Category:Inspection Plan
MONTHYEARIR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) IR 05000390/20230062024-02-28028 February 2024 Annual Assessment Letter for Watts Bar Nuclear Plant Units 1 and 2 - Report 05000390/2023006 and 05000391/2023006 IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request IR 05000390/20220062023-03-0101 March 2023 Annual Assessment Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2022006 and 05000391/2022006 ML22327A1902022-11-28028 November 2022 – Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000390 2023403; 05000391 2023403 ML22250A4852022-09-0707 September 2022 Requalification Program Inspection IR 05000390/20220052022-08-31031 August 2022 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2022005 and 05000391/2022005 - Final IR 05000390/20210062022-03-0202 March 2022 Annual Assessment Letter for Watts Bar Nuclear Plant, Units 1 and 2 (Report No. 05000390/2021006 and 05000391/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar IR 05000390/20200062021-03-0303 March 2021 Annual Assessment Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2020006 and 05000391/2020006 ML20338A3202020-12-0303 December 2020 Notification of an NRC Fire Protection Team Inspection (NRC Inspection Report 05000390/2021011 and 05000391/2021011) and Request for Information ML20268B8672020-09-24024 September 2020 Document Request for Watts Bar Nuclear Plant Radiation Protection Inspection Inspection Report 2020-04 ML20253A1782020-09-0909 September 2020 Emergency Preparedness Program Inspection Request for Information IR 05000390/20200052020-08-31031 August 2020 Assessment Followup Letter and Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2020005 and 05000391/2020005 ML20266G4592020-08-14014 August 2020 Notification of Inspection and Request for Information IR 05000390/20190062020-03-0303 March 2020 Annual Assessment Letter for Watts Bar Nuclear Plant Units 1 and 2 - NRC Report 05000390/2019006 and 05000391/2019006 ML20028D4882019-12-0202 December 2019 Notification of Inspection and Request for Information IR 05000390/20180062019-03-0404 March 2019 Annual Assessment Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2018006 and 05000391/2018006 ML19063B8992019-02-28028 February 2019 ISI Sgisi RFI 2019002 Combined ML18282A4462018-10-0909 October 2018 Emergency Preparedness Program Inspection Request for Information ML18215A1362018-08-0202 August 2018 Radiation Safety Baseline Inspection RFI 2018003 Public ML18191B2472018-07-10010 July 2018 Notification of Conduct of a Triennial Fire Protection Baseline Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000390/2018011 and 05000391/2018011 ML18187A0142018-07-0303 July 2018 RP Inspection Document Request - August 2018 ML18059A1502018-02-28028 February 2018 EOC Assessment Letter ML17271A0052017-09-21021 September 2017 Notification of Inspection and Request for Information ML17142A1862017-05-19019 May 2017 Emergency Preparedness Inspection and Request for Information Dated: May 19, 2017 IR 05000390/20160062017-03-0101 March 2017 Annual Assessment Letter for Watts Bar Nuclear Plant, NRC Inspection Report 05000390/2016006 and 05000391/2016006 ML17059C9572017-02-23023 February 2017 Notification of Inspection and Request for Information IR 05000391/20166112016-08-31031 August 2016 Mid-Cycle Assessment Letter - Watts Bar Nuclear Plant Unit 2 (NRC Inspection Report 05000391/2016611) IR 05000390/20160052016-08-31031 August 2016 Mid Cycle Assessment Letter for Watts Barr Nuclear Plant Unit 1, NRC Inspection Report 05000390/2016005 ML16062A2862016-03-0202 March 2016 Annual Assessment Letter IR 05000391/20166072016-03-0202 March 2016 End-Of-Cycle Assessment Letter - Watts Bar, Unit 2 (NRC Inspection Report 05000391/2016607) IR 05000391/20156062015-09-0101 September 2015 Mid-Cycle Assessment Letter - Watts Bar Nuclear Plant Unit 2 (NRC Inspection Report 05000391/2015606) IR 05000390/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for the Watts Bar Nuclear Plant Unit 1, NRC Inspection Report 005000390/2015005 IR 05000390/20140012015-03-0404 March 2015 Annual Assessment Letter for Watts Bar Nuclear Plant Unit 1, NRC Inspection Report 05000390/2014001 IR 05000391/20156012015-02-27027 February 2015 End-Of-Cycle Assessment Letter - Watts Bar Nuclear Plant, Unit 2 (NRC Inspection Report 05000391/2015601) IR 05000391/20146062014-09-0303 