10/12/2006 Notice of Forthcoming Meeting to Discuss the License Renewal Process and Environmental Scoping for James A. Fitzpatrick Nuclear Power Plant, License Renewal Application Review
ML062680355
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/25/2006
From: Quinones-Hernandez S
NRC/NRR/ADRO/DLR/REBB
To: Rani Franovich
NRC/NRR/ADRO/DLR/REBB
hernandez, s, NRR, DLR,REBB, 415-4049
References
Download: ML062680355 (14)


Text

  • Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings," 67Federal Register 36920, May 28, 2002.September 25, 2006MEMORANDUM TO:Rani L. Franovich, Branch ChiefEnvironmental Branch B Division of License Renewal Office of Nuclear Reactor RegulationFROM:Samuel Hernandez, Project Manager /RA/Environmental Branch BDivision of License Renewal Office of Nuclear Reactor Regulation

SUBJECT:

FORTHCOMING MEETING TO DISCUSS THE FOR JAMES A.FITZPATRICK NUCLEAR POWER PLANT, LICENSE RENEWAL APPLICATION REVIEW DATE AND TIME:CATEGORY 3*:This is a Category 3 Meeting. The public is invited to participate in thismeeting by providing comments and asking questions throughout the meeting.PURPOSE:To discuss the license renewal and environmental scoping process forthe License Renewal Application (LRA) review for James A. Fitzpatrick Nuclear Power Plant. These meetings will provide members of the publicwith the opportunity to provide comments regarding environmental issues that the U.S. Nuclear Regulatory Commission (NRC) should considerduring its review of the LRA. These meetings are being conducted as part of the scoping process outlined in Title 10 of the Code of FederalRegulations Part 51 (10 CFR Part 51) to support development of anenvironmental impact statement related to the LRA. See the enclosed Agenda and Federal Register notice (71 FR 55032). The LRA is available at http://www.nrc.gov/reactors/operating/licensing/renewal/applications/ Fitzpatrick/html, the NRC's publicly available Agencywide DocumentAccess and Management System (ADAMS). The ADAMS Accession Number is ML062160494.

R. Franovich CONTACTS:PURPOSE (Cont'd): Both formal meetings will be preceded by an informal

?open house"beginning one hour prior to each meeting for those who wish to attend.

The open house will provide members of the public with an opportunityto talk informally one-on-one with NRC staff. Members of the publicmay register to present oral comments at the meetings by contactingby October 5, 2006. Those who wish to make commentsmay also register within 15 minutes of the start of each meeting.

Individual oral comments may be limited by the time available, depending on the number of persons who register.ACCOMMODATIONS: If special equipment or accommodations are needed to attend or present or via e-mail at shq@nrc.gov, no later than September 29, 2006, to provide the NRC staff adequate notice to determine whether the request can be accommodated.PARTICIPANTS:NRCMembers of the Public Who Register to SpeakS. Hoffman Lawrence Livermore National LaboratoryBruce McDowellDocket

Enclosures:

1. Agenda
2. Federal Register Noticecc w/encls: See next page R. Franovich CONTACTS:PURPOSE (Cont'd): Both formal meetings will be preceded by an informal

?open house"beginning one hour prior to each meeting for those who wish to attend.

The open house will provide members of the public with an opportunityto talk informally one-on-one with NRC staff. Members of the publicmay register to present oral comments at the meetings by contactingby October 5, 2006. Those who wish to make commentsmay also register within 15 minutes of the start of each meeting.

Individual oral comments may be limited by the time available, depending on the number of persons who register.

ACCOMMODATIONS: If special equipment or accommodations are needed to attend or present or via e-mail at shq@nrc.gov, no later than September 29, 2006, to provide the NRC staff adequate notice to determine whether the request can be accommodated.PARTICIPANTS:NRCMembers of the Public Who Register to SpeakS. Hoffman Lawrence Livermore National LaboratoryBruce McDowellDocket

Enclosures:

1. Agenda
2. Federal Register Noticecc w/encls: See next pageDISTRIBUTION: See next pageAdams Accession No. ML062680355Document Name: E:\Filenet\ML062680355.wpdOFFICEPM:DLR:RLRBLA:DLRPM:DLR:REBBNAMEN. LeY. EdmondsS. Hernandez DATE09/22/06 09/22/06 09/25/06 OFFICIAL RECORD COPY Memo to Rani Franovich from Samuel Hernandez dated September 25, 2006

