Similar Documents at Hatch |
---|
Category:Inspection Plan
MONTHYEARIR 05000032/20240112024-04-25025 April 2024 Notification of Edwin I. Hatch Nuclear Plant - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 0500032/2024011 and 05000366/2024011 IR 05000321/20230062024-02-28028 February 2024 Annual Assessment Letter Edwin I. Hatch Nuclear Plant Units 1 and 2 - Nrc Inspection Report 05000321/2023006 and 05000366/2023006 IR 05000321/20230052023-08-27027 August 2023 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 & 2 - Report 05000321/2023005 and 05000366/2023005 ML23201A0292023-07-20020 July 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000321/20220062023-03-0101 March 2023 Annual Assessment Letter Edwin I. Hatch Nuclear Plant, Units 1 and 2 - NRC Inspection Report 05000321/2022006 and 05000366/2022006 IR 05000321/20220052022-08-23023 August 2022 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units and 2 Report 05000321/2022005 and 05000366/2022005 ML22073A0842022-03-21021 March 2022 An NRC Fire Protection Team Inspection (NRC Inspection Report Nos. 05000321/2022011 and 05000366/2022011) and Request for Information IR 05000321/20210062022-03-0202 March 2022 Annual Assessment Letter for Erwin I. Hatch Nuclear Plant, Units 1 and 2 (Report No. 05000321/2021006 and 05000366/2021006) ML22025A2142022-01-21021 January 2022 Plant Hatch 2022001 RP Baseline Inspection Information Request ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections IR 05000321/20210052021-08-23023 August 2021 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Report 05000321/2021005 and 05000366/2021005) ML21207A1072021-07-26026 July 2021 Biennial Problem Identification and Resolution Inspection Report 05000321/2021010 and 05000366/2021010 IR 05000321/20200062021-03-0303 March 2021 Annual Assessment Letter for Edwin I. Hatch Nuclear Plant - Report 05000321/2020006 and 05000366/2020006 ML21013A4112021-01-13013 January 2021 Notification of Edwin I. Hatch Nuclear Plant Design Bases Assurance Inspection U.S. Nuclear Regulatory Commission Inspection Report 05000321/2021010 and 05000366/2021010 ML20338A3472020-12-0202 December 2020 Notification of Inspection and Request for Information ML20239A7462020-08-25025 August 2020 Rif Letter to Plant Hatch Simulator Inspection 41502 ML20027B4162020-01-27027 January 2020 Notification of Inspection and Request for Information IR 05000321/20190052019-08-27027 August 2019 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant Reports 05000321/2019005 and 05000366/2019005 IR 05000321/20180062019-03-0404 March 2019 Annual Assessment Letter for Edwin I. Hatch - Report 05000321/2018006 and 05000366/2018006 ML19044A6002019-02-13013 February 2019 Notification of Conduct of a Triennial Fire Protection Baseline Inspection (NRC Inspection Report Nos. 0500021/2019011 and 05000366/2019011) IR 05000021/20190112019-02-13013 February 2019 Notification of Conduct of a Triennial Fire Protection Baseline Inspection (NRC Inspection Report Nos. 0500021/2019011 and 05000366/2019011) ML19016A3422019-01-10010 January 2019 U2 ISI 2019001 RFI - Bcc ML19008A2872018-12-20020 December 2018 RP Document Request ML18298A0982018-10-24024 October 2018 Emergency Preparedness Program Inspection Request for Information IR 05000321/20180052018-08-23023 August 2018 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant Units 1 and 2 - NRC Inspection Reports 05000321/2018005 and 05000366/2018005 ML18087A3592018-03-27027 March 2018 Eff & REMP Emailed Information and Doc Request ML18059A1402018-02-28028 February 2018 EOC Assessment Letter IR 05000321/20170052017-08-28028 August 2017 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 - NRC Report 05000321/2017005 and 05000366/2017005 ML17142A2202017-05-19019 May 2017 Emergency Preparedness Inspection and Request for Information Dated: May 19, 2017 IR 05000321/20160062017-03-0101 March 2017 Annual Assessment Letter for Edwin I. Hatch Nuclear Plant Units 1 and 2 (Report 05000321/2016006 and 05000366/2016006) ML17021A0002017-01-20020 January 2017 Notification of Inspection and Request for Information IR 05000321/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Edwin I. Hatch Nuclear Plant Units 1 and 2 - NRC Inspection Report 05000321/2016005 and 05000366/2016005 ML16062A1842016-03-0202 March 2016 Annual Assessment Letter ML16014A7052016-01-14014 January 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection (NRC Inspection Report Nos.0500321/2016007 