ML13197A118

From kanterella
Revision as of 01:36, 22 June 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Supporting Documentation for July 22, 2013, Regulatory Conference to Discuss Inspection Report 05000266/2013011 and 05000301/2013011, Preliminary Yellow Finding
ML13197A118
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 07/15/2013
From: Meyer L
Point Beach
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-13-125, IR-13-011, NRC 2013-0069
Download: ML13197A118 (45)


See also: IR 05000266/2013011

Text

July 15, 2013 U.S. Nuclear Regulatory

Commission

ATTN: Document Control Desk 11555 Rockville

Pike Rockville, MD 20852 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 NEXT era POINT BEACH NRC 2013-0069

Supporting

Documentation

for July 22. 2013. Regulatory

Conference

to Discuss Inspection

Report 05000266/2013011

and 05000301/2013011.

Preliminary

Yellow Finding References:

1) U.S. Nuclear Regulatory

Commission, Point Beach Nuclear Plant, Units 1 and 2 NRC Integrated

Inspection

Report 05000266/2013011

and 05000301/2013011;

Preliminary

Yellow Finding, dated June 18, 2013. (ML 13169A212)

2) Point Beach letter NRC-2013-0054

Response to Inspection

Report 050000266/2013011;

Preliminary

Yellow Finding, dated June 28, 2013. (ML 13179A333)

On June 18, 2013, the Nuclear Regulatory

Commission (NRC) provided NextEra Energy Point Beach, LLC (NextEra)

with the results of the Temporary

Instruction (TI) 2515-187, "Inspection

of Near-Term

Task Force Recommendation

2.3 Flooding Walk Downs," conducted

at the Point Beach Nuclear Plant (PBNP) during the first quarter of 2013, describing

a performance

deficiency

related to the PBNP implementation

of certain procedures

intended to mitigate postulated

flooding events (Reference

1 ). The Reference

1 letter further informed NextEra that NRC had preliminarily

determined

that the significance

of the identified

performance

deficiency

was yellow. On June 28, 2013, NextEra requested

a Regulatory

Conference

to discuss the significance

determination (Reference

2). The requested

Regulatory

Conference

has been scheduled

for July 22, 2013. NextEra has thoroughly

reviewed the issue raised in the Reference

1 letter, and has concluded

that the Individual

Plant Examination

for External Events (IPEEE) contains estimates

and assumptions

that are overly conservative

and it is not appropriate

to use in the safety significance

determination

for this performance

deficiency.

Therefore, NextEra has performed

substantial

additional

analyses utilizing

more recent best-available

information

and modeling to more accurately

determine

the potential

safety significance

of the identified

performance

deficiency.

Using the updated external flooding analysis and Probabilistic

Risk Assessment

NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

Document Control Desk Page 2 (PRA) models of the effects of postulated

flooding is the correct tool for assessing

the safety significance

of the performance

deficiency

.. The results of the updated analyses clearly demonstrate

that the safety significance

of the performance

deficiency

is very low. As requested

in Reference

1, NextEra has provided both a summary description

of the updated analyses and an explanation

of the results in the Enclosure

to this letter. Attachment

1 conta i ns the updated wave run-up analysis performed

by NextEra's independent

contractor.

Attachment

2 is an updated safety significance

determination

analysis showing that the safety significance

of the performance

deficiency

is very low, with margin. Attachment

3 prov i des an explanation

of the PBNP design, showing that the r unning Service Water pumps would continue to operate following

a loss of DC control power. Finally, Attachment

4 is an analysis of the rates of rise of Lake Michigan during various postulated

flooding events, showing that PBNP would have more than eight weeks to respond to pre-storm

level changes before the station's license basis flood level would occur. NextEra looks forward to discussing

these documents, together with our assessment

of the very low safety significance

of the performance

deficiency , in greater detail during the upcoming Regulatory

Conference. This letter contains no new Regulatory

Commitments

and no revisions

to existing Regulatory

Commitments.

If you have any questions

or require additional

information, please contact Mr. Ron Seizert , Licensing

Supervisor

at (920)755-7500.

Very truly yours, NextEra Energy Point Beach, LLC L c Site Vice President

Enclosure

cc: Administrator , Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC Branch Chief, Plant Support, Division of Reactor Safety, Region Ill, USNRC

ENCLOSURE

NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT UPDATED FLOODING ANALYSIS AND SIGNIFICANCE

DETERMINATION

Executive

Summary The NRC preliminary

significance

determination

for the performance

deficiency (Reference

1) was based on determining

the change in Core Damage Frequency (CDF) using the Individual

Plant Examination

of External Events (IPEEE). NextEra has developed

an updated , more accurate storm surge/wave

run-up analysis which provides a more reliable analytical

basis for assessing

the associated

safety significance

of the postulated

flooding event. The application

of this more accurate approach shows that the identified

performance

deficiency

is of very low safety significance, with margin. Description

of the Updated Flooding Analysis and Resulting

Significance

Determination

The external flooding analysis for Point Beach Nuclear Plant (PBNP) contained

in the station's

IPEEE is dominated

by overly conservative

estimations

and assumptions.

These estimations

and assumptions

include the resultant

water elevations, environmental

conditions, equipment

elevations, and site configuration

and topography.

The cumulative

effect of these overly conservative

assumptions

results in significantly

overestimating

the impact of external flooding events, including

wave run-up. In order to better determine

the safety significance

of the identified

performance

deficiency, NextEra retained an expert independent

engineering

firm to update the station's

external flooding analysis utilizing

more recent and more accurate data. The updated analysis assumes the same initiating

still water level frequencies

as those used in the IPEEE. Further, the updated analytical

model utilizes actual plant structures, configuration, topography, and near-shore

bathymetric

survey data in calculating

the range of water levels and associated

wave run-up conditions.

The updated model included no off-setting

credit for any of the flood/wave

run-up mitigation

actually in place at PBNP to determine

water levels outside of the Turbine Building.

The calculated

water level provides the effective

driving head for any potential

water intrusion

into the Turbine Building.

NextEra performed

analysis of the potential

water flow paths in the Turbine Building to determine

the time it takes to accumulate

sufficient

water to impact safety significant

equipment.

A computer model was used to conduct this analysis, based on plant flow paths and rates, which were validated

by walk-downs. Water flow rates were determined

by calculating

flow under doors, over curbs, and through other building characteristics. It would take greater than three hours for water outside the turbine building to impact the Residual Heat Removal (RHR) Pumps and their suction valves from Containment

Sump B. However, for the purpose of simplification

and to build additional

margin into the analysis, the water was assumed to reach equilibrium

inside and outside the buildings

at time zero for the purpose of determining

impact to equipment.

Finally, the calculated

water level outside the Turbine Building was used as an input to the PBNP Probabilistic

Risk Assessment (PRA) to evaluate the risk significance

of the postulated

Page 1 of 8

flooding/wave

run-up scenarios.

This updated risk significance

determination

assumed that the external flooding wave run-up protection

mitigation

features described

in the PBNP Final Safety Analysis Report (FSAR) were not in place. The resulting

significance

determination, using the updated analysis and conservative

assumptions

described

above, demonstrate

that the safety significance

of the performance

deficiency

is very low, with margin. Evaluation

of Flood/Wave

Run-Up, Water Levels and Potential

Equipment

Impacts The PBNP external flooding analysis had been updated to more accurately

predict the potential

flooding/wave

run-up impact on PBNP and the result of the revised analysis was used to assess the potential

impact of the calculated

water levels on plant equipment.

The equipment

impact analysis utilizes the same initial conditions

contained

in the FSAR, updated to include actual site topography, offshore bathymetry

and the as-built shore-line

configuration

to calculate

expected wave phenomena

at various lake levels, including

those of very long recurrence

intervals (e.g., high lake levels). The resultant

wave phenomena

were then used as input data for the DELFT3D computer model, a state of the art model that can simulate both two dimensional (in either the horizontal

or vertical plane) and three dimensional

flow, to analyze Lake Michigan behaviors

during external flooding events and to determine

the resulting

effect of wave run-up at PBNP. The DELFT3D model has been accepted by industry experts and industry organizations

including

more than 70 countries

world-wide that use DEL TARES hydrology

modeling programs and is being used extensively

for post-Fukushima

flood hazard analyses.

The DELFT3D model has also been recently used by several other nuclear plants to demonstrate

compliance

with NRC requirements, including:

  • South Texas Project, Units 3 and 4 COLA and FSAR (Delft3D-FLOW) for breach and wave modeling * Turkey Point Units 6 and 7 (Delft3D-FLOW), tsunami wave analysis * Turkey Point Units 3 and 4 flood hazard reevaluation
  • Nine Mile Point (NMP) (DELFT-SWAN), for

near shore wave heights and periods * Calvert Cliffs used DELFT for storm surge for COLA and flood hazard reevaluation

  • Victoria County Station Early Site Permit Application (Delft3D-FLOW)

for Cooling Basin Breach Analysis Accordingly, NextEra is confident

that its updated engineering

evaluation

of potential

wave run-up effects at PBNP provides the best available

information

to use for safety significance

determinations.

Comparison

of the Updated Storm Surge/Wave

Run-up Analysis to the PBNP IPEEE Analysis The most limiting flooding from Lake Michigan is a function of the still water lake level plus wind generated

waves. To estimate the frequency

of flooding at PBNP, the IPEEE utilized a statistical

frequency

distribution

that was estimated

from Lake Michigan gauge data. This still Page 2 of 8

water lake level has also been used in the updated Storm Surge/Wave

Run-up Analysis (Updated Wave Run-Up Analysis)

as a starting point for the modeling.

However, although the IPEEE utilizes an estimated

wave run-up, it does not describe the estimation

methodology

utilized to determine

its results. It is clear, however, that the IPEEE estimation

methodology

does not take into account site specific shoreline

and near-shoreline

configurations, which are very important

for an accurate determination

of the storm effects. The Updated Wave Run-Up Analysis, on the other hand, utilizes state of the art modeling and analytical

methods, and updated site-specific

input data to determine wave set-up

and wave run-up. Like the IPEEE, the Updated Wave Run-Up Analysis also utilizes conservative

assumptions

for evaluating

the depth of water between the Turbine Building and Pumphouse.

