ML17130A249

From kanterella
Revision as of 15:43, 6 February 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Revision 26 to Updated Final Safety Analysis Report, Section 10.0, Auxiliary Systems
ML17130A249
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 04/06/2017
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML17130A259 List: ... further results
References
Download: ML17130A249 (117)


Text

CHAPTER 10 10.1-1 REV. 21, APRIL 2007 SECTION 10.0 AUXILIARY SYSTEMS

10.1

SUMMARY

DESCRIPTION

This section describes the reactor and plant auxiliary systems

that are required for operation, but which are not integral

portions of the reactor and power conversion equipment or their

safety systems.

CHAPTER 10 10.2-1 REV. 21, APRIL 2007 10.2 NEW FUEL STORAGE 10.2.1 Introduction

New fuel is stored in high density storage racks located in the

spent fuel pool.

10.2.2 Description

New fuel assemblies as received at the plant are stored in metal

boxes inside an outer metal container. Each outer container and

metal box holds two fuel bundles. After removing the box from the

outer container, the boxes are hoisted to the refueling floor and

the fuel bundles are receipt inspected and placed in the spent

fuel pool using the fuel-handling equipment. If a bundle fails

receipt inspection, it is tagged in accordance with procedure, placed back into the container, and left on the refueling floor. A

GE inspector checks the bundle. He either repairs the problem at

the site or returns the damaged bundle for a replacement. In the

event that the new fuel cannot be taken to the refueling floor

immediately, it can be off-loaded and stored in a roped-off area

with a security guard posted.

CHAPTER 10 10.3-1 REV. 26, APRIL 2017 10.3 SPENT FUEL STORAGE 10.3.1 Power Generation Objective

The power generation objective of the spent fuel storage

arrangement is to provide storage space for the spent fuel

assemblies which require shielding during storage and handling.

10.3.2 Power Generation Design Basis

1. Spent fuel storage racks for each reactor are designed to accommodate 3819 fuel assemblies.
2. Spent fuel storage racks are designed and arranged so that the fuel assemblies can be efficiently

handled during refueling operations.

3. Dry storage casks are designed so that spent fuel may be transferred from the wet storage racks into

the casks in an efficient manner

10.3.3 Safety Design Basis

1. All arrangements of fuel in the spent fuel storage racks are maintained in a subcritical configuration having a k eff 0.95 for all conditions.
2. Each spent fuel storage rack loaded with fuel and the pool structure are designed to withstand

seismic loading to minimize distortion of the spent

fuel storage arrangement or loss of spent fuel pool

level.

3. Fuel designated for dry cask storage will have a K eff < 0.95.
4. Dry storage casks are evaluated for design basis environmental events and are placed in

configurations which do not impact the structural

capabilities of the fuel pool, reactor building, or

cask transport path.

10.3.4 Description

The high density spent fuel storage racks provide storage at the bottom of the fuel pool for the spent fuel received

from the reactor vessel and new fuel for loading to the

reactor vessel. The fuel storage racks at the bottom of

the pool are covered with water (normally about 23 ft

CHAPTER 10 10.3-2 REV. 26, APRIL 2017 above the stored fuel) for radiation shielding. Sufficient shielding is provided by maintaining a minimum depth of

water at all times. The racks are freestanding, full-

length top entry and are designed to maintain the spent

fuel in a space geometry which precludes the possibility

of criticality (k eff will not exceed 0.95) under any conditions.

The high density spent fuel storage racks are of the "poison" type, utilizing a neutron absorbing material to

maintain a subcritical fuel array (see Figures 10.3.1, 10.3.2, and 10.3.3). The rack modules are rectilinear in

shape and are of nine different array sizes. The racks

are arranged in the spent fuel pool as shown in Figure

10.3.4 for Unit 2 and Figure 10.3.5 for Unit 3. A total

of 3819 storage locations are provided per pool. The

racks are capable of storing BWR fuel assemblies (with or

without their channels) with a maximum incore k-infinity of 1.270. Maintaining the incore k-infinity 1.270 will assure that the rack k-effective will be equal to or less than that determined in the safety design basis. TS

Amendment Nos. 175/178 demonstrated a k-infinity limit of

< 1.362 using an analysis of the criticality aspects of the storage of PBAPS fuel assemblies having a fuel

enrichment up to 4.5 weight percent of U-235. The

analysis methodology and results were described in the GE

report, GENE-512-92073, "Peach Bottom Atomic Power Station

Spent Fuel Storage K-infinity Conversion Analyses,"

November 1992. The method and the cross-section library

used consist of the GE MERIT computer code, using the

ENDF/B-IV cross section set, which is stated to have been

verified against extensive critical experiments. The

MERIT program is a three-dimensional Monte Carlo neutron

tracking code that calculates the system effective neutron

multiplication factor (K-effective) using a 190 group

cross-section library with the Haywood scattering kernel

of water. A spent fuel storage criticality validation is

performed for each reload to demonstrate that the reload

fuel assemblies meet incore K-infinity and rack K-

effective storage criticality requirements. Rack module

data is given in Table 10.3.2.

TS Amendment 287/290 approved use of neutron absorbing

inserts in the spent fuel pool (SFP) storage racks for the

purpose of criticality control in the SFPs. This amendment

modified TS 4.3, "Fuel storage" and added a new license

condition 2.C(14) to support the installation of NETCO-SNAP-IN neutron absorbing inserts into the individual cells of the existing PBAPS SFP storage racks. The

CHAPTER 10 10.3-3 REV. 26, APRIL 2017 installation of inserts addresses the degradation of the neutron absorbing material (Boraflex) previously installed

in the SFP racks. The rack inserts are manufactured by

NETCO using an aluminum and boron carbide composite

material produced by Rio Tinto Alcan, Inc.

Analyses of the safety considerations concerning the high density spent fuel storage racks are set forth in a

document entitled "Design Report of High Density Spent

Fuel Storage Racks for PECO Energy Company (PECO),

formerly Philadelphia Electric Company, Peach Bottom

Atomic Power Station Units 2 and 3, Revision 2," dated

July 21, 1986. This document describes the high density

spent fuel storage racks in detail and contains analyses

for seismic events, criticality concerns, structural

requirements, thermal and hydraulic requirements, and

postulated accident conditions associated with the high

density spent fuel racks. Additional analysis has been

performed that justifies application of the results of

this document for Spent Fuel Pool water temperatures as low as 40 F. The technical evaluation that allowed the use of GE-14 fuel in the Peach Bottom reactors is contained in ECR PB

99-02682. The acceptability of storing GE-14 fuel in the

Spent Fuel Pool is documented in "GE14 Spent Fuel Storage

Rack Analysis for Peach Bottom Atomic Power Station,"

Global Nuclear Fuel Document No. J11-03761-00-SFP, July

2000. GNF2 Fuel was evaluated in TS Amendment 287/290 for use of the NETCO-SNAP-IN inserts.

The dry storage cask consists of a fuel basket, a cask body, a protective cover, an overpressure system, penetrations with bolted and sealed covers for leak

detection and venting, closure bolts and locating pins.

The cask is designed to be lifted in a single failure

proof configuration.

Analysis of the safety considerations concerning the usage of the dry cask storage system is documented in the PBAPS

Independent Fuel Storage Safety Analysis Report (IFSSAR)

and PBAPS 10CFR 72.212 Report. These documents discuss in

detail the various design basis cask storage at PBAPS.

CHAPTER 10 10.3-4 REV. 26, APRIL 2017 10.3.4.1 High Density Spent Fuel Storage Racks The high density spent fuel racks are constructed of stainless steel materials and each rack module is composed

of cell assemblies, base plate, and base support assembly.

10.3.4.1.1 Cell Assembly

Each cell assembly is composed of (1) a full length enclosure constructed of 0.075 inch thick stainless steel, (2) sections of Bisco Boraflex which is neutron absorbing

material, and (3) wrapper plates constructed of 0.020 inch thick stainless steel. Additionally, NETCO-SNAP-IN inserts provide augmented neutron absorbing capability.

10.3.4.1.1.1 Cell Enclosure

The primary functions of the enclosure are to house fuel assemblies, to maintain the necessary separation between

assemblies for subcriticality and to provide structural

stiffness for the rack module. The inside square

dimension of the cell enclosure is 6.070 inches nominal

which accommodates either channeled or unchanneled fuel or

consolidated fuel assemblies. A partial plan view is

shown in Figure 10.3.6 and a partial elevation view is

shown in Figure 10.3.7.

10.3.4.1.1.2 Neutron Absorbing Material

The Bisco Boraflex manufactured by Brand Industrial Services provided the additional neutron absorbing media

required above that inherent in the rack structure

material. The Boraflex is fabricated to safety-related

nuclear criteria of 10CFR50, Appendix B, and it consists

of boron carbide particles as neutron absorbers held in

place by a nonmetallic binder. Boraflex contains an

initial minimum B 10 areal density of 0.021 gm/cm

2. It is a continuous sheet centered on the length of the active

fuel. Depending on the location of the cells in a rack

module, some cells have the Boraflex on all four sides, some of three sides and some on two sides. Cells with

four wrappers are located in the interior of the rack, cells with three wrappers are located on the periphery of

the rack, and cells with two (adjacent) wrappers are

located at the corners of the rack.

Since NETCO SNAP-IN rack inserts have been fully installed in the Peach Bottom Units 2 and 3 Spent Fuel

CHAPTER 10 10.3-5 REV. 26, APRIL 2017 Pool racks, Boraflex is no longer credited as a neutron absorbing material.

10.3.4.1.1.3 Wrapper Plate

The wrapper plates are attached to the outside of the cell enclosure by intermediate spot welding along the entire

length of the wrapper, forming the encapsulation of the

Boraflex. A water tight seal is not provided between the

wrappers and enclosures.

10.3.4.1.1.4 Neutron Absorbing Inserts The NETCO-SNAP-IN neutron absorbing inserts are manufactured by NETCO using an aluminum and boron

carbide composite material produced by Rio Tinto Alcan, Inc. The material contains 19% by volume of boron

carbide. The minimum certified areal density is 0.0105

grams/cm 2. An AA1100 aluminum alloy is used as a metal matrix to retain the boron carbide.

The inserts are designed to be an integral part of the

existing PBAPS spent fuel racks. The inserts are

nominally 0.075 inch-thick, are chevron shaped and have

a vertical length which is equal to the cell height of

the existing PBAPS spent fuel racks (169 inches). The

aluminum and boron carbide composite inserts function by

maintaining a greater than 90 degree bend angle when

formed, but are subsequently compressed to a 90 degree

bend angle when installed in the individual spent fuel

rack cells, which provides a bearing force against the

inside of the cell walls to retain the inserts in place.

10.3.4.1.1.4.1 Seismic and Structural Integrity A combination of analysis and testing has been used to

demonstrate acceptable structural and seismic

performance of the inserts.

The impact load of a fuel assembly on the neutron

absorbing inserts, generated by the horizontal

acceleration of a fuel assembly during a design-basis

seismic event, was determined to be 403 pounds per square inch (psi). Given that the NETCO-SNAP-IN insert yield stress is approximately 8000 psi, the deformation and subsequent failure of the insert due to seismically-

induced impact loads will not occur.

CHAPTER 10 10.3-6 REV. 26, APRIL 2017 To determine the stresses imparted on the cells of the existing PBAPS spent fuel racks by the inserts, the

limiting case involves the installation of the inserts

into the cells. The stresses imparted on the cell walls

during installation are not expected to exceed the

allowable stress. The additional stress that occurs

during installation of the inserts will have no effect

on the cell wall structural integrity and the stress

remains below the allowable value.

The increased load on the fuel racks from the inserts, which weigh approximately 18 pounds each, will be

insignificant and bounded by the existing design.

Analytical and confirmatory numerical analysis were used

to evaluate the stresses on the inserts during

installation. The stresses remained below the insert

material ultimate stress limit. Some instances were

identified of plastic deformation, particularly in the

wing and bend sections of the insert. However, sufficient elastic margin exists in the inserts, such

that adequate retention force is maintained between the

insert and cell walls.

Pre-installation testing demonstrated that adequate

retention force is maintained by the inserts, such that

they remain in place during normal (i.e., fuel handling)

and abnormal (i.e., design-basis seismic event) loading

conditions. In the unlikely event of warping or bowing

of an insert, any additional drag on a fuel assembly

will be recognized by a hoist load cell, which is

typically used during normal fuel handling activities.

Withdrawal testing showed that the inserts maintained a

static friction-based retention force well above the

established 200 pounds minimum removal criteria. During

a design-basis seismic event, the inserts must maintain

a retention force of 40.8 pounds to ensure that the

insert configuration remains unchanged, which is a 79.6%

reduction of the 200 pound minimum removal force

criteria. Over the 20-year expected life of the inserts, it is expected that the inserts will experience a stress

relaxation of approximately 50%.

CHAPTER 10 10.3-7 REV. 26, APRIL 2017 10.3.4.1.1.4.2 Fuel Handling Accidents The inserts have no effect on previously evaluated fuel handling accidents. This is based on the fact that the

installation of the inserts does not reduce the ability

of the cell wall or rack base plate to resist dynamic

impact loads resulting from a dropped fuel assembly, nor

does it affect whether a fuel assembly may become stuck

at the bottom of the existing racks.

An evaluation was performed to identify any previously

unanalyzed fuel handling accidents resulting from the

use of the tool used for installing and removing the

inserts. Due to similarities in geometry and the lower

weight of the insert tool and inserts compared to a fuel

assembly and grapple device used for normal fuel

handling activities, a postulated drop of the insert

tool and insert is bounded by previously analyzed fuel

handling accidents.

10.3.4.1.1.4.3 Criticality Analysis A SFP criticality analysis crediting the NETCO-SNAP-IN inserts was provided by Global Nuclear Fuel (GNF) report

NECD-33672P, Rev. 1, "Peach Bottom Atomic Power Station:

Fuel Storage Criticality Safety Analysis of Spent Fuel

Storage Racks with Rack Inserts." The analysis

determined a maximum k-effective of 0.92552 at a 95%

probability and 95% confidence level, and provides an

adequate reactivity margin to the regulatory k-effective

limit of 0.95.

Two computational methods were used by GNF in the

criticality analysis. GNF lattice design code TGBLA06

was used to calculate burned fuel compositions and the

in-core k-infinity values. The burned fuel compositions

were then used in MCNP-05P, the GNF proprietary version

of MCNP5, to obtain fuel storage rack k-effective

values. Tables 12, 13, and 14 of NEDC-33672P provide the biases

and uncertainties used to determine the maximum in-rack

k-effective. Biases are arithmetically added to the

calculated k-effective to account for conditions not

directly modeled in the base case analysis. Biases are

added for operational variables, abnormal or accident

conditions, and additional configurations. Uncertainty

components are statistically summed and then added to

the calculated k-effective. Uncertainties include

CHAPTER 10 10.3-8 REV. 26, APRIL 2017 manufacturing tolerances as well as computational uncertainties.

10.3.4.1.1.4.4 Abnormal or Accident Conditions The following abnormal accident conditions were

considered in the PBAPS SFP criticality analysis.

1. Missing NETCO-SNAP-IN insert, 2. Dropped fuel, 3. Damaged fue1, 4. No NETCO-SNAP-IN inserts on rack periphery, 5. Misplacement of a fuel assembly, 6. Lateral movement of a rack module,
7. Loss of SFP cooling, and
8. Inaccessible storage locations.

Analysis has determined the reactivity impact for the

above conditions and determined that they are either

bounded by other conditions or the corresponding

reactivity increase has been added to the calculated k-

effective.

10.3.4.1.1.4.5 Boraflex Credit for the Interim Period As part of a Peach Bottom license amendment (287/290, 5/21/16) for the NETCO SNAP-IN rack inserts, a license condition took credit for Boraflex during an interim period prior to installation of all inserts. Since NETCO SNAP-IN rack inserts have been fully installed in both Peach Bottom Unit 2 and Unit 3 Spent Fuel Pool racks, Boraflex is no longer credited as a neutron absorbing material.

GNF report 000N6365-R0, Revision 0, "Peach Bottom Atomic Power Station Units 2 and 3 Spent Fuel Pool Criticality Analysis Gap Sensitivity Study," provides a supplement to NEDC-33686P, Revision 1 that evaluates additional gap configurations. This analysis demonstrates that the results of NEDC-33686P, Revision 1 are bounding when compared to actual gap distributions in the pool.

10.3.4.1.2 Base Plate

The base plate is a 0.50 inch thick stainless steel plate with chamfered through holes centered at each storage

location which provides for a seating surface for the fuel

assemblies. These holes also provide passage for coolant

flow for each fuel assembly.

CHAPTER 10 10.3-9 REV. 26, APRIL 2017 10.3.4.1.3 Base Support Assembly

Each rack module is provided with base support assemblies which are located at the center of the four corner cells

within the module and at interior module locations to

distribute pool floor loading.

Each base support assembly is composed of a leveling block assembly, a leveling screw, and a support pad (see Figure

10.3.7). The top of the leveling block assembly is welded

to the bottom of the base plate. The leveling block

assembly is threaded at the bottom to accept the leveling

screw which sits in the support pad providing support for

the rack. The screw is remotely adjustable at rack

installation to obtain a level condition. The screw has

an adjustable range up to 1 inch. The leveling pad has a swivel joint to accommodate a maximum of 2 out-or-level condition of the pool liner.

The base support assemblies are welded to the bottom of the base plate at their appropriate support locations for

each rack (refer to Figure 10.3.7). The cell assemblies

are then positioned and welded to the top surface of the

base plate. The cell assemblies are positioned in a

checkerboard pattern with the space between four cell

assemblies forming a fifth storage locations. In addition

to being welded to the base plate, the vertical corners of

adjacent cells are welded to each other at two locations

along their length to form a integral structure. Along

the peripheral rows of the rack module, stainless steel

cover plates are welded between the cell assemblies to

enclose the non-cell locations. Some cover plates have

wrapper plates with Boraflex, identical to those used on

the cells, affixed to their inward side to satisfy

adjacent rack module criticality concerns. Each rack has

provisions for attachment of a lifting fixture for

installation and/or removal of the racks in the spent fuel

pool. The base plate has slotted holes at four locations

designed to accept lift rods which are inserted down

through the storage cells. The lift rods are connected at

the top of a lifting fixture.

The structure of the racks is designed to maintain the required spacing between stored fuel assemblies in the

event of impact of a fuel bundle dropped on the racks from

an elevation of 24 inches (maximum). For this case, the

integrity of the storage rack is not compromised and

damage to the racks is above the poison area; therefore,

CHAPTER 10 10.3-10 REV. 26, APRIL 2017 the criticality requirements are not violated. The structure of the racks is also analyzed for effects of the

impact of a fuel bundle dropped through an empty storage

cavity. The fuel drop accident analysis shows that the

structure absorbs the energy and the criticality

requirements are not violated. Analyses are also

conducted of the stresses on a storage rack due to maximum

uplift of the refueling crane on a fuel bundle which is

stuck. The evaluation of this case showed no permanent

deformation of the storage rack. The high density spent

fuel storage racks are seismic Category I equipment as

defined in NRC Regulatory Guide 1.13. These racks are

designed to withstand the effects of a maximum credible

earthquake and remain functional, in accordance with NRC

Regulatory Guide 1.29 and the Code of Federal Regulations, Title 10, Part 100.

The basic design criteria for the spent fuel storage rack are outlined by the NRC position paper. The NRC position

paper entitled "OT Position For Review and Acceptance of

Spent Fuel Storage and Handling Applications" dated April

14, 1978, as amended by the NRC letter dated January 18, 1979, offers two codes for deriving the allowable

stresses. The two codes are AISC Code or the ASME Code

III Subsection NF. The structural analysis herein is

based on the allowable stresses as outlined in ASME Code

III Subsection NF. The results of the seismic and

structural analyses are interrelated as the loads of the

seismic analysis are used in the structural analysis to

calculate stresses. The resulting margins of safety are

positive and satisfy the requirements of the ASME code.

The pool floor loads resulting from the seismic and

structural analyses also satisfy the requirements of the

PECO specification for the spent fuel storage racks. The

displacement results of the seismic analyses are used in

the lift-off stability calculation and show that factor of

safety against overturning is greater that the 1.5 minimum

requirement of the NRC position paper. The rack seismic

displacements are used in conjunction with thermal

displacements to show that there is no rack-to-rack, rack-

to-pool floor obstruction collision.

10.3.4.2 Spent Fuel Pool

The fuel pool together with the dryer-separator storage pool form a channel-shaped beam supported in the middle by

the biological concrete shield structure and at the outer

ends by the building walls.

CHAPTER 10 10.3-11 REV. 26, APRIL 2017 The pool floor carries a live load in addition to the water load. A system of large steel shapes is used to support the weight of the wet concrete only. Deep beam

action was checked and interactions of elements accounted

for. A finite element analysis was performed to check

temperature stresses in combination with other loads.

