8/21/18: Notice of Public Meeting for Nine Mile Point Nuclear Power Plant and James A. Fitzpatrick Nuclear Generating Station
ML18186A251
Person / Time
Site: Nine Mile Point, FitzPatrick  Constellation icon.png
Issue date: 07/03/2018
From: Anthony Dimitriadis
NRC/RGN-I/DRP/PB5
To:
Exelon Nuclear Generation Corp
Shared Package
ML18186A233 List:
References
MN 18-015
Download: ML18186A251 (3)


Text

MN No.18-015 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF PUBLIC MEETING July 3, 2018 Licensee: Exelon Nuclear Generation Company, LLC. (Exelon)

Facilities: James A. FitzPatrick Nuclear Power Plant (FitzPatrick) and Nine Mile Point Nuclear Generating Station (Nine Mile Point)

Docket Nos.: 50-220, 50-333, and 50-410 Date/Time: Tuesday, August 21, 2018 4:00 p.m. to 7:00 p.m.

Location: Nine Mile Point Nuclear Station Training Building 348 Lake Road Oswego, NY 13126

Purpose:

The U.S. Nuclear Regulatory Commission (NRC) will meet with the public to discuss the NRCs assessment of safety performance at the James A. FitzPatrick Nuclear Power Plant and the Nine Mile Point Nuclear Generating Station for calendar year 2017, as described in the annual assessment letters dated February 28, 2018.

NRC Attendees: A. Dimitriadis, Chief, Projects Branch 5, Division of Reactor Projects E. Miller, Senior Resident Inspector, Nine Mile Point B. Sienel, Resident Inspector, Nine Mile Point J. Dolecki, Resident Inspector, Nine Mile Point K. Kolaczyk, Senior Resident Inspector, FitzPatrick G. Stock, Resident Inspector, FitzPatrick Public Participation: This is a Category 3 Meeting. The NRC staff will hold an open house to discuss the performance of FitzPatrick and Nine Mile Point during calendar year 2017. NRC staff will be available, in an informational setting, to answer questions from members of the public and discuss issues or concerns related to FitzPatrick and Nine Mile Point Meeting

Contact:

Anthony Dimitriadis, Chief, Projects Branch 5 610-337-6953 Email: Anthony.Dimitriadis@nrc.gov The NRCs annual assessment letter regarding FitzPatricks performance during 2017 can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession Number ML18058B215. The annual assessment letter regarding Nine Mile Points performance during 2017 can also be found in ADAMS with the Accession Number ML18053A715. ADAMS is accessible from the NRC website at:

http://www.nrc.gov/reading-rm/adams.html.

2 This meeting is being held in conjunction with Exelons Community Information Night. Parking will be available at the Nine Mile Point Nuclear Power Plant lot and participant will be shuttled to and from the Nine Mile Point Training Building. For information on parking and Exelons Community Night: https://www.eventbrite.com/e/exelon-generation-community-information-night-oswego-tickets-47176275510. There is no cost to attend this event.

Additional information relative to the NRCs annual assessment process and the safety performance of FitzPatrick and Nine Mile Point can be found on the NRCs website at:

https://www.nrc.gov/reactors/operating/oversight.html.

The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC website, http://www.nrc.gov/reading-rm/doc-collections/commission/policy/67fr36920.html, and contains information regarding visitors and security.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate.

If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or other information from the meeting in another format (e.g. braille, large print), please notify the NRCs meeting contact no later than two business days prior to the meeting.

Determinations on requests for reasonable accommodation will be made on a case-by-case basis. Persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting.

Attendance by other NRC personnel at this meeting should be made known by August 19, 2018, via telephone to the NRC meeting contact.

Meetings are sometimes canceled or rescheduled as a result of unforeseen circumstances.

Please confirm the meeting schedule on the NRC website under public meetings.

Approved by: /RA ARosebrook for/ __

Christopher Cahill, Acting Chief Projects Branch 1 Division of Reactor Projects

/RA/_________________

Anthony Dimitriadis, Chief Projects Branch 5 Division of Reactor Projects cc: Distribution via ListServ

ML18186A251 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME ARosebrook CCahill/AR ADimitriadis DATE 7/3/18 7/3/18 7/3/18