Specifically, both analyses assume the following:

  • Yard drains do not contribute

to runoff from flooding.

  • There are no relief paths from flooding (e.g., Turbine Building floor drains and Pumphouse

relief paths). The IPEEE utilizes simplified, conservative

estimates

for the amount of water that would accumulate

between the Turbine Building and the Pumphouse

from wave run-up, but again the IPEEE does not describe the estimation

methodology

used to determine

the presented

results. The Updated Wave Run-Up Analysis incorporates

license basis deep water wave heights, more extensive

local and offshore bathymetry, and the as-built shore-line configuration

and characteristics

to calculate

expected wave response at various still water levels. In determining

the equipment

impacted, the internal water levels were assumed conservatively

to equal the calculated

outside water levels at time zero. A comparison

of the overly conservative

IPEEE and the more accurate Updated Wave Run-Up Analysis showing the differences

in calculated

water level between the PBNP Turbine Building and Pumphouse, is presented

below. Summary of Water Levels IPEEE vs. PBNP Updated Analysis Water Level Resulting

Frequency

of Extrapolated

from Calculated Water Water

Level in Still Water Level Still Water the IPEEE Level (With Wave Turbine (ft-IGLD 1955) Level Estimates (ft-Run-up) Building (yr-1) (ft-IGLD 1955) (inches above IGLD 1955) floor) 583.00 1.4E-02 587.60 583.96 0 585.00 3.2E-04 588.37 585.84 0 586.00 5.4E-05 588.73 587.24 0 587.00 4.2E-06 589.24 588.51 3.7" 587.64 9.9E-07 589.53 588.89 8.3" Page 3 of 8

These results demonstrate

that the IPEEE was overly conservative

in estimating

the water level between the Turbine Building and Pumphouse

and is not appropriate

for use in assessing

safety significance

because it is not the best-available

information.

The result of the Updated Wave Run-Up Analysis is appropriate

input to determine

the safety significance

of the performance

deficiency.

The following

Figure shows the levels resulting

from the updated analysis.

Page 4 of 8

Simplified

PBNP Plant Elevation

with Calculated

Water Level (Not to Scale) Turbine Building I PEEE Describes

Lake L evel of 587' and Wave Run-Up to 596' with Frequency

of 4.2E-6. Updated analysis of lake leve l of 587' with wave run-up, results in calculated

water l evel of 588.51'. PU M PHOUSE VSR I EDG 588.2'-Turbine Building Floor 588.51' -Calculated

Water Level @ Turbine Building [ 587'-IPEEE Still Lake ] I 581.9'-Des i gn Bas i s Fl ood 580.7' -I nsta ll Je rs ey B a rri ers 576'-Appro xi m a t e C u rre n t La k e Mich i gan Lev e l Page 5 of 8

Results of the Updated Wave Run-Up Analysis The Updated Wave Run-Up Analysis shows that the calculated

water levels between the Turbine Building and Pumphouse

would be 588.51 feet of water IGLD 1955 for the event frequency

of 4.2E-06/year-much

less severe than estimated

in the IPEEE. The detailed engineering

evaluation

supporting

NextEra's

Updated Wave Run-Up Analysis is provided in Attachment

1. Point Beach Revised External Flood PRA The still water level flood exceedance

frequencies

from the IPEEE were utilized in Next E ra's updated analysis so that the impacts from this updated analysis could be compared to the same flood frequencies

used by the NRC. With the results from the updated external flooding analyses, conditional

core damage probability

was calculated

using the updated RG 1.200 internal events model. Point Beach letter NRC-2013-0054

Response to Inspection

Report 50000266/2013011 (Reference

2) provided a list of potentially

vulnerable

equipment

impacted by accumulating

water up to 589.2 feet (IGLD 1955). NextEra's

updated analysis conservatively

assumed an internal water level of 588.51 feet (IGLD 1955) based on the same calculated

water level outside the Turbine Building.

This internal water level impacts only the Residual Heat Removal (RHR) pumps and RHR pump suction from Containment

Sump B, therefore

this equipment

is not available

in the revised PRA evaluation. Based on the equipment

impacts described

above , the PRA results indicate that the risk due to external flooding (without barriers)

is very low, with a Core Damage Frequency (CDF) equal to 2.83E-07/year. The associated

change in risk with and without barriers was also determined

to be ve r y low, with a change in CDF equal to ?E-09/year.

The NRC's preliminary

significance

determination

of the performance

deficiency

was based on the 1995 Point Beach IPEEE inputs and assumptions.

This determination

calculated

a conditional

core damage probability

of 2. ?E-02/yr.

and a change in CDF of 1.8E-05/yr.

NextEra's

updated analysis demonstrates

that the IPEEE assumptions

of wave run-up levels and final water levels at and in the Turbine Building were overly conservative.

Principle

contributors

to the differences

in overall safety significance

include the site topography, the existing site layout and features, equipment

elevations, and environmental

conditions.

Each of these items has been considered

in the updated detailed modeling described

herein. Attachment

2 provides the supporting

information

associated

with the PRA evaluation.

Continued

Service Water Pump Availability

with Loss of DC Control Power A significant

contributor

to the difference

between the NextEra and the NRC staff estimated

change in CDF with failure of equipment

up to 589.2 feet IGLD 1955 is the PRA modeling of Service Water (SW) pump availability

upon loss of DC control power. NRC's SPAR model contains a presumption

that the SW pump becomes unavailable

upon loss of DC power. Page 6 of 8

The SW pumps remain available

throughout

this event. If operating

at the time DC power is lost, the SW pumps would continue to operate, because DC power is required to open the breaker supplying

AC power to the pumps. In other words, if DC power is lost, the breakers cannot open to turn off the running SW pumps. If the pumps are not operating

at the time DC power is lost, operators

can start pumps by either realigning

DC control power supplies and/or through local manual operation

of their respective

breakers.

Both actions are directed by existing site procedures

upon loss of DC power. The actions for switching

to the alternate

DC control power source and local operation

of SW pumps, including

flow control, are directed by site procedures. These actions were re-validated

by walk-downs with Auxiliary

Operators

and observed by independent

Nuclear Oversight (NOS) observations.

The validation

indicated

that the actions can be completed within one

hour. Finally, these actions are included in Operator training and evaluation

programs.

Attachment

3 provides the supporting

information

associated

with SW pump availability. Lake Michigan Level Rate of Rise Lake Michigan is a very large body of water and changes in level are very slow in comparison

to river level changes. The PBNP original Final Facility Description

Safety Analysis Report (FFDSAR) section discussing

flooding does not address a rate of rise for the lake, so an evaluation

was performed

to establish

the time that is available

to respond to rising lake levels. The rate of rise in lake level was calculated

using National Oceanographic

and Atmospheric

Administration (NOAA) historical

lake data for the 95 year period from 1918 through 2013. During this period, the greatest increase in Lake Michigan level during a single month was 0.85 ft. The evaluation

concluded

that the time available

to respond to rising Lake Michigan prestorm levels would be approximately

eight weeks from the level at which PBNP procedures

require wave run-up barrier construction

initiation

(580. 7 feet IGLD 1955) until conditions

for the license basis maximum wave run-up could be reached. With respect to the identified

performance

deficiency, this eight week time period provides significant

opportunity

to identify and correct deficiencies

with flood barriers.

The updated analysis performed

in support of this evaluation

contains significant

margin, including

that the PRA analysis does not account for the significant

time available

for Operators

to take actions in response to rising lake levels. Attachment

4 provides the supporting

information

associated

with the rate of change in Lake Michigan water level and required Operator actions. Conclusion

The updated external flooding analysis shows that the frequency

of reaching a calculated

water level that impacts safety related equipment

is very low. The PRA analysis, using the calculated

water levels, determined

that affected equipment

results in a very low CDF. Therefore, the failure to establish

adequate procedure

requirements

to implement

external flooding wave run-up protection

features as described

in the FSAR has very low safety significance, based on the calculated

change in CDF of 7E-09/yr.

The Individual

Plant Examination

for External Events (IPEEE) contains estimates

and assumptions

that are overly conservative

and it is not appropriate

to use in the safety significance

determination

for this performance

deficiency.

The IPEEE estimated

that water levels would be substantially

higher with the same input assumptions, because of the many simplifications

that were used at the Page 7 of 8

time. With more accurate site information

and a more rigorous tool for analysis, the conservatisms

of the IPEEE were shown to be excessive.

Attachments

1) Calculated

Average External Water Levels at Turbine Building 2) Point Beach Revised External Flood Safety Significance

Determination

3) Continued

Service Water Pump Availability

with Loss of DC Control Power 4) Lake Michigan Level Rate of Rise Page 8 of 8

ATTACHMENT

1 NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT CALCULATED

AVERAGE EXTERNAL WATER LEVELS AT TURBINE BUILDING 20 Pages Follow

CALC. NO. CALCULATION

COVER SHEET FPL-076-CALC-004 N E RC O N REV. 1 PAGE NO. 1 of 20 Title: Calculated

external average water levels at turbine building Client: NextEra Energy (NEE) Project: FPLPB025 Item Cover Sheet Items Yes No 1 Does this calculation

contain any assumptions

that require confirmation?

X (If YES, identify the assumptions)

2 Does this calculation

serve as an "Alternate

Calculation"? (If YES, identify the X design verified calculation.)

Design Verified Calculation

No. 3 Does this calculation

supersede

an existing calculation? (If YES, identify the X superseded

calculation.)

Superseded

Calculation

No. Scope of Revision:

Text revised on Page 15 Revision Impact on Results: No impact to results. Text only. Study Calculation

D Final Calculation Safety-Related Non-Safety Related D (Print Name and Sign) Originator:

Shaun W. Kline . o , Date: 0 7/1 Si z_n 1 3 Design Verifier:

Justin Pistininzi

(;16-

......._...