Hydrodynamic effects of water were also included in the

analysis.

Once the integrity of the system was ascertained, local stresses, embedments, connections, girder deflection, and

discontinuities were investigated.

The pool is lined with stainless steel and is designed to preclude inadvertent loss of water from the pool.

There are no connections to the fuel storage pool which could allow the fuel pool to be drained below the pool

gate between the reactor well and the fuel pool when the

pool gate is in place or below 10 feet above the top of

active fuel. Lines extending below this level are

equipped with syphon breaker holes to prevent inadvertent

pool drainage. Systems for maintaining water quality and

quantity are designed so that any maloperation or failure

of such systems will not cause fuel to be uncovered.

The fuel storage pool is designed to seismic Class I criteria and so that no single failure of structures or

equipment will cause the inability (1) to maintain

irradiated fuel submerged in water, (2) to reestablish

normal fuel pool water level, or (3) to safely remove

fuel. To prevent leakage, the pool is lined with

stainless steel. In addition to providing a high degree

of integrity, the lining is reinforced to withstand forces

that might occur when the transfer cask is moved in the

cask storage area.

Interconnected drainage paths are provided behind the liner. These paths are designed (1) to prevent pressure

buildup behind the liner plate, (2) to prevent the

uncontrolled loss of contaminated pool water to the

secondary containment, and (3) to provide expedient liner

leak detection and measurement.

Protection of the pool liner in the cask storage area for the normal cask lowering operation is provided by a 1-inch

thick steel wearing plate. This will prevent any damage

to the liner over plant life occasioned by normal fuel

cask handling. Additionally, interlocks are provided to

prevent the crane trolley, with a predetermined load on

CHAPTER 10 10.3-12 REV. 26, APRIL 2017 its main hook, from passing over the fuel pool. Strict administrative control is used for bypassing the

interlocks during cask handling operations.

The reactor building crane main hook and the lifting device associated with the cask are of a single failure

proof design such that a single failure will not result in

dropping the load. The available makeup water sources to

the spent fuel pool and associated flow rates are

presented in Table 10.3.1.

The spent fuel pool cask pit area restraining structure has been analyzed to withstand cask impacts due to

postulated design events. Cask placement in the center of

the cask pit area is controlled in accordance with station

procedures. This includes maintaining the appropriate

centering tolerance as well the angular placement of the

cask with respect to the trunnions and the restraining

structure.

10.3.4.3 Fuel Pool Level Alarms

Low water level alarms are provided locally and in the main control room in the event of water loss. The low

water level alarms are part of the fuel pool cooling

system. As a backup, flow alarms are provided in the

drain lines of the reactor vessel to drywell seal, drywell

to concrete seal, and fuel pool gate to detect leakage.

10.3.4.4 Dry Cask Storage

Dry Cask Storage of spent nuclear fuel has been evaluated for PBAPS. This program meets the requirements of 10CFR

72 and utilizes the General License issued under 10CFR 72.

10.3.4.4.1 Dry Cask Storage Rigging and Handling

The storage cask is handled by the Reactor Building Crane in a single failure proof configuration. Other cask

components such as the lid and basket hold down ring are

also handled in a single failure proof configuration

unless specifically evaluated otherwise in accordance with

UFSAR Section 10.A.11. All cask movement in the Reactor

Building will be consistent with NUREG-0612, over

designated safe load paths and either with the single

failure proof Reactor Building Crane or with the cask

transporter with the cask at the appropriate analyzed

heights. All cask movement in the Reactor Building will

be on designated safe load paths to ensure that cask drop

loads where applicable will not affect the safety of the

CHAPTER 10 10.3-13 REV. 26, APRIL 2017 PBAPS plant. The cask transporter is not single failure proof but has been evaluated for cask drops and found to

be acceptable. The cask is rigged in a single-failure-

proof configuration while in the spent fuel pool by

ensuring a procedurally controlled amount of water is

removed from the loaded cask.

10.3.4.4.2 Dry Cask Structural Considerations

A calculation was performed to consider the acceptability of a drop of a loaded cask from a cask transporter in the

Reactor Building onto the Elevation 135' floor. The

calculation demonstrates the structural adequacy of the

impact floor and the absence of effects on safety related

equipment beneath it at a lift height less than 2.5".

Superficial damage to the floor at el. 135' would be

repaired as appropriate. The lift height is procedurally

controlled.

The cask will be rigged in a single failure proof configuration while rigged from the reactor building crane

in the Reactor Building hatchway. The placement of the

cask in the hatchway will be such that credible cask

swinging in the hatchway during a seismic event will not

result in cask / plant impacts. Therefore, damage to the

plant is precluded.

The structural capacity of the Reactor Building floor at el. 234' has been evaluated for cask operations. These

analyses assumed a coincident maximum credible earthquake.

The designated cask laydown area is controlled by spent

fuel procedures.

The restraint structure (without the vertical guides) in the spent fuel cask pit area of the fuel pool was modeled

using finite element analysis techniques and evaluated for

structural adequacy under the effects of combined loadings

postulated for the structure consistent with the PBAPS

UFSAR Appendix C.

Cask impacts on the restraint structure due to postulated seismic (MCE) event were evaluated for the suspended cask (pendulum effect during hoisting) and for the free-

standing cask located on the wear plate (sliding and

tipping) and found acceptable.

Administrative controls and procedural requirements assure that the cask is appropriately centered within the

specified tolerance during the move-in/move-out and cask

placement operations.

CHAPTER 10 10.3-14 REV. 26, APRIL 2017 Passage of the cask transporter over the access road and haul path, with or without a cask, does not physically

affect systems, structures and components (SSCs) of the

PBAPS plants. The haul path and access road are well

defined by roadway markings to guide the cask transporter

driver. In the event the transporter fails or is

inadvertently driven off the designated haul path, off-

normal procedures exist to ensure that operations are

halted. Cask drops along the transport route were

evaluated and found acceptable.

10.3.4.4.3 Dry Cask Fuel Pool Operations

Cask insertion into the fuel pool will be controlled by procedures to ensure that the fuel pool level is

maintained. Fuel pool level will be procedurally

controlled by a combination of activities, including as

necessary, turning off the fuel pool cooling system, lowering and raising the fuel pool level control weir

gate, draining/filling the skimmer surge tanks, and

controlling the filling and draining of the casks as

appropriate. None of the involved activities can result

in inadvertent draining of the fuel pool.

Before each cask loading campaign a plan will be prepared that specifies the fuel assemblies to be moved from the

pool into the cask, and their specified assigned location

in the cask fuel basket. Selection of the correct fuel

assemblies from the fuel pool racks and correct placement

in the cask basket will be controlled by procedural

methods. Any mispositioning that could occur would be

detected by confirmatory monitoring. Normal site fuel

movement procedures will be used by appropriately

qualified personnel.

The elevation of the fuel bundles must be increased in order to provide clearance over the lip of the open dry

storage casks, which are taller than the cask for which

the spent fuel pool was originally designed.

The new normal-up setpoint needed to load an ISFSI cask will be used only for fuel cask loading and unloading

operations.

10.3.4.4.5 Dry Cask Storage Design Basis Events

The postulated events that could occur during cask operations are discussed in the IFSSAR and 10CFR 72.212

Report. The following is a summary of those events that

CHAPTER 10 10.3-15 REV. 26, APRIL 2017 could have potential impacts or interaction with PBAPS 2 and 3.

Fuel Bundle Drop

A design basis fuel bundle drop was evaluated and found to be bounded by existing accident analysis. Criticality, radiological releases and effects on the ISFSI cask and

fuel pool liner were evaluated and found acceptable.

Wrong Fuel Insertion

The TN-68 IFSSAR evaluates the impact on the cask if an incorrect fuel assembly is loaded. These events are

precluded due to administrative control and training of

personnel involved with loading the cask. Procedural

controls will ensure that only allowed fuel is selected

for loading into a cask. Additionally, verifications of

fuel being loaded will ensure that incorrectly loaded fuel

does not go undetected. The TN-68 IFSSAR concludes that

fuel with heat generation greater than allowed is not a

concern to the cask as long as the cask is submerged in

the fuel pool. Because there are multiple layers of fuel

verification prior to placing the lid on the cask, there

is no concern for incorrectly loaded fuel with a higher

than allowed heat generation rate. The TN-68 IFSSAR

evaluates the loading of a fuel assembly with higher than

allowed enrichment and determines the impact on the

criticality margin in the cask. For worst case conditions

and placement into the cask, a fuel assembly with an

initial enrichment of 5.0% was evaluated and determined to

not cause any criticality concerns. Loading verifications

prior to placing the lid on the cask would detect the

incorrectly loaded assembly and remove it prior to

continuing loading operations.

Cask Drop / Tip

Various scenarios involving the potential for cask drop/tip were evaluated. In no case, does the cask tip

over. For the drop scenarios, the cask remains within its

licensed design basis.

Natural Events

The cask and associated support equipment has been evaluated for various natural events. In all cases, the

cask was shown to not tip over. Cask drops are possible

when suspended on the transporter, however, these drops

have been evaluated as discussed earlier. Impacts of

CHAPTER 10 10.3-16 REV. 26, APRIL 2017 natural events have been considered in the analysis of the cask while in the Reactor Building and have been found to

not result in an uncontrolled lowering of the cask or

other damage to plant equipment due to cask impacts.

Fires and Explosions

The TN-68 cask is designed to withstand various fires and explosions. The cask is not combustible and therefore

poses no new significant fire or explosion threat to the

plant. The transporter has been evaluated and found

acceptable.

Cask Seal Leak

The worst case seal leakage has been demonstrated in the TN-68 SAR to be well below regulatory limits.

Cask Loading Operations Issues

During cask loading, various contingency actions may be required to perform in the event (for example) of the

inability to get the cask adequately drained and filled

with helium or the inability to meet the leak tightness

requirements. Procedures exist to direct actions in these

off-normal conditions. These conditions are governed by

TN-68 Tech Specs to ensure that cask parameters are not

exceeded. These actions may include returning the cask to

the spent fuel pool for unloading. Because there are

adequate controls on the cask in these off-normal

conditions, there is no impact to PBAPS 2 and 3

operations.

Cask Unloading Operations

If the cask is required to be unloaded or a seal repair is required, the cask is returned to the Reactor Building.

The cask transport route follows the same load path as for

transport to the ISFSI. A cavity gas sample shall be

obtained and analyzes and the cask depressurized to a

nominal atmospheric pressure. The cask is refilled with

water and the outlet line from the cask is piped below the

surface of the pool with a sparger attached at the

discharge end. Steam is quenched by the relatively cool

fuel pool water. Helium bubbles released from the cask

would rise to the surface to mix with the refueling floor

atmosphere and be dissipated by the HVAC system.

Particulates released from the cask would be scrubbed out

by the fuel pool water and filtered by the Spent Fuel Pool

Cooling and Cleanup System (SFPCCS). Except for Kr-85 and

CHAPTER 10 10.3-17 REV. 26, APRIL 2017 I-129, the constituents of the gas gap from leaking rods is scrubbed out by the fuel pool water and handled by the

SFPCCS. The dose due to noble gases from the unloading

operation, assuming 100% failed fuel in the cask, results

in a lower offsite dose than that from the refueling

accident analyzed in Section 14.6.4 of the PBAPS SAR.

The heat added to the pool water is well within the cooling capacity of the SFPCCS. It is capable of

receiving a full core offload directly from the reactor

and still keep the pool temperature at an acceptable

value. The heat from only 68 assemblies plus the latent

heat stored in the cask materials is insignificant

compared to that from a full core offload.

10.3.4.4.6 Dry Cask Storage Programs

As required by 10 CFR 72.212, the PBAPS radiation protection, emergency preparedness, security and training

programs were updated to incorporate dry cask storage.

10.3.4.4.7 Dry Cask Operations

Helium is used during dry cask operations. The exhaust of helium into the reactor building atmosphere is not a

concern to the plant since the helium is an inert gas and

readily dissipates. The exhaust will be vented to the Fuel

Floor area for further processing in the ventilation

system.

The cask is drained of water when it is raised to the fuel pool surface water level. Evaluations and procedural

controls have been developed to ensure that the cask is

not raised out of the pool such that the reactor building

crane or lift beam would exceed its single failure proof

rating.

The casks are dried to ensure that long term corrosion of the cask is minimized. The vacuum pumps exhaust will be

appropriately monitored by radiation protection personnel

and filtered as necessary. The vacuum pump discharge is

directed to the fuel floor area for further processing by

the refuel floor ventilation system. Cask over-

pressurization with helium is not a concern when using

procedurally controlled standard bottles and pressures.

This is due to the large volume of the cask compared to

the small volume of the helium bottle.

Leak testing is performed using calibrated leak testing equipment. This equipment is appropriately controlled and

CHAPTER 10 10.3-18 REV. 26, APRIL 2017 poses no significant risk to the plant. Leak testing ensures that the cask is properly sealed for transport and

storage outside of the reactor building.

The operations skid is designed to facilitate the evaluations required to drain, dry, inert, and test a

spent fuel cask. This equipment is not safety related.

Appropriate I&C measuring and test equipment will be

controlled in accordance with procedures and will be

within calibration frequency.

10.3.5 Safety Evaluation

The design of the spent fuel storage racks and dry storage casks provides for a subcritical effective multiplication

factor (k eff) for both normal and abnormal storage conditions. Under any condition the k eff is equal to or less than 0.95. The spent fuel pool concrete structure, as well as each spent fuel storage rack and fixture loaded

with fuel, are designed to seismic Class I criteria to

withstand the maximum credible earthquake.

The spent fuel pool is adequately protected from the effects of a turbine generated missile. The probability

of a turbine generated missile is small and is detailed in

Section 11.2. The fuel pool is protected against low

trajectory missiles by thick concrete walls between the

turbine and the pool as well as the thick concrete pool

walls. Once a high trajectory missile is generated, the

possibility of it landing in the pool is in the range of

10-4. Therefore, the combined risk to the fuel pool from a high trajectory turbine missile is insignificant.

The spent fuel pools are designed with substantial capability to withstand the effects of a tornado, including tornado-generated missiles. Discussion of this

capability is provided in Paragraph J.5.2.

Additional information is provided in Topical Reports APED-5696, "Tornado Protection for the Spent Fuel Storage

Pool" (General Electric, November, 1969) and "Tornado

Criteria for Nuclear Power Plants" (Bechtel Corporation, July, 1969).

The spent fuel storage pools are located in the reactor buildings which serve as secondary containment for the

reactors (subsection 5.3). Each reactor building is

designed to control leakage from the building and provides

filtration, through the standby gas treatment system, to

limit radioactive discharges in the event of an accident.

CHAPTER 10 10.3-19 REV. 26, APRIL 2017 Ventilation air from the spent fuel pool area is not normally filtered prior to exhaust to the atmosphere. The

standby gas treatment system is described in paragraph

5.3.3.

The consequences and assumptions used in evaluating a refueling accident are presented in paragraph 14.6.4. The

analysis provided in subsection 14.6.4 uses conservative

assumptions, similar to those provided in Regulatory Guide

1.25, to demonstrate that releases from a postulated

refueling accident result in doses which are well within

10CFR100 limits.

Provisions are made for level detection to ensure the fuel in the spent fuel storage is covered with sufficient water

for radiation shielding. Leakage detection

instrumentation is also provided to ensure an adequate

fuel pool water level is maintained. The design of the

spent fuel pool structure is such as to prevent

inadvertent draining of the pool.

The radiation levels are monitored in the refueling floor exhaust duct. Both low and high radiation signals are

alarmed in the control room and a high-high radiation

signal isolates the duct and initiates the standby gas

treatment system.

The high-density SFP storage racks utilize Boraflex as a

neutron absorber material for reactivity control. Due to

Boraflex degradation, PBAPS implemented an ongoing

Boraflex monitoring program, to include RACKLIFE

simulation of the rack degradation and blackness testing

using the BADGER B-10 areal density measurement system.

A SFP rack insert program has also been implemented that

will replace Boraflex. The effect of plant operation at

100% rated thermal power on Boraflex degradation is

accounted for by the Boraflex monitoring program until

installation of the SFP rack inserts is completed. A

reduction in the amount of Boraflex in the SFP racks

will reduce the criticality margin such that actions are

required to ensure that the Licensing Basis requirements

continue to be met. To ensure the SFP storage racks can

maintain criticality margin in accordance with the PBAPS

Technical Specification 4.3.1.1.b requirement of 5

percent (K eff 0.95), the peak in-core fuel bundle K inf is limited as follows:

1.A peak in-core fuel bundle K inf limit of 1.235 has been established and applies until all of the SFP

rack inserts are installed.

CHAPTER 10 10.3-20 REV. 26, APRIL 2017

2. A peak in-core fuel bundle K inf limit of 1.270 has been established and applies after all of the SFP rack inserts are installed.

The peak in-core K inf limit for the fuel bundles used in the representative equilibrium cycle core design is

1.2095, which is bounded by the K inf limits of 1.235 and 1.270. Therefore, these bundle K inf limits ensure the SFP criticality margin is maintained before and after

all of the SFP rack inserts are installed.

Dry cask storage casks were evaluated for various design basis events and normal conditions and found acceptable in

accordance with the IFSSAR and 10CFR 72.212 Report.

10.3.6 Inspection and Testing

Dry storage casks are appropriately inspected and tested to ensure design basis assumptions are met.

The in-service inspection program for the spent fuel storage racks involves periodic assessment of neutron

poison material performance.

10.3.6.1 Boraflex Inspection and Testing

This assessment may utilize jacketed Boraflex specimens contained in surveillance coupon assemblies hung on the

periphery of a rack module.

A computer based Boraflex performance model and direct measurement of the B-10 areal density of representative

in-service spent fuel storage rack panels may be used in

conjunction with or in replacement of coupon inspection.

10.3.6.2 Neutron Absorbing Inserts Surveillance Program The rack insert surveillance program is designed to

monitor the physical properties of the insert material by

performing periodic physical inspection and neutron

attenuation testing to confirm the ability of the material

to perform its intended function. 10.3.6.2.1 Fast Start Coupon Surveillance Program Exelon initiated a "Fast Start" coupon surveillance

program at LaSalle County Generating Station to provide

early performance data on the coupon exposure to maximum

temperature and gamma irradiation. The program consists of

CHAPTER 10 10.3-21 REV. 26, APRIL 2017 24 coupons suspended inside of a spent fuel storage rack cell and surrounded in all adjacent cells with freshly

discharged fuel. Two of the coupons will be removed

approximately every six months for testing, inspection and

comparison to their pre-installed condition. Initial

results showed essentially no change in the coupon

characteristics. Because the spent fuel pool chemistries

at PBAPS are similar to LaSalle, this program provides

information on initial material performance and is a basis

for confidence that early insert response to the SFP

environment is acceptable.

PBAPS will monitor LaSalle's program to identify any

unanticipated insert material performance issues including

review of their coupon test reports. Information obtained

will be used to evaluate the long-term and the full rack

insert surveillance programs at PBAPS and make any

necessary modifications.

10.3.6.2.2 Long-Term Coupon Surveillance Program

The long-term coupon surveillance program consists of a

specially designed monitoring tree to which a series of

surveillance coupons are attached. The monitoring tree, placed within the PBAPS spent fuel pools, will reside

there as long as the spent fuel storage racks with NETCO-SNAP-IN rack inserts continue to be used. Periodically, as described below, coupons will be removed and sent to a qualified laboratory for testing.

CHAPTER 10 10.3-22 REV. 26, APRIL 2017 Table 10.3.6.1 Long-Term Surveillance Coupons Coupon Type NumberObjective General 48 (See next Table)

Bend 24 Track effects along bend radii Galvanic (bi-metallic) 24 Trend galvanic corrosion with 304SS, Inconel 718 and Zircaloy coupons Specific coupons will be removed from the tree on a frequency

schedule in the following tables. The general coupons will be

subject to pre- and post-examination according to the following:

CHAPTER 10 10.3-23 REV. 26, APRIL 2017 Table 10.3.6.2 Long-Term Surveillance General Coupon Characterization

Pre-Characterization Post-Characterization Acceptance Criteria Visual (high

resolution

digital photo) X X Evidence of Visual

indications Dimension X X Min.

thickness:

0.005 inch less than

nominal thickness

Length Change: Any

change of +/-0.02

inch Width Change:

Any change of +/-

0.02 inch Thickness

Change: Any change

of +0.010 inch/-

0.004 inch Dry Weight X X Any change of +/- 5%

Density X X Any change of +/- 5% Areal Density X on select coupons X 0.0102 Boron-10 g/cm 2 minimum loading Weight Loss X Any change of +/- 5%

Corrosion Rate X < 0.05 mil/yr Microscopy X as required At the discretion of the test engineer Bend Coupon

Stress Relaxation X 50% stress reduction (to maintain 100 lbf

retention force)

The frequency for coupon inspection is shown in the following table.