and 05000366/2016007) ML16011A3542016-01-11011 January 2016 Notification of Inspection and Request for Information IR 05000321/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Edwin I. Hatch Nuclear Plant Unit 1 and Unit 2 (NRC Inspection Report 05000321/2015005 and 05000366/2015005) IR 05000321/20140012015-03-0404 March 2015 Annual Assessment Letter for Edwin I. Hatch Nuclear Plant Unit 1 and Unit 2 (NRC Inspection Report 05000321/2014001 and 05000366/2014001) ML14245A1692014-09-0202 September 2014 Mid-Cycle Letter IR 05000321/20130012014-03-0404 March 2014 Annual Assessment Letter for Edwin I. Hatch Nuclear Plant Unit 1 and Unit 2 (NRC Inspection Report 05000321/2013001 and 05000366/2013001) ML14009A2382014-01-0909 January 2014 Notification of Inspection and Request for Information ML13246A1152013-09-0303 September 2013 Mid Cycle Assessment Letter ML13175A3312013-06-24024 June 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000321/20120012013-03-0404 March 2013 Annual Assessment Letter for Edwin I. Hatch Nuclear Plant Unit 1 and Unit 2 (NRC Inspection Report 05000321/2012001 and 366/2012001) IR 05000321/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan Edwin I. Hatch Nuclear Plant (IR 05000321-12-006, 05000366-12-006) ML12065A2302012-03-0505 March 2012 Report 22 ML1124403852011-09-0101 September 2011 Report 22 - Hatch ML1106302392011-03-0404 March 2011 Inspection/Activity Plan, 01/01/2011 - 06/30/2012, Report 22 ML1024406352010-09-0101 September 2010 09/01/2010 - 12/31/2011, Report 22 ML1024406322010-09-0101 September 2010 Mid Cycle Letter ML1006209002010-03-0303 March 2010 Enclosure - Hatch Inspection/Activity Plan Report 22, 2009 2024-04-25
[Table view] Category:Letter
MONTHYEARIR 05000321/20240102024-11-0606 November 2024 NRC Inspection Report 05000321/2024010 and 05000366/2024010 ML24299A2222024-10-31031 October 2024 Audit Summary for License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components IR 05000321/20240032024-10-30030 October 2024 Edwin I Hatch, Units 1 and 2 - Integrated Inspection Report 05000321/2024003 and 05000366/2024003 NL-24-0357, Notification of Deviation from the Inspection Frequency Requirements of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) BWR Jet Pump Assembly Inspection and Flaw Evaluation Guidelines2024-10-30030 October 2024 Notification of Deviation from the Inspection Frequency Requirements of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) BWR Jet Pump Assembly Inspection and Flaw Evaluation Guidelines ML24292A1602024-10-22022 October 2024 Request for Withholding Information from Public Disclosure License Amendment Request to Revise Technical Specification Surveillance Requirements to Increase Safety/Relief Valve Setpoints ML24290A0792024-10-18018 October 2024 SLR Environmental Preapplication Meeting Summary ML24303A4102024-10-17017 October 2024 Dir Results Letter to NRC - Hatch - Hurricane Helene IR 05000321/20244012024-10-10010 October 2024 Security Baseline Inspection Report 05000321-2024401 and 05000366-2024401 ML24256A0282024-09-12012 September 2024 2024 Hatch Requal Inspection Corporate Notification Letter NL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc IR 05000321/20240912024-08-27027 August 2024 NRC Investigation Report 2-2023-003 and NOV - NRC Inspection Report 05000321/2024091 and 05000366/2024091 IR 05000321/20240052024-08-26026 August 2024 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 - Report 05000321/2024005 and 05000366/2024005 NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information IR 05000321/20240022024-08-0808 August 2024 Edwin I Hatch Nuclear Plants, Units 1 and 2 – Integrated Inspection Report 05000321-2024002 and 05000366-2024002 NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24198A1252024-07-16016 July 2024 Edwin I Hatch Nuclear Plant Units 1 - 2 Notification of Conduct of Title 10 of the Code of Federal Regulations 50 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 05000321/LER-2024-002-01, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications 05000321/LER-2024-003, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 ML24163A0532024-06-14014 June 2024 Audit Plan - Alternative Seismic Method LAR NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations IR 05000321/20240902024-05-15015 May 2024 NRC Inspection Report 05000321-2024090 and 05000366-2024090, Investigation Report 2-2023-003; and Apparent Violation NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 