04/03/2008 - Notice of Meeting with Entergy Nuclear Northeast to Discuss Safety Performance of the James A. FitzPatrick Nuclear Power Plant Annual Assessment for Cy 2007
ML080780025
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 03/14/2008
From: Cobey E
Reactor Projects Branch 2
To:
Cobey, Eugene W. RI/DRP/PB2/610-337-5171
References
MN 08-010
Download: ML080780025 (4)


Text

March 14, 2008 MN No.08-010 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF SIGNIFICANT MEETING

Licensee: Entergy Nuclear Northeast Facility: James A. FitzPatrick Nuclear Power Plant Docket No. 50-333

Date and Time: April 3, 2008, from 2:00 p.m. to 3:30 p.m.

Location: Joint News Center Oswego County Airport County Route 176 Fulton, NY 13069 Purpose: The NRC requested an Annual Assessment Meeting with Entergy to discuss the NRC's assessment of the safety performance of the James A. FitzPatrick Nuclear Power Plant for calendar year 2007.

The NRC's assessment is documented in a letter dated March 3, 2008. Attendees*:

NRC: E. Cobey, Chief, Projects Branch 2, Region I G. Hunegs, Senior Resident Inspector S. Rutenkroger, Resident Inspector Entergy: P. Dietrich, Site Vice President K. Mulligan, General Manager of Plant Operations S. Bono, Director of Engineering B. Finn, Director of Nuclear Safety Assurance Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have opportunities to communicate with the NRC staff following the business portion, but before the meeting is adjourned.

The NRC's Annual Assessment Letter - James A. FitzPatrick Nuclear Power Plant, can be located in ADAMS (Accession Number ML080630118). ADAMS is accessible from the NRC Web Site at: http://www.nrc.gov/reading-rm/adams.html.

2Additional information relative to the NRC's Annual Assessment Process and the safety performance of James A. FitzPatrick Nuclear Power Plant can be found on the NRC's web site at: www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html. Meeting Contact: Eugene W. Cobey, Chief, Projects Branch 2 610-337-5171 E-mail: ewc@nrc.gov

  • Handicapped persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by March 26, 2008, via telephone to the NRC meeting contact.

Approved by: /RA by Blake D. Welling For/

Eugene W. Cobey, Chief Projects Branch 2 Division of Reactor Projects

3 Agenda NRC's Annual Assessment Meeting James A. FitzPatrick Nuclear Power Plant April 3, 2008 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (5 minutes)

Review of Reactor Oversight Process . . . . . . . . . . . . . . . . . . . . . . . . . NRC (10 minutes)

Discussion of James A. FitzPatrick Nuclear Station Performance . . . . NRC (10 minutes)

Entergy's Response and Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . Entergy (25 minutes)

Closing Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (5 minutes)

Short Break . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (5 minutes)

NRC to address public questions . . . . . . . . . . . .NRC/Members of the Public (as needed) 3Agenda NRC's Annual Assessment Meeting James A. FitzPatrick Nuclear Power Plant April 3, 2008 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (5 minutes) Review of Reactor Oversight Process . . . . . . . . . . . . . . . . . . . . . . . . . NRC (10 minutes)

Discussion of James A. FitzPatrick Nuclear Station Performance . . . . NRC (10 minutes) Entergy's Response and Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . Entergy (25 minutes) Closing Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (5 minutes)

Short Break . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (5 minutes) NRC to address public questions . . . . . . . . . . . .NRC/Members of the Public (as needed)

Distribution w/encl: (VIA E-MAIL) Executive Director for Operations, OEDO (RIDSEDOMAILCENTER RESOURCES) Deputy Executive Director for Reactor Programs, OEDO (RIDSEDOMAILCENTER RESOURCES)

Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD) Deputy Director, Office of Nuclear Reactor Regulation, NRR/ADPR (RIDSNRROD) RIDSNRRADRO RIDSNRRDIRS RIDSNRRDIRSLPAB RIDSNRRDORL RIDSNRRDORlLpl1-1 RIDSNRRDORlLpl1-2 Asst. General Counsel Materials Litigation and Enforcement, OGC (RIDSOGCMAILCENTER) S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP G. West, RI OEDO J. Lubinski, NRR E. Cobey, DRP D. Jackson, DRP B. Welling, DRP T. Wingfield, DRP G. West, RI OEDO (Acting) M. Kowal, NRR J. Boska, PM NRR J. Hughey, NRR G. Hunegs, DRP, Senior Resident Inspector S. Rutenkroger, DRP, Resident Inspector K. Kolek, Resident OA D. Roberts, DRS M. Gamberoni, DRS D. Screnci, PAO N. Sheehan, PAO N. McNamara, SLO M. McLaughlin, SLO Region I Docket Room (w/concurrences)

Regional Administrator Secretary, RI Deputy Regional Administrator Secretary, RI DRP Division Secretary, RI DRS Division Secretary, RI DNMS Division Secretary, RI DRM Division Secretary, RI Region I Receptionist DOCUMENT NAME: T:\DRP\BRANCH2\Meetings\2008 Annual Assessment Meetings\Fitz\Fitzpatrick Meeting Notice.doc SUNSI Review Complete: SCM (Reviewer's Initials) After declaring this document "An Official Agency Record" it will be released to the Public. To receive a copy of this document, indicate in the box:

" C" = Copy without attachment/enclosure " E" = Copy with attachment/enclosure " N" = No copy ML080780025 OFFICE RI/DRP RI/DRP RI/PAO NAME SMcCarver/SCM ECobey/BDW For/

DScrenci/DPS

DATE 03/11/08 03/14/08 03/14/08 OFFICIAL RECORD COPY