Crystal River, Unit 3 - Response to Request for Additional Information Re Certified Fuel Handler Training and Retraining Program
ML13225A495
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 07/24/2013
From: Hobbs T
Duke Energy Florida
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
3F0713-06
Download: ML13225A495 (4)


Text

ENERiGY.Crystal River Nuclear Plant15760 W. Power Line StreetCrystal River, FL 34428Docket 50-302Operating License No. DPR-7210 CFR 50.2July 24, 20133F0713-06 U.S. Nuclear Regulatory Commission Attn: Document Control DeskWashington, DC 20555-0001

Subject:

Reference:

Crystal River Unit 3 -Response to Request for Additional Information Regarding the Certified Fuel Handler Training and Retraining ProgramCR-3 to NRC letter dated April 15, 2013, "Crystal River Unit 3 -Request forApproval of the Certified Fuel Handler Training and Retraining Program"(ADAMS Accession No. ML13130A1 25)

Dear Sir:

In accordance with 10 CFR 50.2, Duke Energy Florida, Inc., formerly known as Florida PowerCorporation, hereby submits the response to a Nuclear Regulatory Commission (NRC) requestfor additional information (RAI) received during a teleconference between the NRC ProjectManager and Crystal River Unit 3 (CR-3) on June 27, 2013 regarding the April 15, 2013submittal (Reference).

The attachment to this letter provides the RAI response.

There are no new regulatory commitments made within this submittal.

If you have any questions regarding this submittal, please contact Mr. Dan Westcott, Licensing Supervisor, at (352) 563-4796.

Sincerely, Terry; Hb~bDecommissioning DirectorCrystal River Nuclear PlantTH/samAttachment Response to Request for Additional Information

-Certified Fuel Handler Trainingand Retraining Programxc: NRR Project ManagerRegional Administrator, Region IISenior Resident Inspector DUKE ENERGY FLORIDA, INC.DOCKET NUMBER 50 -302 / LICENSE NUMBER DPR -72ATTACHMENT RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION CERTIFIED FUEL HANDLER TRAININGAND RETRAINING PROGRAM U. S. Nuclear Regulatory Commission Attachment 3F0713-06 Page 1 of 2RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION

-CERTIFIED FUELHANDLER TRAINING AND RETRAINING PROGRAMBy letter dated April 15, 2013 (Reference 1), Duke Energy Florida, Inc., formerly known asFlorida Power Corporation, requested approval of the Certified Fuel Handler (CFH) Training andRetraining Program for Crystal River Unit 3 (CR-3). On June 27, 2013, during a teleconference between the Nuclear Regulatory Commission (NRC) Project Manager and CR-3, the NRCasked the following question:

REQUEST FOR ADDITIONAL INFORMATION Is the CR-3 CFH Training and Retraining Program in conformance with Regulatory Guide 1.8,"Qualification and Training of Personnel for Nuclear Power Plants"?Response:

The CR-3 CFH Training and Retraining Program will conform to the requirements in Regulatory Guide 1.8, Revision 1, with clarifications.

CR-3 Final Safety Analysis Report, Table 1-3, "CrystalRiver Unit 3 Quality Program Commitments,"

will be revised after the CFH Training andRetraining Program and License Amendment Request (LAR) #313 (Reference

2) are approvedby the NRC. The wording in Table 1-3 will be revised to identify:

-Requirements for Senior Reactor Operator (SRO) Licenses will be replaced with CFHcertification upon approval of LAR #313.-Years of power plant experience and nuclear experience remain applicable, but thespecific experience requirements of power operation above 20 percent full power,startup, and shutdown, identified by the American National Standards Institute (ANSI) inANSI/ANS 3.1-1981, "Selection, Qualification and Training of Personnel for NuclearPower Plants,"

sections 4.3.1.1.b, "Shift Supervisor Experience,"

and 4.3.1.2.b, "SeniorOperator Experience,"

which refer to operating modes that will not occur, are no longerapplicable based upon the permanently shut down and defueled condition of CR-3(Reference 3).-The Shift Supervisor and SRO training programs will no longer be accredited by theInstitute of Nuclear Power Operations, once the licenses are terminated.

The CFH Training and Retraining Program will be based on a systems approach to training(SAT), in accordance with Section 50.120 of Title 10 of the Code of Federal Regulations, "Training and qualification of nuclear power plant personnel,"

and ANSI/ANS 3.1-1981.

As aconsequence, but in accordance with the SAT process, some items on the detailed list of courseinstruction provided in ANSI/ANS 3.1-1981, sections 5.2.1.1, "Nuclear Power PlantFundamentals,"

5.2.1.2, "Plant Systems,"

and 5.2.1.6, "Senior Reactor Operator Instruction,"

may be deleted from the program as they no longer become applicable to a decommissioning plant.

U. S. Nuclear Regulatory Commission Attachment 3F0713-06 Page 2 of 2REFERENCES

1. CR-3 to NRC letter dated April 15, 2013, "Crystal River Unit 3 -Request for Approval ofthe Certified Fuel Handler Training and Retraining Program" (ADAMS Accession No.ML13130A125)
2. CR-3 to NRC letter dated April 25, 2013, "Crystal River Unit 3 -L icense Amendment Request #313, Revision 0, Revision to Improved Technical Specifications Administrative Controls for Permanently Defueled Conditions" (ADAMS Accession No. ML13128A286)