Date: o ? /1 1.-/ ":l '0/J Approver:

Paul Martlnchlch

/ '-:J.z (j AA ... Date: t7 7 J1 0 J U)3 /

CALC. NO. CALCULATION

FPL-076-CALC-004

REV. 1 REVISION STATUS SHEET PAGE NO. 2 of 20 CALCULATION

REVISION STATUS REVISION DATE DESCRIPTION

1 July 15, 2013 Initial Issue PAGE REVISION STATUS PAGE NO. REVISION PAGE NO. REVISION All pages 1

REVISION STATUS Attachment

NO. PAGE NO. REVISION NO. Attachment

NO. PAGE NO. REVISION NO. All Attachments

All Pages 1

CALC. NO * .. CALCULATION

FPL-076-CALC-004

I j I E N ERC ON DESIGN VERIFICATION

PLAN REV. 1 AND SUMMARY SHEET PAGE NO. 3 of20 Calculation

Design Verification

Plan: Apply CSP Number 3.01, Revision 6, Section 4.5.a, Design Review Method and to include at a minimum: 1. Review and verify the design inputs, references

and tables to ensure that the Calculations

Results, as they conform to the design methodology

and design guidance, are correct. (Print Name and Sign for Approval-mark "NIA" if not required)

Approver:

Paul Martinchich Date: 07/ >:s-)"A?J J 3 Calculation

Design Verification

SummarY':

After reviewing

this calculation

and all related documents

for Revision 0, I have come to the following

conclusions:

1. The methodology, design inputs and approach are appropriate

for the derivation

of all calculated

results. 2. The results of the Calculation

are reasonable

based on verified input values. 3. The report text and general flow of the document is clear and concise. Based on the above summary, the calculation

is determined

to be acceptable. (Print Name and Sign) Design Verifier:

Justin Pistininzi

S/eZJ_p/-_ Date: 0 7/tr::-/ 'J-o£3. Others: N/A ?/"' Date: I I

CALC. NO. FPL-076-CALC-004

I W EN E RCON CALCULATION

DESIGN VERIFICATION

REV. 1 CHECKLIST

PAGE NO. 4 of20 Item Cover Sheet Items Yes No N/A 1 Design Inputs -Were the design inputs correctly

selected, referenced (latest X revision), consistent

with the design basis and incorporated

in the calculation?

2 Assumptions-

Were the assumptions

reasonable

and adequately

described, X justified

andfor verified, and documented?

3 Quality Assurance-

Were the appropriate

QA classification

and requirements

X assigned to the calculation?

4 Codes, Standard and Regulatory

Requirements-

Were the applicable

codes , X standards

and regulatory

requirements, including

issue and addenda, properly identified

and their requirements

satisfied?

5 Construction

and Operating

Experience

-Has applicable

construction

and X operating

exper i ence been considered?

6 Interfaces-

Have the design interface

requirements

been satisfied, including

X interactions

with other calculations?

7 Methods -Was the calculation

methodology

appropriate

and properly applied X to satisfy the calculation

objective?

8 Design Outputs-Was the conclusion

of the calculation

clearly stated, did it X correspond

directly with the objectives

and are the results reasonable

compared to the inputs? 9 Radiation

Exposure-Has the calculation

properly considered

radiation

X exposure to the public and plant personnel?

10 Acceptance

Criteria -Are the acceptance

criteria incorporated

in the X calculation

sufficient

to allow verification

that the design requirements

have been satisfactorily

accomplished?

11 Computer Software -Is a computer program or software used, and if so, are X the requirements

of CSP 3.02 met? COMMENTS: (Print Name and Sign) Design Verifier:

Justin Plstlnlnzi Date: D7 It s/ J..o£3. Others: N/A ,?/ Date: I

E N ERCO N CALCULATION

CONTROL S H EE T T AB L E O F C ONT E NT S C ALC. NO. F PL-076-CALC-004

R E V. 1 PAG E NO. 5 of 20 1. PURPOSE AND SCOPE ............................................................

.........................................................

....... 6 2. SUMMARY OF RESULTS AND CONCLUSIONS

............................................................................

.........

6 3. REFERENCES

..........

.............

.................................................................................................................... 9 4. ASSUMPTIONS

..............................

................................................................................

.......................... 10 5. DESIGN INPUTS ..............................................

......................................

.............................

..................... 10 6. METHODOLOGY

........................................................................................................

...................

.......... 11 7. CALCULATIONS

............................

......................................

.................................................................... 14 List of Figures FIGURE 1-1: COASTAL INUNDATION

COMPONENTS

......................................................

........................

.... 6 FIGURE 2-1: OBSERVATION

POINTS AT POINT BEACH NUCLEAR PLANT (PBNP) .....................

............

8 FIGURE 6-1: EFFECTIVE

RUNUP SCHEMATIC

...............................

............

..............

.................................. 14 FIGURE 7-1: MAXIMUM WAVE BREAKING DISTANCE OF THE LARGEST WAVES NORMAL TO THE SOUTHWEST

CORNER OF THE PUMP HOUSEfTURBINE

BUILDING AT POINT BEACH NUCLEAR PLANT (PBNP) ........................................................................................................

........................... 18 FIGURE 7-2: SCHEMATIC

OF RESULTS FROM TABLE 7-3 FOR SWL=587.00 FT-IGLD55

USING TH9 MEAN WAVE SETUP .......................

......................

...........................

......................

....................

....... 19 List of Tables TABLE 5-1: INCIDENT WAVE RUN UP AND WATER ELEVATION

CALCULATION

INPUTS ........................ 10 TABLE 7-2: CALCULATION

RESULTS FOR THE MAXIMUM STRUCTURAL

LOADING ANALYSIS ...........

16 TABLE 7-3: CALCULATION

RESULTS FOR THE AVERAGE EXTERNAL WATER LEVEL PROXIES ON THE TURBINE BUILDING ...................................................................................................

................. 17

E N ERCO N CALCULATION

CONTROL SHEET 1. Purpose and Scope CALC. NO. FPL-076-CALC

-004 REV. 1 PAGE NO.6 of 20 This calculation

is performed

under NextEra Energy (NEE) contract order 02306247 to determine

a(n) * average water level proxy at the turbine building for the PRA leakage analysis, and * maximum water level proxy at the turbine building for a structural

loading analysis on the turbine building's

rollup doors and the jersey barriers due to effects of storm surge in Lake Michigan at the Point Beach Nuclear Plant (PBNP). The purpose of this calculation

is to provide a calculation

by empirical

relationship

of incident wave run up elevations

beyond the standing water elevation, which is comprised

of the still water level (SWL) and wave setup (FEMA, 2005; Dean and Dalrymple, 2007; USACE, 2011). The initial SWL is prescribed

and the wave setup is computed by the DELFT3D model (ENERCON , 2013a). Wave runup includes many simultaneous

processes , and is the sum of static wave setup, dynamic wave setup, and incident wave runup (swash), as shown in Figure 1-1. To adequately

address the water elevations

on critical infrastructure

at PBNP, an empirical

relationship

computation

of the latter parameter (incident

wave runup) is required.

Proxies for critical total water elevations (which include the combined effects of SWL, wave setup, and individual

wave swash) on the turbine building are also computed. Results and conclusions

from this calculation

can be used to determine

the effect of waves and flooding on the turbine building at PBNP. For instance, the calculated

average water levels can be used to compute water leakage into the building and the maximum water level can be used to determine

the highest forces against the turbine building rollup doors. In ci dent I ************** ****** Coastal Inundation

Components (adapted from USACE. 2012) I ********************************************...

.......... ':::.::::.:.:**************** .. . Wav e Setup ******************** \ \. .... ** ******** Stand i ng Water Eleva l i on .. 2 J _ / ** ............ ** Still Wa t er level SWL Wind S elul

level)

Pre-slormAnl e cedent ----Water level (of la k e Mich i gan) G) Determined

In CLB (FSAR & IPEEE) Calculated

by Numerical

Modeling (DELFT3D)

@ Hand-Calculated

by Empirical

Relationships (FEMA & USACE) Note: Drawing not lo s ca le Figure 1-1: Coastal Inundation

Components

2. Summary of Results and Conclusions Conservative parameters

were used whenever available

in this analysis. Where conservative

values were not available, reasonable

inputs in accordance

with industry standard practice and justification

were used. Therefore, the results of this analysis are bound i ng for PBNP.

ENERCON CALCULATION

CONTROL SHEET CALC. NO. FPL-076-CALC-004

REV. 1 PAGE NO.7 of 20 This analysis first considered

incident wave runup, which empirically

has been shown to be a function of deep-water

characteristics

and beachface

slope (Stockdon, 2006; FEMA, 2005; Dean and Dalrymple, 2007; USAGE, 2011 ), to help determine

a total water elevation

above the still water level and wave setup components

modeled in DELFT3D (ENERCON, 2013a). Beach/beachface

characteristics

and breaking wave locations

were found near the southwest

corner of the pump house adjacent to the turbine building (observation

point BP2, see Figure 2-1), where ponding occurs in the most severe cases (ENERCON, 2013a). We also provide a water elevation

proxy considering

the mean setup, rather than the peak surge level simulated

in DELFT3D (ENERCON, 2013a). The calculated

average setup method produces a maximum mean water level proxy of 0.31 feet on the turbine building (588.51 ft-IGLD) during the case IPEEE still water level elevation

of 587 ft-IGLD55 (PBNP, 1995; PBNP, 2013). This value can be used to determine

the effective

water leakage experienced

into the turbine building from pooling water against the doors. We find an incident wave run up greater than 1.65 feet will occur for less than 2% of the storm duration (ENERCON, 2013a). Accordingly , a wave bore exceeding

2.19 feet (590.39 ft-IGLD55)

could be expected less than 2% of the storm at the turbine building in the most severe IPEEE still water level case of 587 feet-International

Great Lakes Datum 1955 (henceforth

IGLD55) (PBNP, 1995; PBNP, 2013). For an initial water level of 586 ft-IGLD, maximum runup may reach the turbine building, but mean water level proxies indicate no persistent

water present. This calculation

can support analyses of door, building, and barrier stability

in the presence of increased water

level and/or wave attack. The results in this calculation

are applicable

for a small, yet critical range of the turbine building near the southwest

corner of the pump house. Conservative

methods were applied to account for uncertainties

related to the inputs. This incident runup calculation

and total water elevation

proxies can be applied to other PBNP locations, but the methodology

and assumptions

presented

should be considered

first. The total water elevations

are expected to be lower at other PBNP turbine building locations

of interest, since the maximum setup of the observations

in Figure 2-1 was selected for this analysis (ENERCON, 2013a).

