MONTHYEARML24302A2402024-10-28028 October 2024 CFR 21 Report 1-BY-BC-1-LV Battery Charger IR 05000338/20240032024-10-28028 October 2024 – Integrated Inspection Report 05000338-2024003 and 05000339-2024003 ML24302A2342024-10-23023 October 2024 Request for Project Number Related to Dominion Energy Services New Nuclear Program at North Anna Power Station ML24283A0392024-10-0909 October 2024 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.D ML24281A1372024-10-0707 October 2024 ISFSI - Submittal of Cask Registration for Spent Fuel Storage 05000338/LER-2024-001-01, Automatic Reactor Trip Due to Prni High Negative Rate2024-09-24024 September 2024 Automatic Reactor Trip Due to Prni High Negative Rate IR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter ML24243A0872024-09-20020 September 2024 Response to EPA Comments Regarding the Final Site Specific Supplement to the Generic Eist for License Renewal North Anna Power Station, Units 1 and 2 IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) 05000339/LER-2024-001-01, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant 05000338/LER-2024-001, Automatic Reactor Trip Due to Prni High Negative Rate2024-07-25025 July 2024 Automatic Reactor Trip Due to Prni High Negative Rate ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24165A1462024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 05000339/LER-2024-001, Loss of Generator Field for 2J EDG During 2-PT-82.282024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24110A1502024-04-18018 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24110A1392024-04-18018 April 2024 Annual Environmental Operating Report ML24110A1462024-04-18018 April 2024 Independent Spent Fuel Storage Installation (Sfsi) - Annual Radiological Environmental Operating Report ML24087A0572024-04-16016 April 2024 Correction to Issuance of Amendment Nos. 296 and 279 ML24088A2692024-03-27027 March 2024 Core Operating Limits Report Cycle 31 Pattern Sos Revision 0 2024-09-24
[Table view] Category:Inspection Plan
MONTHYEARIR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) IR 05000338/20230062024-02-28028 February 2024 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2023006 and 05000339/2023006 IR 05000338/20230052023-08-25025 August 2023 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338 2023005 and 05000339 2023005) IR 05000338/20220062023-03-0101 March 2023 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2022006 and 05000339/2022006 ML23046A1952023-02-15015 February 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000338/20220052022-08-30030 August 2022 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 Reports 05000338/2022005 and 05000339/2022005 IR 05000338/20210062022-03-0202 March 2022 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 (Reports No. 05000338/2021006 and 05000339/2021006) IR 05000338/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2021005 and 05000339/2021005) ML21165A1222021-06-14014 June 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21154A0662021-06-0202 June 2021 Notification of North Anna Power Station, Units 1 & 2 - Design Bases Assurance Inspection (Team) U.S. Nuuclear Regulatory Commission Inspection Report 05000338/2021010 and 05000339/2021010 ML21145A0052021-05-25025 May 2021 2021003 North Anna Nuclear Power Station Document Request Letter ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 IR 05000338/20200062021-03-0303 March 2021 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 NRC Inspection Reports 05000338/2020006 and 05000339/2020006 ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information IR 05000338/20200052020-08-24024 August 2020 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2020005 and 05000339/2020005) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20182A0332020-06-30030 June 2020 Notification of Inspection and Request for Information ML20175A5532020-06-23023 June 2020 Emergency Preparedness Exercise Inspection Request for Information IR 05000338/20190062020-03-0303 March 2020 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2019006 and 05000339/2019006 ML19326C9882019-11-21021 November 2019 Requalification Program Inspection North Anna Power Station IR 05000338/20190052019-08-27027 August 2019 Updated Inspection Plan for North Anna Power Station, Units 1 and 2, NRC Report 05000338/2019005 and 05000339/2019005 ML19235A1992019-08-23023 August 2019 Baseline Inservice Inspection RFI IR 05000338/20180062019-03-0404 March 2019 Annual Assessment Letter for North Anna, Units 1 and 2; NRC Inspection Report 05000338/2018006 and 05000339/2018006 ML19030A6962019-01-29029 January 2019 ISI RFI IR 05000338/20180052018-08-23023 August 2018 Updated Inspection Plan for North Anna Power Station Units 1 and 2, NRC Report 05000338/2018005 and 05000339/2018005 ML18059A0942018-02-28028 February 2018 EOC Assessment Letter IR 05000338/20170052017-08-21021 August 2017 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - Report 05000338/2017005 and 05000339/2017005 ML17156A0662017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000338/20160062017-03-0101 March 2017 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2016006 and 05000339/2016006 IR 05000338/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Report 05000338, 339/2016005 ML16222A9132016-08-0808 August 2016 Notification of Inspection and Request for Information IR 05000338/20150062016-03-0202 