11/20/18 Summary of Public Teleconference Call with Entergy Nuclear Operations. Inc., Regarding Emergent Alternative Request for Repair of Central Rod Drive Nozzles at Palisades Nuclear Plant
ML18351A238
Person / Time
Site: Palisades Entergy icon.png
Issue date: 12/18/2018
From: Kimberly Green
Plant Licensing Branch III
To:
Entergy Nuclear Operations
Green K,
References
EPID L-2018-LRM-0087
Download: ML18351A238 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, 0.C. 20555-0001 Dacember 18, 2018 LICENSEE:

Entergy Nuclear Operations, Inc. FACILITY:

Palisades Nuclear Plant

SUBJECT:

SUMMARY

OF NOVEMBER 20, 2018, PUBLIC TELECONFERENCE CALL WITH ENTERGY NUCLEAR OPERATIONS, INC., REGARDING EMERGENT ALTERNATIVE REQUEST FOR REPAIR OF CONTROL ROD DRIVE NOZZLES AT PALISADES NUCLEAR PLANT (EPID L-2018-LRM-0087)

On November 20, 2018, a Category 1 public teleconference call was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Entergy Nuclear Operations, Inc. (Entergy, the licensee).

The purpose of the call was to discuss a proposed emergent request for an alternative involving repair to certain control rod drive mechanism (CROM) nozzle-to-reactor-head penetrations at the Palisades Nuclear Plant (PNP). The meeting notice can be found in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML18320A094.

The meeting notice is also posted on the NRC public Web site. Entergy stated that it plans to submit an emergent request for an alternative to requirements in American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code, Section Ill, "Rules for Construction of Nuclear Facility Components";

Section XI, "Rules for lnservice Inspection of Nuclear Power Plant Components";

and Code Case N-638-6, "Similar and Dissimilar Metal Welding Using Ambient Temperature Machine GTAW [Gas Tungsten Arc Weld] Temper Bead Technique,Section XI, Division 1." The request is needed for repairs to CROM nozzle numbers 25, 33, and possibly 36. Entergy and representatives from Framatome briefly described the unique features of the PNP reactor vessel head. The Framatome representative continued with a description of the proposed repair method for the nozzles. The planned repair method is commonly referred to as the "half nozzle repair" technique.

Entergy enumerated the reasons for the request. The NRC staff asked a few clarifying questions regarding the evaluations performed to support the request. More specifically, the staff asked if corrosion of the reactor vessel head had been considered.

Entergy stated that the corrosion had been considered, and that the corrosion and fatigue analyses showed that the remaining flaw after repair will be acceptable for essentially 27 years. Entergy stated that it plans to submit the request by November 26, 2018, and will ask for verbal authorization by December 3, 2018. The public was invited to listen to the call and was given an opportunity to communicate with the NRC after the business portion, but before the call was ended. Members of the public were present on the call; however, no comments were made to the NRC staff. No regulatory decisions or commitments were made during the meeting. No public meeting feedback forms were received.

A list of meeting attendees is enclosed.

Please direct any inquiries to me at 301-415-1627, or Kimberly.Green@nrc.gov.

Docket No. 50-255

Enclosure:

List of Attendees cc: Listserv K2~ctManager Plant Licensing Branch Ill Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LIST OF ATTENDEES SEPTEMBER 20, 2018, PUBLIC TELECONFERENCE CALL WITH ENTERGY NUCLEAR OPERATIONS, INC. PALISADES NUCLEAR PLANT NAME ORGANIZATION Kim Green NRC/NRR/DORL John Tsao NRC/NRR/DMLR Steve Cumblidge NRC/NRR/DMLR Bob Davis NRC/NRR/DMLR Mel Holmberg NRC/Region Ill Paul LaFlamme NRC/Region Ill Julie Boettcher NRC/Region Ill Billy Dickson NRC/Region Ill Bruce Bartlett NRC/Region Ill Jack Rutkowski NRC/Region Ill Ty Ospino NRC/Region Ill Matt Domke NRC/Region Ill Edison Fernandez NRC/Region Ill David Hill NRC/Region Ill Jim Neurauter NRC/Region Ill Otto Gustafson Entergy/Palisades Jeff Erickson Entergy/Palisades Barb Dotson Entergy/Palisades William Sims Entergy/Palisades Edward Blackard Entergy/Palisades Joe Weicks Entergy/Palisades Kevin O'Connor Entergy/Palisades Brian Sova Entergy/Palisades Adam Bono Entergy/Palisades Greg Hubers Entergy/Palisades Jeff Nordby Entergy/Palisades Joe Jerz Entergy/Palisades Phil Couture Entergy/Palisades Dave Waskey Framatome Charles Graves Framatome Steve Hunter Framatome Jeff Brown Framatome Enclosure NAME ORGANIZATION Todd Richards Framatome Brian Haibach Framatome TimWiger Framatome Ryan Hosler Framatome Travis Olson Framatome Jim Ostroff S&P Global Platts Jeff Quinn Engineering Planning and Management, Inc.

SUBJECT:

SUMMARY

OF NOVEMBER 20, 2018, PUBLIC TELECONFERENCE CALL WITH ENTERGY NUCLEAR OPERATIONS, INC., REGARDING EMERGENT ALTERNATIVE REQUEST FOR REPAIR OF CONTROL ROD DRIVE NOZZLES AT PALISADES NUCLEAR PLANT (EPID L-2018-LRM-0087)

DATED DECEMBER 18, 2018 DISTRIBUTION:

PUBLIC RidsACRS_MailCTR Resource RidsNrrDorl Resource RidsNrrDorlLpl3 Resource RidsNrrDmlrMphb Resource RidsNrrLASRohrer Resource RidsNrrLAJBurkhardt Resource RidsNrrPMPalisades Resource RidsRgn3MailCenter Resource JJohnston, NRR LBurkhart, OEDO CCook, OEDO RIii JTsao, NRR SCumblidge, NRR RDavis, NRR ADAMS Accession Nos.: Meeting Notice ML18255A013 Summary ML18351A238 OFFICE NRR/D0RL/LPL3/PM NRR/D0RL/LPL3/LA NRR/D0RL/LPL3 NAME KGreen SRohrer (JBurkhardt DWrona for) DATE 12/18/18 12/18/18 12/18/18 OFFICIAL RECORD COPY NRR/D0RL/LPL3/PM KGreen 12/18/18