05000321/LER-2024-002, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 IR 05000032/20240112024-04-25025 April 2024 Notification of Edwin I. Hatch Nuclear Plant - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 0500032/2024011 and 05000366/2024011 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 ML23032A3322024-04-24024 April 2024 Issuance of Amendments Nos. 322 and 267, Regarding LAR to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in TS Table 1.1-1, Modes 05000366/LER-2024-002, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications IR 05000321/20240012024-04-22022 April 2024 Integrated Inspection Report 05000321/2024001 and 05000366/2024001 NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint 05000321/LER-2024-001, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. ML23275A2402024-03-22022 March 2024 SNC Fleet - Issuance of Environmental Assessment and Finding of No Significant Impact Regarding Exemption from the Requirements of 10 CFR Part 73, Section 73.2, Definitions (EPID Nos. L-2023-LLE-0018 & L-2023-LLE-0021) - Letter NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission ML24069A0012024-03-0909 March 2024 – Correction of Amendment No. 266 Regarding License Amendment Request Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program (TSTF-425, Revision 3) ML24047A0362024-03-0404 March 2024 Response to Hatch and Vogtle FOF Dates Change Request (2025) NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 2024-09-09
[Table view] |
Inspection Report - Hatch - 2014001 |
---|
|
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303
-1257 March 4, 2015 Mr. David R. Vineyard Vice President Southern Nuclear Operating Company, In Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513 SUBJECT: ANNUAL ASSESSMENT LETTER FOR EDWIN I. HATCH NUCLEAR PLANT UNIT 1 AND UNIT 2 (NRC INSPECTION REPORT 05000321/201 4001 A ND 05000366/201 4 001) Dear Mr. Vineyard
- On February 1 2, 201 5 , the NRC completed its end
-of-cycle performance review of Edwin I. Hatch Nuclear Plant Unit s 1 and The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 201 4 through December 31, 201 This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facilit The NRC determined that overall, Hatch Unit s 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objective The NRC determined the performance at Hatch Unit 1 and Unit 2 during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low safety significance (i.e., Green), and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facilit The enclosed inspection plan lists the inspections scheduled through June 30, 201 Routine inspections performed by resident inspectors are not included in the inspection pla In addition to baseline inspections, the NRC will conduct reactor operator initial licensing examination The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid
-cycle performance revie The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issue The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any change This inspection plan does not include security related inspections which will be sent via separate, non
-publicly available correspondenc Additionally, an NRC audit of licensee efforts towards compliance with Order EA
-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond
-Design-Basis External Events," and Order EA
-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation" is ongoing for various site The audit includes an onsite visit for the NRC staff to evaluate mitigating strategies as described in the licensee D. Vineyard 2 submittals and to receive and review information relative to associated open item This onsite audit will occur prior to the first unit at the site achieving compliance with the Orders and the audit will aid NRC staff in developing a final Safety Evaluation for the sit The audit at your site will occur in the Fall of 2015
. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparation In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404
-997-4 482 with any questions you have regarding this lette
Sincerely,
/RA/ Joseph Austin , Acting Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.:
50-321, 50-366 License Nos.: NPF
-57, NPF-5 Enclosure: Hatch Inspection/Activity Plan (03/01/2015
- 06/30/2016)
cc Distribution via ListServ
_____________________
SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE /RA By CWR1/
/RA By JDA/
NAME C. Rapp J. Austin . DATE 3/4/2015 3/4/2015 E-MAIL COPY?