March 2016 Annual Assessment Letter for North Anna Power Station Units 1 and 2 - NRC Inspection Report 05000338/2015006 and 05000339/2015006 ML16013A0622016-01-12012 January 2016 North Anna Power Station, Unit 2 - Notification of Inspection and Request for Information IR 05000338/20150052015-09-0101 September 2015 Mid-Cycle Letter for North Anna Power Station, Units 1 and 2 - NRC Assessment Report 05000338/2015005 and 05000339/2015005 IR 05000338/20140012015-03-0404 March 2015 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2014001 and 05000339/2014001 ML14245A1902014-09-0202 September 2014 Mid-Cycle Ltr 2014 IR 05000338/20130012014-03-0404 March 2014 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2013001 and 05000339/2013001 ML14022A0412014-01-21021 January 2014 TI-182 Phase 2 RFI Final ML13246A1322013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000338/20120012013-03-0404 March 2013 Annual Assessment Letter North Anna, Units 1 and 2, 05000338/2012001 and 05000339/2012001 ML13037A1712013-02-0101 February 2013 Notification of Inspection and Request for Information ML13032A5532013-02-0101 February 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML12248A1102012-09-0404 September 2012 Mid Cycle Assessment Letter North Anna 2012 ML12235A2912012-08-17017 August 2012 IR 05000338-12-012, 05000339-12-012, on 10/28/2011, North Anna Power Station, Units 1 & 2 - Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML1206506412012-03-0505 March 2012 End of Cycle Assessment Report 22 ML1124400992011-09-0101 September 2011 Report 22, Inspection/Activity Plan ML1106303432011-03-0404 March 2011 Inspection/Activity Plan 03/01/2011 - 06/30/2012, EOC Report 22 ML1024402812010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan 2024-08-27
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 4, 2012 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Dominion Nuclear Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
MID-CYCLE LETTER FOR NORTH ANNA POWER STATION UNITS 1 AND 2 -
NRC ASSESSMENT REPORT 05000338, 339/2012006
Dear Mr. Heacock:
On August 16, 2012, the NRC completed its mid-cycle performance review of North Anna Power Station Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011, through June 30, 2012. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This assessment reflects the integration of the Security Cornerstone into the ROP performance assessment program
governed by IMC 0305, "Operating Reactor Assessment Program." The security inspection plan will be sent via separate correspondence.
The NRC determined the performance at North Anna Power Station Units 1 and 2 during the
most recent quarter was within the Regulatory Response Column of the NRC's Reactor
Oversight Process (ROP) Action Matrix because a White finding for both units in Mitigating Systems cornerstone was issued on May 8, 2012, for failure to establish and maintain emergency diesel generator (EDG) maintenance procedures associated with the 2H EDG jacket water cooling inlet jumper gasket. The NRC determined that both units had been in the Regulatory Response Column since the fourth quarter of 2011.
On July 26, 2012, your staff notified the NRC of your readiness for it to conduct a supplemental inspection to review the actions taken to address the performance issue. Therefore, in addition to ROP baseline inspections, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001, "Inspection for One or Two White Inputs in a Strategic Performance Area," beginning September 10, 2012. This inspection procedure is conducted to provide assurance that the root causes and contributing causes of risk significant performance issues are understood, the extent of condition is identified, and the corrective actions are sufficient to prevent recurrence.
D. Heacock 2
The enclosed inspection plan lists the inspections scheduled through December 31, 2013. In addition to the baseline inspections, we will conduct the Operating License Initial Exam, Temporary Instruction (TI) 2515/177, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, TI 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks, and consistent with the Agency's actions related to Fukushima, TI-2515/187, "Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns" and TI-2515/188 "Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns." Routine inspections performed by the resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability is sues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Gerald McCoy at 404-997-4551 with any questions you may have regarding this letter. Sincerely,
/RA/ Richard P. Croteau, Director Division of Reactor Projects
Docket Nos.: 50-338, 50-339 License Nos.: NPF-4, NPF-7
Enclosure:
North Anna Inspection/ Activity Plan (09/01/2012 - 12/31/2013)
cc w/Encl: (See page 3)
_________________________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE SON /RA/ GJM /RA/ NAME SNinh GMcCoy DATE 08/23/2012 08/28/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO D. Heacock 3 cc w/encl: Mr. Gerald T. Bischof Site Vice President
North Anna Power Station Virginia Electric & Power Company Electronic Mail Distribution
Fred Mladen Director, Station Safety & Licensing Virginia Electric and Power Company Electronic Mail Distribution
Michael Crist Plant Manager
North Anna Power Station Virginia Electric & Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq.