September 2014 Mid-Cycle Assessment Letter Watts Bar Nuclear Plant, Unit 2 (NRC Inspection Report 05000391/2014606) ML14245A1232014-09-0202 September 2014 Mid-Cycle Letter ML14125A0452014-05-0505 May 2014 Plant, Notification of Inspection and Request for Information IR 05000390/20130012014-03-0404 March 2014 Annual Assessment Letter Watts Bar Nuclear Plant Unit 1 (Report 05000390/2013001) IR 05000391/20136062013-09-0303 September 2013 Mid-Cycle Assessment Letter - Watts Bar Nuclear Plant Unit 2 (NRC Inspection Report 05000391/2013606) ML13246A1912013-09-0303 September 2013 Mid Cycle Assessment Letter ML13123A2732013-05-0303 May 2013 Ti 2515-182 Phase 1 RFI - MSC IR 05000390/20136012013-03-0404 March 2013 Annual Assessment Letter for Watts Bar Nuclear Plant Unit 2 (IR 05000390-13-601) IR 05000390/20120012013-03-0404 March 2013 Annual Assessment Letter for Watts Bar Nuclear Plant Unit 1 (Report 05000390/2012001) ML12248A1022012-09-0404 September 2012 Mid Cycle Assessment Letter Watts Bar 2012 IR 05000390/20120062012-09-0404 September 2012 Mid Cycle Assessment Letter Watts Bar 2012 ML12065A3502012-03-0505 March 2012 Inspection/Activity Plan, 03/01/2012 - 06/30/2013 2024-02-28
[Table view] Category:Inspection Report
MONTHYEARIR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) IR 05000390/20240102024-03-0808 March 2024 Age-Related Degradation Inspection Report 05000390/2024010 and 05000391/2024010 IR 05000390/20230062024-02-28028 February 2024 Annual Assessment Letter for Watts Bar Nuclear Plant Units 1 and 2 - Report 05000390/2023006 and 05000391/2023006 IR 05000390/20230042024-02-13013 February 2024 Integrated Inspection Report 05000390/2023004 and 05000391/2023004 and Apparent Violation IR 05000390/20234412023-12-21021 December 2023 Plant–Final Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public IR 05000390/20234042023-12-14014 December 2023 – Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23296A0242023-10-24024 October 2023 Biennial Problem Identification and Resolution Inspection Report and Preliminary Greater than Green Finding and Apparent Violation IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 IR 05000390/20234012023-03-13013 March 2023 – Security Baseline Inspection Report 05000390 2023401 and 05000391 2023401 IR 05000390/20220062023-03-0101 March 2023 Annual Assessment Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2022006 and 05000391/2022006 IR 05000390/20220042023-02-10010 February 2023 – Integrated Inspection Report 05000390/2022004 and 05000391/2022004 IR 05000390/20224202022-12-0101 December 2022 Security Baseline Inspection 05000390/2022420 and 05000391/2022420 Cover Letter ML22318A0072022-11-14014 November 2022 Integrated Inspection Report 05000390/2022003 and 05000391/2022003 IR 05000390/20220102022-10-28028 October 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000390/2022010 and 05000391/2022010 ML22256A2952022-09-14014 September 2022 Operation of an Independent Spent Fuel Storage Installation Report 07201048/2022001 IR 05000390/20220052022-08-31031 August 2022 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2022005 and 05000391/2022005 - Final IR 05000390/20220022022-08-12012 August 2022 Integrated Inspection Report 05000390/2022002 and 05000391/2022002 and Exercise of Enforcement Discretion IR 05000390/20224012022-08-0303 August 2022 Security Baseline Inspection Report 05000390/2022401 and 05000391/2022401 ML22123A2412022-05-11011 May 2022 Review of the Fall 2021 Mid-Cycle Steam Generator Tube Inspection Report IR 05000390/20220012022-05-11011 May 2022 Integrated Inspection Report 05000390/2022001 and 05000391/2022001 IR 05000390/20210062022-03-0202 March 2022 Annual Assessment Letter for Watts Bar Nuclear Plant, Units 1 and 2 (Report No. 05000390/2021006 and 05000391/2021006) IR 05000390/20210042022-02-10010 February 2022 Integrated Inspection Report 05000390/2021004 and 05000391/2021004 IR 05000390/20223012022-01-0707 January 2022 Notification of Licensed Operator Initial Examination 05000390/2022301 and 05000391/2022301 IR 05000390/20210032021-11-10010 November 2021 Integrated Inspection Report 05000390/2021003 and 05000391/2021003 IR 05000390/20214022021-11-0202 November 2021 Security Baseline Inspection Report 05000390/2021402 and 05000391/2021402 IR 05000390/20214032021-10-26026 October 2021 Material Control and Accounting Program