ENERCON CALCULATION

CONTROL SHEET Shoreline

CALC. NO. FPL-076-CALC-004

REV. 1 PAGE NO.8 of 20 .fo4LN3 0 Observation

points that provided water levels (wave setup) used in the wave runup calculation. Approximate

Scale: 1" = 200' Figure 2-1: Observation

Points at Point Beach Nuclear Plant (PBNP).

E N ERC ON CALCULATION

CONTROL SHEET 3. References

CALC. NO. FPL-076-CALC-004

REV. PAGE NO. 9 of 20 3.1 Dean and Dalrymple, 2007, "Water Wave Mechanics

for Engineers

and Scientists," World Scientifc , 353 pp. 3.2 Deltares, 2012, Deltares Systems, "DELFT3D-WAVE

User Manual," updated 2012. 3.3 ENERCON, 2013a, ENERCON Services, Inc. (ENERCON), "DELFT3D Modeling of Surge and Wave Runup, Revision 0," Calculation

Number FPL076-CALC-003 , 2013. 3.4 ENERCON, 2013b, ENERCON Services, Inc. (ENERCON), "Mean Wave Flow, Revision 0," Calculation

Number FPL-076-CALC

-006, 2013. 3.5 FEMA, 2005, Federal Emergency

Management

Administration (FEMA), "Guidelines

and Specifications

for Flood Hazard Mapping Partners," D.4.5 Wave Setup, Runup, and Overtopping.

3.6 FEMA, 2007, Federal Emergency

Management

Administration (FEMA), "Guidelines

and Specifications

for Flood Hazard Mapping Partners," D.2.8 Wave Runup, and Overtopping.

3.7 FEMA, 2012, Federal Emergency

Management

Administration (FEMA)," FEMA Great Lakes Coastal Guidelines, Appendix D.3 Update," D.3 Coastal Flooding Analyses and Mapping: Great Lakes. 3.8 Mase , 1988, "Spectral

Characterisitcs

of Random Wave Runup," Coastal Engineering, Vol. 12, No.2, pp.175-189. 3.9 Melby, 2012, United States Army Corps of Engineers, Coastal and Hydraulic

Laboratory, "Wave Runup Prediction

for Flood Hazard Assessment (Draft)." 3.10 PBNP, 1995, Point Beach Nuclear Plant (PBNP), "Point Beach Nuclear Plant Individual

Plant Examination

of External Events (IPEEE) for Severe Accident Vulnerabilities

-Summary Report ," Wisconsin

Electric Power Company, June 30, 1995. 3.11 PBNP, 2013, Point Beach Nuclear Plant (PBNP) Design Information

Transmittal (OfT), Modification

Process, " Still Water Elevations (IGLD55) to be used for the FPL-076 series of calculations

in the PBNP wave analysis to match up with existing event probabilities," July 11, 2013. 3.12 S&L, 1967, Sargent and Lundy (S&L), "Maximum Deep Water Waves & Beach Run-up at Point Beach," 1967. 3.13 Stockdon, 2006, "Empirical

parameterizat

i on of setup, swash, and runup," Coastal Engineering, Vol. 53, No. 2 , pp. 573-588. 3.14 USAGE, 2011, United States Army Corps of Engineers (USACE), "Coastal Engineering

Manual," EM 1110-2-1100 , updated 2011. 3.15 USACE, 2012, United States Army Corps of Engineers (USACE), "Statistical

Analysis and Storm Sampling for Lakes Michigan and St. Clair," 2012.

E N E R C ON CALCULATION

CONTROL SHEET 4. Assumptions

CALC. NO. FPL-076-CALC-004 REV. 1 PAGE NO. 10 of 20 4.1 No reduction

factors due to differing

surface roughnesses

have been applied. The beach/beachface

extent includes predominately

sand, grass, gravel, and asphalt, which require no reduction (FEMA, 2005). Applying no reduction

factors is the most conservative

approach for wave runup calculations.

4.2 The conversion

from 2% incident wave runup elevation

to 50% incident wave runup elevation

is based on an empirical

relationship

applied to total run up for i rregular waves (Mase, 1988; USACE, 2011 ). It is assumed that the conversion

applies equivalently

for wave setup and incident runup and that the conversion

is valid for waves modeled in FPL-076-CALC-003.

Given the conservative

method of calculating

incident runup and the lack of accepted industry standards

for calculating

mean incident runup heights, this is a reasonable

approach.

4.3 An effective

runup elevation, or average elevation

of the wave runup bore over its entire wavelength (wave period), is determined

by assuming the runup bore maintains

a sinusoidal

shape above the mean water surface, which is a conservative

approach for a linear wave form. An effective (average)

height for this bore is used to provide a proxy for mean effective

incident runup elevations. Although breaking waves become nonlinear

and lose their sinusoidal

shape (Dean and Dalrymple, 2007), this approach provides an approximation

of the average (effective)

runup height. It is a reasonable

and conservative

approach given the lack of industry standard in the derivation

of such a parameter.

4.4 Wave setup is assumed to be a constant value near the turbine building.

The maximum or mean water level at observation

points (BP2, SS4, or SS5) near the turbine building are used to determine

the wave setup value (height above the initial still water level). This calculation

provides a value of water levels near the southwest

corner of the pump house and may differ at other PBNP locations. However, the calculated

level bounds the expected level at the turbine building.

5. Design Inputs The design inputs are listed in Table 5-1 below. A maximum wave period of 10 seconds was used to account for the maximum wind-generated

periods determined

in FPL-076-CALC-003 (Enercon, 2013a). Table 5-1: Incident Wave Run up and Water Elevation

Calculation

Inputs Value Units Source(s)

Ho 23.5 ft ENERCON, 2013a T 10 s ENERCON, 2013a Wave 120 degrees ENERCON, 2013a Direction

Wind 90 degrees ENERCON, 2013a Direction

PBNP, 2012 m 0.025 ft/ft S&L, 1976 ENERCON, 2013a 587.64 587 PBNP, 1995 SWL 586 ft-IGLD55

585 PBNP, 2013 583

CALCULATION

CONTROL SHEET 6. Methodology

6.1 Runup CALC. NO. FPL-076-CALC-004

REV. PAGE NO. 11 of 20 Run up (R) is the maximum elevation

of wave uprush above the still water level, consisting

of wave setup (11). the elevation

of the water surface due to wave action, and oscillatory

wave swash from breaking waves (USAGE, 2011 ): R = 1J + R/Nc (FEMA, 2005 , 0.4.5-1) where: R = total runup (ft) 11 = combined static and

dynamic wave setup (ft) R1Nc = incident wave run up due to oscillatory

wave swash (ft) Physically, R is the local maximum in water elevation (USAGE, 2011 ). No reliable theoretical

formulations

for run up exist currently

because the controlling

processes

are complex and nonlinear.

Rather, empirically

derived relationships

are used to estimate runup (USAGE, 2011). Many of these formulae relate total runup (R) to wave characteristics

and beachface

morphology (i.e. slope). For the purposes of this analysis, however, such a computation

would not be required. Computed OELFT30 water levels (in FPL-076-CALC-003)

include wave setup (11). Thus, the only additional

increase to the maximum water elevation

is the oscillatory

wave swash, RING. 6.2 Incident wave runup and maximum water levels for stability

analysis FEMA defines the 2% incident wave run up (RING 2%), the oscillatory

water elevations

attributable

to wave swash that is to exceed less than 2% of the time, as where: 111 R1Nc 2% = 0.6 f!!Q Ho -.ITO (FEMA, 2005, 0.4.5-11) R1Nc 2% = incident wave run up elevation

beyond water surface exceeded by <2% of waves (ft) m = beach slope (dimensionless)

Ho = deep-water

wave height (ft) Lo = deep-water

wavelength (ft) Thus, maximum incident runup occurs on steep beaches for large, long waves. Equation 0.4.5-11 was developed

empirically

along the Pacific coast (FEMA, 2005). It was chosen for this calculation

for two major reasons: 1) it provided a clear evaluation

of the incident wave run up, rather than the combined effects of incident runup and setup, and 2) it is conservative

approach, since frictional

dissipation

over a wide, sloped dissipative

beach, like Lake Michigan , would yield lower incident runup heights than the steeper, narrower surf zones of the Pacific coast (Stockdon, 2006). FEMA (2012) does provide unofficial (draft) guidelines

for the flood mapping on the Great Lakes, and promotes the use of Melby's (2012) compilation

of wave runup formulations

when applicable.

However, equations

therein reference

a total run up elevation (Melby, 2012, Figure 1 ). FEMA (2012) defines run up as a "statistic

associated with a group of waves or a particular

storm," indicating

that the equations

do not separate setup from individual

wave swash. Runup formulations

for structures

are also provided (FEMA, 2012), but are irrelevant

when the largest waves modeled in FPL-076-CALC-003

break far seaward of PBNP and do not

E N ERCO N CALCULATION

CONTROL SHEET CALC. NO. FPL-076-CALC-004

REV. PAGE NO. 12 of 20 directly impact any vertical infrastructure.

Hence, Equation 0.4.5.11 is the best known, applicable, yet conservative

estimate of only incident wave swash. The beach is defined as the area between wave breaking and the landward extent of wave runup (FEMA, 2005). The landward extent of the beach is defined as the turbine building near the southwest

corner of the pump house (observation

point BP2) where ponding was predicted

in the most severe cases (ENERCON, 2013a; Table 7-2). Additionally, the turbine building would interrupt

runup flow and is the structure

of top importance. The elevation

of the bottom of the turbine building door is 588.2 ft-IGLD55. At PBNP, the seaward extent of the beach was located where wave breaking occurred, as predicted

by the DELFT30-WAVE

model (ENERCON, 2013a). Larger waves began breaking -700 feet from the turbine building, whereas smaller wind-generated

waves, which produce significantly

less incident runup broke approximately

-250 feet from the BP2 observation

point (ENERCON, 2013a). In deep-water, wavelengths

are directly related to the wave period (T): (FEMA, 2005, 0.4.5-10)

where: T =wave period (s) Incident runup heights thus become a function of deep-water

wave height and period, as well as the beach slope. The largest incident wave run up values occur on steep beachfaces

for waves that are large {Ho) and long (T). Thus, the simulations

with the largest Ho and T values along the deep-water

boundaries

would produce the highest incident wave run up elevations.

