4/23/2015 - Notice of Category 3 Public Meeting with FitzPatrick to Discuss Annual Assessment
ML15103A019
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 04/10/2015
From: Arthur Burritt
Reactor Projects Branch 2
To:
Burritt A
References
MN 15-016
Download: ML15103A019 (3)


Text

MN No.15-016 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF PUBLIC MEETING April 10, 2015 Licensee: Entergy Nuclear Northeast (Entergy)

Facility: James A. FitzPatrick Nuclear Power Plant Docket No: 50-333 Date/Time: Thursday April 23, 2015 4:30 p.m. - 6:00 p.m.

Location: Town of Scriba Municipal Building 42 Creamery Road Oswego, NY 13126

Purpose:

The U. S. Nuclear Regulatory Commission (NRC) will meet with the public to discuss the NRCs assessment of safety performance at James A. FitzPatrick Nuclear Power Plant for 2014, as described in the annual assessment letter dated March 4, 2015.

NRC Attendees: A. Burritt, Chief, Projects Branch 2, Division of Reactor Projects E. Knutson, Senior Resident Inspector B. Sienel, Resident Inspector Public Participation: This is a Category 3 Meeting. The NRC staff will hold an open house to discuss the performance of James A. FitzPatrick Nuclear Power Plant during calendar year 2014. NRC staff will be available, in an informational setting, to answer questions from members of the public and discuss issues or concerns related to James A. FitzPatrick Nuclear Power Plant.

Meeting

Contact:

Arthur L. Burritt, Chief, Projects Branch 2 610-337-5069 E-mail: Arthur.Burritt@nrc.gov The NRCs annual assessment letter regarding James A. FitzPatrick Nuclear Power Plants performance during 2014 can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession Number ML15057A358. ADAMS is accessible from the NRC website at: http://www.nrc.gov/reading-rm/adams.html.

Additional information relative to the NRCs annual assessment process and the safety performance of James A. FitzPatrick Nuclear Power Plant can be found on the NRCs website at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

2 The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC website, http://www.nrc.gov/reading-rm/doc-collections/commission/policy/67fr36920.html, and contains information regarding visitors and security.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate.

If you need a reasonable accommodation to participate in this meeting, or need the meeting notice or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis. Persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting.

Attendance by other NRC personnel at this meeting should be made known by April 13, 2015, via telephone to the NRC meeting contact.

Meetings are sometimes canceled or rescheduled as a result of unforeseen circumstances.

Please confirm the meeting schedule on the NRC website under public meetings.

Approved by: /RA/

Arthur L. Burritt, Chief Projects Branch 2 Division of Reactor Projects cc: Distribution via ListServ

ML15103A019 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME TSetzer/TCS ABurritt/ALB DATE 4/9/15 4/10/15