CHAPTER 10 10.3-24 REV. 26, APRIL 2017 Table 10.3.6.3 Frequency for Coupon Inspection Coupon Type First Ten Years After 10 Years with Acceptable Performance General 2 coupons every 2 years 2 coupons every 4 years Bend 1 coupon every 2 years 1 coupon every 4 years Galvanic Couples 304

Stainless

Zircaloy Inconel 718 1 couple every 6 years

1 couple every 6 years

1 couple every 6 years 10.3.6.2.3 Full Rack Insert Surveillance Inspections Two rack inserts will be visually inspected by camera at the

frequency of the general coupon removal schedule described

above to visually monitor for physical deformities such as

bubbling, blistering, corrosion pitting, cracking, or

flaking. Special attention will be paid to development of

any edge or corner defects.

A region of high duty spent fuel storage rack cell locations

will be identified and will be monitored for fuel insertion

and removal events to ensure that their service bounds that

of the general population of storage locations. Once every

10 years, an insert will be removed from this region and will

be inspected for thickness along its length at several

locations and be compared with the as-built thickness

measurements of the removed insert to verify it has sustained

uniform wear over its service life. After the inspection, the

insert will not be reinstalled.

CHAPTER 10 10.3-25 REV. 21, APRIL 2007 TABLE 10.3.1 AVAILABLE MAKEUP WATER SOURCES

Rate Source Route (gpm)

Torus One RHR pump to fuel 10,000 pool (1)

Refueling water One refueling water pump 1,650 storage tank and/

to reactor well header, to or condensate fuel pool cooling pumps, to storage tank bypass filter, to fuel pool

Condensate storage High-pressure decontami-25 tank nation pump to fuel pool

Condensate storage Fuel pool makeup from con-60 tank densate transfer pump

Demineralized To demin. water supplies 150 water storage in service boxes

Total demineralized 1,885 water available

immediately

Total demineralized 11,885 water available

after 1 hr (2)

River water High-pressure service water 18,000 pumps via RHR cross-tie (2,3)

River water Fire waterhose stations 70 (2-3 in)

Total river water 70 available immediately

Total river water 18,070 available after 1 hr (3)

(1) Approximately 1 hr is required to install the removable spool before supply can be used.

(2) Can only be used if plant is shut down and RHR cooling is with RHR pumps A and/or C.

(3) Alternate to torus water using RHR pumps.

CHAPTER 10 10.3-26 REV. 21, APRIL 2007 TABLE 10.3.2 RACK MODULE DATA (PER UNIT)

QTY

ARRAY STORAGE LOCATIONS

RACK ASSY

DIMENSIONS (INCHES)

DRY WEIGHT (LBS)

PER RACK ASSY 1 9 x 14 126 54 x 89 x 180 10,000 2 10 x 14 280 64 x 89 x 180 11,200 1 11 x 14 Mod. 119 70 x 89 x 180 9,500 1 12 x 15 180 76 x 95 x 180 14,400 1 12 x 17 204 76 x 107 x 180 16,300 2 12 x 20 480 76 x 126 x 180 19,200 2 15 x 19 570 95 x 120 x 180 22,800 1 17 x 20 340 107 x 126 x 180 27,200 4 19 x 20 1,520 120 x 126 x 180 30,400 15 racks 3,819

Storage locations center-to-center spacing (inches) 6.28 Storage cell liner dimension (inches) 6.07

Intermediate storage location inner dimension (inches) 6.12

CHAPTER 10 10.4-1 REV. 26, APRIL 2017 10.4 TOOLS AND SERVICING EQUIPMENT 10.4.1 Introduction

All tools and servicing equipment necessary to meet the reactor

general servicing requirements are supplied for efficiency and

safe serviceability. The flow chart in Figure 10.4.1 defines in a

general way the steps that make up a routine refueling outage. The

heavy lines on the chart define the critical path in a normal

outage. Deviations to this path may be encountered under abnormal

circumstances. The following paragraphs describe the use of some

of the major tools and servicing equipment.

10.4.2 Fuel Servicing Equipment

Two fuel preparation machines located in each fuel storage pool

are used to remove and install channels to support inspection or

servicing of fuel assemblies. The fuel preparation machines are

also used for the placement of new fuel assemblies into the spent

fuel pool. These machines are designed to be removed from the

pool for servicing.

An equipment support railing is provided around the pool periphery

in order to tie off miscellaneous service equipment and for

personnel safety. Equipment lugs fabricated as part of the pool

liner are required for fixtures that might later be desired by

plant operating personnel. In addition, a curb with a plate of

thick stainless steel on top is provided around the entire

periphery of the refueling volume. Additional equipment may be

mounted by welding to, or drilling into, the plate. The curb may

be used as an additional support or tie-off area. Cable ways are

recessed into the floor around the pool periphery with openings to

pass cables into the pool from underneath this curbing.

The new fuel inspection stand is provided to restrain the fuel

assembly in a vertical position for inspection. The inspection

stand can hold two assemblies. The general purpose grapple is a

small, hand actuated tool used generally with fuel. The grapple

can be attached to the reactor building auxiliary hoist, the jib

crane, and the auxiliary hoists on the refueling platform. The

general purpose grapple is used to place new fuel in the

inspection stand and transfer it to the fuel pool.

A channel handling boom, with spring loaded takeup reel, is used

to assist the operator in supporting the weight after the channel

is removed from the fuel assembly. The boom is located between

the two fuel preparation machines. With the channel handling tool

attached to the reel, the channel may be conveniently moved

between fuel preparation machines.

CHAPTER 10 10.4-2 REV. 26, APRIL 2017 The complete channeling procedure is as follows. Using the refuel platform and the mast grapple, a spent fuel assembly is lifted

into the fuel preparation machine with the carriage lowered.

After raising the assembly to its high position, the channel is

unbolted from the fuel assembly using the channel bolt wrench

furnished for this purpose. This wrench is used to unscrew the

bolt and capture it. The channel handling tool is attached to the

channel handling boom and lowered to the channel. The tool is

attached to the channel triangular corner tabs by expanding two

fingers on the tool. The channel is then held, and the fuel

preparation machine carriage is lowered, causing the fuel bundle

to slide down out of the channel. The channel is then positioned

over the other fuel preparation machine, containing a new fuel

assembly, and the procedure is reversed. A channel storage rack

for accumulating channels is located on the wall between the fuel

preparation machines. A channel check gage may be mounted on the

wall adjacent to the fuel machines so the operator can check

channels. The channeled fuel is stored in the pool storage racks, ready for insertion in the reactor.

10.4.3 Servicing Aids

General and local area underwater lights are provided to

illuminate the internal region of the reactor vessel. Drop lights

are used for intense radial illumination where needed. These

lights are small enough in diameter to fit into fuel channels or

control blade guide tubes. A portable underwater television

camera and monitor are part of the plant optical aids. The

transmitted image can be viewed on the refueling platform. This

remote display assists in the inspection of the vessel internals, and general underwater surveillance in the reactor vessel and fuel

storage pool. General purpose, clear plastic viewing aids that

will float are used to break the water surface for better

visibility.

A portable underwater vacuum cleaner is provided to assist in

removing debris and miscellaneous objects from the pool floor or

the reactor vessel. The pump and the filter unit are completely

submersible for extended periods. Fuel pool tool accessories are

also provided to meet servicing requirements.

10.4.4 Reactor Vessel Servicing Equipment

Reactor vessel servicing equipment is supplied for safe handling

of the vessel head and its components, including nuts, studs, bushings, and seals.

The drywell head strongback is used for lifting the drywell head

and mirror insulation. Cruciform in shape, with four equally

spaced lifting points, the strongback is designed to keep the

CHAPTER 10 10.4-3 REV. 26, APRIL 2017 drywell head level during lifting and transport. Redundant rigging is used to connect the drywell head to the single-failure-

proof strongback, resulting in a single-failure-proof lift. An exception to the single-failure-proof requirements in ANSI N14.6-1978 is that two structural features added during modifications to upgrade this device were not impact-tested. (Ref. ECR 13-00378)

The Reactor Pressure Vessel (RPV) head strongback/carousel is used

for lifting the vessel head. The strongback/carousel is an

integrated piece of equipment consisting of a cruciform shaped

strongback, a circular monorail, and a circular storage tray.

The strongback is a box beam structure which has a hook box with

three pins in the center for engagement with the reactor building

crane main hoist hook. Each arm has a liftrod for engagement to

the four lift lugs on the RPV head. The monorail is mounted on

extensions of the strongback arms and four additional arms equally

spaced between the strongback arms. The monorail circle matches

the stud circle of the reactor vessel and it serves to suspend

stud tensioners and nut handling device.

The head strongback carousel service the following functions:

Lifting of Vessel Head - The strongback, when suspended from the reactor building crane main hook, transports the RPV head

plus the carousel with all its attachments between the

reactor vessel and storage on the pedestals. The strongback

and its connections to the RPV head are single-failure-proof.

One exception to the single-failure-proof requirements in

ANSI N14.6-1978 is that the hook and load pin material for

this device was not impact-tested as specified in ANSI N14.6-

1978. (Ref. ECR 13-00378)

Tensioning of Vessel Head Closure - The carousel, when supported on the RPV head on the vessel can carry up to eight

tensioners, its own weight, the strongback, storage of nuts, washers, thread protectors, and associated tools and

equipment. The stud tensioners are suspended equally spaced

from a monorail above the vessel stud circle. Each tensioner

has an air-operated hoist with individual controls.

The head holding pedestals are designed to support the vessel head

to permit seal replacement and seal surface cleaning and

inspection. The mating surface between vessel and pedestal is

selected to minimize the possibility of damaging the vessel head.

A reactor servicing platform permits the operator to work at a

level just above the reactor vessel flange, and permits servicing

access for the full core diameter. A service platform support is

provided, which rests on the vessel flange surface, and serves as

CHAPTER 10 10.4-4 REV. 26, APRIL 2017 both a track for the servicing platform and as a seal surface protector.

A separate seal surface protector made of aluminum is provided to

protect the sealing surface of the reactor pressure vessel flange

when the service platform or its track is not used.

A stud tensioner assembly is provided, and consists of four

tensioners transported by the reactor building crane main hoist or

the head strongback/carousel. The tensioners are controlled by a

hydraulic unit with pressure gages. Each tensioner contains:

1. An integral nut wrench for rotating the nut.
2. One stud elongation gage plus one elongation rod per stud to permit initial and periodic pressure/stretch

indication.

10.4.5 In-Vessel Servicing Equipment

The single or multiple instrument strongback is attached to the

reactor building crane auxiliary hoist and is used to lift

replacement in-core detectors from their shipping container. The

instrument handling tool is attached to the in-core detector by

the operators on the refueling platform. The single or multiple

strongback initially supports the in-core detector(s) as they are

lowered into the vessel, and the in-core detector is then

decoupled from the strongback. Final in-core detector insertion

is accomplished with the instrument handling tool. The instrument

handling tool is used for removing and installing fixed in-core

detectors, as well as for handling neutron sources and the WRNM

dry tubes.

10.4.5.1 Reactor Cavity Work Platform

The Reactor Cavity Work Platform (RCWP) is a tool used to allow in

vessel inspection/activities concurrent with fuel movement thereby

reducing refueling critical path time. The RCWP is a stainless

steel structure which consists of four (4) quadrants connected

using three sets of splice plates. The RCWP is stored in four (4)

specially designed sea land containers, and is brought to the

refueling floor and assembled prior to use.

The RCWP has an octagonal shaped structural framework with eight

radial legs which support four (4) personnel work baskets. The

eight support legs rest on the reactor building elevation 234'-0"

floor slab. The platform, when placed in the reactor cavity above

the open reactor pressure vessel (RPV), is slightly submerged into

the reactor cavity water. The bottom of the work baskets is

approximate elevation 231'-0" which provides approximately 7'-0"

CHAPTER 10 10.4-5 REV. 26, APRIL 2017 clearance to the underside of the refueling bridge. The RCWP legs have the capability to both extend/retract and rotate in order to

avoid obstructions such as the electrical pits and refuel bridge

gearbox, which are present on the operating deck. The RCWP has a

30-degree refueling opening in the direction of the fuel pool toallow for refuel bridge mast and fuel bundle movement whileperforming in vessel activities. Electrical power and station air

outlets are also provided in the RCWP work baskets.

10.4.6 Refueling Equipment

The refueling platform is used as the principal means of

transporting fuel assemblies back and forth between the reactor

well and the storage pool. The platform travels on rails

extending along each side of the reactor well and fuel pool. The

platform supports the fuel grapple and the frame-mounted and

monorail auxiliary hoists. The grapple is suspended from a

trolley system that can traverse the width of the platform.

Platform operations are controlled from either auxiliary hoist

control pendant or the fuel grapple controller consoles. The

platform contains a position-indicating system that indicates the

position of the fuel grapple over the core. The platform is

prevented from contacting the fuel pool and reactor walls by a

boundary zone interlock system.

One-half ton auxiliary hoists are mounted on both the reactor well

side of the refueling platform and on the platform trolley. These

hoists normally can be used with appropriate grapples to handle

control rods, in-core detectors, sources, and other internals of

the core. The auxiliary hoists can also serve as a means of

shuffling fuel elements and other equipment within the pool and

reactor.

A single operator is capable of controlling all the motions of

the platform required to handle the fuel assemblies during

refueling. Interlocks on both the grapple hoist and auxiliary

hoists prevent lifting a fuel assembly over the core with control rod withdrawn; interlocks also prevent withdrawal of a control rod

with a fuel assembly over the core attached to either the fuel

grapple or auxiliary hoists. Interlocks also block travel of the

refueling platform over the reactor in the startup mode. The

refueling interlocks are described and evaluated in subsection

7.6, "Refueling Interlocks."

A Service Pole Caddy platform is attached on the rear side of

either the Unit 2 or Unit 3 refueling platform at PBAPS. The

platform provides an auxiliary work station for unlatching and

latching the steam separator head bolts during refueling

activities. The platform can also be utilized for other

underwater servicing needs, such as jet pump beam bolt untorquing

CHAPTER 10 10.4-6 REV. 26, APRIL 2017 and steam line plug installation. The platform is provided with high torque service poles and a motorized hoist to handle the

poles.

10.4.7 Storage Equipment

In addition to the new and spent fuel storage racks, other storage

equipment is provided.

Defective fuel assemblies may be placed in special fuel cans which

would be stored in the defective fuel storage rack.

10.4.8 Under-Reactor-Vessel Servicing Equipment

The necessary equipment to remove CRD's during a refueling outage

is provided. An equipment handling platform with a rectangular

open center is provided. This platform is rotatable to provide

space under the vessel so the CRD can be lowered and removed.

A thermal sleeve installation tool (Figure 10.4.3) is used to

rotate the thermal sleeve (Figure 10.4.2) within the CRD housing.

Sleeve rotation permits disengagement of the guide tube. A rope

and pulley integral with the tool permits complete sleeve removal.

Miscellaneous wrenches are provided to install and remove the

neutron detectors. Flow through the drain tube pulls the fixed

in-core detector string into the in-core guide tube thus sealing

the opening in the in-core flange during in-core servicing. A

drain can be opened after in-core insertion to drain any residual

water. Correct seating of the in-core string is indicated when

drainage ceases.

10.4.9 Equipment Storage Pit

Large radioactive components, such as the steam dryer and steam

separator assembly are stored in the storage pit. The storage pit

is separated from the drywell by removable concrete blocks that

serve as a shield when the dryer and separator are stored and the

water level is lowered. Other large items, such as the pressure

vessel head and drywell head, are stored on the refueling floor.

To minimize worker exposure, a wet transfer of the dryer is

normally expected. To minimize operator exposure during a dry

transfer of the dryer assembly, the storage pit canal is deep

enough so that the top of the dryer can be kept at least 2 ft

below the operating floor level during transfer. The storage pit

is deep enough below the canal that, with the reactor well

drained, a minimum of 6 in of water shielding can be maintained

above the separator plenum dome.

CHAPTER 10 10.4-7 REV. 26, APRIL 2017 Special liner considerations account for the abrasion and high unit loadings that occur on areas where the dryer and separator

assemblies are placed.

The storage pit is lined with stainless steel for leaktightness

and corrosion resistance.

10.4.10 Reactor Building Crane

The reactor building crane for each unit is designed such that no

credible postulated failure of any crane component will result in

the dropping of the fuel cask; therefore, the consequences of this

accident are precluded.

The reactor building cranes have been evaluated using the criteria

of NUREG-0554 and NUREG-0612, Appendix C to establish the maximum

critical load (MCL) rating at which they can be considered single-

failure proof. The results of this evaluation resulted in a MCL

rating of 125 tons for the main hoist reactor building cranes.

Thus, for loads within this limit, a load drop is not credible.

The design of the main hoist is as follows:

A single hoist motor drives two separate shafts. The motor has

two centrifugally tripped limit switches, one outboard of each

hoist input pinion at each end of the motor shaft assembly. These

provide an automatic safety shutdown and protection from any

control or motor malfunction which might result in a runaway

condition of the load. Each motor driven shaft passes through a

150 percent capacity solenoid-actuated brake. A failure of either

the motor shaft, the connecting shafts, or the shaft couplings

singly would not result in a load drop as the brakes would be

effective in holding the load. On loss of power to the motor, both brakes engage. They can also be engaged by the operator.

Additionally, there is a 90 percent capacity eddy-current brake to

limit the rate of load lowering.

After the brake, each motor shaft enters its own gear reducer. If

a component of one gear case (gear teeth, shafts, bearings, or

structural component) should fail, the other gear reducer holds

the load with its brake with a safety factor of 5.

Each gear case is fitted on its output end with a pinion meshing

with the drum gear. A failure of a pinion, drum gear, pinion

shaft, or pinion bearing results in the load being carried by the

other similar set of parts on the other end of the drum. Again a

safety factor of 5 remains in the functioning parts. In each of

the main hoist gear cases, there is a mechanical load brake, with

cooling of the gear case oil, to offer additional safety in load

handling.

CHAPTER 10 10.4-8 REV. 26, APRIL 2017 In the event of failure of the drum shaft, drum bearing, or drum bearing bracket, the drum flange drops a fraction of an inch onto

machined structural seats so located that the drum is supported

and the remaining pinion and gear stay in mesh to restrain the

load. A safety factor of 5 still remains.

Two separate ropes are led from the drum, each being reeved

through a set of block sheaves, upper and lower, and back to an

equalizer bar, and are arranged for equal division of the load

between the two ropes. With both ropes functioning and equalized, the safety factor of the ropes is 7 on a static basis. If one rope

fails, the remaining rope supports the load with a residual safety

factor of 3.5 on a static basis. The equalizer bar is fitted with

double acting hydraulic cylinders and hydraulic accumulator to

minimize the shock when the entire load is transferred to one

rope. Therefore, load drop is precluded for a postulated single

rope failure. The equalizer bar is contained within structural

components so that if it breaks or if its pivot point breaks, the

parts are retained within the trolley and load drop is precluded.

To protect against overloading of the cables a load sensing system

consisting of tension type load cells supports the load sensing

sheave frame assembly. The load cells are supported by the load

cell support brackets attached to the trolley frame. To protect

against an unbalanced load, limit switches provide visual warning

indication to the crane operator. The limit switches, attached to

the trolley frame, are activated by movement in the equalizer bar

assembly.

All sheaves, both upper and block sheaves, are contained in heavy

structural casings which usually carry a negligible load. In the

event of a sheave pin failure, the sheaves rise to the top of the

block or drop to the base of the upper sheave housing and stop at

those points, and load drop is precluded. The block assembly

contains two 100 percent capacity hooks of "load carrying

devices." This redundancy in attachment to lifting assembly and

in load carrying capability are such that a single failure does

not cause load drop. Additional nondestructive testing (ultrasonic and magnaflux testing for the load block swivel and

the sheave shafts of the upper assembly) provides further

assurance that this crane is of a quality suitable for nuclear

services. Electrical circuits have been reviewed and it has been

determined that no single credible electrical component failure

causes the load to drop.

The auxiliary hoist is designed to satisfy the Single-Failure-

Proof Guidelines of Section 5.1.6 of NUREG-0612, and thus

eliminating the need to analyze the effects of drops of heavy

loads per the evaluation criteria of Section 5.1 of NUREG-0612.

CHAPTER 10 10.4-9 REV. 26, APRIL 2017 Protection of the pool liners in the cask storage area for the normal cask lowering operation is provided by a 1 in thick steel

wearing plate. This prevents any damage to the liner over plant

life occasioned by normal fuel cask handling.

