9 to Updated Final Safety Analysis Report, PEA Chapter 00, Cover Page and General Table of Contents
ML23110A246
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 04/10/2023
From:
Constellation Energy Generation
To:
Office of Nuclear Reactor Regulation
Shared Package
ML23110A266 List: ... further results
References
Download: ML23110A246 (1)


Text

Peach Bottom Atomic Power Station Updated Final Safety Analysis Report Revision 29, April 2023

UFSAR General Table of Contents Page 1 of 8 PEACH BOTTOM ATOMIC POWER STATION Updated Final Safety Analysis Report General Table of Contents Chapter 1 Introduction and General Description of Plant Chapter 2 Site Characteristics Chapter 3 Reactor Chapter 4 Reactor Coolant System and Connected Systems Chapter 5 Containment Chapter 6 Core Standby Cooling Systems Chapter 7 Instrument and Control Systems Chapter 8 Electrical Power Systems Chapter 9 Radioactive Waste Systems Chapter 10 Auxiliary Systems Chapter 11 Power Conversion Systems Chapter 12 Structures and Shielding Chapter 13 Conduct of Operations Chapter 14 Plant Safety Analysis Appendix A Pressure Integrity of Piping and Equipment Appendix B Technical Specifications Appendix C Structural Design Criteria Appendix D Quality Assurance Program Appendix E Station Atmospheric Release Limit Calculation Appendix F Interaction of Units 2 and 3 Appendix G Plant Nuclear Safety Operational Analysis Appendix H Conformance to AEC (NRC) Criteria Appendix I In-Service Inspection Program Appendix J Identification Resolution of AEC-ACRS and Staff Concerns Appendix K Reactor Pressure Vessel Design Summary Report Appendix L Fuel and Core Thermal Hydraulic Design Appendix M Containment Report Appendix N Peach Bottom Site Meteorology Appendix O Emergency Plan and Security Plan Appendix P Environmental Technical Specifications Appendix Q License Renewal Aging Management UFSAR Supplement Appendix R Second License Renewal Aging Management UFSAR Supplement FFP Fire Protection Plan Rev. 29, April 2023

UFSAR General Table of Contents Page 2 of 8 Chapter 1 Introduction and General Description of Plant 1.1 Project Identification 1.2 Definitions 1.3 Methods of Technical Presentation 1.4 Classification of BWR Systems, Criteria, and Requirements for Safety Evaluation 1.5 Principal Design Criteria 1.6 Plant Description 1.7 Comparison of Principal Design Characteristics 1.8 Summary of Radiation Effects 1.9 Plant Management 1.10 Quality Assurance Program 1.11 Station Research Development and Further Information; Requirements and Resolutions Summary Chapter 2 Site Characteristics 2.1 Summary Description 2.2 Site Description 2.3 Meteorology 2.4 Hydrology 2.5 Geology and Seismology 2.6 Environmental Radiation Monitoring Program 2.7 Foundation Analysis 2.8 Slope Stability Chapter 3 Reactor 3.1 Summary Description 3.2 Fuel Mechanical Design 3.3 Reactor Vessel Internals Mechanical Design 3.4 Reactivity Control Mechanical Design 3.5 Control Rod Drive Housing Supports 3.6 Nuclear Design 3.7 Thermal and Hydraulic Design 3.8 Standby Liquid Control System Chapter 4 Reactor Coolant System and Connected Systems 4.1 Summary Description 4.2 Reactor Vessel and Appurtenances Mechanical Design 4.3 Reactor Recirculation System 4.4 Nuclear System Pressure Relief System 4.5 Main Steam Line Flow Restrictors 4.6 Main Steam Line Isolation Valves 4.7 Reactor Core Isolation Cooling System 4.8 Residual Heat Removal System 4.9 Reactor Water Cleanup System 4.10 Nuclear System Leakage Detection and Leakage Rate Limits 4.11 Main Steam Lines, Feedwater Piping, and Drains Rev. 29, April 2023