SUBJECT:

FORTHCOMING MEETING TO DISCUSS THE FOR JAMES A. FITZPATRICKNUCLEAR POWER PLANT, LICENSE RENEWAL APPLICATION REVIEW DISTRIBUTION

Hard CopyS. HernandezE-MailPublicPMNS BRidsNrrAdro RidsNrrDlrRebb RidsNrrDlrReba RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsOgcMailRoom RidsOpaMailR. Schaff E. Benner A. Mullins S. Hernandez J. Muir S. Werts S. Hoffman B. McDowell ()S. Hoffman M. Zobler N. LeR. Shane, OCA B. Keeling, OCA T. Combs, OCA D. McIntyre, OPA E. Cobey, Region 1 G. Hunegs, Region 1 D. Dempsey, Region 1 N. Sheehan, OPA Region 1 Samuel Lee, EDO Contact, Region I C. Colleli R. K. Wild J. Storch AGENDA FOR PUBLIC MEETINGS TO DISCUSS THELICENSE RENEWAL PROCESS AND PROCESS FOR JAMES A. FITZPATRICK NUCLEAR POWER PLANT LICENSE RENEWAL APPLICATIONTwo Identical Meetings (1:30 p.m. to 4:30 p.m. and 7:00 p.m. to 10:00 p.m.*)I.Welcome and Purpose of Meeting 10 minutes (S. Hoffman)

II.Overview of License Renewal Process 15 minutes (N. Le)

III.Overview of the Environmental Review Process 15 minutes (S. Hernandez/J. Muir)IV.Public CommentsAs Required (S. Hoffman)

V. Closing/Availability of Transcripts 5 minutes (S. Hoffman)*The NRC staff will host informal discussions one hour prior to each meeting session. Noformal comments on the proposed scope of the Environmental Impact Statement (EIS) will beaccepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meetings (see agenda, above) or in writing, as described in the attached Federal Register notice. NUCLEAR REGULATORY COMMISSION[Docket No. 50-333]

Notice of Acceptance for Docketing of the Application, Notice of Opportunity for Hearingand Notice of Intent To Prepare an Environmental Impact Statement and Conduct Scoping Process for Facility Operating License No. DPR-59 for an Additional 20-YearPeriod, Entergy Nuclear Operations, Inc., James A. Fitzpatrick Nuclear Power Plant The U.S. Nuclear Regulatory Commission (NRC or the Commission) is considering anapplication for the renewal of Operating License No. DPR- 59, which authorizes Entergy Nuclear Operations, Inc. (Entergy), to operate the James A. FitzPatrick Nuclear Power Plant (JAFNPP) at 2536 megawatts thermal. The renewed license would authorize the applicant to operate the JAFNPP for an additional 20 years beyond the period specified in the current license. JAFNPP is located on Lake Ontario in Oswego County, approximately seven miles northeast of the City of Oswego, New York. The current operating license for the JAFNPP expires on October 17, 2014.

On August 1, 2006, the Commission's staff received the application from Entergy, to renew the Operating License No. DPR-59 for JAFNPP, pursuant to 10 CFR part 54. A Notice of Receipt and Availability of the license renewal application (LRA) was published in the FederalRegister on August 11, 2006 (71 FR 46245).

The Commission's staff has reviewed the LRA for its acceptability and has determined thatEntergy has submitted sufficient information in accordance with 10 CFR 54.19, 54.21, 54.22,54.23, and 51.53(c), and the application is acceptable for docketing. The current Docket No.50-333 for Operating License No. DPR-59 will be retained. The docketing of the renewalapplication does not preclude requesting additional information as the review proceeds, nor does it predict whether the Commission will grant or deny the application. Before issuance of each requested renewed license, the NRC will have made the findingsrequired by the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations. In accordance with 10 CFR 54.29, the NRC may issue a renewed license onthe basis of its review if it finds that actions have been identified and have been or will be takenwith respect to: (1) Managing the effects of aging during the period of extended operation on the functionality of structures and components that have been identified as requiring aging management review, and (2) time-limited aging analyses that have been identified as requiring review, such that there is reasonable assurance that the activities authorized by the renewedlicense will continue to be conducted in accordance with the current licensing basis (CLB), andthat any changes made to the plant's CLB comply with the Act and the Commission's regulations. The Commission also must first find that the requirements of subpart A of 10 CFR 51 have been satisfied, and that matters raised under 10 CFR 2.335 have been addressed.