The adequacy of the drywell head for a postulated drop of one of

the shield plugs was performed in a load drop analysis performed

in the Peach Bottom Calculation PS-0288, "Drywell Head Load Drop

Analysis."

No vital equipment is located in compartments below the fuel pool

floor; therefore, no loss of function of vital equipment would

result from falling objects and flooding caused by a postulated

event.

Strict administrative control assures that the cask is not

unnecessarily lifted higher than required during maneuvering above

the refueling floor and also that the cask is not brought over the

reactor vessel or the fuel storage portion of the pool.

10.4.11 Heavy Loads Compliance The licensee has a defense-in-depth program to manage the handling

of heavy loads on site such that no credible load drop will

endanger the public safety and health. Loads that are either not

considered as 'heavy loads' (i.e., less than 1200 pounds) or have

been determined to not potentially impact irradiated fuel, the

reactor vessel, or safe shutdown equipment are not within the

scope of the 'heavy loads' program. Any heavy loads that have not

previously been evaluated will be evaluated prior to being lifted.

This evaluation would include ensuring at least one of the

following measures are in place for the lift:

Mechanical stops or electrical interlocks that prevent heavy

loads movement over irradiated fuel or safe shutdown equipment, Verification analysis that the consequences of a potential load

drop are within accepted bounds, or Use of a single-failure-proof handling system.

Lifts are conducted in accordance with good rigging practices and

in accordance with the licensee's approved procedures.

In July 1980, the NRC issued NUREG-0612, Control of Heavy Loads at

Nuclear Power Plants. This NUREG was issued to resolve NRC

Generic Technical Activity A-36. This generic issue involved

reviewing the adequacy of NRC requirements for controlling the

handling of heavy loads over or in proximity to spent fuel, the

reactor core, and safe shutdown equipment. NUREG-0612

recommendations were planned to be assessed by the NRC in two

phases (i.e., Phase I and Phase II). Phase I concerned itself

CHAPTER 10 10.4-10 REV. 26, APRIL 2017 with seven requirements that assured a defense-in-depth approach was taken in regards to handling heavy loads. Phase II of NUREG-

0612 concerned itself with plant specific analyses to ensure that

the potential for load drop was extremely small or if there was a

load drop no significant impact to spent fuel, the reactor vessel

or safe shutdown equipment would occur. The NRC issued a safety

evaluation report concerning Peach Bottom compliance to NUREG-0612

Phase I on 9/21/83. Peach Bottom submitted its intent concerning

compliance with Phase II. However, prior to NRC issuance of a

final SER for Peach Bottom, the NRC discontinued its review of

Phase II submittals. In Generic Letter 85-11, dated 6/28/85, the

NRC reported to the industry that due to their reviews of Phase I

activities and proposed Phase II activities, there did not warrant

a need to take further action on Phase II. The Peach Bottom

response to this generic letter on 2/11/86 stated that changes to

Phase II actions would be considered on a case-by-case basis.

Lifts are conducted in accordance with good rigging practices and

in accordance with the licensee's approved procedures.

10.4.11.1 NUREG-0612 Phase I Requirements All heavy loads that could be brought over or in proximity to

irradiated fuel, the reactor vessel or safe shutdown equipment are

handled in accordance with a defense in depth philosophy. The

following seven criteria ensure appropriate handling of heavy

loads is in place.

1. Safe Load Paths Safe Load Paths (SLP's) are established for the movement of heavy

loads to minimize the potential for heavy loads, if dropped, to

impact irradiated fuel in the reactor or spent fuel pool, or to

impact safe shutdown equipment required to be operable. These

load paths are controlled under approved design documents. Design

documents and procedures also control rigging exclusion zones and

height/weight restrictions. Administrative procedures require

that the cognizant supervisor review safe load paths prior to the

lift. Any deviations from designated SLP's must be approved by

engineering.

Concerning the Emergency Diesel Generator (EDG) Cranes, heavy

loads lifts may only be performed when the EDG is inoperable or

declared inoperable for purposes of heavy load lifts.

Load movements along the safe load paths are directed by a

qualified signalman.

2. Load Handling Procedures

CHAPTER 10 10.4-11 REV. 26, APRIL 2017 Load handling procedures are in place for the handling of heavy loads over or in proximity to reactor fuel or safe shutdown

equipment. A governing administrative procedure defines the

overall requirements to perform these lifting operations including

the NUREG-0612 Phase I requirements. Implementing procedure(s)

ensure that appropriate details of complicated lifts are defined.

As appropriate, the above procedures direct the identification of

required equipment, inspections and acceptance criteria required

before moving the load, the steps and proper sequence to be

followed in handling the load, definition and use of appropriate

safe load paths and require that Phase I requirements are met for

heavy load operations.

3. Crane Operator Training

For lifts performed within the scope of the heavy loads program, crane operators will be trained, qualified and conduct themselves

in accordance with Chapter 2-3 of ANSI B30.2-1976, 'Overhead and

Gantry Cranes'.

4. Special Lifting Devices

Special Lifting Devices used in areas where a load is carried over

or in proximity to the reactor vessel, spent fuel pool, or safe

shutdown equipment meet the requirements of ANSI N14.6-1978 with

the following exceptions:

a.Inspections shall be performed at least once per

operating cycle rather than annually.

b.Critical welds may be non-destructively examined in lieu

of the routine 150% load test

c.Dry fuel storage cask trunnions are waved from the

periodic load test or examination requirements.

d.The drywell strongback has two steel features that were

added during modifications that did not receive the

required materials testing (Charpy impact or drop weight

testing). (Ref. ECR 13-00378).

e. The RPV head carousel hook and load pins did not receive the required materials testing (Charpy impact or drop

weight testing) (Ref. ECR 13-00378).

The stress design factor stated in section 3.2.1.1 of ANSI N14.6-

1978 is based on the combined maximum static and dynamic loads

that could be imparted on the handling device based on the

characteristics of the crane which will be used. Devices used for

CHAPTER 10 10.4-12 REV. 26, APRIL 2017 handling the spent fuel cask/lid are designed to ANSI N14.6 - 1986 which is equivalent to or exceeds the 1978 version.

5. Lifting Devices (not specifically designed)

Procedures are in place which require that all lifting devices not

specifically designed (i.e., slings) that are used to lift heavy

loads over or in proximity to the reactor vessel, spent fuel pool

or safe shutdown equipment meet the requirements of ANSI B30.9-

1971, 'Slings' or Twin-Path Extra TPXC Synthetic Round Slings

constructed with K-Spec fiber meeting the requirements of ASME

B30.9-2010, used in combination with engineered softeners and

abrasion protection devices as required by station procedures.

Additionally, a dynamic load factor of 25% of the dead load will

be used in selecting the sling.

6. Cranes (Inspection, testing and maintenance)

Procedures are in place which ensure that crane inspection, testing and maintenance is performed in accordance with ANSI B30.2

(1967 version), 'Overhead and Gantry Cranes'. Additionally, if

repairs of load sustaining members are made by welding, identification of materials shall be made and appropriate welding

procedures will be followed.

7. Crane Design

The Reactor Bldg, Turbine Bldg, Pump Structure, and EDG Cranes

meet the intent of the requirements of Chapter 2-1 of ANSI B30.2-

1976, 'Overhead and Gantry Cranes' and of CMAA-70, 'Specifications

for Electric Overhead Traveling Cranes'. Turbine Building Cranes

are upgraded to meet single failure proof requirements of NUREG-

0554 for the increased main and auxiliary hoist capacities of 115

Ton and 30 Ton respectively. Structural analyses are performed

using commercially available, NRC-approved computer programs.

Concrete anchor bolts are analyzed per American Concrete Institute (ACI) Code 349-01, approved by the NRC for this purpose.

10.4.11.2 NUREG-0612 Phase II Requirements

Heavy load lifts made by permanent station cranes and hoists, as

well as by mobile cranes and temporary rigging, are performed in a

manner to minimize the threat to irradiated fuel, the reactor

vessel or safe shutdown equipment. This necessitates that the

following three criteria of NUREG-0612, Phase II are met, except

for alternatives which may be approved on a case-by-case basis in

accordance with station procedures:

1.The lift is performed as single failure-proof equivalent (either using redundant rigging or increased safety factors)

or,

CHAPTER 10 10.4-13 REV. 26, APRIL 2017 2.The lifting system has electrical interlocks or mechanical stops such that loads could not be handled over or in

proximity to fuel, the reactor vessel, or safe shutdown

equipment or, 3.An evaluation is performed that ensures that a load drop

could not cause damage to fuel, the reactor vessel, or loss

of a safe shutdown function.

10.4.11.3 Safety Evaluation

Heavy load lifts are performed using a defense-in-depth program

such that no credible load drop will endanger the public safety

and health. The procedural controls that implement NUREG-0612

Phase I make the risk of a load drop very unlikely. In addition, single-failure-proof lifts are employed to further reduce the risk

of load drop to an acceptably low level. Where single-failure-

proof lifts are not used, the consequences of a postulated load

drop are evaluated, and must be demonstrated to be acceptable.

Resulting restrictions on load height, weight, lift configuration, and/or equipment required to be operable are procedurally

controlled.

CHAPTER 10 10.5-1 REV. 26, APRIL 2017 10.5 FUEL POOL COOLING AND CLEANUP SYSTEM 10.5.1 Power Generation Objective The power generation objectives of the fuel pool cooling and cleanup system are to provide fuel pool water temperature control

and to maintain fuel pool water clarity, purity, and level.

10.5.2 Power Generation Design Basis

1. The fuel pool cooling and cleanup system minimizes corrosion product buildup and controls water clarity

through filtration and demineralization.

2. The fuel pool cooling and cleanup system minimizes fission product concentrations which could be released

from the pool water to the reactor building environment.

3. The fuel pool cooling and cleanup system monitors fuel pool water level and maintains a water level above the

fuel sufficient to provide shielding for normal building

occupancy.

4. The fuel pool cooling and cleanup system limits the fuel pool water temperature during normal and refueling

operations.

10.5.3 Description The fuel pool cooling and cleanup system cools the fuel storage

pool by transferring decay heat through heat exchangers to the

service water system (Drawing M-363, Sheets 1 and 2). Water

purity and clarity in the storage pool, reactor well, and dryer-

separator storage pit are maintained by filtering and

demineralizing the pool water (Drawing M-364, Sheets 1 and 2).

See paragraph 10.3.4.2 for the description of the spent fuel pool.

Connections also exist to use the "B" filter-demineralizer to

process liquid radwaste, as shown on Drawing M-363, Sheet 1.

The system consists of three fuel pool cooling pumps, three heat

exchangers, filter-demineralizer(s), two skimmer surge tanks, and

associated piping, valves, and instrumentation. The three fuel

pool pumps are connected in parallel, as are the three heat

exchangers. The pumps and heat exchangers are located in the

reactor building below the bottom of the fuel pool.

The filter-demineralizers, which collect radioactive corrosion

products, are located in the radwaste building and are typically

arranged so that one filter-demineralizer is aligned to each

reactor unit and the third is a spare. Up to three filter-

CHAPTER 10 10.5-2 REV. 26, APRIL 2017 demineralizers may be aligned to one unit to support water clarity and water chemistry improvements, as required.

The pumps circulate the pool water in a closed loop, taking

suction from the skimmer surge tanks through the heat exchangers, circulating the water through the filter demineralizer, and

directing the processed spent fuel cooling water through the

system discharge lines located in the fuel pool and reactor well.

This return flow of spent fuel cooling water is discharged

downward from the discharge lines into the pool at an elevation

that is above the top of the storage racks. The cooled water

traverses the pool picking up heat and debris before starting a

new cycle by discharging over the skimmer weirs and scuppers into

the skimmer surge tanks. Makeup water for the system can be

transferred from the condensate storage tank to the skimmer surge

tanks. System and equipment parameters are listed in Table

10.5.1.

An evaluation of the fuel pool cooling system was performed for normal refueling of approximately 40% (320 bundles) of the core

every 24 months and a full core offload just before normal

refueling assuming all storage cells in the spent fuel pool are

filled. The evaluations assume that the offloaded fuel has

operated in the reactor at 3951 MW. For the normal refueling

offload of 40% of the core, the evaluation assumes a normal

complement of three fuel pool cooling trains (three fuel pool

cooling pumps and three fuel pool cooling heat exchangers) in

service as well as a single failure where only two fuel pool

cooling trains (two fuel pool cooling pumps and two fuel pool

cooling heat exchangers are in service). For the full core

offload case, no fuel pool cooling trains are assumed available

and fuel pool cooling is performed by the RHR system. The

evaluation also considered the time for the fuel pool to boil if

there is a loss of fuel pool cooling. See Table 10.5.2 for a

summary of the results of these cooling system evaluations.

When flooded up, the Fuel Pool Cooling system and the RHR fuel

pool assist mode can be used to remove decay heat from both the

spent fuel pool and the reactor vessel by cooling the spent fuel

pool. A cross-connection between the drain line from the skimmer

surge tank and the RHR system allows the RHR system to take a

suction from the fuel pool. This is called Fuel Pool Assist mode, when water is returned to the fuel pool and called Alternate Decay

Heat Removal (ADHR) mode when water is returned to the reactor

vessel through the normal shutdown cooling return line. In

addition, a Split Flow mode is available when the RHR discharge

flow is split between the fuel pool and the reactor vessel.

During ISFSI operation, it may be necessary to return a loaded dry

storage cask to one of the Spent Fuel pools for unloading. The

CHAPTER 10 10.5-3 REV. 26, APRIL 2017 heat introduced to the pool by the latent heat of the cask materials and the decay heat of the 68 contained assemblies is

less that the full core offload heat that the Fuel Pool Cooling

and Cleanup System has been analyzed for.

Since each refueling offload is cycle specific, then the

variations in the number of fuel assemblies discharged, the in-

core decay time, the fuel assembly transfer rate and the power

history can vary as long as analysis shows that the spent fuel pool bulk temperature will not exceed 150 F and localized boiling will not be expected to occur.

The system flow rate is larger than that required for two complete

water changes per day of the fuel pool, or one change per day of

the fuel pool, reactor well, and dryer-separator pit. The maximum

system flow rate is twice the flow rate needed to maintain water

quality.

For refueling operations, water to fill the reactor well and

dryer-separator storage pit is stored in the refueling water tank.

Water is transferred to the refueling area by two refueling water

pumps and/or via the CST and core spray system. During drainage, water can be pumped through one of the condensate filter-

demineralizer units before being returned to the storage tank.

When placing a dry fuel storage cask into the fuel pool, the water

level of the pool is managed by controlling the skimmer surge tank

level and the fuel pool level as needed. Procedures ensure that a

new cask is inspected and cleaned as necessary prior to placement

in the pool.

Fuel pool water is continuously recirculated. The circulation

patterns within the reactor well and fuel pool are established by

the placement of the diffusers in the reactor well and the

placement of skimmers and discharge lines in the fuel pool so as

to sweep particles dislodged during refueling operations away from

the work area and out of the pools.

Pool water clarity and purity are maintained by a combination of

filtration and ion exchange. The filter-demineralizer units are

located separately in shielded cells. The filter-demineralizer

maintains the Fuel Pool water quality to within the limits

specified in EPRI BWR Water Chemistry Guidelines for compatibility

with materials and equipment in the fuel pool that require

corrosion protection. Particulate matter is removed by the

filter-demineralizer unit in which finely divided, powdered ion-

exchange resin and fiber material serves as the filtering medium.

Alternately, a combination of powdered resin and cellulose may be

used as the disposable filter medium. The filter elements are a

CHAPTER 10 10.5-4 REV. 26, APRIL 2017 stainless steel mesh element mounted vertically in a tube sheet and replaceable as a unit. The filter vessel is constructed of

carbon steel and coated with a phenolic material. The resin is

replaced when the pressure drop across the filter is excessive or

when instrumentation indicates the ion exchange capacity is low.

Alarms, differential pressure indicators, and flow indicators

monitor the condition of the filter-demineralizers. Backwashing

and precoating operations are controlled from a local panel in the

radwaste building. The spent filter medium is removed from the

elements by backwashing with air and condensate, then flushed to

the waste sludge tank.

There are no connections to the fuel storage pool which could

allow the fuel pool to be drained below the pool gate between the

reactor well and the fuel pool when the pool gate is in place or

below 10 feet above the top of active fuel. Fuel pool cooling and

RHR discharge lines that extend below this level are equipped with

syphon breaker holes to prevent inadvertent pool drainage. A level

indicator, mounted at the valve rack, monitors reactor well water

level during refueling. Any significant leakage through the

refueling bellows assembly, drywell to reactor seal, or the fuel

pool gates is annunciated on the operating floor instrument racks

and in the main control room.

Instrumentation is provided for both automatic and manual

operation. The surge tanks have high and low level alarms and

pump trip switches. The pumps are controlled locally at the pump

or from a control panel near the filter-demineralizers. Pump low

suction pressure automatically turns off the pumps. A pump low

discharge pressure causes alarm annunciation in the main control

room and in the pump room. Also see paragraph 10.3.4.3 for spent

fuel pool instrumentation.

10.5.4 Inspection and Testing

No special equipment tests are required because at least one pump, heat exchanger, and filter-demineralizer are normally in

operation while fuel is stored in the pool.

Routine visual inspection of the system components, instrumentation, and trouble alarms is adequate to verify system

operability. Pool level indicators and associated alarms are

tested by simulating low water level to the sensors.

CHAPTER 10 10.5-5 REV. 25, APRIL 2015 TABLE 10.5.1 FUEL POOL COOLING AND CLEANUP SYSTEM

Design Core Thermal Power 4,030 MWt Total Pool, Well, and Pit Volume 111,400 cu ft Fuel Storage Pool Volume 53,350 cu ft System Design Flow 555 gpm Maximum Flow 1,665 gpm

Fuel Pool Cooling Water Pumps Quantity 3 Type

Horizontal, centrifugal

Design Flow/TDH (each) 580 gpm/250 ft Motor hp 60 hp

Fuel Pool Cooling Heat Exchangers Quantity 3 Heat Exchanger Capability

One exchanger in service

= 3.75 x 10 6 Btu/hr Two exchangers in service

= 7.50 x 10 6 Btu/hr Three exchangers in service

=11.25 x 10 6 Btu/hr Material Tube/Shell 304 SS/carbon steel Design Code ASME B&PV, Sec. VIII

CHAPTER 10 10.5-6 REV. 25, APRIL 2015 TABLE 10.5.1 (Continued)

Fuel Pool Filter-Demineralizers

Type Pressure precoat

Quantity 1 per unit, 1 common spare Design Filter Area 270 sq ft

Filter Capacity 550 gpm/unit

Pressure Drop 25 psi (dirty)

Design Code ASME & B&PV, Sec.

VIII

Holding Pump Flow 27 gpm Precoat Flow 450 gpm Flow Control Valve Pressure Drop 100 psi (max)

10 psi (min)

CHAPTER 10 10.5-7 REV. 25, APRIL 2015 TABLE 10.5.2

SUMMARY

OF COOLING SYSTEM ANALYSIS RESULTS

1) Heat Exchanger Capability

One exchanger in service = 3.75 x 10 6 Btu/hr Two exchangers in service = 7.50 x 10 6 Btu/hr Three exchangers in service = 11.25 x 10 6 Btu/hr

2) Maximum Pool Heat Load to insure exit temperature is below 150 F One exchanger in service = 8.66 x 10 6 Btu/hr Two exchangers in service = 17.33 x 10 6 Btu/hr Three exchangers in service = 26.0 x 10 6 Btu/hr
3) Normal Refueling a)Full Cooling Capability Equipment in service:

3 FPCCS Pumps (1665 gpm total SFP flow) 3 FPCCS Heat Exchangers (2400 gpm total service water flow, 90 o F service water temperature) Start of Offload (hours after shutdown): 80 Max. SFP Temperature: 140 o F Time to Boil from Max. Temperature: 11.4 hrs Makeup Flow Required at Boiling: 49 gpm Max Heat Load (MBTU/hr): 23.9 b)Single Failure Equipment in service:

2 FPCCS Pumps (1110 gpm total SFP flow) 2 FPCCS Heat Exchangers (1600 gpm total service water flow, 90 o F service water temperature) Start of Offload (hours after shutdown): 200 Max. SFP Temperature: 150 o F Time to Boil from Max. Temperature: 12.3 hrs Makeup Flow Required at Boiling: 40 gpm Max Heat Load (MBTU/hr): 19.5 TABLE 10.5.2 (continued)

CHAPTER 10 10.5-8 REV. 25, APRIL 2015

4) Full-Core Offload, Full Cooling Capability Equipment in service:

1 RHR Pump (5000 gpm total SFP flow) 1 RHR Heat Exchanger (4500 gpm total HPSW flow, 92 o F HPSW water temperature) Start of Offload (hours after shutdown): 150 Max. SFP Temperature: 140 o F Time to Boil from Max. Temperature: 6.0 hrs Makeup Flow Required at Boiling: 88 gpm Max Heat Load (MBTU/hr): 41.3

CHAPTER 10 10.6-1 REV. 21, APRIL 2007 10.6 SERVICE WATER SYSTEM 10.6.1 Power Generation Objective

The power generation objective of the service water system is to

supply water required for plant services.