The water elevation

given by SWL +I"JMAX+RINC

2% (Wl2%) is a proxy for the maximum water level reached during the storm. It is the value used in stability

analysis used of the turbine building's

rollup doors and jersey barriers.

6.3 Effective

incident runup to determine

external water levels on turbine building The incident wave runup (RINC) is only an instantaneous

water elevation (Figure 6-1). To better understand

the time-averaged, mean total water level, an average runup elevation

proxy may be developed. At PBNP, the mean water level is an important

factor in the leakage experienced

in the turbine building.

After a wave breaks, it continues

as a bore up the beachface

until gravity limits its upward swash rush or it is interrupted

by a hard structure. For sinusoidal

bores that are equally spaced (i.e. the length of the bore is equal to the space between bores, the mean elevation

can be given in two parts. The first part is the same calculation

performed

in FPL-076-CALC-006, and the result from that analysis (Equation

6-2 in FPL-076-CALC-006)

is provided here: where: A = n1Nc2%L BORE 2 1f AsoRE = area under the wave bore (ft 2) L = wavelength (ft) (6-1) The average height of that bore is given by dividing by half of the nearshore

wavelength, L/2 (see Figure 6-1 ): where: -h -_ A BORE _ RINC 2% BORE -Lj2 --lf-hBoRE = average height of the bore (ft) (6-2)

ENERCON CALCULATION

CONTROL SHEET CALC. NO. FPL-076-GALC-004

REV. 1 PAGE NO. 13 of 20 Note that the height of the wave bore is not a true wave height; rather, it is a wave amplitude, since the trough of the bore is neglected. The second part of the calculation

is the space between bores, which is assumed to be at the standing water elevation (Figure 6-1). Since the 'bore' has a height of zero in this range, the overall effective

height of the bore, and subsequently

of the incident run up (REFF 2%), if the next bore is assumed to follow the profile in Figure 6-1, is given by: R _ hBoRE _ R/Ncz% EFF2% (6-3) where: REFF 2% = effective

run up height (ft) This value (REFF 2%) is used as a proxy of the wave runup provided by the incident runup (RJNc) predicted

by Equation 0.4.5-11 from FEMA (FEMA, 2005). This approximation

is a conservative

approach of the linear wave profile since the wave trough is neglected.

Additionally, the USAGE (2011) provides empirical

formulas for various total run up thresholds (e.g. RMAx, R2%, R) for irregular

waves (USAGE, 2011 ). If incident wave run up and wave setup, the two components

of total wave runup, are assumed to vary equally (i.e. increase/decrease

by the same percentage)

between these various thresholds, then a comparison

of the empirical

formulas will allow for a conversion

of REFF 2%, derived from applying Equation 6-3 to an R1Nc 2% computation, to an equivalent

REFF 5o% proxy for R, the mean run up calculation (USAGE, 2011): where: R o.aaR EFF 50% = l.0 6 EFF 2% REFF 50% = effective

run up height proxy for R (ft) REFF 2% = effective

run up height proxy for R1Nc (ft) (6-4) The coefficients

in Equation 6-4 (0.88 and 1.86) are found in Section 11-4-4 of USAGE (2011 ). This value (Rm 5o%) can be used as a proxy for average runup elevation, although it should be noted that this elevation

is not static and the instantaneous

level oscillates

around this value, as shown in Figure 6-1. Physically, REFF so% is equivalent

to the average height that run up will reach 50% of the time. Similarly, REFF 2% is the average height that runup will reach 2% of the time. Thus, SWL +i]+REFF 50% (WL50% EFF) where iJ is the mean wave setup, can be thought of as a proxy for the mean water level. Instantaneous

water elevations

range between the standing water level and the maximum extent of run up. WLso% EFF is used to compute mean water leakage into the turbine building.

E N ERCO N Turbine building Note: drawing not to scale U2 CALC. NO. FPL-076-CALC-004

CALCULATION

CONTROL SHEET REV. L PAGE NO. 14 of 20 Instantaneous

water level Standing water elevation (SWL + fl*) Floor elevation

(588.2 ft-IGLD55)

  • Note: wave setup (fl) was considered

either as a maximum modeled level (flMAX), which was used in calculations

for the structural

loading analysis, or a mean level (ij), which was used in the computations

for average external water level proxies at the turbine building. Figure 6-1: Effective

Run up Schematic

7. Calculations

These cases examine the incident wave run up for the largest (significant

wave height, Hs = Ho = 23.5 feet) and longest (T = 10 seconds) deep-water

waves with no barriers present and each evaluated

SWL, shown in Table 7-1 (ENERCON, 2013a). From Equation 0.4.5-10, the deep-water

wavelength (Lo) of these waves would be 512.32 feet. These parameters

provide a worst-case

flooding scenario for each initial SWL; all input values are shown in Table 5-1. For these deep-water

wave conditions, the maximum wave setup ('lMAX) was 1.74 feet, corresponding

to the still water level of 587 ft-IGLD55, as found in FPL-076-CALC-003 (ENERCON, 2013a). For the lower still water levels, the maximum wave setup narrowly ranged between 1.20 and 1.28 feet (ENERCON, 2013a). This result is likely attributable

to the relatively

steep sloping bathymetry

at the seaward edge of PBNP. For the highest still water level, 587.64 ft-IGLD55, the maximum setup at BP2 was 1.46 feet. Above a threshold

water level (between 586 and 587 ft-IGLD55), waves and accompanying

setup make it close to the turbine building;

below it, the wave setup height appears to be quite stable. Please refer to FPL-076-CALC-003

for a more comprehensive

discussion

and presentation

of the DELFT3D setup results. Mean wave setup (i]) ranged from 1.12 to 1.39 feet (ENERCON, 2013a). If observation

point BP2 was submerged , then it was used to determine

the maximum and average wave setup, as it was d i rectly adjacent to the turbine building (see Figure 2-1). If that point was dry for the entire simulation, then observation

point 884 or 885, the next closest inundated

points, were used. The mean wave setup was computed for only the durations

in which BP2 (or neighbor observation

point) experienced

flooding, which often lagged the start of the model by several minutes (ENERCON, 2013a).

ENERCON CALCULATION

CONTROL SHEET CALC. NO. FPL-076-CALC-004

REV. 1 PAGE N0.15 of 20 The largest waves, responsible

for the highest incident run up elevations, break furthest seaward of the turbine building (Figure 7-1). The slope of the beach/beachface

for this calculation

was divided into two segments, after the methodology

shown in Figure 0.2.8-1 of FEMA (2007). The landward segment extended from near the turbine building (observation

point BP2, see Figure 2-1) out to the edge of the topographic

map of PBN. The elevation

of the BP2 is 587.35 feet-IGLD55

and the elevation

at the seaward edge of the topographic

map is 573.35 feet-IGLD55.

The distance between these points is 350 feet, providing

an upper beach slope of 0.04. Seaward of this segment, the beach slope is 0.01 out to 1,000 feet from the turbine building (S&L, 1976). The DELFT3D model showed wave breaking initiating

-700 feet from the turbine building (Figure 7-1), so the horizontal

extent of this segment is 350 feet. A weighted average of the overall beach slope was computed to yield an average value of 0.025. This beach slope (m) was used in all of the wave runup calculations, since only minor shifts (-20 feet) occurred in wave breaking locations

due to different

initial still water levels. From the calculated

beachface

slopes and deep-water

wave conditions, the incident wave runup (RINc) was calculated

to be 1.65 feet. This oscillatory

swash operates on top of the wave setup (11), so this result must be added to the SWL (583, 585, 586, 587, OR 587.64 ft-IGLD55)

and modeled maximum or mean setup. Thus, the water elevation (SWL +11MAx+R1Nc

2%) which would be exceeded less than 2% of the storm is 590.39 IGLD55 in the 587 ft-IGLD55

SWL case, the most severe still water level in the IPEEE (PBNP, 1995; PBNP, 2013). For this incident wave runup, an instantaneous

water depth of up to 2.19 feet at 590.39 ft-IGLD55 (Table 7-2) when SWL = 587 ft-IGLD55

could be realized at the turbine building. This water depth may be used to calculate

loading against the turbine doors. Physically, this elevation

is a close proxy for the maximum water elevation

for the provided still water level, wind, and wave characteristics, but could be exceeded less than 2% of the storm. The effective

runup (Rm 2%), calculated

from Equation 6-3, is 0.26 feet. The effective

height that 50% of individual

wave run ups will exceed (REFF so%), calculated

from Equation 6-4, is 0.12 feet. Using inputs from Table 5-1 and the calculated

R1Nc, REFF2%, and REFFSo% from section 6.2 and 6.3, water level proxies were computed for turbine building's

east wall. Results are shown in Table 7-3, and the most severe IPEEE case is shown schematically

in Figure 7-2 (PBNP, 1995; PBNP, 2013). The incident runup remains the same in each case, but the overall water elevation

proxies differ (Table 7-3). When the BP2 observation

point was dry, the next closest submerged

observation

point (SS4 or SS5) was used to determine

the maximum or mean wave setup (see Figure 2-1 and ENERCON, 2013a). The mean water surface proxy (WLso% EFF) is above the elevation

of the turbine building floor during only the most elevated initial still water levels, 587 and 587.64 ft-IGLD55.

For the 586 ft-IGLD55

case, runup would be expected to impact the structure

less than 0.65 feet (588.85 ft-IGLD55)

for 98% of the storm. The effective

runup elevations

indicate no permanent

ponding due to wave setup and swash. In the other two initial water level cases, 583 and 585 ft-IGLD55, more than 98% of the incident wave runups would not reach the turbine building floor; similarly, the mean water surface elevation

proxy indicates no persistent

water on the building doors. A maximum mean setup (if) also was used to calculate

the total effective

water elevation

proxies used to determine

leakage into the turbine building. The mean water level proxy (WLsoo;, EFF) is above the turbine building floor elevation

by 0.31 feet in the most severe IPEEE case, SWL = 587.00 ft-IGLD55 (PBNP, 1995; PBNP, 2013). No standing water is predicted

for the SWL = 586 ft-IGLD55

case, with WLso% EFF = 587.24 IGLD55. Further, no standing water and less than 2% of incident wave runup is expected for the initial SWL = 583 or 585 ft-IGLD55

cases.