Within 60 days after the date of publication of this Federal Register Notice, the applicant may file a request for a hearing, and any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene with respect to the renewal of the license. Requests for a hearing and a petition for leave to intervene shall be filed in accordance with the Commission's Rules of Practice for Domestic Licensing Proceedings in 10 CFR part 2. Interested persons should consult a current copy of 10 CFR 2.309, which is available at the Commission's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852 and is accessible from the Agencywide DocumentsAccess and Management System (ADAMS) Public Electronic Reading Room on the Internet at http://www.nrc.gov/reading-rm/ adams.html. Persons who do not have access to ADAMS orwho encounter problems in accessing the documents located in ADAMS should contact the 1 To the extent that the application contains attachments and supporting documents that are not publiclyavailable because they are asserted to contain safeguards or proprietary information, petitions desired access to thisinformation should contact the applicant or applicant's counsel to discuss the need for a protective order. NRC's PDR reference staff by telephone at 1-800-397-4209, or 301-415-4737, or by e-mailat pdr@nrc.gov. If a request for a hearing/petition for leave to intervene is filed within the 60-day period, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel will rule on therequest/petition; and the Secretary or the Chief Administrative Judge of the Atomic Safety andLicensing Board will issue a notice of a hearing or an appropriate order. In the event that norequest for a hearing/petition for leave to intervene is filed within the 60-day period, the NRC may, upon completion of its evaluations and upon making the findings required under 10 CFR parts 51 and 54, renew the license without further notice.

As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by theresults of the proceeding, taking into consideration the limited scope of matters that may be considered pursuant to 10 CFR parts 51 and 54. The petition must specifically, explain the reasons why intervention should be permitted with particular reference to the following factors:

(1) The nature of the requestor's/petitioner's right under the Act to be made a party to the proceeding; (2) the nature and extent of the requestor's/petitioner's property, financial, or otherinterest in the proceeding; and (3) the possible effect of any decision or order which may be entered in the proceeding on the requestor's/petitioner's interest. The petition must also set forth the specific contentions which the petitioner/ requestor seeks to have litigated at theproceeding.

Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the requestor/petitioner shall provide a brief explanation of the basesof each contention and a concise statement of the alleged facts or the expert opinion thatsupports the contention on which the requestor/ petitioner intends to rely in proving the contention at the hearing. The requestor/petitioner must also provide references to thosespecific sources and documents of which the requestor/ petitioner is aware and on which the requestor/petitioner intends to rely to establish those facts or expert opinion. The requestor/petitioner must provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact.

1 Contentions shall be limited to matterswithin the scope of the action under consideration. The contention must be one that, if proven,would entitle the requestor/petitioner to relief. A requestor/petitioner who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as aparty.

The Commission requests that each contention be given a separate numeric or alpha designation within one of the following groups: (1) Technical (primarily related to safety concerns); (2) environmental; or (3) miscellaneous.

As specified in 10 CFR 2.309, if two or more requestors/petitioners seek to co-sponsor a contention or propose substantially the same contention, the requestors/petitioners will berequired to jointly designate a representative who shall have the authority to act for the requestors/petitioners with respect to that contention. Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conductof the hearing. A request for a hearing or a petition for leave to intervene must be filed by:

2 If the request/petition is filed by e-mail or facsimile, an original and two copies of the document must bemailed within 2 (two) business days thereafter to the Secretary, U.S. Nuclear Regulatory Commission, Washington,DC 20555- 0001; Attention: Rulemaking and Adjustication Staff. (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. NuclearRegulatory Commission, Washington, DC, 20555- 0001, Attention: Rulemaking andAdjudications Staff; (2) courier, express mail, and expedited delivery services: Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryl and,20852, Attention: Rulemaking and Adjudications Staff; (3) e-mail addressed to the Office of theSecretary, U.S. Nuclear Regulatory Commission, HEARINGDOCKET@NRC.GOV; or (4)facsimile transmission addressed to the Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC, Attention: Rulemakings and Adjudications Staff at 301-415-1101, verification number is 301-415-1966.