10.6.2 Power Generation Design Basis

1. The service water system continuously supplies screened and chlorinated cooling water to the plant during normal

plant operation and shutdown periods.

2. System interconnections are provided to enable the emergency service water system to serve the reactor

building cooling water heat exchangers in the event of a

loss of off-site power. This design feature exists

although the heat sink, emergency service water (ESW),

for the reactor building closed cooling water (RBCCW)

system has been eliminated as a result of locking closed

the ESW-RBCCW cross-tie valves. Therefore, little, if

any, cooling would be provided to the service water

system loads during a loss of off-site power.

3. The service water system supplies cooling water to the core standby cooling equipment and space coolers during

normal plant operation and shutdown period only.

4. The system inhibits the release of radioactive material into the river.

10.6.3 Description

The service water system consists of three one-half capacity

service water pumps in the pump structure, three horizontal fuel

pool service water booster pumps in the reactor building, and

associated piping, valves, and instrumentation (Drawing M-314, Sheets 1 through 9).

The three service water pumps are vertical, turbine-type pumps, connected in parallel, taking suction from the pump structure, and

each delivering 14,000 gpm at a pump head of 155 ft. The pump

bearings are supplied from lube water pumps. Nominal system

pressure is 65 psig. The three fuel pool service water booster

pumps deliver service water to the fuel pool cooling heat

exchangers. These horizontal, centrifugal pumps are rated at 900

gpm at a pump head of 135 ft.

The safeguards equipment coolers and space air cooler are

automatically served by the emergency service water system.

CHAPTER 10 10.6-2 REV. 21, APRIL 2007 To inhibit leakage of radioactivity from potentially contaminated

systems (mechanical vacuum pump and fuel pool heat exchangers),

service water pressure is maintained higher than process fluid

pressure. A radiation monitor on the service water effluent

header from the reactor building cooling water heat exchangers

detects leakage of radioactive material from these exchangers. The

monitor indicates, records, and alarms in the main control room.

10.6.4 Inspection and Testing

The service water system components are proven operable by their

use during normal plant operations. Portions of the system

normally closed to flow can be tested to ensure their operability

and the integrity of the system.

CHAPTER 10 10.6-3 REV. 21, APRIL 2007 TABLE 10.6.1 SERVICE WATER SYSTEM DATA

Service Water Pumps

Quantity 3

Type Vertical, Turbine Type, Wet-Pit

Flow/Pump Head 14,000 gpm/155 ft

Bhp Rating 655 hp Speed 900 rpm

Motor Type Vertical, Induction Type

Voltage/Phase/Frequency 2,300 V/3 phase/60 Hz

Rated Horsepower 700 hp

Fuel Pool Service Water Booster Pumps

Quantity 3

Type Horizontal Centrifugal

Flow/Pump Head 900 gpm/135 ft

Bhp Rating 39 hp Speed 3,600 rpm

Motor Type Horizontal

Voltage/Phase/Frequency 460 V/3 phase/60 Hz

Rated Horsepower 40 hp

CHAPTER 10 10.7-1 REV. 26, APRIL 2017 10.7 HIGH PRESSURE SERVICE WATER SYSTEM 10.7.1 Safety Objective

The safety objective of the high pressure service water system is

to provide a reliable supply of cooling water for RHR under post-

accident conditions.

10.7.2 Safety Design Basis

1. The high pressure service water system is designed to seismic Class I criteria to withstand the maximum

credible earthquake without impairing system function.

2. The high pressure service water system is operable during flood conditions.
3. The high pressure service water system is designed with capacity and redundancy to supply cooling water to the

RHRS under post-accident conditions.

4. The high pressure service water system is operable during the loss of offsite power.

10.7.3 Power Generation Objective

The power generation objective of the high pressure service water

system is to supply cooling water to the RHRS for shutdown cooling

and for torus cooling.

10.7.4 Power Generation Design Basis

1. The high pressure service water system supplies a

reliable source of cooling water to the RHRS.

2. The high pressure service water system is designed for

remote-manual initiation.

3. The high pressure service water system inhibits leakage

of radioactive material from the RHRS to the environment.

4. The high pressure service water system provides an

additional source of water for post-accident containment flooding

by a cross tie between the high pressure service water system and

the RHRS.

10.7.5 Description Each high pressure service water system consists of four 4,500-gpm pumps installed in parallel in the pump structure (Drawing

CHAPTER 10 10.7-2 REV. 26, APRIL 2017 M-315, Sheets 1 through 4). Normal water supply to the suction of the pumps is from Conowingo Pond. When the high pressure service

water system is operated in conjunction with the emergency heat

sink (subsection 10.24, "Emergency Heat Sink"), the suction is

from the HPSW pump bay which is fed from emergency cooling tower

basin. The pump discharge is manifolded and provided with a

normally closed, motor-operated valve separating the four pumps

into groups of two. Two parallel headers run from the pump

structure to the reactor building. Each header delivers the

discharge from two pumps to two RHR heat exchangers also in

parallel. Under normal conditions, when the respective loop of

HPSW is in operation, the service water pressure on the discharge

side of the RHR heat exchanger is maintained positive with respect

to the RHRS side to inhibit leakage of radioactive material into

the environment. In the event of a design basis accident or

transient in which additional containment cooling capacity is required, a second HPSW pump can be aligned to a second RHR heat

exchanger by opening the cross-tie valve.

Under abnormal operating conditions RHRS pressure could exceed

high pressure service water system pressure. An RHR heat

exchanger leak under these abnormal conditions would result in

radioactive RHR water migrating into the high pressure service

water system and into the river. To limit the release of

radioactive water to the river from this potential release path, signals from the radiation monitors in the sample system which

samples the high pressure service water system upstream and

downstream of the RHR heat exchangers initiate an alarm in the

control room at a predetermined radiation level.

Flanged connection points are available on the high pressure

service water system, downstream of the RHR heat exchangers, to

allow for a temporary flow path of the RHR heat exchanger cooling

water in the event that the normal flow path becomes unavailable.

This alternative flow path is intended to be routed through

secondary containment. Therefore, this flow path may only be used

when secondary containment is not required.

An intertie is provided between units 2 and 3 high pressure

service water system to provide flexibility. A cross tie to the

RHRS provides the capability for primary containment flooding.

The high pressure service water system pumps are vertical

multistage turbine type. The pump mounting base is of watertight

construction to withstand the hydrostatic pressure at the design

flood condition. The pump design data is given in Table 10.7.1.

The high pressure service water system piping and valves are

designed as described in Appendix A.

CHAPTER 10 10.7-3 REV. 26, APRIL 2017 10.7.6 Safety Evaluation

The high pressure service water system pumps are installed in a

seismic Class I structure. The system meets seismic Class I

criteria and is protected against the design flood level.

Each pump is sized to accommodate the design heat removal capacity

of one RHRS heat exchanger. They have adequate head (1) to

maintain the high pressure service water system cooling water at a

higher pressure than the RHRS, thus inhibiting the release of

radioactive material to the environment, and (2) to permit

operation in conjunction with the emergency heat sink. Further, the pumps have both a normal and a standby power supply. In the

event of the loss of offsite power, the pumps are supplied from

the diesel generators and manually started as required.

Sufficient redundancy is provided in the number of pumps and power

supplies, and in the piping arrangement, so that no single system

component failure can prevent the system from supplying cooling

water to accommodate the normal shutdown mode and the containment

cooling mode. Therefore, core decay heat removal during the

shutdown periods, or containment cooling during the post-accident

condition, can be maintained.

10.7.7 Inspection and Testing

Pumps in the high pressure service water system are proven

operable by their use or testing during normal station operations.

Motor operated isolation valves can be tested to assure they are

capable of opening and closing by operating manual switches in the

control room and observing the position lights. Portions of the

high pressure service water system normally closed to flow can be

tested to ensure their operability and the integrity of the

system.

CHAPTER 10 10.7-4 REV. 23, APRIL 2011 TABLE 10.7.1 HIGH PRESSURE SERVICE WATER SYSTEM

EQUIPMENT DATA

High Pressure Service Water Pumps

Quantity 4 Per Unit

Type Vertical, Turbine Type

Flow/Head Design Point 4,500 gpm at 700 ft

Bhp at Rating

< 975 hp Speed 1,770 rpm Number of Stages 6

Pump Design:

Shut-Off Head

> 368 and < 445 psig

Material:

Bowl/Impeller Cast Carbon Steel or Moly Iron/Bronze or Cast Stainless Steel Discharged Head/Column Carbon Steel/Carbon Steel

Line Shaft Stainless Steel

Bearings Brass/Bronze/Rubber

Motor:

Type Vertical, Induction

Horsepower 1,000 hp Voltage/Phase/Frequency 4,160 V/3 Phase/60 Hz

CHAPTER 10 10.8-1 REV. 21, APRIL 2007 10.8 REACTOR BUILDING COOLING WATER SYSTEM 10.8.1 Power Generation Objective

The power generative objective of the reactor building cooling

water system is to provide cooling water to auxiliary plant

equipment associated with the nuclear steam supply system (NSSS).

10.8.2 Power Generation Design Basis

1. The reactor building cooling water system is designed to cool auxiliary plant equipment over the full range of

reactor power operation.

2. The reactor building cooling water system is designed to inhibit the release of radioactive material to the

environment.

10.8.3 Description

The reactor building cooling water system consists of two full-

capacity pumps, two full-capacity heat exchangers, one head tank, one chemical feed tank, and associated piping, valves, and

controls (Drawing M-316). The cooling water pumps and heat

exchangers are located in the reactor building auxiliary bay. The

head tank is located on the reactor building refueling floor. The

system equipment data is given in Table 10.8.1.

The system is a closed loop utilizing inhibited demineralized

water. The heat exchangers are designed with service (river)

water on the tube side and demineralized water on the shell side.

The reactor building cooling water system is designed for an

operating pressure of 140 psig.

The head tank, located at the highest point in the loop, accommodates system volume changes, maintains static suction

pressure on the pump, aids in detecting gross leaks in the reactor

building cooling water system, and provides for adding makeup

water. An automatic makeup control valve maintains water level in

the tank. The automatic function is not required and may be

valved out to monitor system inventory. High and low water levels

are alarmed in the main control room. An inhibitor is added as

necessary to the demineralized water by means of a chemical

addition tank to limit corrosion.

The reactor building cooling water system supply and return

headers penetrating the primary containment are each provided with

a motor-operated isolation valve outside the containment. These

isolation valves are manually controlled remotely from the main

control room.

CHAPTER 10 10.8-2 REV. 21, APRIL 2007 Electrical power for operating the reactor building cooling water

system pumps during failure of offsite power is supplied from the

standby power supply.

In the event of offsite power failure, the reactor building

cooling water system supply to the reactor water cleanup system

non-regenerative heat exchanger and pumps, instrument nitrogen

compressor skids, and various sample station coolers is isolated, and the water supply is maintained to the reactor recirculation

pump motor oil and mechanical seal water coolers and the reactor

building equipment drain sump cooler. In addition, water is

supplied to the drywell air cooling system and the drywell

equipment drain sump cooler, which are normally served by the

chilled water system, and to the CRD pump oil coolers and air

compressor jacket and after coolers, which are normally served by

the turbine building cooling water system.

The reactor building cooling water system can also supply water to

the fuel pool cooling heat exchangers, via removable spool pieces, in the event of loss of normal cooling water. The control and

instrumentation is designed for remote system startup from the

main control room.

These design features do exist although the heat sink, emergency

service water (ESW), for the reactor building closed cooling water (RBCCW) system has been eliminated as a result of locking closed

the ESW-RBCCW cross tie valves. These valves were locked closed because of the lack of required structural design of the piping, and due to the adverse hydraulic effects to safety related

components served by ESW. Therefore, the cooling effect of the

RBCCW system to any of the components described above will be

minimal.

A radiation monitor is provided at the cooling water return header

to indicate, record, and alarm leakage of radioactivity.

10.8.4 Inspection and Testing

Equipment in the reactor building cooling water system is proven

operable by use during normal plant operations. Motor operated

isolation valves can be tested to assure they are capable of

opening and closing by operating manual switches in the control

room and observing the position lights. Portions of the reactor

building cooling water system normally closed to flow can be

tested to ensure their operability and the integrity of the

system.

CHAPTER 10 10.8-3 REV. 21, APRIL 2007 TABLE 10.8.1 REACTOR BUILDING COOLING WATER SYSTEM

EQUIPMENT DATA

Reactor Building Cooling

Water System Pumps 2 (full-capacity)

Type Horizontal Centrifugal

Flow and Head 1,350 gpm at 140 ft

Bhp at Rating 65 hp Material:

Casing/Impeller/Shaft Cast Iron/Bronze/Stainless Steel Motor: Size 75 hp Voltage/Phase/Frequency 440 V/3 Phase/60 Hz

Speed 3,600 rpm

Reactor Building Cooling

Water System Heat Exchangers

Quantity 2 (full-capacity)

Type Horizontal, Shell and Tube

Heat Transfer Duty 25,500,000 Btu/hr

Shell Design:

Pressure/Temperature 150 psig/200 F Material Carbon steel

Flow Medium Inhibited Demineralized Water Tube design:

Pressure/Temperature 125 psig/200 F Material:

Tube Admiralty

Tube Sheet Carbon Steel

Tube Joint Rolled Flow Medium River Water

CHAPTER 10 10.9-1 REV. 21, APRIL 2007 10.9 EMERGENCY SERVICE WATER SYSTEM 10.9.1 Safety Objective

The safety objective of the emergency service water system is to

provide a reliable supply of cooling water to diesel generator

coolers, ECCS and RCIC compartment air coolers, Core Spray Pump

Motor Oil Coolers and other selected equipment during a loss of

offsite power or during a loss of normal station service water due

to the design flood condition or the loss of the Conowingo pond.

10.9.2 Safety Design Basis

1. The emergency service water system is designed to seismic Class I criteria.
2. The emergency service water system is operable during the design flood condition and loss of Conowingo pond.
3. The emergency service water system has sufficient capacity and redundancy so that no single active

component failure can prevent the system from achieving

its safety objective.

4. The emergency service water system is operable during the loss of offsite power.

10.9.3 Description

The emergency service water system is common to both Units 2 and

3. The system consists of two full-capacity pumps installed in

parallel in the seismic Class I portion of the pump structure, and

associated equipment coolers, valves, and controls (Drawing M-

315). Normal water supply to the suction of the emergency service

water system pumps is from Conowingo Pond. The pump discharge

piping consists of two headers with service loops to ensure water

supply to the diesel engine coolers. These two headers combine, forming a common header, to supply selected equipment coolers.

Valves in the supply headers provide loop isolation. A common

discharge header routes the system effluent normally to the pond.

The emergency service water system pumps are vertical, single-

stage, turbine type with an 8,000 gpm capacity developing a normal

average system pressure of 40 psig and a normal system flow of

approximately 4500 gpm. The pump mounting base is of watertight

construction to withstand hydrostatic pressure at the maximum

design flood condition. The pump design data is given in Table

10.9.1.

The emergency service water system is a standby system to provide

adequate cooling water supply to the emergency equipment coolers

CHAPTER 10 10.9-2 REV. 21, APRIL 2007 and compartment air coolers during a loss of offsite power or during a loss of normal station service water due to the design

flood condition or the loss of the Conowingo pond. During normal

plant operating conditions, the cooling water supply to the

equipment served by the emergency service water system, except the

diesel generator coolers, is normally provided from the

service water system. This allows testing of safeguards equipment

using service water without starting the emergency service water

system pumps.

Chemical injection and corrosion monitoring systems are installed

to mitigate corrosion damage to emergency service water system

piping.

The emergency service water system may also be operated in

conjunction with the emergency heat sink (subsection 10.24). This

configuration (closed loop) is the preferred system alignment

during the design flood condition and loss of Conowingo pond.

Both emergency service water pumps start after a 36 second time

delay whenever 4 kV power is available (following the loss of

offsite power or a diesel generator start). One of the emergency

service water system pumps is manually shut off if both pumps are

running and emergency service water system pressure is verified to

be adequate. All system supervisory instrumentation and controls

are located in the main control room.

The emergency service water system piping and valves are designed

as described in Appendix A.

10.9.4 Safety Evaluation

The emergency service water system pumps are installed in a

seismic Class I structure. The system meets seismic Class I

criteria, and the pumps are further protected against the design

flood level using watertight construction. The emergency service

water system is designed with redundant pumps and piping. Each

loop is powered from a separate division of both normal and

standby power. Therefore, the system is both redundant and single

failure proof and is operable in the event of a loss of offsite

power.

10.9.5 Inspection and Testing

The cooling of equipment served by the emergency service water

system, except the standby diesel generator coolers, is

functionally tested using the plant service water system. Pump

operation and diesel generator cooling capability is verified when

operability of the diesel generators is tested. Motor operated

CHAPTER 10 10.9-3 REV. 21, APRIL 2007 valves can be exercised to confirm operability. Emergency service water system operability is verified by flow and heat transfer

testing. Emergency service water system piping integrity is

verified by visual and ultrasonic inspection and corrosion

monitoring.

Emergency service water pump performance is verified in accordance

with ASME Code requirements. Cooling equipment minimum flows are

verified by magnetic or ultrasonic flow measurement devices.

The timer used to sequence the emergency service water pump during

a LOCA is tested (with offsite power available) in accordance with

surveillance test procedures. The test verifies the setting, operability, and functional performance of the relay, and provides

assurance that the automatic loading sequence is being maintained

and performs as required.

CHAPTER 10 10.9-4 REV. 21, APRIL 2007 TABLE 10.9.1 EMERGENCY SERVICE WATER SYSTEM EQUIPMENT DATA

Emergency Service Water System Pumps*

Quantity 2 (common for Units 2 and 3)

Type Vertical, Turbine Type

Flow/Head 8,000 gpm/96 ft

Bhp at Rating 237 hp Speed 1,170 rpm Number of Stages 1

Pump Design:

Shutoff Head 132 ft Maximum Working Pressure 200 psig

Material: Moly Iron

Bowl/Impeller Cast Iron/Bronze

Discharge Head/Column Carbon Steel/Carbon Steel

Line Shaft Stainless Steel

Bearings Rubber Motor Design:

Type Vertical Induction Type

Horsepower 250 hp Voltage/Phase/Frequency 4,160 V/3 Phase/60 Hz

  • Emergency cooling water pump and motor are identical except

for the pump column length.

CHAPTER 10 10.10-1 REV. 21, APRIL 2007 10.10 TURBINE BUILDING COOLING WATER SYSTEM 10.10.1 Power Generation Objective

The power generation objective of the turbine building cooling

water system is to provide cooling water to auxiliary plant

equipment associated with the power conversion systems.

10.10.2 Power Generation Design Basis

The turbine building cooling water system is designed to cool non-

nuclear auxiliary plant equipment over the full range of plant

operation.

10.10.3 Description

The system consists of two full-capacity pumps, two full-capacity

heat exchangers (system design does allow use of both heat

exchangers if necessary due to high river temperatures or other

limiting operating conditions), one head tank, one chemical feed

tank, and associated piping, valves, and controls (Drawing M-316, Sheets 1 to 4). The cooling water pumps and heat exchangers are

located on the turbine building ground floor. The system design

data is given in Table 10.10.1.

The system is a closed loop utilizing inhibited demineralized

water. The heat exchangers are designed with service (river)

water on the tube side and demineralized water on the shell side.

The head tank, located at the highest point in the loop, accommodates system volume changes, maintains static suction

pressure on the pumps, aids in detecting gross leaks in the

turbine building cooling water system, and provides a means for

adding makeup water. An automatic makeup control valve maintains

water level in the tank. The automatic function is not required

and may be valved out to monitor system inventory. High and low

water levels are alarmed in the main control room. An inhibitor

is added as necessary to the demineralized water by means of a

chemical addition tank to limit corrosion.

In the event of offsite power failure, the turbine building

cooling water system is not operated. Under loss of offsite

power, the water supply to the instrument and service air

compressor skids, CRD pump lube oil coolers and the thrust bearing

housings is maintained from the reactor building cooling water

system. This design feature still exists although the heat sink, emergency service water (ESW), for the reactor building closed

cooling water (RBCCW) system has been eliminated as a result of

locking closed the ESW cross tie valves.