--**--------CALC. NO. FPL -076-CALC-004

E N ERCO N CALCULATION

CONTROL SHEET REV. 1 PAGE N0.16 of 20 Table 7-2: Calculation

Results for the Maximum Structural

Loading Analysis.

Inputs for Maximum Incident Runup (Rmc2%) and Setup (I"JMAX) for each SWL Case. Output is a Dynamic Total Water Level (WL2%). Ho T (s) m RiNC2% SWL Frequency

of I'] MAX SWL + I']MAX Wl:z% (ft) (ft/ft) (ft) (ft-IGLD55)

SWL (yr 1)* (ft) ** (ft-IGLD55) (ft-IGLD55)

23.50 10.00 0.025 1.65 587.64 9.9E-07 1.46 589.10 590.75 23.50 10.00 0.025 1.65 587.00 4.2E-06 1.74 588.74 590.39 23.50 10.00 0.025 1.65 586.00 5.4E-05 1.20 587.20 588.85 23.50 10.00 0.025 1.65 585.00 3.2E-04 1.21 586.21 587.86 23.50 10.00 0.025 1.65 583.00 1.4E-02 1.28 584.28 585.93 * SWL frequencies

are provided by PBNP (2013), formulated

from data i n PBNP (1995). ** maximum setup values (r]MAX), measured at either observation

point BP2 or SS5 (if BP2 was dry), obtained from DELFT3D simulations (FPL-076-CALC-003)

corresponding

to still water levels (SWL) and deep-water

wave conditions

of Ho = 23.5 feet and direction=

120 °. Note: This table represents

a temporary

condition

that would induce maximum wave runup for use in calculating

structural

loading on the turbine building.


*-------------------------------------------------------------

CALC. NO.

FPL -076-CALC-004

E i!" J E N ERCON CALCULATION

CONTROL SHEET REV. 1 PAGE N0.17 of20 Table 7-3: Calculation

Results for the Average External Water Level Proxies (WLso.,. EFF) on the Turbine Building.

Inputs for Highest Effective

In cident Run up (REFF so%) and Mean Setup (7]) for each SWL Case. Ho T (s) m REFFSO% SWL Frequency

of i] (ft) -SWL+i] Wlso%EFF (ft) (ftlft) (ft) (ft-IGLD55)

SWL (yr 1) '* (ft-IGLD55) (ft-IGLD55)

23.50 10.00 0.025 0.12 587.64 9.9E-07 1.13 588.77 588.89 23.50 10.00 0.025 0.12 587.00 4.2E-06 1.39 588.39 588.51 23.50 10.00 0.025 0.12 586.00 5.4E-05 1.1 2 587.12 587.24 23.50 10.00 0.025 0.12 585.00 3.2E-04 0.72 585.72 585.84 23.50 10.00 0.025 0.12 583.00 1.4E-02 0.84 583.84 583.96 * SWL frequencies

are provided by PBNP (2013), formulated

from data in PBNP (1995) . .. mean setup values (ij') averaged over the entire simulation

when flooding occurred, measured at either observation

point BP2 or SS4 (if BP2 was dry), obtained from DELFT3D simulations (FPL-076-CALC-003)

corresponding

to still water levels (SWL) and deep-water

wave condit i ons of Ho = 23.5 feet and direction

= 120 °. Note: This table represents

average water level proxies at the turbine building.


. -* ---------.... -.. -... 1:1 E N ERCO N *ru .. -,..-;:;-*

-" ..... 44.2835 44.283 44.2825 t §: 44.282 "' .5 .., 0 44.2815 0 <.> >-44.281 44.2805 44.28 44.2795 -87.538 CALCULATION

CONTROL SHEET -87.537 -87.536 -87.535 CALC. NO. FPL-076-CALC-004

REV. 1 PAGE NO. 18 of 20 --87.534 -87.533 -87.532 x coordinate (m) Figure 7-1: Maximum Wave Breaking Distance of the Largest Waves Normal to the Southwest

Comer of the Pump House/Turbine

Building at Point Beach Nuclear Plant (PBNP). Percent Breaking (Oo/o=No Breaking, 1=100% Breaking)

i s Shown in the Color Map Above.

Turbine building Note: drawing not to scale CALCULATION

CONTROL SHEET CALC. NO. FPL-076-CALC-004

REV. 1 PAGE NO. 19 of 20 SWL = 587 ft-IGLD55

Mean setup ________________

Wlsocro...£fu588.51

tt-IGLD55)"" i REFFSO%

Standing water elevation, SWL + i'j (588.39 ft-IGLD55)

Door/floor

elevation

(588.2 ft-IGLD55)

Results for deep-water

wave height= 23.5 ft. deep-water

wave direction=

120 °, SWL = 587 ft-IGLD55, and no barriers present. Legend R 1 Nc = max. incident wave run up ReFF = effective

wave run up ('time-averaged'

R 1 Nc) SWL = still water level (587 ft-IGLD55)

fj =mean wave setup at BP2 (ft) Wlso% EFF = 'average'

water elevation

proxy including

ReFF soo/o Figure 7-2: Schematic

of Results from Table 7-3 for SWL=587 .00 ft-IGLD55

using the Mean Wave Setup. The WLr;. EFF and EFFWL 2% are the Effective

Water Level Proxies Used to Determine

Water Leakage into the Turbine Building.

E N E R C ON CALCULATION

CONTROL SHEET CALC. NO. FPL-076-CALC-004

REV.1 PAGE NO. 20 of 20 Attachment

A (On DVD) Pages/ Worksheets/

File Name (References)

Revision File Dean and Dalrymple, 2007 NA File Delatres, 2012.pdf NA File ENERCON, 2013a 0 File ENERCON, 2013b 0 File FEMA, 2005 NA File FEMA, 2007 NA File FEMA, 2012 NA File Mase, 1988 NA File Melby, 2012 NA File PBNP, 1995 NA File PBNP, 2013 NA File S&L, 1967 NA File Stockdon, 2006 NA File USACE, 2011.pdf NA File USACE, 2012.pdf NA File

ATTACHMENT

2 NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT POINT BEACH REVISED EXTERNAL FLOOD SAFETY SIGNIFICANCE

DETERMINATION

Performance

Deficiency

The licensee failed to establish

appropriate

procedural

requirements

to implement

external flooding wave run-up protection

design features as described

in the FSAR. Executive

Conclusion

The safety significance

of this issue is assessed to be of very low with margin for Units 1 and 2. Table 4 provides the core damage frequency (CDF) with and without barriers as well as the change in core damage frequency

with and without the barriers.

The basis of this conclusion

is that a detailed wave run-up analysis results in a calculated

water level much lower than the water levels previously

evaluated

in the IPEEE. The PRA analysis based on the updated engineering

analysis confirms that the IPEEE water levels were dominated

by estimates

and assumptions

that resulted in excessive

conservatism

for the 4.2E-06/yr

frequency

event. These lower water levels from the updated engineering

analysis result in fewer equipment

impacts. Background

The IPEEE response to GL 88-20, "Individual

Plant Examination

for Severe Accident Vulnerabilities," evaluated

external flood hazards for PBNP. This evaluation

was based in part on the analysis for external flood events conducted

in conjunction

with the NRC's TAP A-45 study. In order to evaluate the safety significance

of this issue, the data provided in the IPEEE was used to evaluate the change in CDF and large early release frequency (LERF). For the purpose of this evaluation

the "change" being considered

is the plant with and without the barrier protection

to 589.2 (IGLD-1955), as described

in the IPEEE report. To perform this evaluation, some simplifying

conservative

assumptions, providing

margin, are made: 1) Above 589.2 ft. IGLD 1955 (+9ft.), the impact of the flood is the same with and without barriers.

2) For the purposes of the PRA calculations, the water level inside the buildings

was assumed to equal the water level outside the Turbine Building at time zero. 3) Below 588.2 ft. IGLD 1955 (+8ft.), there is no impact from the flood (with or without barriers). 4) The PRA evaluation

assumes a concurrent

dual unit loss of offsite power (LOOP) due to the storm which is conservative

because the postulated

storm does not reach sustained

wind speeds that are expected to cause damage to offsite power distribution.

Page 1 of 8

Risk Assessment

PBP PRA Model Rev. 5.02 was used for this assessment.

Since this evaluation

will be applying the frequency

of the external flood outside of the PRA model, all initiators

in the internal events model were set to 0.0 with the exception

of the weather-centered

LOOP initiator (INIT-T1W).

By doing this, the value being quantified

is the conditional

core damage probability (CCDP), i.e., the core damage probability

assuming the initiator (external

flood in this case) occurs The following

steps were taken to evaluate the significance

of this issue: 1) Run CAFTA cases (average Testing & Maintenance)

for Units 1 and 2 with an E-10 truncation

limit with flags set to account for the postulated

equipment

failures. The results of the cases representing

the CCDPs for the five bins comprising

varying depths of water on the Turbine Building floor are shown in Table 1. For simplicity, only the maximum CCDP for each bin will be carried through the rest of this calculation.

2) In order to calculate .LlCDF for the water height ranges in this report , flood event frequencies

had to be derived. That was done by defining a relationship

between calculated

water levels and still water levels from Attachment

1. This relationship

is shown in Table 2. 3) The results of the curve-fit of the flood exceedance

frequencies

from Table 5.2.5-2 of the IPEEE are presented

in Table 3. Note that due to the data, two curve fits are presented.

The first curve fit represents

still water elevations

s585.1 ft IGLD 1955 and the second curve fit represents

still water elevations

> 585.1 ft IGLD 1955. 4) By using these developed

relationships, a frequency

is derived for a given calculated

flood level by determining

the associated

still water level from Table 2 and then using it to determine

the frequency

from Table 3. 5) The CDF is calculated

by multiplying

the Incremental

Flood Frequency (determined

from the relationships

in Tables 2 and 3, by the CCDP and is presented

in Table 4. 6) The .LlCDF was calculated

by subtracting

the CDF with barriers from the CDF without barriers for each bin. The Total .LlCDF was obtained by subtracting

the CDF Total with barriers from the CDF Total without barriers.