UFSAR General Table of Contents Page 3 of 8 Chapter 5 Containment 5.1 Summary Description 5.2 Primary Containment 5.3 Secondary Containment System Chapter 6 Core Standby Cooling Systems 6.1 Safety Objective 6.2 Safety Design Basis 6.3 Summary Description 6.4 Description 6.5 Safety Evaluation 6.6 Inspection and Testing 6.7 Conformance of Peach Bottom Atomic Power Station Units 2 and 3 Emergency Core Cooling Systems to AEC/NRC Interim Acceptance Criteria for Light Water Reactors Chapter 7 Instrument and Control Systems 7.1 Summary Description 7.2 Reactor Protection System 7.3 Primary Containment and Reactor Vessel Isolation Control System 7.4 Core Standby Cooling Systems Control and Instrumentation 7.5 Neutron Monitoring System 7.6 Refueling Interlocks 7.7 Reactor Manual Control System 7.8 Reactor Vessel Instrumentation 7.9 Recirculation Flow Control System 7.10 Feedwater Control System 7.11 Pressure Regulator and Turbine Generator Control System 7.12 Process Radiation Monitoring 7.13 Area Radiation Monitoring System 7.14 Site Environs Radiation Monitoring Program 7.15 Health Physics and Laboratory Analysis Radiation Monitors 7.16 Process Computer System 7.17 Nuclear System Stability Analysis 7.18 Separate Shutdown Control Panels 7.19 Class 1e Equipment Environmental Qualification 7.20 Accident Monitoring 7.21 Seismic Instrumentation Rev. 29, April 2023

UFSAR General Table of Contents Page 4 of 8 Chapter 8 Electrical Power Systems 8.1 Summary Description 8.2 Generator 8.3 Transmission System 8.4 Auxiliary Power Systems 8.5 Standby AC Power Supply and Distribution 8.6 120 VAC Power System 8.7 125/250 VDC Power Supplies and Distribution 8.8 24 VDC Power Supply and Distribution Chapter 9 Radioactive Waste Systems 9.1 Summary Description 9.2 Liquid Radwaste System 9.3 Solid Radwaste System 9.4 Gaseous Radwaste/Off-Gas System Chapter 10 Auxiliary Systems 10.1 Summary Description 10.2 New Fuel Storage 10.3 Spent Fuel Storage 10.4 Tools and Servicing Equipment 10.5 Fuel Pool Cooling and Cleanup System 10.6 Service Water System 10.7 High-Pressure Service Water System 10.8 Reactor Building Cooling Water System 10.9 Emergency Service Water System 10.10 Turbine Building Cooling Water System 10.11 Chilled Water System 10.12 Fire Protection Program 10.13 Main Control Room Air Conditioning 10.14 Emergency Ventilating Systems 10.15 Plant Heating, Ventilating, and Air Conditioning Systems 10.16 Makeup Water Treatment System 10.17 Instrument Air, Service Air, and Instrument Nitrogen Systems 10.18 Domestic and Sanitary Water System 10.19 Plant Equipment and Floor Drainage System 10.20 Process Sampling System 10.21 Communications Systems 10.22 Station Lighting System 10.23 Plant Auxiliary Boilers 10.24 Emergency Heat Sink Rev. 29, April 2023

UFSAR General Table of Contents Page 5 of 8 Chapter 11 Power Conversion Systems 11.1 Summary Description 11.2 Turbine-Generator 11.3 Main Condenser 11.4 Main Condenser Gas Removal and Sealing Steam Systems 11.5 Turbine Bypass System 11.6 Circulating Water System and Cooling Towers 11.7 Condensate Filter-Demineralizer System 11.8 Condensate and Feedwater Systems Chapter 12 Structures and Shielding 12.1 Summary Description 12.2 Design and Description 12.3 Radiation Shielding 12.4 Radioactive Materials Safety Chapter 13 Conduct of Operations 13.1 Summary Description 13.2 Organizational Structure 13.3 Training 13.4 Pre-Operational Test Program 13.5 Startup and Power Test Program 13.6 Normal Operations and Procedure Control 13.7 Records 13.8 Operational Review and Audits Chapter 14 Plant Safety Analysis 14.1 Analytical Objective 14.2 Unacceptable Safety Results for Abnormal Operational Transients 14.3 Unacceptable Safety Results for Accidents 14.4 Approach To Safety Analysis 14.5 Analyses of Abnormal Operational Transients 14.6 Analysis of Design Basis Accidents 14.7 Conclusions 14.8 Analytical Methods 14.9 Evaluations Using AEC Method Appendix A Pressure Integrity of Piping and Equipment A.1 Summary Description A.2 Classification of Piping and Equipment Pressure Parts A.3 Design A.4 Materials A.5 Welding Procedures and Processes A.6 Fabrication and Erection A.7 Testing and Inspection Requirements A.8 Cleaning A.9 Piping Design Requirements A.10 High Energy Pipe Break Outside The Primary Containment Rev. 29, April 2023

