RAI, Request for Additional Information Regarding Amendment Additional to Modify Technical Specifications for the Diesel Generator Endurance Test
ML072000254
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 07/23/2007
From: Boska J
NRC/NRR/ADRO/DORL/LPLI-1
To: Balduzzi M
Entergy Nuclear Operations
Boska J, NRR, 301-415-2901
References
TAC MD4923
Download: ML072000254 (6)


Text

July 23, 2007Mr. Michael A. BalduzziSr. Vice President & COO Regional Operations, NE Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601

SUBJECT:

INDIAN POINT NUCLEAR GENERATING UNIT NO. 2 - REQUEST FORADDITIONAL INFORMATION REGARDING AMENDMENT APPLICATION TO MODIFY TECHNICAL SPECIFICATIONS FOR THE DIESEL GENERATOR ENDURANCE TEST (TAC NO. MD4923)

Dear Mr. Balduzzi:

On March 22, 2007, Entergy Nuclear Operations, Inc. (Entergy), submitted an application for aproposed amendment for Indian Point Nuclear Generating Unit No. 2 which would revise the test acceptance criteria for the endurance test for the emergency diesel generators, Technical Specification Surveillance Requirement 3.8.1.10.The Nuclear Regulatory Commission staff is reviewing the submittal and has determined thatadditional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). In an email dated July 10, 2007, the Entergy staff indicated that a response to the RAI would be provided within 45 days of the date of this letter. Please contact me at (301) 415-2901 if you have any questions on this issue.Sincerely,/RA/John P. Boska, Senior Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-247

Enclosure:

RAIcc w/encl: See next page

ML072000254*See memo dated 6/19/07OFFICELPL1-1/PMLPL1-1/LAEEEB/BCLPL1-1/BCNAMEJBoskaSLittleGWilson*MKowalDATE7/23/077/23/076/19/077/23/07 Indian Point Nuclear Generating Unit No. 2 cc:

Mr. Michael R. KanslerPresident & CEO / CNO Entergy Nuclear Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213Mr. John T. HerronSr. Vice President Entergy Nuclear Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213Sr. Vice PresidentEngineering & Technical Services Entergy Nuclear Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213Mr. Fred R. DacimoSite Vice President Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249Mr. Anthony Vitale - ActingGeneral Manager, Plant Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway P.O. Box 249 Buchanan, NY 10511-0249Mr. Oscar LimpiasVice President Engineering Entergy Nuclear Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213Mr. Joseph P. DeRoyVice President, Operations Support Entergy Nuclear Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213Mr. John A. VentosaGM, Engineering Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. John F. McCannDirector, Nuclear Safety & Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Ms. Charlene D. FaisonManager, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. Ernest J. HarknessDirector, Oversight Entergy Nuclear Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213Mr. Patric W. ConroyDirector, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249Mr. T.R. Jones - ActingManager, Licensing Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P. O. Box 249 Buchanan, NY 10511-0249Mr. William C. DennisAssistant General Counsel Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Indian Point Nuclear Generating Unit No. 2 cc:

Mr. Michael BalboniDeputy Secretary for Public Safety State Capitol, Room 229 Albany, NY 12224Mr. John P. SpathNew York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399Mr. Paul EddyNew York State Department of Public Service 3 Empire State Plaza Albany, NY 12223-1350Regional Administrator, Region IU.S. Nuclear Regulatory Commission

475 Allendale Road King of Prussia, PA 19406Senior Resident Inspector's OfficeIndian Point 2 U. S. Nuclear Regulatory Commission P.O. Box 59 Buchanan, NY 10511Mr. Charles Donaldson, EsquireAssistant Attorney General New York Department of Law 120 Broadway New York, NY 10271Mr. Raymond L. AlbaneseFour County Coordinator 200 Bradhurst Avenue Unit 4 Westchester County Hawthorne, NY 10532Mayor, Village of Buchanan236 Tate Avenue Buchanan, NY 10511Mr. William DiProfioPWR SRC Consultant 48 Bear Hill Road Newton, NH 03858Mr. Garry RandolphPWR SRC Consultant 1750 Ben Franklin Drive, 7E Sarasota, FL 34236Mr. William T. RussellPWR SRC Consultant 400 Plantation Lane Stevensville, MD 21666-3232Mr. Jim RiccioGreenpeace 702 H Street, NW Suite 300 Washington, DC 20001Mr. Phillip MusegaasRiverkeeper, Inc.

828 South Broadway Tarrytown, NY 10591Mr. Mark JacobsIPSEC 46 Highland Drive Garrison, NY 10524 EnclosureREQUEST FOR ADDITIONAL INFORMATIONREGARDING AMENDMENT APPLICATION TO MODIFY TECHNICAL SPECIFICATIONSFOR THE DIESEL GENERATOR ENDURANCE TESTENTERGY NUCLEAR OPERATIONS, INC.INDIAN POINT NUCLEAR GENERATING UNIT NO. 2DOCKET NO. 50-247By letter to the Nuclear Regulatory Commission (NRC) dated March 22, 2007, (AgencywideDocuments Access Management System Accession No. ML070890307), Entergy Nuclear Operations, Inc. (the licensee) requested an amendment to the Indian Point Nuclear Generating Unit No. 2 (IP2) Technical Specifications (TS) Surveillance Requirement (SR) related to testacceptance criteria for emergency diesel generator (EDG) testing. The NRC staff is reviewing the submittal and has the following questions:1.Define the IP2 EDG ratings (continuous, 2000-hour, 2-hour, and 1/2-hour) and timeconstraints for operating at those ratings, similar to how the Indian Point Nuclear Generating Unit No. 3 (IP3) TS Bases define the ratings and time constraints for the Unit 3 EDGs (Revision 3, page B 3.8.1-4). Explain any discrepancies between the IP2 and IP3 definitions of the time constraints for operating at the load values of the ratings. 2.Provide the basis for why there is a sequential limitation whereby it is unacceptable tooperate the IP2 EDGs for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at 2100 kW followed by operating at 2300 kW for 1/2-hour, and why any other combination of the IP2 EDG ratings is acceptable. Also provide the technical basis and acceptance (and its basis) from the EDG vendor for operating the EDGs for two consecutive overloading periods (30 minutes at the 30-minute rating and then 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at the 2-hour rating) without adversely affecting EDG design function capability and without requiring additional maintenance and/or inspection after the first overload period prior to operating at the second overload period.

Provide the details of the EDG maintenance that is required as a result of operating the EDGs at the short-term ratings and as described in the license amendment request.

This response needs to include the generator/excitation system capability as well as the engine's capability.3.Provide the EDG loading calculation which establishes the KVAR, kilowatt, and powerfactor values, and the load profile (load values and duration of those values) until steady state loading conditions (no expected increases in loading) are reached after initiation of the worst-case design-basis event for each of the IP2 EDGs.4.Provide the bases that confirm the IP2 EDGs are capable of handling the worst-caseload profile after considering derating of the EDGs, if any, due to EDG loading, engine coolant outlet temperature, air intake (combustion air) temperature, or other potential factors that may result in derating of the EDGs. 5.Describe IP2's commitments to (and exceptions taken to) applicable guidance andstandards regarding EDG design and testing, such as NRC Regulatory Guides and IEEE standards. Include the revision numbers of the applicable guidance documents and standards.6. Provide the applicable marked-up version of the IP2 TSs Bases pages.