Senior Counsel Dominion Resources Services, Inc.
Electronic Mail Distribution
Tom Huber Director, Nuclear Licensing & Operations
Support Innsbrook Technical Center Electronic Mail Distribution Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197
Richmond, VA 23209
Attorney General Supreme Court Building
900 East Main Street
Richmond, VA 23219
Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission P.O. Box 490
Mineral, VA 23117
Executive Vice President Old Dominion Electric Cooperative Electronic Mail Distribution
Donald R. Taylor Licensing Supervisor North Anna Power Station P. O. Box 402
Mineral, VA 23117-0402
Michael M. Cline Director Virginia Department of Emergency Services Management Electronic Mail Distribution
County Administrator Louisa County P.O. Box 160
Louisa, VA 23093
Doug Smith President (Public Correspondence Only)
Lake Anna Civil Association Electronic Mail Distribution
D. Heacock 4 Letter to David A. Heacock from Richard P. Croteau dated September 4, 2012
SUBJECT:
MID-CYCLE LETTER FOR NORTH ANNA POWER STATION UNITS 1 AND 2 -
NRC ASSESSMENT REPORT 05000338, 339/2012006
Distribution w/encl
- C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS
PUBLIC RidsNrrPMNorthAnna Resource INPO ROP Reports
North Anna Inspection / Activity Plan 09/01/2012
-12/31/2013 Unit Number Page 1 of 2 09/04/2012 08:19:31 Report 22 No. of Staff on Site Planned Dates Start End Inspection Activity Title 2 DRP/RPB5-95001 SUPPLEMENTAL INSPECTION 1, 2 09/09/2012 09/14/2012 IP 95001 Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area 3 OL EXAM-INITIAL EXAM - WEEK 1 1 09/10/2012 09/14/2012 V23372 NORTH ANNA / SEPTEMBER 2012 EXAM AT POWER FACILITIES 4 TI-177-TI-177 1, 2 10/22/2012 10/26/2012 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 4 NA TFPI-TRIENNIAL FIRE PROTECTION INSPECTION 1, 2 11/06/2012 11/08/2012 IP 7111105T Fire Protection [Triennial]
1, 2 11/26/2012 11/30/2012 IP 7111105T Fire Protection [Triennial]
1, 2 12/10/2012 12/14/2012 IP 7111105T Fire Protection [Triennial]
1 TI-182-TI-182 BURIED PIPING/TANK - PHASE 1 1, 2 01/07/2013 01/11/2013 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 5 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 1, 2 03/11/2013 03/15/2013 IP 71152B Problem Identification and Resolution 1, 2 03/25/2013 03/29/2013 IP 71152B Problem Identification and Resolution 1 ISI-UNIT 2 INSERVICE INSPECTION 2 04/15/2013 04/19/2013 IP 7111108P Inservice Inspection Activities - PWR 4 PSB1-RP-RP PUBLIC RAD SAFETY BASELINE 1, 2 05/13/2013 05/17/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 05/13/2013 05/17/2013 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 05/13/2013 05/17/2013 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 05/13/2013 05/17/2013 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2 05/13/2013 05/17/2013 IP 71151 Performance Indicator Verification 1 EP-MERGENCY PREPAREDNESS INSPECTION 1, 2 06/24/2013 06/28/2013 IP 7111402 A lert and Notification System Testing 1, 2 06/24/2013 06/28/2013 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 06/24/2013 06/28/2013 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 06/24/2013 06/28/2013 IP 71151 Performance Indicator Verification 1 ISI-UNIT 1 INSERVICE INSPECTION 1 09/16/2013 09/20/2013 IP 7111108P Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
North Anna Inspection / Activity Plan 09/01/2012
-12/31/2013 Unit Number Page 2 of 2 09/04/2012 08:19:31 Report 22 No. of Staff on Site Planned Dates Start End Inspection Activity Title 1 SGISI-UNIT 1 SG INSERVICE INSPECTION 1 09/23/2013 09/27/2013 IP 7111108P Inservice Inspection Activities - PWR Comments: This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.