UFSAR General Table of Contents Page 6 of 8 Appendix B Technical Specifications Appendix C Structural Design Criteria C.1 Classification of Structures C.2 Structural Design Basis C.3 Analysis of Class I Structures C.4 Implementation of Structural Criteria C.5 Components Appendix D Quality Assurance Program D.1 Introduction D.2 Deleted D.3 Deleted D.4 Deleted D.5 Deleted D.6 Deleted D.7 Deleted D.8 Deleted D.9 Deleted D.10 Deleted D.11 Quality Assurance During the Operations Phase D.12 Deleted Appendix E Station Atmospheric Release Limit Calculation E.1 Analytical Model E.2 Verification of Analytical Model E.3 Stack Release Limit Calculations for Peach Bottom Site E.4 Building Exhaust Vent Release E.5 All Sources of Airborne Radioactivity E.6 Summary Appendix F Interaction of Units 2 and 3 F.1 Summary Description F.2 Shared Site Facilities F.3 Shared Systems and Equipment F.4 Interaction of Units 2 and 3 Following an Accident Appendix G Plant Nuclear Safety Operational Analysis G.1 Analytical Objective G.2 Introduction G.3 Method of Analysis G.4 Display of Operational Analysis Results G.5 Operational Analyses for Peach Bottom Atomic Power Station G.6 Remainder of Nuclear Safety Operational Analysis Rev. 29, April 2023

UFSAR General Table of Contents Page 7 of 8 Appendix H Conformance To AEC (NRC) Criteria H.1 Summary Description H.2 Criteria Conformance Appendix I In-Service Inspection Program Appendix J Identification Resolution of AEC-ACRS and Staff Concerns J.1 Summary Description J.2 Areas Specified in the Peach Bottom Units 2 and 3 AEC-ACRS Construction Permit Letter J.3 Areas Specified in the Peach Bottom Units 2 and 3AEC Staff Construction Permit Safety Evaluation Report J.4 Areas Specified in Other Related AEC-ACRS Construction and Operating Permit Letters J.5 Areas Specified In Other Related AEC-Staff Construction or Operating Permit Safety Evaluation Reports Appendix K Reactor Pressure Vessel Design Summary Report K.1 Design and Fabrication Requirements Appendix L Fuel and Core Thermal Hydraulic Design Appendix M Containment Report M.1 Introduction and Summary M.2 Basis for Containment Design M.3 Containment System Design M.4 Initial Overload and Leakage Rate Test Appendix N Peach Bottom Site Meteorology N.1 Introduction N.2 Two-Year Meteorology Summaries by Location, Wind Direction, Wind Speed, Turbulence Class, and Season N.3 Three-Year Annual Meteorology Summaries by Location, Wind Direction, Wind Speed, and Turbulence Class N.4 Three-Year Annual Meteorology Summaries by Location, Wind Direction, Wind Speed, and Lapse Rate Appendix O Emergency Plan and Security Plan 0.1 Emergency Plan 0.2 Security Plan Appendix P Environmental Technical Specifications Rev. 29, April 2023

UFSAR General Table of Contents Page 8 of 8 Appendix Q License Renewal Aging Management UFSAR Supplement Q.0 Introduction Q.1 Existing Aging Management Activities Q.2 Enhanced Aging Management Activities Q.3 New Aging Management Activities Q.4 Time-Limited Aging Analyses Activities Q.5 Time-Limited Aging Analyses Summaries Q.6 References Appendix R Second License Renewal Aging Management UFSAR Supplement R.1 Introduction R.2 Aging Management Programs R.3 NUREG-2191 Chapter X Aging Management Programs R.4 Time-Limited Aging Analyses R.5 Second License Renewal Commitment List Fire Protection Plan Chapter 1 Introduction Chapter 2 Fire Protection System Description Chapter 3 Comparison Between PBAPS Fire Protection Program and NRC Guideline Documents Chapter 4 Evaluation of Potential Fire Hazards Chapter 5 Analysis of Capability to Achieve Safe Shutdown Chapter 6 Special Topics Chapter 7 Fire Protection Requirements Rev. 29, April 2023