CHAPTER 10 10.10-2 REV. 21, APRIL 2007 Therefore, little, if any, cooling would be provided by the reactor building cooling water system during a loss of offsite

power.

10.10.4 Inspection and Testing

Equipment in the turbine building cooling water system is proven

operable by use during normal plant operations. Transfer valves

in the system can be tested to ensure that they are capable of

transferring the water supply of essential equipment from the

turbine building cooling water system to the reactor building

cooling water system on loss of offsite power. This design

feature still exists although the heat sink, emergency service

water (ESW), for the reactor building closed cooling water (RBCCW)

system has been eliminated as a result of locking closed the ESW

cross tie valves. Therefore, little, if any, cooling would be

provided by the reactor building cooling water system during a

loss of offsite power. System subsections normally closed to flow

can be tested to ensure their operability and system integrity.

CHAPTER 10 10.10-3 REV. 21, APRIL 2007 TABLE 10.10.1 TURBINE BUILDING COOLING WATER SYSTEM EQUIPMENT DATA

Turbine Building Cooling Water System Pumps

Quantity 2 (full-capacity)

Type Horizontal, Centrifugal

Flow and Head 525 gpm at 180 ft

Bhp at Rating 34 hp Material:

Casting/Impeller/Shaft Cast Iron/Bronze/Stainless

Steel Motor: Size 40 hp Voltage/Phase/Frequency 440 V/3 Phase/60 Hz

Speed 3,600 rpm

Turbine Building Cooling Water System Heat Exchangers

Quantity 2 (full-capacity)

Type Horizontal, Shell and Tube

Heat Transfer Duty 3,850,000 Btu/hr

Shell Design:

Pressure/Temperature 150 psig/200 F Material Carbon Steel

Flow Medium Inhibited Demineralized Water Tube Design:

Pressure/Temperature 125 psi/200 F

CHAPTER 10 10.10-4 REV. 21, APRIL 2007 TABLE 10.10.1 (Continued)

Material:

Tube Admiralty

Tube Sheet Carbon Steel

Tube Joint Rolled Flow Medium River Water

CHAPTER 10 10.11-1 REV. 21, APRIL 2007 10.11 CHILLED WATER SYSTEM 10.11.1 Power Generation Objective

The power generation objective of the chilled water system is to

provide cooling water to the auxiliary equipment inside the

primary containment.

10.11.2 Power Generation Design Basis

1. The chilled water system is designed to cool the auxiliary equipment inside the primary containment over

the full range of plant operation.

2. The chilled water system provides a reliable source of cooling water.
3. The chilled water system is provided with inter-ties with the reactor building cooling water system, which

serves the chilled water system during a loss of offsite

power. This design feature exists although the heat

sink, emergency service water (ESW), for the reactor

building closed cooling water (RBCCW) system has been

eliminated as a result of locking closed the ESW-RBCCW

cross tie valves. Therefore, little, if any, cooling

would be provided by the chilled water system during a

loss of offsite power.

10.11.3 Description

The chilled water system consists of three half-capacity, centrifugal refrigeration units, three half-capacity chilled water

pumps, an expansion tank, piping, valves, instrumentation, and

controls (Drawing M-327, Sheets 1 through 4). It is a closed-loop

system utilizing inhibited demineralized water. The pumps

circulate warm return water to the refrigeration unit chillers.

The chilled water is then piped to the drywell air coolers, the

recirculation pump motor coolers, and the drywell equipment sump

cooler. Two parallel supply headers and return headers penetrate

the primary containment. A motor operated isolation valve is

located outside the containment in each line. The inter-tie with

the reactor building cooling water system is made by motor

operated three-way valves. An automatic transfer from system to

system is made upon loss of offsite power. Chilled water system

shutdown requires a manual switchover. Chillers and pumps are

remotely controlled from the main control room. A standby start

feature is provided for each chilled water pump. Standby equipment

is provided to assure system reliability.

CHAPTER 10 10.11-2 REV. 21, APRIL 2007 10.11.4 Inspection and Testing

The chilled water system is proved operable by use during normal

plant operation. Portions of the system normally closed to flow

can be tested to ensure operability and integrity of the system.

CHAPTER 10 10.12-1 REV. 21, APRIL 2007 10.12 FIRE PROTECTION PROGRAM The Fire Protection Program (FPP) is described in a document

transmitted to the NRC on September 30, 1986 titled, "Fire

Protection Program, Peach Bottom Atomic Power Station, Units 2 and

3", and is hereby incorporated by reference into the UFSAR.

Chapter 1 of the FPP is an introduction.

Chapter 2 provides a general description of the fire detection and

suppression systems.

Chapter 3 presents an item-by-item comparison of the Peach Bottom

Atomic Power Station Units 2 and 3 fire protection program with

the guidelines set forth in Branch Technical Position APCSB 9.5-1, Appendix A, the requirements of Appendix R to 10CFR50, and the

requirements of the Fire Protection Safety Evaluation Report.

Chapter 4 provides a tabulation of the combustible loadings in

plant fire areas, describes fire barriers, and describes fire

detection and suppression systems in each area. The plant is

divided into 47 fire areas.

Chapter 5 provides an evaluation of the ability to safely shut the

plant down in the event of a fire in any one of the plant's 47

fire areas.

Chapter 6 addresses special topics.

Chapter 7 contains the fire protection requirements which have

been relocated from the Technical Specifications by Technical

Specifications Change Request 90-05, which was submitted to the

NRC on March 28, 1994. The relocation of these requirements was

in accordance with NRC Generic Letters (GL) 86-10, "Implementation

of Fire Protection Requirements," and GL 88-12, "Removal of Fire

Protection Requirements from Technical Specifications."

In addition to the above, administrative procedures, system

operating procedures, surveillance tests, and pre-fire strategy

plans have been established to implement the Fire Protection

Program.

CHAPTER 10 10.13-1 REV. 26, APRIL 2017 10.13 MAIN CONTROL ROOM AIR CONDITIONING 10.13.1 Power Generation Objective

The power generation objective of the main control room air

conditioning system is to provide a suitable environment for

continuous personnel occupancy and to ensure the operability of

control room equipment and instruments under normal and accident

conditions per 12.3.4.

10.13.2 Power Generation Design Basis

1. The system is designed to provide an environment with a controlled temperature. Humidity control is available

during periods of auxiliary boiler operation.

2. The system is capable of purging the main control room.
3. Redundant components are provided to ensure reliable system operation.

10.13.3 Safety Design Basis

1. The system is designed such that the control room is habitable even under the design basis accident

conditions.

2. The fresh air portion of the system is designed to be operable during the loss of offsite power by using the

standby power supplies.

3. The fresh air intake is filtered when main control room emergency ventilation is initiated to prevent iodine and

particulate contamination of the main control room air.

10.13.4 Description

The main control room air conditioning system consists of

ventilation air supply fans (normal), emergency air supply fans, air conditioning supply and return fans, filters, heating coils

and cooling coils, refrigerant water chillers, chilled water

pumps, dampers, duct work, instrumentation, and controls (Drawing

M-384).

Outside air is drawn through a filter by a fresh air supply fan

and is discharged to the inlet of the air conditioning supply fan

suction, and is then discharged to duct work leading to the main

control room and adjacent offices. This air is conditioned to

maintain a controlled temperature environment using heating and

CHAPTER 10 10.13-2 REV. 26, APRIL 2017 cooling coils. Humidity is conditioned during periods of auxiliary boiler operation. Normally, control room air is

recirculated by one of two return air fans. These fans take a suction from the north and south ends of the control room and

discharge to the air conditioning supply fan suction with filtered

outside air from the fresh air supply fans.

The control room heating coils are supplied from the auxiliary

steam supply. Cooling is provided by a chilled water system

consisting of two 100% chiller units, two 100% chilled water

pumps, and a piping system which also supplies chilled water to

the cable spreading room fan-coil supply unit and the health

physics and chemistry labs fan-coil supply unit. The fresh air

supply fans, both normal and emergency, are operable from the

standby power supply during the loss of offsite power. The

control room chiller and air conditioning supply and return fans

do not run following loss of offsite power. The instrumentation

and control for the main control room air conditioning system is

designed for automatic operation. One fresh air supply fan, one

air conditioning supply fan, and one return air fan are normally

in operation. Emergency cooling and ventilation systems for the

control room and other safety-related equipment rooms are

installed in seismic Class I structures and are provided with 100

percent redundancy. Monitoring and adjustment of the control room

emergency ventilation system air flow may be performed locally.

If an operating fan fails, the loss of duct pressure is sensed and

the standby fan starts automatically, the associated fan dampers

open, and an alarm sounds in the control room. Fans may also be

started manually.

A radiation monitoring system in the fresh air intake duct work

monitors the radioactivity level in the incoming outside air. This

system includes two flow switches that monitor air flow through

the fresh air intake duct work. If a high activity level or loss

of flow is detected, the operating normal fresh air supply fan

stops, one emergency air supply fan starts, and the air

conditioning supply and return air fans shut down. The air is

diverted through one of the two high efficiency and charcoal

filter trains automatically. The monitor also annunciates in the

control room. If a high-high activity level is detected, the

monitor will indicate in the control room.

The control room is capable of being purged with 100 percent

outside air. A once-through flow is established using the air

conditioning supply fans, with the return air fans discharging to

atmosphere at the radwaste building roof.

CHAPTER 10 10.13-3 REV. 26, APRIL 2017 10.13.4.1Control Room Habitability The primary design function of the Main Control Room (MCR) / Main

Control Room Emergency Ventilation (MCREV) System is to provide a

safe environment in which the operator can keep the nuclear

reactor and auxiliary systems under control during normal

operations and can safely shut down those systems during abnormal

situations to protect the health and safety of the public and

plant workers.

Technical Specifications 3.7.4 and its Bases are in place to

ensure that appropriate equipment is maintained operable and

inoperabilities are managed through compensatory actions and other

plant actions.

A Control Room Envelope (CRE) Habitability Program is required by

Technical Specifications 5.5.13. The program is established and

implemented to ensure that the CRE habitability is maintained such

that, with an operable MCREV system, CRE occupants can control the

reactor safely under normal conditions and maintain it in a safe

condition following a radiological event, hazardous chemical

release as applicable, or a smoke challenge. The program shall

ensure that adequate radiation protection is provided to permit

access and occupancy of the CRE under design basis accident (DBA)

conditions without personnel receiving radiation exposures in

excess of 5 rem total effective does equivalent (TEDE) for the

duration of the accident. The program includes elements required

by Technical Specification 5.5.13.

As a result of Technical Specification 3.7.4 and 5.5.13

requirements, PBAPS is committed to applicable portions of NRC Reg

Guide 1.197, NRC Reg Guide 1.196 as invoked by the Technical

Specifications or its Bases. PBAPS is committed to NRC Reg Guide

1.78 (6/74) and NRC Reg Guide 1.95 (2/75), as applicable, for

hazardous chemical assessments. The computer code HABIT is

utilized for hazardous chemical assessments, which was approved in

Revision 1 of Reg Guide 1.78. This is an exception to Revision 0, to which PBAPS remains committed. Additionally, Peach Bottom performs hazardous chemical assessments by probabilistic analysis in accordance with NUREG-0800, Standard Review Plan, Section 2.2.3.

10.13.5 Safety Evaluation

The fresh air portion of the main control room ventilation system

permits continuous occupancy of the main control room

under normal and accident conditions, including maximum credible

earthquake, contaminated outside air, and loss of offsite power.

The system has sufficient redundancy to maintain uninterrupted

main control room ventilation for personnel occupancy and

CHAPTER 10 10.13-4 REV. 26, APRIL 2017 instrument operability. Evaluation as to the expected dose rates under the design basis accident conditions is included in

paragraph 12.3.4.

10.13.6 Inspection and Testing

The main control room air conditioning system is proven operable

by its use during normal plant operation. Portions of the system

normally closed to flow can be tested to ensure operability and

integrity of the system.

CHAPTER 10 10.14-1 REV. 21, APRIL 2007 10.14 EMERGENCY VENTILATING SYSTEM 10.14.1 Safety Objective

The safety objective of the emergency ventilating systems is to

maintain suitable temperatures in the plant engineered safeguards

equipment rooms for equipment protection.

10.14.2 Safety Design Basis

1. The systems protect the safeguards equipment against overheating.
2. Selected systems shall be provided with redundant components for reliable operation.
3. The equipment is provided with alternate power supplies in the event of loss of offsite power.
4. The equipment is designed to seismic Class I criteria.

10.14.3 Description

The emergency ventilating systems include the following:

1. Emergency switchgear and battery rooms.
2. Standby diesel generator rooms.
3. Pump structure ventilation system (ESW/HPSW Compartment).
4. Pump rooms for the RHR, RCIC, HPCI, and core spray pumps.

The reactor building heating and ventilating system normally

supplies ventilation air to the RHR, RCIC, HPCI, and core spray

pump rooms (paragraph 5.3.2).

10.14.3.1 Emergency Switchgear and Battery Rooms

The system consists of a common air supply system and separate

exhaust systems for emergency switchgear and battery rooms (Drawing M-399). Outdoor air is filtered, conditioned by heating

coils when required, and discharged by one of the two supply fans

to the emergency switchgear and battery rooms of Units 2 and 3.

One of the two emergency switchgear room return air fans exhaust

air to atmosphere at the radwaste building roof or back to the suction of the supply fan as controlled by an air-operated damper.

One of the two battery room exhaust fans discharges exhaust air

from the battery rooms to atmosphere at the radwaste building

CHAPTER 10 10.14-2 REV. 21, APRIL 2007 roof. Loss of duct pressure automatically starts standby fans and sounds an alarm in the main control room.

The equipment is installed in a seismic Class I structure adjacent

to the main control room. The ventilation system is normally in

operation and continues to operate during accident conditions

including the loss of offsite power. All system controls are from

a local panel. Redundant fans are provided for reliable system

operation. A seismically supported, safety grade, pneumatic

supply has been provided to maintain the dampers open in accident

conditions.

10.14.3.2 Standby Diesel Generator Rooms

Each standby diesel generator room is provided with ventilation

air supply fans and an exhaust relief damper (Drawing M-385).

Combustion air for the diesel engine is taken from the room. The

ventilation systems are supplied with power from the diesels

during the loss of offsite power.

10.14.3.3 ESW/HPSW Compartments

The ESW/HPSW compartment housing the high pressure service water

pumps, emergency service water pumps, fire pumps, and service

water screen wash pumps is provided with a ventilation supply and

exhaust system in each of the two seismic Class I compartments.

The ventilation system is supplied with standby power during the

loss of offsite power. Redundant ventilation equipment is

furnished in each compartment for uninterrupted service. The pump

structure ventilation system for each HPSW subsystem is single

failure proof.

10.14.4 Safety Evaluation

The emergency equipment rooms are provided with cooling and

ventilating systems with sufficient redundancy to ensure proper

operation of equipment during normal and accident conditions. In

addition, equipment is designed and installed in accordance with

seismic Class I criteria and is supplied with normal and standby

power.

10.14.5 Inspection and Testing

The emergency ventilating systems are proved operable by use

during normal plant operation. The effectiveness of the energy

removal from the local environments can be evaluated by measuring

the compartment air temperatures where the equipment is located.

Portions of the systems normally closed to flow can be tested to

ensure operability and integrity of these systems.

CHAPTER 10 10.14-3 REV. 21, APRIL 2007 The instantaneous auxiliary relays used to sequence the diesel generator room vent supply fans and the residual heat removal

compartment fan coolers during a LOCA (with offsite power

available) will be tested in accordance with surveillance test

procedures. The test will verify the settings, operability, and

functional performance of the relays, and will provide assurance

that the automatic loading sequence is being maintained and will

perform as required.

CHAPTER 10 10.15-1 REV. 21, APRIL 2007 10.15 PLANT HEATING, VENTILATING, AND AIR CONDITIONING SYSTEMS 10.15.1 Power Generation Objective

The power generation objective of the plant heating, ventilating, and air conditioning systems is to control the plant air

temperatures and the flow of airborne radioactive contaminants to

ensure the operability of plant equipment and the accessibility

and habitability of plant buildings.

10.15.2 Power Generation Design Basis

The plant heating, ventilating, and air conditioning systems:

1. Provide appropriate temperature control for personnel comfort and equipment performance.
2. Provide sufficient filtered fresh air supply for personnel.
3. Provide air movement patterns from areas of lesser to areas of progressively greater contamination potential

prior to final exhaust.

4. Minimize the possibility of plant exhaust air recirculation into the plant air intake.

10.15.3 Description

10.15.3.1 General

The plant heating, ventilating, and air conditioning systems

provide heated or cooled air to main areas of the plant. Supply

air temperature is controlled by heating coils and cooling coils.

Generally, airflow is routed from areas of lesser to areas of

progressively greater contamination potential prior to final

exhaust. Also, the ventilation system has sufficient design

capacity to protect equipment from excessive temperatures.

The exhaust ventilation air from the turbine building and radwaste

building is discharged to atmosphere from the ventilation stack

above the reactor building roof. Exhaust from areas where

radioactive particulate may be present, such as equipment rooms, is not recirculated but is exhausted through high-efficiency

filters to atmosphere. Clean exhaust air from other plant areas

is not filtered prior to being released to atmosphere.

The reactor building heating and ventilating system is described

in paragraph 5.3.2. The main control room air conditioning system

is described in subsection 10.13, and the emergency heating and

ventilating systems are described in subsection 10.14.

CHAPTER 10 10.15-2 REV. 21, APRIL 2007 10.15.3.2 Turbine Building

The ventilation system supplies filtered and tempered outdoor air

to the operating floor, main condenser area, and equipment

compartments (Drawing M-387). The main condenser area is

maintained at a slight negative pressure to reduce exfiltration of

potential radioactive contaminants to the adjacent areas.

Ventilation air to the operating floor is recirculated or

exhausted as required to maintain space temperature. The exhaust

air from the operating floor and the main condenser area is

discharged to the atmosphere through the ventilation stack located

at the top of the reactor building. Air from potentially

contaminated equipment compartments is exhausted through high-

efficiency filters prior to release to the atmosphere at the

ventilation stack. Supplementary cooling in the main condenser

area and condensate pump room is provided by fan-coil units using

service water for cooling. Additionally, unit heaters are

provided in various areas for equipment freeze protection.

10.15.3.3 Radwaste Building

The ventilation system for the radwaste building maintains a

supply of filtered and tempered fresh air to all areas of the

radwaste building (Drawing M-389). Generally, air is distributed

from areas of lesser to areas of progressively higher

contamination.

Two exhaust systems are used: normal and equipment compartment

exhaust. The normal exhaust is unfiltered and is discharged to

atmosphere at the reactor building roof through the ventilation

stack. The equipment compartment exhaust air is filtered prior to

release to atmosphere from the ventilation stack. Air vented from

tanks containing radioactive liquids is exhausted through high-

efficiency filters prior to joining the equipment compartment

exhaust duct work.

10.15.3.4 Miscellaneous Rooms and Buildings

The cable spreading room, located beneath the main control room, is provided with its own supply and exhaust fans, filters, heating

and cooling coils, duct work, instrumentation, and controls.

Redundancy in the number of fans provides continued operation of

the system. These fans shut down on a loss of offsite power.

The computer room, located in the cable spreading room area, is

provided with self-contained air conditioning units, filters, and

controls to maintain constant temperature and humidity in the

room. These units operate from the standby power supply during a

loss of offsite power.

CHAPTER 10 10.15-3 REV. 21, APRIL 2007 The administration building, chemical laboratory rooms, shop and

warehouse building, water treatment building, and other structures

in the plant are provided with separate conventional heating, ventilating, and/or air conditioning system.

10.15.4 Inspection and Testing

The plant heating, ventilating, and air conditioning systems are

proved operable by their use during normal plant operation.

Portions of the systems normally closed to flow can be tested to

ensure operability and integrity of the systems.

CHAPTER 10 10.16-1 REV. 23, APRIL 2011 10.16 MAKEUP WATER TREATMENT SYSTEM 10.16.1 Power Generation Objective

The power generation objective of the plant makeup water treatment

system is to provide a supply of water suitable as makeup for the

plant and reactor systems and other water requirements.

10.16.2 Power Generation Design Basis

The makeup water treatment system is designed to provide reactor

quality water for pre-operational tests, startup, and normal power

operation.

10.16.3 Description

The makeup water treatment system is common to Units 2 and 3 (Drawings M-317 and M-319).

The makeup water treatment system receives river water from the

service water system. The system consists of a raw water

treatment system, a clarified water storage tank, a makeup

demineralizer system, a demineralized water tank, and associated

pumps, piping, and instrumentation.

The raw water treatment system consists of skid mounted equipment that is vendor supplied and operated. This equipment produces up to 400 gpm of clarified and filtered water with a nominal flow of 200 gpm for use in the makeup demineralizer system, domestic water, and other uses. This water is pumped to a 200,000 gallon clarified water storage tank. The clarified and filtered water is continuously monitored by vendor supplied turbidity and pH measuring devices which initiate an alarm on a vendor panel.