2 A copy of the request for hearing andpetition for leave to intervene must also be sent to the Office of the General Counsel, U.S.

Nuclear Regulatory Commission, Washington, DC, 20555- 0001, and it is requested thatcopies be transmitted either by means of facsimile transmission to 301-415-3725 or by e-mail to OGCMailCenter@nrc.gov. A copy of the request for hearing and petition for leave to intervene should also be sent to the attorney for the applicant, Mr. Terrence A. Burke, Entergy Nuclear, 1340 Echelon Parkway, Mail Stop- ECH-62, Jackson, Mississippi 39213. Non-timely requests and/or petitions and contentions will not be entertained absent adetermination by the Commission, the presiding officer, or the Atomic Safety and LicensingBoard that the petition, request and/or contentions should be granted based on a balancing ofthe factors specified in 10 CFR 2.309(a)(1)(i)-(viii). In addition, the purpose of this notice is to inform the public that the NRC will be preparing anenvironmental impact statement (EIS) related to the review of the LRA and to provide the publican opportunity to participate in the environmental scoping process, as defined in 10 CFR 51.29.

In accordance with 10 CFR 51.95(c), the NRC will prepare an environmental impact statementthat will be used as a supplement to the Commission's NUREG-1437, Generic EnvironmentalImpact Statement for License Renewal of Nuclear Power Plants (GEIS), dated May 1996.

Pursuant to 10 CFR 51.26, and as part of the environmental scoping process, the NRC staffintends to hold a public scoping meeting. In addition, as outlined in 36 CFR 800.8,

Coordination with the National Environmental Policy Act, the NRC plans to coordinatecompliance with section 106 of the National Historic Preservation Act in meeting the requirements of the National Environmental Policy Act of 1969 (NEPA).

In accordance with 10 CFR 51.53(c) and 10 CFR 54.23, Entergy prepared and submitted the Environmental Report (ER) as part of the LRA. The LRA and the ER are publicly available at the NRC's PDR, located at One White Flint North, 11555 Rockville Pike, Rockville, Maryl and,20852, or from the NRC's ADAMS. The ADAMS Public Electronic Reading Room is accessibleat http:// adamswebsearch.nrc.gov/dologin.htm. The ADAMS Accession Numbers for the LRA and the ER are ML062160494 and ML062160557, respectively. Persons who do not have access to ADAMS, or who encounter problems in accessing the documents located in ADAMS, should contact the NRC's PDR reference staff by tel ephone at 1-800-397-4209, or301-415-4737, or by e-mail at pdr@nrc.gov. The LRA and the ER may also be viewed on the Internet at http:// www.nrc.gov/reactors/operating/ licensing/renewal/applications/fitzpatrick.html. In addition, the LRA and the ER are available for public inspection near the JAFNPP at the following public libraries: Penfield Library SUNY, 7060 State Route 104, Oswego, New York 13126; and Oswego Public Library, 140-142 East Second Street, Oswego, New York 13126. Possible alternatives to the proposed action (license renewal) include no action andreasonable alternative energy sources. The NRC is required by 10 CFR 51.95 to prepare asupplement to the GEIS in connection with the renewal of an operating license. This notice isbeing published in accordance with 10 CFR 51.26.

The NRC staff will first conduct a scoping process for the supplement to the GEIS and, assoon as practicable thereafter, will prepare a draft supplement to the GEIS for public comment.Participation in the scoping process by members of the public and local, State, Tribal, and Federal government agencies are encouraged. As described in 10 CFR 51.29, the scoping process for the supplement to the GEIS will be used to accomplish the following: d.Define the proposed action which is to be the subject of the supplement to the GEIS.

e.Determine the scope of the supplement to the GEIS and identify the significant issues to beanalyzed in depth. f.Identify and eliminate from detailed study those issues that are peripheral or that are notsignificant. g.Identify any environmental assessments and other ElSs that are being or will be preparedthat are related to, but are not part of, the scope of the supplement to the GEIS beingconsidered. h.Identify other environmental review and consultation requirements related to the proposedaction. i.Indicate the relationship between the timing of the preparation of the environmentalanalyses and the Commission's tentative planning and decision-making schedule. j.Identify any cooperating agencies and, as appropriate, allocate assignments for preparationand schedules for completing the supplement to the GEIS to the NRC and any cooperatingagencies. k.Describe how the supplement to the GEIS will be prepared, and include any contractorassistance to be used. The NRC invites the following entities to participate in scoping: l.The applicant, Entergy Nuclear Operations, Inc.