This information

is also presented

in Table 4. Note that based upon previous evaluations

and the very small CDF values, values for LERF were not calculated.

Due to the nature of the initiating

event, i t is judged that there is no unique challenge

to L E RF. Thus , the .LlLERF for this evaluation

is judged to be well below 1 E-09 /yr. The final calculation

of .LlCDF for this issue is determined

to be ?.E-09 /yr, which is of very low safety significance , with margin. Page 2 of 8

Margin The flood consequence

is considered

to be bounding and conservative

for the following

reasons: 1) All equipment

affected by the flood is assumed to be failed at time zero. Based on engineering

evaluations, the water accumulation

inside various areas of the plant would take over three hours prior to affecting

any safety significant

equipment.

2) No credit for

flood mitigation

actions taken in response to rising water levels throughout

the plant has been modeled. Due to the relatively

slow progression

of the postulated

flood, there should be time for the operators

or plant staff to respond to the rising water level and to protect and/or realign equipment.

3) No credit for

recovery actions taken in response to equipment

issues in the plant has been modeled. It is expected that some equipment

may be able to be recovered

and that other means to provide decay heat removal could be used, e.g., pumper trucks, B.5.b equipment, and portable generators.

4) The concrete barriers installed

at a lake level of 580.7 ft. (IGLD 1955), in accordance

with PC 80 Part 7, "Lake Water Level Determination," are assumed to be ineffective

in limiting the quantity of water. Page 3 of 8

Ta bl e 1 Maximum Conditional

Co r e Damage P robability

vs. Water Level Range Bins Range of Water Level CCDP (max) Bin on Turbine Equipment

Assumed Failed (1,7) Building Floor (4) (inches) (2,3) Offsite power assumed lost, Offsite Power Transformers

(1 X-01/03, 1 0 to <4.0 2X-01/03), 4.25 E-05 RHR Pumps (1/2P-1 OAIB), RHR Pump Suction from Containment

Sump B (1/2SI-851AIB) Charging Pumps (1 CV-2AIB/C and 2CV-2 4.0 to <8.0 2AIB/C), 6.87 E-04 Station Battery Chargers (D-07/D-08/D-09)

A Train Emergency

Diesel Generators (G-01, G-02), G-01/G-02 EDG Alarm & Electrical

Panels (C-34/C-35), G-01/G-02

EDG DC Power Transfer Control Panels (C-78/C-79), 3 8.0 to <12.5 4.16 KV Switchgear ( 1/2A-03/04

), 7.70 E-03 (5) 4.16 KV Vital Switchgear

A Train (1/2A-05), 1/2HX-11A, B RHR HX Shell Side Inlet Valves (1/2CC-738AIB), Non-Safety

Related 480V MCCs (B-33, 8-43), Steam Generator

Feedwater

Pump Seal Water Injection

Pumps (1/2P-99AIB)

480 V Vital MCCs A Train (1/2B-32), 4 Safeguards

Batteries (D-01, D-02), (6) 12.5 to <17 Service Air Compresso r (K-3B,) 8.92 E-02 Diesel Driven Fire Pump (P-35B), Instrument

Air Compressors (K-2AIB) Condensate

Pumps (1/2P-25AIB), Feedwater

Pumps (1/2P-28AIB), Service Water Pumps (P-32AIB/C/D/E/F), DC Distribution

Panels (D-63, D-64 ), Stand-by Steam Gene r ator Pumps 5 (P-38AIB), 1.00 Turbine Driven Auxiliary

Feedwater

Pumps (1/2P-29), Motor Driven Auxiliary

Feedwater

Pumps (1/2P-53), Service Air Compressor (K-3A), Safety Injection

Pumps (1/2-P12AIB)

Page 4 of 8

Notes: (1) "Equipment

Assumed Failed" for each range of water levels greater than 588.2 ft. IGLD 1955 is based on the elevation

of the limiting vulnerable

subcomponent.

(2) "Range of Water Level" is based on inches of water on the turbine building floor. (3) "Range of Water Level" 0 inches equals 588.2 ft. IGLD 1955. (4) The maximum CCDP from either unit is used in the downstream

calculations.

(5) It has been identified

that P-35A, Electric Fire Pump, may fail at an elevation

in Bin 3. Since this bin already fails 1A-05 (which powers 1 B-03, which powers the electric fire pump), there is no additional

consequence

of this component

failure. (6) It has been identified

that a control panel associated

with the 2P-29, Turbine Driven Aux Feedwater

Pump low suction pressure trip, may fail at an elevation

in Bin 4. A sensitivity

case was run that showed that the CCDP value would increase slightly to 9.0E-2. This small difference

compared to the CCDP value used for Bin 4 is not significant

in the conclusions

of this evaluation.

(7) Equipment

failures at the water level elevations

have been validated

against the most recent walk-downs

as documented

in EC 279398. Page 5 of 8

-l.() l.() m ..--I 0 _J <.9 :S (ii > Q) _J '-Q) ..... ro s "0 Q) -m ::J .2 ro l) Table 2 Calculated

Water Level Based on Still Water Lake Elevation

Still Water Elevation

to Calculated

Water Level Relationship

St ill Water Lake Calculated

Water Ele v ation Leve l (ft.IGLD-(ft. IGLD-1955) * 1955) 587.64 588.89 587.00 588.51 586.00 587.24 585.00 585.84 583.00 583.96 Relationship

Between Still Water Lake Elevation

and Calculated

Water Level (Level Against Turbine Hall) 590 589 588

587 586 585 584 583 582 583 584 585 586 587 Still Water Elevation (ft IGLD-1955)

588 NOTE: *Calculated

Water Level is taken from Table 7-3 of Enercon Calculation

FPL-076-CALC-004

Page 6 of 8

Annual Frequency (per yr) 3.69E-02 2.53E-04 3.45E-07 8.25E-11 Table 3 Annual Frequency

Based on Still Water Elevation

[Derived from Information

in IPEEE] Flood Frequency

-Curve Fit Equat ions Frequency-

Curve Fit (per yr) Still Water Elevation

IPEEE (ft IGLD 1955) from IPEEE StiiiWaterFREQ1

StiiiWaterFREQ2

IPEEE Table 5.2.5-2 582.5 3.7E-02 585.1 2.7E-04 4.8E-04 588.0 4.1 E-07 591.0 2.9E-10 Note where two values are provided, IPEEE StillWater

FREQ2 was used. (.J 1: (!) ::J C" E LL Ill ::J 1: 1: Point Beach Flood Hazard Frequency (from IPEEE Table 5.2.5-2) 1.E-01 ,-----------------------

---, <( 1.E-06

1.E-07

1.E-10 +-----,--------.-----,--------.----.---L----J

580.0 582.0 584.0

586.0 588.0 590.0 592.0 Still Water Flood Elevation (ft IGDL-1955)

Page 7 of 8

Tab le 4 .t.CDF Calcu l a t ion With and Without Barriers {1 'lH' t-t*n r:l:Iffl'm

Effective

Flood Incremental

Still Water Water

Bin Frequency

Flood Lake Level CCDP CDF CCDP CDF ACDF1 Frequency

Elevation (Range) (1) peryr peryr

ft (IGLD-peryr peryr peryr 1955) inches 1 5.6E-06 2.9E-06 586.93 0 to <4.0 4.25E-05 1.23E-1 0 O.OOE+OO O.OOE+OO 1.23E-10 2 2.7E-06 1.4E-06 587.23 4.0 to <8.0 6.87E-04 9.54E-10 O.OOE+OO O.OOE+OO 9.54E-10 587.53 8.0 to 3 1.3E-06 7.3E-07 <12.5 7.70E-03 5.60E-09 O.OOE+OO O.OOE+OO 5.60E-09 4 5.7E-07 3.2E-07 587.87 12.5 t o<17 8.92E-02 2.8 4 E-08 8.92E-02 2.84E-08 O.OOE+OO 5 2.5E-07 2.5E-07 588.21 >17 1.00E+OO 2.48E-07 1.00E+OO 2.48E-07 O.OOE+OO CDF CDF Total 2.83E-07 Total 2.76E-07 7.E-0 9 (1) E ff ect i ve wate r level is t he level o f water in the t urbine build i ng. Page 8 o f 8

ATTACHMENT

3 NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT CONTINUED

SERVICE WATER PUMP AVAILABILITY

WITH LOSS OF DC CONTROL POWER As discussed

in Reference

2, a significant

contributor

to the difference

between initial NextEra and NRC staff estimated

changes in Core Damage Frequency (CDF) with failure of equipment

up to 589.2 feet of water IGLD 1955 is the PRA modeling of Service Water (SW) pump availability

upon loss of DC control power. NRC's SPAR model contains a presumption

that the SW pump becomes unavailable

upon loss of DC power. (It is important

to note that NextEra's

updated analysis does not result in water levels which would impact DC power.) With a Loss of Offsite Power (LOOP), all four installed

Emergency

Diesel Generators (EDGs) will start and energize their associated

buses. All six Service Water (SW) pump supply breakers will then sequence onto their respective

AC load centers. With respect NRC's SPAR model assumption

that SW would be unavailable

upon loss of DC power, an interruption

in DC control power does not cause re-positioning

of breakers.

DC control power provides remote breaker operation

of the 480 volt SW supply breakers by momentarily

energizing

either the opening or closing solenoid coils. The overcurrent

protective

device is not dependent

on DC control power and remains functional

without DC control power. Once a breaker is closed, a loss of DC control power will not cause it to open, and the connected

load will continue to be energized.

Therefore, the operating

SW pumps will remain in operation

if DC control power is lost. DC control power supplies the starting circuit of the EDGs, the power to initially

flash the field on an EDG that is starting, and provides the ability to remotely adjust the electric governor setpoint, and to adjust the voltage regulator

setpoint.

If an operating

EDG suffers a complete loss of DC control power, the electronic

governor will fail to full fuel demand, and the backup mechanical

governor will take over speed regulation.