The makeup water demineralizer system consists of three feed pumps

taking suction on the clarified water storage tank and discharging

to vendor supplied ultra pure water equipment. The discharge from

the ultra pure water equipment goes to a 50,000-gal demineralized

water storage tank. The discharge to the storage tank is

monitored for quality by conductivity measuring devices which

initiate an alarm on a local panel. Also, silica content is

continuously monitored and recorded. The quality of water

discharged to the storage tank is controlled to maintain water

within the limits specified in EPRI BWR Water Chemistry

Guidelines.

The piping, tanks, and associated equipment of the demineralized

water treatment system are of corrosion-resistant metals which

prevent contamination of the makeup water with foreign material.

CHAPTER 10 10.16-2 REV. 23, APRIL 2011 10.16.4 Inspection and Testing The makeup water treatment system is an operational system in

daily use and as such does not require testing to ensure

operability. High demineralizer effluent conductivity

automatically initiates an alarm. Grab samples are tested in the

laboratory to check demineralizer performance and to ascertain

stored water quality.

CHAPTER 10 10.17-1 REV. 25, APRIL 2015 10.17 INSTRUMENT AIR, SERVICE AIR, AND INSTRUMENT NITROGEN SYSTEMS 10.17.1 Safety Objective

The safety objective of the instrument air, service air, and

instrument nitrogen systems is to provide a safety grade, pneumatic supply to support short-term and long-term operations of

safety equipment.

10.17.2 Safety Design Basis

1. The containment atmospheric control system containment purge and vent isolation valves are each provided with a

backup, safety grade, pneumatic (nitrogen) supply to the

valves' inflatable seals.

2. The containment isolation and flow control valves in the CAD vent lines are each provided with a separate, backup, safety grade, pneumatic (nitrogen) supply. The

control valves in the CADS supply are provided with a

safety grade supply of nitrogen from the CADS nitrogen

supply.

3. The ADS valves are provided with a separate short-term, safety grade, pneumatic supply and also a long-term, backup, safety grade, pneumatic supply of nitrogen. To

fulfill the requirements of Appendix R to 10CFR, Part 50

manual actions may be performed to connect a back-up

safety grade pnuematic nitrogen supply to enable remote

operation of safety relief valves. See FPP Table A-4

for actions required to credit this pneumatic supply.

4. A separate short-term, backup, safety grade, pneumatic supply is provided to each of the MSIVs.
5. The suppression chamber-to-secondary containment vacuum breaker air-operated valves are each provided with a

backup, safety grade, pneumatic supply.

6. The emergency switchgear and battery room dampers are provided with a backup, safety grade, pneumatic supply.

10.17.3 Power Generation Objective

The power generation objective of the instrument air and service

air systems is to supply suitable quality air at adequate pressure

for power plant operation.

CHAPTER 10 10.17-2 REV. 25, APRIL 2015 10.17.4 Power Generation Design Basis

1. The instrument air system supplies clean, dry, oil-free air, nominally at 100 psig, to station instrumentation

and controls.

2. The service air system supplies clean air, nominally at 100 psig, for station services.
3. Standby onsite power is provided to the backup air compressors, following a loss of offsite power, to

replenish compressed air storage as required. This

design feature exists although the heat sink, emergency

service water (ESW), for the reactor building closed

cooling water (RBCCW) system has been eliminated as a

result of locking closed the ESW-RBCCW cross tie valves.

Therefore, little, if any, cooling would be provided to

the backup air compressors during a loss of offsite

power.

4. Service air use is restricted during emergency conditions so that the instrument air supply shall not

be impaired.

5. Two separate systems are provided for each unit for the condensate filter demineralizer backwash operations.
6. Instrument nitrogen/instrument air is provided to the MSIV's for maintaining the valves open when operating

the steam cycle.

7. A separate air supply system is provided to selected radwaste equipment.

10.17.5 Description

The instrument air and service air systems (Drawing M-320) consist

of four air compressors per unit operating in parallel to supply

common discharge headers via individual air receiver tanks, piping, valves, and instrumentation. The instrument and service

air systems of Units 2 and 3 can be crosstied.

Two of the three larger compressors (650 SCFM) normally supply all

compressed air requirements for one reactor unit during normal

operation. The three larger compressors are fed from non-1E power

sources. During emergency conditions when neither station nor

offsite power are available, the smaller (419 SCFM) compressor, which is fed by a Class 1E power source, is designed to provide

desired operational flexibility. This design feature exists

although the heat sink, emergency service water (ESW), for the

CHAPTER 10 10.17-3 REV. 25, APRIL 2015 reactor building closed cooling water (RBCCW) system has been eliminated as a result of locking closed the ESW-RBCCW cross tie

valves. Therefore, little, if any, cooling would be provided to

the air compressors during a loss of offsite power.

The instrument air compressors normally operate (load and unload)

within a pressure range of approximately 10 psi. The service air

compressor, which can feed either of the instrument air headers

and the service air header, operates over approximately a 15 psi

range so that it will not assume control from the instrument air

compressors. In the unlikely event that header pressure decays to

97 psig, an air operated valve in the supply to the service air

header will close, thus utilizing the instrument and service air

compressors for instrument air only. The duty status of all three

compressors can be changed to allow for maintenance and

equalization of wear. During a loss of station or offsite power, only the 419 SCFM compressor (backup compressor), is fed by diesel

backed power. This design feature exists although the heat sink, emergency service water (ESW), for the reactor building closed

cooling water (RBCCW) system has been eliminated as a result of

locking closed the ESW-RBCCW cross tie valves. Therefore, little, if any, cooling would be provided to the air compressors during a

loss of offsite power. During a LOCA event the affected unit's

backup compressor will trip if running or will be prevented from

starting for 60 seconds. Identical backup compressors are

provided for each unit, and manual crossties are provided so that

either or both backup compressors can be utilized to supply either

unit. A single backup compressor is sufficient to supply

operational flexibility for one unit during shutdown following a

LOOP and/or LOCA.

Each of the four compressors is of the 2-stage oil-free rotary

screw design. These compressors are water cooled and are complete

packaged units, incorporating an inter-cooler, after-cooler, oil

cooler, bleed-off cooler, and all controls and instrumentation in

a single sound attenuating enclosure. "Compressor trouble" alarms

actuated by any compressor trip functions are provided both in the

control room and locally on the compressors.

The lead compressors are rated at 691 ACFM at 125 psig maximum and

utilize a 150 HP motor with a 1.15 service factor. The backup

compressors are rated at 456 ACFM at 125 psig maximum and utilize

a 100 HP motor with a 1.15 service factor. All compressor motors

are capable of starting and accelerating at 75% of nominal

voltage.

The prefilters of the air dryer are the coalescing type and are

designed to remove effluent to 0.0013 ppmw. The dual tower

instrument air dryer package is rated at 900 scfm, is of the

heatless design and utilizes activated alumina desiccant for

absorption of moisture. The dryer is designed for a discharge dew

CHAPTER 10 10.17-4 REV. 25, APRIL 2015 point of -40 F. Each dryer incorporates a moisture sensing control which measures the actual moisture load present on the desiccant during each cycle. It then limits the number of

regeneration (purge) cycles to only those required to remove

moisture to maintain the required outlet dew point. The after

filters are designed to remove particulate to 0.9 micron absolute.

Also incorporated in the dryer skid package are a flow meter and a

dew point analyzer. The flow meter is provided with flow

recording and totalizing capabilities to enable continuous

monitoring of plant air usage. The dew point meter gives a

continuous readout of moisture level. There are local alarms on

each dryer skid to indicate high differential pressure across the

prefilters, high moisture content in the outlet air, and dryer

control malfunctions. There is one common alarm window per unit, located on C212L in the control room, to indicate an alarm

condition exists on either of the two dryer skids for that unit.

The discharge from the dryer package than passes to the plant

instrument air headers.

Breathing air stations are provided with air from the service air

system headers.

Since the air is supplied by non-lubricated compressors, the

instrument air system is supplied with clean, dry, oil-free air

for use by instrumentation and controls. This system supplies air

to the main steam isolation valves external to containment. The

main steam isolation valves are provided with accumulators for

reliable operation without compressor operation.

The control rod hydraulic control system air requirement is for

scram reset purposes only, and its demand is met by the CRDS

storage capacity. Other pneumatic-operated devices are also

designed for the fail-safe mode, and do not require a continuous

air supply under abnormal conditions.

The Condensate Filter Demineralizer backwash operation employs the

use of two separate air backwash systems. The primary system is a

high pressure air surge system which uses a non-lubricated, two

stage, water cooled compressor rated at 200 scfm at 200 psig.

Each unit has two separate receiver tanks (150 ft 3 each) which are cross-tied to allow either compressor to charge both units. In

addition each unit is provided with a backup low pressure air

scrub backwash system using low pressure centrifugal blowers rated

at 1400 scfm.

The containment atmospheric control system purge and vent valves

are supplied with separate safety grade pneumatic supplies to the

inflatable seals to maintain their leaktight condition. The

source of this pneumatic supply is from the Safety Grade

CHAPTER 10 10.17-5 REV. 25, APRIL 2015 Instrument Gas (SGIG) system. The SGIG supplies pressurized nitrogen gas from the CAD tank as a backup to normal instrument

air. The safety grade pneumatic supply is isolated from the

nonsafety grade portion of the air supply by spring-loaded, soft-

seat, check valves designed for zero leakage. The purge and vent

valves alarm upon opening or on loss of seal pressure.

The suppression chamber-to-secondary containment vacuum breaker

air-operated valves are each supplied with separate, safety grade, pneumatic supplies. There are two suppression chamber-to-

secondary containment vacuum breaker lines on each unit. Each

line is provided with a normally closed, fail open, air-operated

butterfly valve. Each of these valves is provided with a safety

grade pneumatic supply in order to maintain valve closure. One

valve on each unit is equipped with an inflatable seal which is

also supplied by the safety grade pneumatic supply. These valves

alarm upon opening or, for the valves equipped with the inflatable

seal, on loss of seal pressure. The source of this pneumatic

supply is from the Safety Grade Instrument Gas (SGIG) system. The

SGIG supplies pressurized nitrogen gas from the CAD tank as a

backup to normal instrument air. The safety grade pneumatic

supply is isolated from the nonsafety grade portion of the air

supply by spring-loaded, soft-seat, check valves designed for zero

leakage.

The safety grade supply to the CADS valves is described in

paragraph 5.2.3.9 of subsection 5.2.

A separate air supply system is provided to selected radwaste

equipment; the system contains two air compressors, associated

controls, a receiver, and separate piping to connect the air

supply to the equipment. This system eliminates the potential of

service air system contamination in other areas of the plant due

to backflow from radwaste equipment.

The ADS accumulators, which provide the short-term, backup, safety

grade supply, and their long-term, safety grade, pneumatic supply

are described in paragraph 4.4.5 of subsection 4.4.

An MSIV accumulator is located close to each isolation valve to

provide pneumatic pressure for valve closing in the event of

failure of the normal, non-safety grade, air supply system. The

accumulator volumes are designed for inboard and outboard

isolation valves when the normal pneumatic supply to the

accumulator has failed. The supply line to the accumulator is

large enough to make up pressure to the accumulator at a rate

faster than the rate the valve operation bleeds pressure from the

accumulator during valve opening and closing. The air supply

lines are provided with check valves to assure the integrity of

the accumulator air supplies.

CHAPTER 10 10.17-6 REV. 25, APRIL 2015 In order to eliminate the introduction of compressed air into the containment and to minimize the need for venting and discharge of

the primary containment gases to the environment, an instrument

nitrogen system is provided for pneumatic service to ensure the

oxygen concentration is maintained less than 5 percent inside the

drywell (Drawing M-333, Sheets 1 and 2).

Essentially, this system takes suction from the containment

nitrogen atmosphere and discharge to a receiver which will be the

source of supply for the required pneumatic services inside the

drywell. In this manner, no air will be added to the containment

atmosphere, but rather the containment nitrogen atmosphere will be

recycled, with any losses of nitrogen made up by the normal

inerting system.

The instrument nitrogen system lines are seismic Class I from the

containment penetrations to the second isolation valve, and have

automatic isolation valves which function as part of the primary

containment and reactor vessel isolation control system when

required.

Pneumatically operated devices located within the primary

containment are normally operated by the instrument nitrogen

system. A cross connection is provided between the instrument air

system and the instrument nitrogen system to service the

components in the primary containment should the instrument

nitrogen system be inoperable. Additionally, vital components, such as the main steam isolation valves and main steam relief

valves, are provided with accumulators for reliable operation

without compressor operation.

The emergency switchgear and battery room dampers are supplied

with safety grade pneumatic supplies to maintain the dampers open.

The source of the pneumatic supply is nitrogen cylinders. The

safety grade pneumatic supply is isolated from the non-safety

grade potion of the air supply by spring-loaded, soft seat, check

valves. The safety grade supply to the E.S.G.B.R. dampers is

described in paragraph 10.14.3.1.

10.17.6 Safety Evaluation

The safety grade, pneumatic supplies to the essential valves of

the CADS are provided so that the system can supply post-LOCA

nitrogen addition to the containment and can facilitate controlled

venting of containment. The safety evaluation for the CADS is

contained in paragraph 5.2.3.9.

The safety grade, pneumatic supply to the containment purge and

vent valves is provided to maintain pressure in the inflatable

CHAPTER 10 10.17-7 REV. 25, APRIL 2015 valve seats to assure leaktight conditions. The safety evaluation is contained in paragraphs 5.2.3.7 and 5.2.4.

The safety grade, pneumatic supply to each of the suppression

chamber-to-secondary containment vacuum breaker butterfly valve is

provided to maintain valve closure. It also provides the

pneumatic supply to the inflatable seal utilized in one of the

valves on each unit. The safety evaluation is contained in

paragraphs 5.2.3.6 and 5.2.4.

Each ADS valve is provided with a short-term, backup, safety

grade, pneumatic supply by means of its associated accumulator and

check valve to provide sufficient capacity to cycle the valve open

five times at atmosphere pressure, twice at 70% of containment

design pressure, or once at containment design pressure, all

within a 4-hour period.

A long-term, backup, safety grade, pneumatic supply has been

provided to the ADS valve accumulators inside the primary

containment to assure ADS valve operability for a period of 100

days following an accident.

A split ring header is installed inside the containment with three

ADS valves connected to one section of the split header and the

remaining two ADS valves connected to the other section of the

split header. The safety grade, pneumatic pressure is a series of

nitrogen cylinders located within the reactor building with a

connection provided outside the reactor building for the

installation of additional bottles, as required. Also, a long-

term, backup, safety grade pneumatic nitrogen supply has been

provided to SRVs RV2(3)-02-071E, H&J. This pneumatic supply is

provided to enable remote operation of the above valves for a

period of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> following a Design Basis fire in Fire Areas

6S (Unit 2) and 13S (Unit 3) which has been postulated to render

the ADS valves available for only short-term operation. The

source of the pneumatic nitrogen supply is the Safety Grade

Instrument Gas (SGIG) system. The SGIG system is tied into the

6,000 gallon liquid nitrogen tank which supplies the Containment

Atmospheric Dilution (CAD) system. The CAD tank is located

outside of Fire Areas 6S (Unit 2) and 13S (Unit 3).

Spare primary containment penetrations, two for each unit, have

been modified to provide a permanent means of connection to each

section of the safety grade, pneumatic supply headers within each

drywell. Containment isolation has been provided for the

instrument gas supply lines into containment by the use of check

valves and other automatic valves outside the primary containment.

The outer, automatic valves are manually controlled from the

control room and automatically close on low differential pressure

CHAPTER 10 10.17-8 REV. 25, APRIL 2015 between pneumatic supply pressure and containment pressure or if gas flow becomes excessively high.

The MSIV accumulators are provided to supply a safety grade, backup, pneumatic supply to close the MSIV's by pneumatic pressure

following the loss of normal non-safety grade pneumatic supply.

The safety function of the accumulators is assured by a safety

grade check valve which isolates the accumulators and allows them

to perform their safety function.

The safety grade, pneumatic supply to the emergency switchgear and

battery room dampers is provided to assure continued operation of

the ventilation system.

10.17.7 Inspection and Testing

The instrument air and service air systems are proved operable by

their use during normal plant operation. Portions of the system

normally closed to flow can be tested to ensure operability and

integrity of the system.

The post-LOCA CADS is functionally tested in accordance with plant procedures. The atmospheric analyzing system is functionally tested in accordance with the Technical Requirements Manual.

Inspection and testing of the ADS is discussed in paragraph 4.4.8.

CHAPTER 10 10.18-1 REV. 21, APRIL 2007 10.18 DOMESTIC AND SANITARY WATER SYSTEM 10.18.1 Power Generation Objective

The power generation objective of the domestic and sanitary water

system is to provide the potable water supplies and sewage

treatment necessary for normal plant operations and shutdown

periods.

10.18.2 Power Generation Design Basis

1. Domestic water is chlorinated.
2. Sanitary system water (sewage) is treated prior to release.

10.18.3 Description

Domestic water is supplied from the clarified water system, discussed in subsection 10.16, "Makeup Water Treatment System."

The domestic water system consists of a 5,000-gal domestic water

storage tank, two domestic water pumps, a domestic water hydro-

pneumatic tank, hypo-chlorinator, and distribution piping (Drawing

M-317). Clarified and filtered water is chlorinated and stored in

the domestic water storage tank, then pumped to the hydro-

pneumatic tank, where it is pressurized for system distribution.

Water heating units are provided for domestic showers.

An onsite sewage treatment plant is provided to treat the normal

sewage prior to release. The facility has the capacity to handle

Units 2 and 3 and to handle the variable loading at the plant due

to population fluctuations between outage and non-outage periods.

The sewage treatment system is designed to provide an effluent

that meets the regulations of the Commonwealth of Pennsylvania.

10.18.4 Inspection and Testing

The domestic and sanitary water system is proved operable by its

use during normal plant operation. Portions of the system

normally closed to flow can be tested to ensure operability and

integrity of the system.

CHAPTER 10 10.19-1 REV. 25, APRIL 2015 10.19 PLANT EQUIPMENT AND FLOOR DRAINAGE SYSTEM 10.19.1 Power Generation Objective

The power generation objective of the plant equipment and floor

drainage system is to collect and remove waste liquids from their

points of origin to a suitable disposable area.

10.19.2 Power Generation Design Basis

1. Liquid waste drains are classified in accordance with radioactive contamination potentials and conductivity

levels and chemical content.

2. Potentially radioactive liquid wastes are collected separately from the non-radioactive wastes, in a

controlled and safe manner.

10.19.3 Description

The plant equipment and floor drainage system handles both

radioactive and potentially radioactive wastes. Radioactive

wastes are collected in the building sumps and transferred to the

radwaste building for treatment, sampling, and analysis prior to

disposal or reuse in the plant. Non-radioactive wastes are pumped or drained by gravity into the sewer system, storm drain system, or intake bay, and released.

10.19.3.1 Radioactive Equipment Drainage System

1. Reactor Building Drains

Reactor containment systems' equipment wastes are collected in two separate systems. The drywell

equipment drain sump system collects equipment drains

located in the primary containment. The reactor

building equipment drain sump system handles drainage

from equipment drains located in the secondary

containment. Equipment drains are collected in closed

piping and discharged to the equipment drain sump.

Pumps transfer these wastes to the radwaste system.

Containment is provided in transferring waste from the

sumps to the radwaste system by maintaining a minimum

water level in the sump, which seals the pump suction

lines. To prevent blowout of water seals, the drywell

equipment drain discharge line penetrating the primary

containment has two isolation valves which close upon a

high drywell pressure signal.

CHAPTER 10 10.19-2 REV. 25, APRIL 2015

2. Turbine Building

The turbine building radioactive equipment drainage system is collected in sumps located below the basement

level. Sump pumps transfer the liquid to the radwaste

system.

3. Radwaste Building

The radwaste building is provided with an equipment drain sump. Sump pumps transfer the liquid to the

radwaste system. Radioactive drainage within the

radwaste onsite storage facility is discussed in section

9.3.3.2.

4. Recombiner Building

The recombiner building is provided with an equipment drain sump. Sump pumps transfer the liquid to the

radwaste system.

10.19.3.2 Floor Drainage System

In general, floor drains from the primary containment, reactor

building, turbine building, recombiner building, and radwaste

building are collected in sumps located in the basement or lowest

level of the building. Sump pumps transfer the waste from the

sumps to the radwaste system.