m.Any Federal agency that has jurisdiction by law or special expertise with respect to anyenvironmental impact involved, or that is authorized to develop and enforce relevant environmental standards. n.Affected State and local government agencies, including those authorized to develop andenforce relevant environmental standards. o.Any affected Indian tribe.

p.Any person who requests or has requested an opportunity to participate in the scopingprocess. q.Any person who has petitioned or intends to petition for leave to intervene. In accordance with 10 CFR 51.26, the scoping process for an EIS may include a publicscoping meeting to help identify significant issues related to a proposed activity and to determine the scope of issues to be addressed in an EIS. The NRC will hold public meetings forthe JAFNPP license renewal supplement to the GEIS, at the Town Municipal Building, 42 Creamery Road, Oswego, New York 13126, on Thursday, October 12, 2006. There will be twoidentical meetings to accommodate interested parties. The first meeting will conv ene at 1:30p.m. and will continue until 4:30 p.m., as necessary. The second meeting will convene at 7 p.m.

and will continue until 10 p.m., as necessary. Both meetings will be transcri bed and will incl ude:(1) An overview by the NRC staff of the NRC's license renewal review process; (2) an overviewby the NRC staff of the NEPA environmental review process, the proposed scope of thesupplement to the GEIS, and the proposed review schedule; and (3) the opportunity for interested government agencies, organizations, and individuals to submit comments orsuggestions on the environmental issues or the proposed scope of the supplement to the GEIS.Additionally, the NRC staff will host informal discussions one hour prior to the start of eachsession at the same location. No formal comments on the proposed scope of the supplement tothe GEIS will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meetings or in writing, as discussed below. For more information about the proposed action, the scoping process, and the environmentalimpact statement, please contact the NRC Environmental Project Manager, Mr. SamuelHernandez, at Mail Stop O-11F1, U.S. Nuclear Regulatory Commission, Washington, DC20555, by telephone at 1-800-368- 5642, extension 4049, or by e-mail at shq@nrc.gov.Persons may register to attend or present oral comments at the meetings on the scope of theNEPA review by contacting Mr. Hernandez. Members of the public may also register to speak at the meeting within 15 minutes of the start of each meeting. Individual oral comments may belimited by the time available, depending on the number of persons who register. Members of the public who have not registered may also have an opportunity to speak, if time permits.

Public comments will be considered in the scoping process for the supplement to the GEIS. Mr.Hernandez will need to be contacted no later than September 29, 2006, if special equipment oraccommodations are needed to attend or present information at the public meeting, so that theNRC staff can determine whether the request can be accommodated. Members of the public may send written comments on the environmental scope of the JAFNPP license renewal review to: Chief, Rules and Directives Branch, Division of Administrative Services, Office of Administration, Mail Stop T-6D59, U.S. Nuclear Regulatory Commission, Washington, DC, 20555- 0001, and should cite the publication date and pagenumber of this Federal Register notice. Comments may also be delivered to the U.S. Nuclear Regulatory Commission, Mail Stop T-6D59, Two White Flint North, 11545 Rockville Pike,Rockville, Maryland, 20852, from 7:30 a.m. to 4:15 p.m. during Federal workdays. To beconsidered in the scoping process, written comments should be postmarked by November 14, 2006. Electronic comments may be sent by e-mail to the NRC at FitzPatrickEIS@nrc.gov, andshould be sent no later than November 14, 2006, to be considered in the scoping process.

Comments will be available electronically and accessible through ADAMS. Participation in the scoping process for the supplement to the GEIS does not entitleparticipants to become parties to the proceeding to which the supplement to the GEIS relates.

Matters related to participation in any hearing are outside the scope of matters to be discussed at this public meeting.