The exciter and voltage regulator

are self-energized

from the generator

output, and will fail to the as-set voltage. The ability to locally adjust frequency

on the running generator

will remain available.

The pending loss of DC control power due to flooding would be anticipated, and would be acted upon by the Operator before the actual loss occurred.

Each battery charger would initiate a trouble alarm when it failed, providing

a minimum of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> notice of the loss of the supplied bus. The one hour time is based on the minimum capacity of the batteries, and provides time to align the DC control power supplied to running EDGs, 4 kV switchgear, and 480 V Load Centers prior to the complete loss of control power. Abnormal Operating

Procedure

AOP-0.0 directs the Operator to realign control power from the normal source to the alternate

DC control power source. This includes realigning

the DC control power for Emergency

Diesel Generators

and 4 kV switchgear, and the direction

would be exercised

in anticipation

of the loss of the busses when the inability

to recover the overheated

chargers became evident. Page 1 of 2

If a running "B" train EDG were lost for any reason, the remaining "B" train EDG would be aligned to re-energize

the bus previously

supplied by the lost EDG using either ECA-0.0 (loss of AC power) or OI-35A (standby emergency

power alignment).

This would ensure the availability

of power to all 3 "B" train SW pumps. In the event that a SW pump needs to be started on an energized

bus , but does not have DC control power available

to effect remote operation, the procedural

direction

to "start pumps as necessary" will cause the Operator to start the pump by closing the breaker locally. The low service water pressure alarm response procedure

would direct this action, as would di r ection in the various abnormal operating

and emergency

operating

procedures.

Based on these considerat

i ons, it is concluded

that the postulated

combination

of a LOOP, loss of the "A" train buses, and loss of the D-07 , D-08, D-09 battery chargers does not limit the plant to only a single SW pump during long term operation. The actions for switching

to alternate

DC Control power are as follows: * The operators

will respond to control room alarms based on degrading

DC voltage * AOP 0.0 Vital DC System Malfunction, entry conditions

would be satisfied

and direct switching

to alternate

DC Control power for G-04 EDG. * If G-04 E DG would lose DC control power, guidance for local speed control is provided in E CA 0.0, Loss of all AC, for hydraulic

governor operation. * AOP 1 OA, Safe Shutdown local control procedure, provides guidance for local operation

of the Service Water pump breakers, if local operation, is required.

  • A Nuclear Oversight

Observer completed

a satisfactory

observation

of the above actions in the field by 3 Auxiliary

Operators.

  • The above field actions were timed and validated

to be completed

in aggregate

of <1 hour. * These Operator actions are part of the IN PO accredited

training programs for both initial and continuing

training for the Auxiliary

Operators. Local operation

of these breakers is trained on, tested, and evaluated

by our Operator Initial and Continuing

Training programs.

Conclusion

If a Service Water Pump is operating

when DC Control Power is lost it will continue operating

and if it is not operating

when DC Control Power is lost, the Operators

are trained and are procedurally

directed to start the pumps locally. If DC Control Power is lost to G-04 EDG , the operators

are trained and have procedural

guidance to locally control G-04 EDG's speed with the hydraulic

governor.

Page 2 of 2

ATTACHMENT

4 NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT PBNP TIME TO RESPOND TO RATES OF RISE IN LAKE MICHIGAN WATER LEVEL Purpose The purpose of this evaluation

is to establish

the time available

to respond to rising levels in Lake Michigan before the design basis flood threat may be reached. This evaluation

does not rigorously

reevaluate

the point at which there is a threat from rising water. Design and Licensing

Basis No flood height elevation

has been calculated

for anything but the vertical wall on the east side of the forebay to date. This value is stated in the FSAR (Section 2.5) as 8.42 feet plant elevation.

It is based on a maximum undisturbed

lake level of +1.7 ft. plant elevation

plus a wave run-up of 6.55 feet against a vertical surface, and a sustained

level change of +0.17 feet of water based on conservative

value of sustained

easterly wind velocity of 40 mph over a fetch length of 70 miles and average depth of 465 feet of water. Thus, the maximum expected run-up on a vertical structure

would be 6.72 feet above the normal water level (resulting

in a plant elevation

of 8.42 feet) and somewhat less on a riprap slope. Plant Reaction to Lake Level Changes Prior to Revision 4 (issued March 14, 2013) Point Beach procedure

PC 80 Part 7 required installation

of pre-cast concrete barriers within 3 weeks when the level of Lake Michigan reached a reported level of 580. 7ft. IGLD 1955. The detailed directions

in the procedure

on how to obtain this information

would have resulted in using the currently

accepted International

Great Lakes Datum ("IGLD") of 1985. This elevation

equates to -0.2 feet plant elevation.

This procedure

is performed

monthly and ensures advance preparation

in anticipation

of a potential

high water event. Historical

Lake Level Changes To determine

how much advance notice it would have ensured, the historical

lake data archived by the National Oceanographic

and Atmospheric

Administration (NOAA) was reviewed.

The data for monthly average lake level contained

data from January 1918 through March 2013 was converted

to feet, and the difference

between successive

months calculated

to obtain the monthly rate of level change. As shown in the histogram

below, the distribution

of level change is asymmetrical.

Page 1 of 4

Histogram

of Rate of Level Change 140 9 0.00% 120 . 80.00% 100 70.00% 6 0.00% > 80 v c Gl :I .... 5 0.00% 60 ... 40.00% 40 3 0.00% 20.00% 20 0

Rate of Lake Level Change (ft/month)

Because the lake level as a function of time cannot be replicated

by any meaningful

function, it is instructive

to calculate

the maximum historical

one month and two month level changes. On one occasion, the rate of rise in the lake reached 0.85 ft in a single month (April, 1960). The next highest rate of rise ever observed was 0.69 ft/month during two successive

months (April and May 1929). As the length of the period increases, the monthly average rate of rise decreases.

The maximum monthly rate of rise for a three month period is 0.55 ft!month, and for a four month period it has been 0.48 ft!month.

A full listing of the data is appended to this evaluation.

IPEEE Trigger Points From Table 3-3 in the TAP A-45 report (recreated

in the IPEEE submittal), the combination

of lake level and wave run-up which gets to the 8ft plant elevation

(588.2ft IGLD 1955) occurs with a still lake level of about 582ft IGLD 1955. Since 580.2 IGLD 1955 corresponds

to 0.0 feet plant elevation, the still lake level at which the wave run-up reaches 8.0 feet , is 1.8 feet plant elevation.

Using this as the lake level at which the threat from rising water materializes , there is 2 feet between the "install barriers" trigger point contained

in PC 80 Part 7 and the threat level. Using the maximum historical

rise rates for one, two, three, and four months to consume the entire 2 foot margin (height differential)

would require a period (denoted as " available

time period") of: ( 2ft ) weeks T = * 4.33-----,--

Rate (n Months) month Page 2 of 4

Using this formulation, the following

results are obtained:

Rate of Rate Period Available

Rise Time Period Height From Differential (ft) ft!month months weeks Trigger Point (Weeks) 2 0.48 4 17.3 18.1 2 0.55 3 13.0 15.8 2 0.69 2 8.7 12.6 2 0.85 1 4.3 10.2 In all cases, the available

time period for the 2 foot rise exceeds the highest historical

value for that same time period. Therefore, the rate of rise and the available

time for each case is conservative. This indicates

that even in the "worst case" where lake level were rising at the most rapid historic 1 month rate of 0.85 ft!month, and sustained

it for an unprecedented

10 weeks, it would still take a little more than those 10 weeks to consume the 2 feet of margin from the time that the trigger point is reached until the threat level was reached. However, the surveillance

is only performed

monthly. So it is possible that the reported lake level could be just below (e.g., 0.1 foot less than) the "trigger point" level of 580.7 ft at the time that the procedure

is performed.

It would then take another month (4.3 weeks) to discover that the trigger point level had been exceeded.

Under this postulation, it is appropriate

to use the rise rate for n+1 months to determine

time to achieve the total rise. T = [( 2 ft ) -1 month] * 4.33 _w_e_e_k.,...s

Rate (n + 1 Months) month Using this formulation, the following

results are obtained:

Rate of Rate Period Available

Rise Time Period Height From Differential (ft) ft!month months weeks Detection

to Threat Level (Weeks) 2 0.48 4 17.3 -2 0.55 3 13.0 13.7 2 0.69 2 8.7 11.4 2 0.85 1 4.3 8.2 Using the conservative

approach described

above, it would still leave at least 8.2 weeks, after discovery

that the trigger point

had been exceeded, to complete preparations

for high water, even if the first opportunity

had been missed. The procedure

allows three weeks for installation

so that there would be 5.2 weeks available

to address barrier deficiencies

before lake level reaches the design basis flood level. At the time that the barriers would have been set, the deficiencies

in setting, placement, gaps, etc. would have been self-evident, just as they were when the station performed

a trial placement

in 2012. Page 3 of 4

Station Actions related to increasing

lake levels: * Weather Conditions

are monitored

daily by the Shift Technical

Advisor and inputted into Safety Monitor * Weekend look ahead by Work Week manager for weather effects on weather impact for weekend on Safety Monitor * Procedurally

directed Monthly Recording

of Lake Level per PC 80 Part 7 "Lake Level Determination" * Per PC 80 Part 7 at a Lake Level (580.7 ft.') the Jersey Barriers are installed

  • At a lake level of greater than or equal to 588.2 ft the plant will declare an Unusual Event (HU 1.7) * At a lake level of greater than or equal to 589.2 ft the plant will declare an Alert (HA 1.6) As described

previously, it has been calculated

that, with the maximum historical

lake rise, it would take greater than 8 weeks to reach the CLB lake level of 581.9 ft. from a starting level of 580.7 ft. The jersey barriers , including

approximately

1000 sand bags, was installed

and inspected

in less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Conclusion

The time available

to respond to rising Lake Michigan pre-storm levels would be at least 8.2 weeks from the time of discovery

until the license basis flood level could be attained.

During 2012 , when the barriers were installed, it took less than 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. Additionally , installation

of the modified barrier (which includes approximately

1000 sand bags) was completed

in less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Therefore, there is ample time to install the barriers and take appropriate

additional

actions. Page 4 of 4