Inspection Report 05000390/2021403 and 05000391/2021403 (OUO Removed) ML21263A0042021-09-24024 September 2021 Review of the Fall 2020 Steam Generator Tube Inspection Report IR 05000390/20214012021-08-31031 August 2021 Security Baseline Inspection Report 05000390/2021401 and 05000391/2021401 IR 05000390/20210052021-08-24024 August 2021 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 & 2 Report 05000390/2021005 and 05000391/2021005 IR 05000390/20210022021-08-0404 August 2021 Integrated Inspection Report 05000390/2021002 and 05000391/2021002 IR 05000390/20210122021-07-0101 July 2021 Biennial Problem Identification and Resolution Inspection Report 05000390/2021012 and 05000391/2021012 IR 05000390/20210102021-05-0606 May 2021 NRC Inspection Report 05000390/2021010 and 05000391/2021010 IR 05000390/20210012021-05-0505 May 2021 Integrated Inspection Report 05000390/2021001 and 05000391/2021001 IR 05000390/20210112021-04-13013 April 2021 Triennial Fire Protection Inspection Report 05000390/2021011 and 05000391/2021011 2024-08-07
[Table view] Category:Letter
MONTHYEARIR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000391/LER-2024-002, Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO2024-05-0606 May 2024 Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements 05000391/LER-2024-001, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-03-27027 March 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-025, Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule2024-03-25025 March 2024 Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule ML24081A0262024-03-21021 March 2024 Emergency Plan Implementing Procedure Revisions ML24079A0312024-03-19019 March 2024 Wb 2024-301, Corporate Notification Letter (210-day Ltr) 2024-09-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 August 31, 2016 Mr. Joseph Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37402-2801 SUBJECT: MID CYCLE ASSESSMENT LETTER FOR WATTS BAR NUCLEAR PLANT UNIT 1, NRC INSPECTION REPORT 05000390/201 6 00 5
Dear Mr. Shea:
On August 10, 201 6, the NRC completed its mid-cycle performance review of Watts Bar Nuclear Plant (WBN) Unit 1. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1 , 20 1 5, through June 30 2016. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Watts Bar Unit 1 operated in a manner that preserved public health and safety and met all cornerstone objectives.
The NRC determined the performance at the Watts Bar Nuclear Plant Unit 1 during the most recent quarter was within the Licensee Response Column of the NRC
's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The NRC also identified a cross-cutting theme in the Safety Conscious Work Environment (SCWE) cross-cutting area. Specifically, on March 23, 2016, the NRC issued a Chilling Effect Letter for Watts Bar and the NRC identified one inspection findings in the assessment period with a cross-cutting aspect of S.1 SCWE Policy.
The NRC will follow-up on the SCWE theme using baseline inspection sample because this is the first assessment cycle in which the cross-cutting theme was identified.
The enclosed inspection plan lists the inspections scheduled through June 30 , 2018. Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In addition to the ROP baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include:
Inspection Procedure (IP) 43004, Inspection of Commercial-Grade Dedication Programs, and Operator Licensing Examinations. The NRC will continue to evaluate the effectiveness of TVA's oversight and management of operations during Unit 2 startup and transition to dual unit operattion. This will include inspections and reviews addressing the organizational and operational challenges associated with the integration of both Watts Bar units.
The NRC staff completed Temporary Instruction 2515/191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans" at Watts Bar on January, 16 2016 to confirm full implementation of orders Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" and Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation." The results of the inspection can be found in inspection report 05000390/2015609 and 05000391/2015616.
In Staff Requirements Memorandum
- SECY 16-0009, "Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities," the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, "Operating Reactor Assessment Program."
