Revision 309 to Final Safety Analysis Report, Chapter 1, Introduction and General Description of Plant, Section 1.4
ML16256A127
Person / Time
Site: Waterford Entergy icon.png
Issue date: 08/25/2016
From:
Entergy Operations
To:
Office of Nuclear Reactor Regulation
Shared Package
ML16256A115 List: ... further results
References
W3F1-2016-0053
Download: ML16256A127 (1)


Text

WSES-FSAR-UNIT-3 1.4-1 Revision 11-A (02/02)1.4IDENTIFICATION OF AGENTS AND CONTRACTORS Louisiana Power & Light Company, as owner, has arranged for the purchase of equipment and consulting, engineering, and construction services for the installation of Waterford Steam Electric Station Unit No. 3.

As owner, Louisiana Power & Light Company is responsible for the design, construction, and operation of

the unit.Ebasco Services Incorporated has been retained for engineering, procurement and management ofconstruction services. Ebasco is also providing assistance in obtaining licenses and permits, in

preoperational testing, in quality control, and in initial startup of the plant.(DRN 01-758)

Combustion Engineering, Inc. has been contracted to design, manufacture, and deliver to the site acomplete Nuclear Steam Supply System including first core fuel. In addition, Combustion Engineering, Inc.

is supplying competent technical and professional consultation for erection, initial fuel loading, testing and initial startup of the complete Nuclear Steam Supply System. Combustion Engineering, Inc. is participating

in plant personnel training.(DRN 01-758)

The Westinghouse Electric Corporation is supplying the turbine generator and its auxiliaries.