April 5, 2005 MN No.05-018 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF SIGNIFICANT MEETING Licensee: Entergy Nuclear Northeast Facility: James A. FitzPatrick Nuclear Power Plant Docket Nos. 50-333 Time and Date: 12:00 p.m. on April 28, 2005 Location: Joint News Center Oswego County Airport County Route 176 Fulton, NY 13069

Purpose:

The NRC requested an Annual Assessment Meeting with Entergy to discuss NRCs assessment of the safety performance of the James A.

FitzPatrick Nuclear Power Plant for calendar year 2004. NRCs assessment is documented in a letter dated March 2, 2005.

Attendees*:

NRC: B. McDermott, Chief, Projects Branch 2, DRP, Region I P. Milano, Senior Project Manager, NRR L. Cline, Senior Resident Inspector D. Dempsey, Resident Inspector D. Screnci, Senior Public Affairs Officer, Region I Entergy: T. Sullivan, Site Vice President K. Mulligan, General Manager, Plant Operations P. Berry, Acting Director, Nuclear Safety Assurance S. Bono, Director, Director, Site Engineering J. Fulton, Assistant General Counsel Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned. The NRC will also conduct a discussion on Nine Mile Point and James A.

FitzPatrick performance with the public at the Assembly Hall in the Town of Scriba at 42 Creamery Road, Oswego, NY between 7-8 p.m., on April 28, 2005 (See Notice 05-019).

2 NRCs Annual Assessment Letter - James A. FitzPatrick Nuclear Power Plant, can be found in the ADAMS (Accession Number ML050610511). This meeting notice with the attached agenda and the meeting slides can be located in ADAMS with an accession number of ML050880041 and ML050910183. ADAMs is accessible from the NRC Web Site at:

http://www.nrc.gov/reading-rm/adams.html.

Meeting

Contact:

Brian McDermott, Chief, Projects Branch 2 610-337-5233 E-mail: bjm@nrc.gov.

  • Handicapped persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by April 21, 2005, via telephone to the NRC meeting contact.

/RA/

Approved by: _____________________________

Brian J. McDermott, Chief Projects Branch 2 Division of Reactor Projects cc w/encl:

G. Taylor, CEO, Entergy Operations M. Kansler, President, Entergy K. Mulligan, General Manager, Plant Operations D. Pace, VP Engineering B. OGrady, VP Operations Support M. Colomb, Director of Oversight S. Bono, Director, Nuclear Safety Assurance A. Halliday, Manager, Regulatory Compliance J. Fulton, Assistant General Counsel Supervisor, Town of Scriba S. Lyman, Oswego County Administrator C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law P. Eddy, Electric Division, Department of Public Service, State of New York P. Smith, President, New York State Energy Research and Development Authority J. Spath, SLO Designee, New York State Energy Research and Development Authority S. Lousteau, Treasury Department T. Judson, Central New York Citizens Awareness Network D. Katz, Citizens Awareness Network

3 Distribution w/encl:

Regional Administrator Secretary, RI Deputy Regional Administrator Secretary, RI DRP Division Secretary, RI DRS Division Secretary, RI DNMS Division Secretary, RI DRM Division Secretary, RI Region I Receptionist

4 Distribution w/encl: (VIA E-MAIL)

Executive Director for Operations, OEDO (RIDSEDOMAILCENTER)

Deputy Executive Director for Reactor Programs, OEDO (RIDSEDOMAILCENTER)

Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD)

Deputy Director, Office of Nuclear Reactor Regulation, NRR/ADPR (RIDSNRROD)

Director, Division of Regulatory Improvement Programs, NRR (RIDSNRRDRIP)

Director, Division of Inspection Program Management, NRR (RIDSNRRDIPM)

Director, Division of Licensing Project Management, NRR (RIDSNRRDLPM)

Project Directorate I-1 (PD1/2), NRR (RIDSNRRDIPMLPDI)

Asst. General Counsel Materials Litigation and Enforcement, OGC (RIDSOGCMAILCENTER)

S. Lee, RI OEDO R. Laufer, NRR P. Milano, NRR D. Skay, (Backup) PM, NRR R. Clark, (Backup), PM, NRR S. Collins, RA J. Wiggins, DRA K. Farrar, Regional Counsel D. Screnci, PAO N. Sheehan, PAO R. Bores, SLO G. Matakas, ORA W. Lanning, DRS J. Lubinski, DRS B. McDermott, DRP J. Trapp, DRP D. Jackson, DRP L. Cline, DRP - NRC Senior Resident Inspector D. Dempsey, DRP, Resident Inspector K. Kolek, Resident OA PMNS SISP Review Complete: BJM (Reviewers Initials)

DOCUMENT NAME:E:\Filenet\ML050880041.WPD After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI:DRP RI:DRP NAME Msnell BMcDermott/B JM DATE 03/ /05 04/01/05 OFFICIAL RECORD COPY

5 Agenda NRCs Annual Assessment Meeting James A. FitzPatrick April 28, 2005 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (3 minutes)

Review of Reactor Oversight Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (5 minutes)

National Summary of Plant Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (7 minutes)

Discussion of FitzPatrick Plant Performance . . . . . . . . . . . . . . . . . . . . . . . . NRC (15 minutes)

Entergys Response and Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ENE (25 minutes)

Closing Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (5 minutes)

Short Break . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (5 minutes)

NRC to address public questions . . . . . . . . . . . . . . . NRC/Members of the Public (as needed)