At the conclusion of the scoping process, the NRC will prepare a concise summary of thedetermination and conclusions reached, including the significant issues identified, and will senda copy of the summary to each participant in the scoping process. The summary will also beavailable for viewing in ADAMS. The staff will then prepare and issue for comment the draftsupplement to the GEIS, which will be the subject of separate notices and separate publicmeetings. Copies will be available for public viewing at the above-mentioned addresses, andone copy per request will be provided free of charge, to the extent of supply. After receipt andconsideration of the comments, the NRC will prepare a final supplement to the GEIS, which willalso be available for public viewing. Information about the proposed action, the supplement to the GEIS, and the scoping processmay be obtained from Mr. Hernandez at the aforementioned telephone number or e-mail address. Dated at Rockville, Maryland, this 14th day of September 2006. For the Nuclear Regulatory Commission. Eric J. Benner, Acting Director, Division of License Renewal, Office of Nuclear Reactor Regulation.

[FR Doc. 06-7974 Filed 9-19-06; 8:45 am]

FitzPatrick Nuclear Power Plant Environmental Service List cc:

Mr. Gary J. TaylorChief Executive Officer Entergy Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213Mr. John T. HerronSr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. Peter T. DietrichSite Vice President Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant

P.O. Box 110 Lycoming, NY 13093Mr. Kevin J. MulliganGeneral Manager, Plant Operations Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant

P.O. Box 110 Lycoming, NY 13093Mr. Oscar LimpiasVice President Engineering Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. Christopher SchwarzVice President, Operations Support Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. John F. McCannDirector, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Resident Inspector's OfficeJames A. FitzPatrick Nuclear Power Plant U. S. Nuclear Regulatory Commission

P.O. Box 136 Lycoming, NY 13093Ms. Charlene D. FaisonManager, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. Michael J. ColombDirector of Oversight Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. David WallaceDirector, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant

P.O. Box 110 Lycoming, NY 13093Mr. James CostedioManager, Regulatory Compliance Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant

P.O. Box 110 Lycoming, NY 13093Assistant General CounselEntergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. Charles Donaldson, EsquireAssistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 FitzPatrick Nuclear Power Plant Environmental Service List cc:

Regional Administrator, Region IU.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406Mr. Steven LymanOswego County Administrator 46 East Bridge Street Oswego, NY 13126Mr. Peter R. Smith, PresidentNew York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399Mr. Paul EddyNew York State Dept. of Public Service 3 Empire State Plaza Albany, NY 12223-1350Kenneth E. Burdick, SupervisorTown of Scriba Route 8, Box 382 Oswego, NY 13126Mr. James H. SniezekBWR SRC Consultant 5486 Nithsdale Drive Salisbury, MD 21801-2490Mr. Michael D. LysterBWR SRC Consultant 5931 Barclay Lane Naples, FL 34110-7306Mr. Garrett D. Edwards814 Waverly Road Kennett Square, PA 19348Mr. Rick PlasseProject Manager, License Renewal Entergy Nuclear Operations, Inc.

James A. Fitzpatrick Nuclear Power Plant

P.O. Box 110 Lycoming, NY 13093Mr. James RossNuclear Energy Institute 1776 I Street, N.W. Suite 400 Washington, DC 20006-3708 Mr. Randolph BatemanMayor of Oswego, NY (Acting) 13 West Oneida Street Oswego, NY 13126Leonard J. PonziOswego County Legislator 28 Mitchell Street Oswego, NY 13126Ms. Mary BennettPenfield Library SUNY-Oswego 7060 State Route 104 Oswego, NY 13126Ms. Carol FerlitoOswego Public Library 140-142 East Second Street Oswego, NY 13126The Honorable William Jacobs, ChiefCayuga Nation

P.O. Box 116 Akron, NY 14001The Honorable Ray Halbritter,Representative Oneida Indian Nation 5218 Patrick Road Verona, NY 13478The Honorable Irving Powless, Jr., ChiefOnondaga Indian Nation Box 319B Nedrow, NY 13120The Honorable Barry E. Snyder, PresidentSeneca Nation of Indians 12837 Route 438 Irving, NY 14081 FitzPatrick Nuclear Power Plant Environmental Service List cc:The Honorable James Ransom, ChiefSt. Regis Mohawk Tribe 412 State Route 37 Akwesasne, NY 13655The Honorable Roger Hill, ChiefTonawanda Band of Senecas 7027 Meadville RoadBasom, NY 14013The Honorable Leo Henry, ChiefTuscarora Nation 2006 Mt. Hope Road Lewiston, NY 14092