In accordance with 10 CFR 2.390 of the NRC's "Agency Rules of Practice and Procedure
," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (404) 997-4 415 with any questions you have regarding this letter.
Sincerely,
/RA/ Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No.
- 50-390 License No.
- NPF-90 Enclosure:
Watts Bar Inspection/Activity Plan (0 9/01/201 6 - 06/3 0/201 8) c c: Distribution via List Serv
_________________________
SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE CRK1 AJB3 NAME C. Kontz A. Blamey DATE 8/5/2016 8/31/2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO Page 1 of 2 08/31/2016 08:08:16 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteWatts BarInspection / Activity Plan 09/01/2016-06/30/2018 ISFSI-ISFSI DRY RUN AND INITIAL LOADING 2 1 IP Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 60854.1 08/29/2016 09/02/2016 1 IP Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 60854.1 09/12/2016 09/16/2016 1 IP Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 60854.1 09/19/2016 09/24/2016 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 5 1, 2 IP Problem Identification and Resolution71152B 09/12/2016 09/15/2016 1, 2 IP Problem Identification and Resolution71152B 10/31/201611/04/2016 EP-EP PROGRAM INSPECTION 5 1 IP A lert and Notification System Testing711140211/14/201611/18/2016 1 IP Emergency Preparedness Organization Staffing and Augmentation System711140311/14/201611/18/2016 1 IP Emergency Action Level and Emergency Plan Changes711140411/14/201611/18/2016 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies711140511/14/201611/18/2016 1 IP Performance Indicator Verification7115111/14/201611/18/2016OL RQ-REQUAL INSP 2 1 IP Licensed Operator Requalification Program7111111B11/28/2016 12/02/2016 ISI-UNIT 1 IN-SERVICE INSPECTION & RVH EXAM 2 1 IP Inservice Inspection Activities - PWR7111108P 03/27/2017 03/31/2017 RP-RP OCCUPATIONAL INSPECTION WEEK 1 2 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 03/27/2017 03/31/2017 1 IP Occupational ALARA Planning and Controls71124.02 03/27/2017 03/31/2017 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 03/27/2017 03/31/2017 1 IP Occupational Dose Assessment71124.04 03/27/2017 03/31/2017 1 IP Radiation Monitoring Instrumentation71124.05 03/27/2017 03/31/2017 1 IP Performance Indicator Verification71151 03/27/2017 03/31/2017 SGISI-UNIT 1 SG IN-SERVICE INSPECTION 1 1 IP Inservice Inspection Activities - PWR7111108P 04/03/2017 04/07/2017 RP-RP OCCUPATIONAL INSPECTION WEEK 2 3 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 04/17/2017 04/21/2017 1 IP Occupational ALARA Planning and Controls71124.02 04/17/2017 04/21/2017 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 04/17/2017 04/21/2017 1 IP Occupational Dose Assessment71124.04 04/17/2017 04/21/2017 1 IP Radiation Monitoring Instrumentation71124.05 04/17/2017 04/21/2017 1 IP Performance Indicator Verification71151 04/17/2017 04/21/2017 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
Page 2 of 2 08/31/2016 08:08:16 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteWatts BarInspection / Activity Plan 09/01/2016-06/30/2018 TFPI-TRIENNIEL FIRE PROTECTION INSPECTION 5 1 IP Fire Protection [Triennial]7111105T 09/18/2017 09/22/2017 1 IP Fire Protection [Triennial]7111105T 10/02/2017 10/06/2017 ISI-UNIT 2 IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 10/23/2017 10/27/2017 SGISI-UNIT 2 SG IN-SERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 10/30/201711/03/2017 EP-EP EXERCISE 3 1 IP Exercise Evaluation711140111/13/201711/17/2017 1 IP Emergency Action Level and Emergency Plan Changes711140411/13/201711/17/2017 1 IP Exercise Evaluation - Scenario Review711140811/13/201711/17/2017 1 IP Performance Indicator Verification7115111/13/201711/17/2017 MODS-PLANT MODIFICATIONS INSPECTION 3 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 04/16/2018 04/20/2018 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 04/30/2018 05/04/2018 HS-TRIENNIAL HEAT SINK PERFORMANCE 1 1, 2 IP Heat Sink Performance7111107T 06/04/2018 06/04/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.