial nuclear plants in the United States, will be used to evaluate the U.S. nuclear industry's readiness to safely respond to similar events. These results will also help the NRC to determine if additional regulatory actions are warranted.
The inspection examined activities conducted under your license as they relate to the implementation of 10 CFR 50.54(hh)(1), your compliance with the Commission's rules and regulations, and with the conditions of your operating licenses. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel.
UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV1600 EAST LAMAR BLVDARLINGTON, TEXAS 76011-4511 Based on results of this inspection, no NRC-identified or self-revealing findings were identified. However, three observations were identified by the inspectors for your future consideration.
The observations were of very low safety significance and were determined not to be violations
of regulatory requirements.
If you contest any finding or the subject in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at Grand Gulf Nuclear Station.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information - Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390 (b)(1).
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Should you have any questions regarding this inspection, we will be pleased to discuss the issues with you.
Sincerely,
/RA/
Vincent G. Gaddy, Chief
Operations Branch
Division of Reactor Safety
Docket No. 50-458 License No. NPF-47
Nonpublic Enclosure:
Inspection Report 05000458/2013406; w/Attachment: Supplemental Information Cover Letter Only Non Sensitive Publicly Available VGG SUNSI Review Complete Sensitive Non-Publicly Available Entire Report Non Sensitive Publicly Available Keyword: MD 3.4 Non-Public A.3 Sensitive Non-Publicly Available VGG OE:OB OE:OB C:PBC C:OB SHedger DStrickland JQuichocho VGaddy /RA/ /RA/ /RA/ /RA/ 9/25/2013 9/26/2013 9/26/2013 9/30/2013 ADAMS ACCESSION NUMBER:
ML13276A836