10.19.3.3 Non-Radioactive Drainage System

Roof drains from the reactor buildings, turbine building, radwaste

building, and other buildings, and some floor drains in the

turbine building service areas are collected and typically discharged by gravity to the storm drain system. Floor and equipment drains associated with the Unit 2 and Unit 3 critical pump portions of the Circulating Water Pump Structure are collected in a common sump and pumped to the intake bay.

Rainwater from the roof drain is normally routed directly to the intake bay. Refer to UFSAR Section 12.2.10 for details regarding how this drainage system provides protection of critical equipment during external flood conditions.

10.19.3.4 Miscellaneous Drainage System

Non-radioactive chemical liquid wastes are collected, neutralized, and routed to the settling basin prior to release to the pond.

Oil drains and oil-contaminated liquid drains are collected in a

separate oil collection tank for offsite disposal.

CHAPTER 10 10.19-3 REV. 25, APRIL 2015 10.19.3.5 Torus Dewatering Facilities

A 1.2 million-gal capacity storage tank and associated valving and

piping is provided for dewatering the torus to support containment

suppression chamber inspections and/or modifications. The tank

provides temporary storage for the entire volume of the torus.

The Torus De-Watering System (TDWS) is only connected to the torus

for dewatering/polishing in plant modes 4 and 5. Removable spool

pieces with isolation valves are utilized to allow the TDWS pump

suction to be connected to the torus. The spool piece assemblies (with closed isolation valves) are fully qualified to allow the

torus to maintain a reliable source of water for ECCS operation

while operations with the potential to drain the vessel are in

progress.

Torus water transfer is via the torus dewatering pumps (Units 2

and 3) and sludge pump (Unit 3 only). The torus water may be sent

to either the Condensate Storage Tank or the Torus Dewatering Tank (TDT). Transfer is generally routed through a condensate filter

demineralizer to improve water quality prior to storage in the

TDT. Additionally, the TDWS may be used to filter and polish the

torus water by operating the system in closed loop from the torus

through a condensate filter demineralizer, and back to the torus.

10.19.4 Inspection and Testing

The plant equipment and floor drainage system is proved operable

by use during normal plant operation. Portions of the system

normally closed to flow can be tested to ensure operability and

integrity of the system.

CHAPTER 10 10.20-1 REV. 21, APRIL 2007 10.20 PROCESS SAMPLING SYSTEM 10.20.1 Power Generation Objective

The power generation objective of the process sampling system is

to monitor the operation of equipment and systems, and to provide

information for making operational decisions.

10.20.2 Power Generation Design Basis

1. The process sampling system is designed to obtain representative samples which can be used in the

radiochemical laboratory.

2. The process sampling system minimizes contamination and radiation effects at the sampling stations.
3. The process sampling system is designed to reduce decay and sample line plateout.

10.20.3 Description

Samples are taken at locations throughout the plant from the

process and auxiliary systems (Table 10.20.1). Sample points are

grouped as much as possible at normally accessible locations, and

drains are provided at these locations to limit the risk of

contamination. Lines are sized to ensure purging and sufficient

velocities to obtain representative samples. The samples are

analyzed and the resulting information is used to evaluate the

condition of the plant.

10.20.4 Inspection and Testing

The process sampling system is proved operable by its use during

normal plant operation. Grab samples are taken to verify the

proper operation of the continuous samplers. Portions of the

system normally closed to flow can be tested to ensure the

operability and integrity of the system.

CHAPTER 10 10.20-2 REV. 23, APRIL 2011 TABLE 10.20.1 PROCESS SAMPLING SYSTEM

Description Locations Purpose

Nuclear Steam Supply System

Reactor water Recirculation pump discharge Reactor water quality, crack arrest verification

Main steam Main steam line Carryover, moisture RHRS RHR HX outlet HX leakage

Cleanup Demineralizer

Filter-demineralizer Influent header Reactor water quality Filter-demineralizer Powdex unit effluent Filter condition Filter-demineralizer Precoat recycle line Element leakage Regenerative HX Return to reactor HX leakage Non-regenerative HX Cooling water outlet pipe HX leakage

Condensate System

Condensate Hotwell trays Tube leakage Condensate Condensate pump discharge Tube leakage, water quality Condensate demineralizer Influent header Condensate quality Condensate demineralizer Powdex unit effluent Filter condition Condensate demineralizer Effluent header Treated condensate quality Consensate demineralizer Precoat recycle line Element leakage

Feedwater Systems

Heater drains Heater No. 3 outlet Water quality Feedwater Heater No. 5 outlet Water quality Feedwater Reactor inlet Water quality Closed Cooling Water Systems

Turbine building cooling water Pump discharge Inhibitor concentration Reactor building cooling Pump discharge Inhibitor concentration

Circulating and Service Water Systems

Service water Pump discharge header Determine background Circulating water Condenser outlet Chlorine residual Circulating water Discharge canal Activity release

CHAPTER 10 10.20-3 REV. 23, APRIL 2011 TABLE 10.20.1 (Continued)

Description Locations Purpose

Circulating and Service Water Systems

Service water Pump discharge header Determine background Circulating water Condenser outlet Chlorine residual Circulating water Discharge canal Activity release

Liquid Radwaste System

Laundry drain tank Pump discharge Process data Laundry drain filter Filter effluent Water quality Floor drain collector tank Pump discharge Process data Floor drain filter Filter effluent Process data Floor drain demineralizer Demineralizer effluent Process data Floor drain sample tank Pump discharge Discharge suitability Waste collector tank Pump discharge Process data Waste surge tank Pump discharge Process data Waste collector filter Filter effluent Process data Waste demineralizer Demineralizer effluent Process data Waste sample tank Pump discharge Discharge suitability R/W fuel pool F/D precoat Precoat recycle line Element testing Fuel pool HX HX outlet Fuel pool quality, HX leakage Fuel pool filter demineralizer Powdex unit effluent Filter/demineralizer condition Chemical waste tank Pump discharge Process data Condensate phase separator decant Pump discharge Process data Cleanup phase separator decant Pump discharge Process data Centrifuge liquid effluent Liquid discharge pipe Process data

Makeup Water Treatment Systems

Raw water inlet GE M52 skid inlet Process data Filtered water outlet GE M52 outlet Process data Domestic water Pump discharge Chlorine residual Carbon filter Filter effluent Process data

CHAPTER 10 10.20-4 REV. 23, APRIL 2011 TABLE 10.20.1 (Continued)

Description Locations Purpose

Makeup Water Treatment Systems (Continued)

Cation unit Effluent Process data Anion unit Effluent Process data Mixed bed unit Effluent Water quality Dilute acid Header Process data Dilute caustic Header Process data Neutralizer tank Outlet pipe Process data Demineralized water storage tank Pump discharge Water quality Condensate transfer system Pump discharge Water quality Refueling water transfer system Pump discharge Water quality

Plant Off-Gas Systems

Air ejector discharge Header Activity; H 2 , 0 2 , and air in-leakage Off-gas stack sample Main stack Noble gas monitoring and particulate

and iodine samples to determine release rates Recombiner area monitoring Fan discharge from individual Activity equipment rooms, hydrogen analyzers, instrument racks, equipment sumps, and cooling water surge tank. Identifica-tion of specific source of leakage is obtainable.

Building ventilation exhaust Building ventilation stack Noble gas monitoring and particulate

and iodine samples to determine release rates Control room, radwaste, Fan discharge Activity recombiner ventilation

CHAPTER 10 10.21-1 REV. 21, APRIL 2007 10.21 COMMUNICATIONS SYSTEMS 10.21.1 Power Generation Objective

The power generation objective of internal and external

communications is to establish a combined system of loudspeakers

and telephones to provide convenient, effective operational

communications between various plant buildings and locations.

10.21.2 Power Generation Design Basis

1. Voice communication to points outside the station is provided by a dial telephone system.
2. Voice communication between various plant buildings and locations is provided.

10.21.3 Description

The following means of communication are provided in the plant:

1. A dial phone system with a self-contained power supply is provided for communicating with points outside the

station.

2. An intraplant communication system consisting of handsets and loudspeakers is provided for paging and

communications in all appropriate areas. The intraplant

system employs equipment that operates from the AC

instrument bus. Loudspeakers powered by individual

amplifiers are located throughout the station, with

muting facilities provided where required. Paging plus

two-party line channels are provided for simultaneous

operation.

3. A separate intraplant telephone system allows uninterrupted private communication for maintenance and

general use between the main control room, reactor

refueling area, and other selected plant areas. The

system is designed to ensure that no interference in

vital communication is caused by other plant

communication systems.

4. An evacuation alarm system is located in strategic points throughout the plant to warn personnel of

emergency conditions. Additional speakers are located, especially in high noise areas, to provide plant

evacuation signal.

CHAPTER 10 10.21-2 REV. 21, APRIL 2007 5. A distributed antenna system was installed throughout the plant to provide the capability of using low power walkie talkies as a supplementary means of communicating

within the plant. Because these walkie talkies are low

power, they will not interfere with plant

instrumentation.

6. A dedicated communications system, using the distributed antenna system is installed to allow plant operators to

communicate between the main control room and the Unit 2

and Unit 3 Alternative Control Stations. This system is

used for coordinating testing of the Alternative Control

Stations and in an Emergency, for a Safe Shutdown from

the Alternative Control Stations. See the Fire

Protection Program (FPP) for details.

10.21.4 Inspection and Testing

The communication systems are proved operable by use during normal

plant operation. Loss of offsite power operation can be tested to

ensure operability and integrity of the systems.

CHAPTER 10 10.22-1 REV. 21, APRIL 2007 10.22 STATION LIGHTING SYSTEM 10.22.1 Power Generation Objective

The power generation objective of the station lighting system is

to provide adequate normal and emergency indoor station lighting.

Power is supplied from a normal AC source, standby AC system, and

from the station battery system.

10.22.2 Power Generation Design Basis

1. Lighting intensities approximate levels recommended by the Illuminating Engineering Society.
2. Mercury vapor fixtures and mercury switches are not used inside the primary containment or directly above the

reactor on the refueling floor.

3. The main control room has a fluorescent lighted, glare-free, luminous ceiling to reduce glare and shadows at

the control boards.

4. Emergency lighting is provided in the control room, diesel generator rooms, emergency switchgear area, and

other points where lighting may be required under

abnormal conditions.

10.22.3 Description

The station lighting system is supplied from the station auxiliary

power system described in Section 8.0, "Electrical Power Systems."

Normal power is supplied from the unit auxiliary or the startup

transformers. The power supply for lighting areas required during

shutdown or abnormal conditions is automatically transferred to

the standby diesel generator system if the normal power supply is

lost.

The lighting distribution system has separate, dry-type lighting

transformers and circuit breaker type panel boards.

A separate emergency DC lighting system, energized from the

station batteries, is provided for safe exit lighting if all AC

power sources are lost.

Separate 8-hour, battery-powered lighting is provided to support

safe shutdown operations remote from the control room (Reference

Table A-4 of the PBAPS Fire Protection Program). Task lighting is

provided at the sites of the operations. The routes used to

access and egress the sites are also illuminated. See Fire

Protection Program (FPP) for details.

CHAPTER 10 10.22-2 REV. 21, APRIL 2007 10.22.4 Inspection and Testing

The station lighting system is proven operable during normal plant

operation. Loss of offsite power operation can be tested to

ensure operability and integrity of the system.

CHAPTER 10 10.23-1 REV. 23, APRIL 2011 10.23 PLANT AUXILIARY BOILERS 10.23.1 Power Generation Objective

The power generation objective of the plant auxiliary boiler

system is to supply necessary steam for plant uses.

10.23.2 Power Generation Design Basis

1. The plant auxiliary steam system operates independently from the nuclear steam system. Wherever the two systems

have interfaces, a positive means of separation is

provided.

2. The auxiliary steam system is designed to provide operational flexibility to accommodate the seasonal

steam demand.

10.23.3 Description

The plant auxiliary boilers are common to both Units 2 and 3. The

auxiliary steam system consists of two 40,000-lb/hr, oil-fired, water-tube package boilers and associated equipment and

instrumentation (Drawing M-324, Sheets 1, 1A, 2, 2A, 3, 3A, and 4). The boilers have a design and maximum allowable working pressure of 275 psig. The boilers are designed, fabricated, tested, and stamped in accordance with the ASME Boiler and

Pressure Vessel Code,Section I, and the rules and regulations of

the Commonwealth of Pennsylvania.

Process steam (200 psig system) and plant heating steam (50 psig

system) are distributed from the boiler steam outlet header.

Except for cold startup of a boiler or a startup subsequent to a

safety trip, the boiler control system is designed for unattended

operation.

The 200 psig process steam header provides the following process

steam during the plant startup until the nuclear steam pressure is

adequate:

1. Condensate deaeration in the hotwell during startup.
2. Turbine shaft seal steam during startup.

The condensate from this process is not returned to the deaerator

but is drained to the main condenser.

CHAPTER 10 10.23-2 REV. 23, APRIL 2011 10.23.4 Inspection and Testing

The auxiliary steam system is proven operable by its use during

normal plant operation. Portions of the system normally closed to

flow can be tested to ensure operability and integrity of the

system.

CHAPTER 10 10.24-1 REV. 25, APRIL 2015 10.24 EMERGENCY HEAT SINK 10.24.1 Power Generation Objective

The power generation objective of the emergency heat sink is to

provide an onsite heat removal capability so that the reactors of

Units 2 and 3 can be shut down in the event of the unavailability

of the normal heat sink.

10.24.2 Power Generation Design Basis

1. The emergency heat sink has a sufficient capacity for removing the sensible and decay heat from the reactors'

primary systems and auxiliary systems so that the

reactors can be shut down in the event of the

unavailability of the normal heat sink.

2. The emergency heat sink has the heat removal capacity to supply a source of cooling water to the emergency

service water system and the high pressure service water

system when required.

3. The emergency heat sink provides sufficient water storage capacity to permit emergency cooling tower operation until a makeup water supply can be

established.

4. The emergency heat sink can operate during a loss of offsite power and can withstand a seismic event.

10.24.3 Description

The emergency heat sink facility consists of a fireproof, multicell, mechanical, induced-draft cooling tower, constructed as

a seismic Class I structure, with an integral onsite 3.55 million-

gal water storage reservoir (Drawing C-2). The facility operates in conjunction with the high pressure service water pumps (subsection 10.7), the emergency service water pumps (subsection

10.9) at the pump structure, and the emergency service water

booster pumps (Drawing M-330). The equipment, valves, and piping

in the emergency heat sink system are designed in accordance with

seismic Class I criteria. Power requirements are supplied from

the standby power supply. Equipment data is shown in Table

10.24.1.

The high pressure service water pumps take suction from the pump

bays to supply water to the RHR heat exchangers. Sufficient head

is available to pump the return water directly to the emergency

cooling tower. Water supplied from the onsite reservoir flows by

gravity to the pump structure in two full-capacity lines, this

CHAPTER 10 10.24-2 REV. 25, APRIL 2015 flow being regulated by two motor operated flow control valves in series in each line. The emergency service water pumps, also

located in the pump structure, take suction from the pump bays and

supply water to standby diesel generator coolers and the CSCS's

pump room air coolers. The return water from the various coolers

is boosted in pressure by one of two full-capacity emergency

service water booster pumps and delivered to the emergency cooling

tower. After an extended period of time, the fuel pool cooling

system may be served by the emergency service water system by

adding cross connections.

Sluice gates in the pump structure isolate the high pressure

service water and emergency service water pump bays from Conowingo

Pond. These gates are manually closed prior to utilizing the

onsite reservoir.

The cooling tower is a mechanical, induced-draft type consisting

of three cells each capable of handling the heat transfer duty of

one RHR heat exchanger (one HPSW pump) plus the plant auxiliary

cooling requirement (one ESW pump). The tower heat transfer duty

is based on the heat duty occurring when the RHRS operating mode

is switched from the containment (torus) cooling mode to the

shutdown cooling mode at the time the reactor water temperature reaches 300 F. The emergency heat sink system supplies cooling water to two high

pressure service water pumps and one emergency service water pump

continuously until all the nuclear fuel can be shipped offsite.

Makeup water is supplied from an offsite source.

The installed capacity of 3.55 million gal of water stored in the

emergency cooling reservoir is adequate for 1 week of operation

without makeup. Makeup of water to the system will be initiated

as expeditiously as possible after shutdown of the reactors and

will be continued for an indefinite period as required.

After a two-reactor shutdown, assuming the turbine condensers are

not available as heat sinks, it is estimated that continued

operation of the RHRS in the shutdown cooling mode can cool the reactors to 212 F in approximately 12 hr and to 125 F in about 3 weeks. Based on controlled cooling tower operation at the rated flow condition, the total water consumed at the end of 7 days is

approximately 2.9 x 10 6 gal and a makeup rate of 250 gpm will be required after the first week. The turbine-condensers, if available, will be used as heat sinks for the removal of reactor

heat as long as effective. The minimum Conowingo Pond level required for effective operation of the main condenser circulating water pumps is approximately 93.8 feet (C.D.). Note: Water level

CHAPTER 10 10.24-3 REV. 25, APRIL 2015 in the pump bays will be lower due to level differential across the traveling screens.

The offsite makeup water supply to the plant will be made by truck

trailers, or temporary hose lines, and portable pumping equipment

will be available and used to withdraw water from waterholes in

the Susquehanna River or Rock Run Creek. Water transportation

into the plant will be initiated as soon as practicable after the

loss of the dam accident. The 250 gpm makeup rate required 1 week

after reactor shutdown represents about three 5,000 gal water

trucks per hour.

The feasibility of transporting a large quantity of water was

demonstrated during the 1965 drought period in York, Pennsylvania, when several million gallons were delivered by truck daily to the

potable water system of that city. Fuel oil is also delivered (two or three trucks per hour) to several generating stations on

the licensee's system.

10.24.4 Inspection and Testing

To assure that the emergency heat sink will function properly, the

tower and reservoir are inspected for integrity and reservoir

level. The high pressure service water, emergency service water, and emergency cooling water pumps are tested in conjunction with

their systems' testing. Portions of the system normally closed to

flow can be tested to ensure operability and integrity of the

system.

Flow measurement devices are provided in the emergency cooling

water system to facilitate testing of the emergency cooling water

pump and the emergency service water booster pumps in accordance

with AMSE Code requirements.

The timer used to sequence the emergency cooling water pump during

a LOCA will be tested in accordance with surveillance test

procedures. The test will verify the setting, operability, and

functional performance of the relay, and will provide assurance

that the automatic loading sequence will be maintained and will

perform as required.

CHAPTER 10 10.24-4 REV. 21, APRIL 2007 TABLE 10.24.1 EMERGENCY HEAT SINK EQUIPMENT DATA

Design Performance and Type

Type Induced Draft/

Counter Flow Design Wet Bulb Temperature 78.0 F Number of Towers/Number of Cells per Tower 1 / 3 Total Heat Load 357 x 10 6 Btu/hr Water Side High Pressure Flow Hot Water Flow 9,000 gpm Hot Water Temperature 160 F Cold Water Temperature 90 F Evaporation Loss at Rated Flow 7%

Low Pressure Flow Hot Water Flow 8,000 gpm Hot Water Temperature 100 F Cold Water Temperature 90 F Evaporation Loss at Rated Flow 1%

Total Water Concentration/Cell 3.69 gpm/ft 2 Water Load on Tower Base Area 187 gal/ft 2* Hot Water Overload Capability 50% (Approx.) Cold Water Temperature at Overload Flow 96 F

  • Drift Water Loss at Rated Flow

<0.05% Retention Time through Tower 7.0 sec Air Flow Stack Height 20.0 ft Air Flow 8.01 x 10 6 lb/hr Draft Loss Inches 0.633 in H 2 0 Total Fan Power Demand, Bhp at Motor Coupling 185.0/cell

  • Both systems at 50 percent overload.

CHAPTER 10 10.24-5 REV. 21, APRIL 2007 TABLE 10.24.1 (Continued)

Mechanical Equipment (per Cell)

Fans Number 1 RPM 116.7 rpm Blade Material Reinforced Fiberglass Epoxy

Tower and Cell Structure

Tower Height 57 ft 4 in Air Intake Height 10 ft 6 in Cell Dimension 48.0 ft x 48.0 ft Stack Height 20.0 ft

Emergency Cooling Water Pumps For specifications see Table 10.9.1

Emergency Service Water Booster Pumps

Quantity 2 (common to both units)

Pump Design Type Horizontal split Flow/Head 8,000 gpm/100 feet Bhp at Rating 230 Speed 1,170 rpm Number of Stages 1

Material Bowl Bronze Shaft AISI 303 Shaft Sleeve AISI 440c Wear Ring Bronze Impeller/Liner ASTM B143 Bronze

Motor Design Type Horizontal Induc-tion Type Horsepower 250 hp Voltage/Phase/Frequency 4,000 V/3 Phase/

60 Hz