YES NO YES NO Page 1 of 2 03/04/2015 09:40:34 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site HatchInspection / Activity Plan 03/01/2015
-06/30/2016ASM EP-2015 EP ASM & RES BASELINE 3 1, 2 IP Drill Evaluation7111406 01/01/2015 12/31/2015OL EXAM-INITIAL LICENSE EXAM 3 1 HATCH/MARCH 2015 INITIAL EXAM AT POWER FACILITIES V23426 03/23/2015 04/03/2015 CDBI-COMPONENT DESIGN BASES INSPECTION 7 1, 2 IP Component Design Bases Inspection7111121 08/31/2015 09/04/2015 1, 2 IP Component Design Bases Inspection7111121 09/21/2015 09/25/2015 1, 2 IP Component Design Bases Inspection7111121 10/05/2015 10/09/2015 1, 2 IP Component Design Bases Inspection7111121 10/19/2015 10/23/2015 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 4 1, 2 IP Problem Identification and Resolution71152B11/16/201511/20/2015 1, 2 IP Problem Identification and Resolution71152B 12/07/201512/11/2015 EP-EP EXERCISE 8 1, 2 IP Exercise Evaluation7111401 12/07/201512/11/2015 1, 2 IP Emergency Action Level and Emergency Plan Changes7111404 12/07/201512/11/2015 1, 2 IP Performance Indicator Verification71151 12/07/201512/11/2015ASM EP-2016 EP ASM & RES BASELINE 3 1, 2 IP Drill Evaluation7111406 01/01/2016 12/31/2016 RP-RAD HAZARDS AND TRANSPORTATION 2 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 02/08/2016 02/12/2016 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 02/08/2016 02/12/2016 ISI-UNIT 1 IN-SERVICE INSPECTION 1 1 IP Inservice Inspection Activities - BWR7111108G 02/29/2016 03/04/2016 TFPI-TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 IP Fire Protection [Triennial]7111105T 04/04/2016 04/08/2016 1, 2 IP Fire Protection [Triennial]7111105T 04/18/2016 04/22/2016 HS-TRIENNIAL HEAT SINK PERFORMANCE 1 1, 2 IP Heat Sink Performance7111107T 05/16/2016 05/20/2016 RP-RP PUBLIC RAD SAFETY BASELINE 2 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 05/16/2016 05/20/2016 1, 2 IP Radiological Environmental Monitoring Program71124.07 05/16/2016 05/20/2016 1, 2 IP Performance Indicator Verification71151 05/16/2016 05/20/2016 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedure Page 2 of 2 03/04/2015 09:40:34 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site HatchInspection / Activity Plan 03/01/2015
-06/30/2016OL EXAM-INITIAL LICENSE EXAM PREP 3 1 HATCH JUNE 2016 INITIAL EXAM AT POWER FACILITIES V23473 05/23/2016 05/27/2016 MODS-PLANT MODIFICATIONS INSPECTION 3 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 06/06/2016 06/10/2016 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 06/20/2016 06/24/2016OL EXAM-INITIAL LICENSE EXAM 3 1 HATCH JUNE 2016 INITIAL EXAM AT POWER FACILITIES V23473 06/20/2016 07/01/2016 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.