Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate
ML11214A079
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 08/05/2011
From: Mozafari B L
Plant Licensing Branch II
To: Jefferson W
Carolina Power & Light Co
Mozafari B L
References
TAC ME6169
Download: ML11214A079 (4)


Text

UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 August 5, 2011 Mr. William Jefferson, Jr. Vice President Carolina Power & Light Company Shearon Harris Nuclear Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 -REQUEST FOR ADDITIONAL INFORMATION REGARDING MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE (TAC NO. ME6169)

Dear Mr. Jefferson:

By letter dated April 28, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 11124A 180), as supplemented by letter dated June 23, 2011 (ADAMS Accession No. ML 11179A052), Carolina Power &Light Company requested approval from the U.S. Nuclear Regulatory Commission (NRC) to increase the core thermal power level of Shearon Harris Nuclear Power Plant, Unit 1, from 2,900 megawatts thermal (MWt) to 2,948 MWt, an increase of approximately 1.66% over the present licensed power level and to change the power plant technical specifications accordingly.

The NRC staff is reviewing your submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). It is requested that your RAI response be provided by August 30, 2011, as discussed with your staff on July 29, 2011. If more time is needed to respond to the RAI, your request for additional time should include a basis for the need for an extension.

w. -2 Please feel free to contact me at 301-415-2020 or bye-mail at brenda.mozafari@nrc.gov if you have any questions on this issue or require additional time to submit your response.

Sincerely, Brenda Mozafari, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.

Request for Additional cc w/encl: Distribution via SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 REQUEST FOR ADDITIONAL INFORMATION REGARDING MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE TAC NO. ME6169 By letter dated April 28, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 11124A 180), as supplemented by letter dated June 23, 2011 (ADAMS Accession No. ML 11179A052), Carolina Power

& Light Company (the licensee) requested approval from the U.S. Nuclear Regulatory Commission (NRC) to increase the core thermal power level of Shearon Harris Nuclear Power Plant (HNP), Unit 1, from 2,900 megawatts thermal (MWt) to 2,948 MWt, an increase of approximately 1.66% over the present licensed power level and to change the power plant technical specifications accordingly.

The NRC staff has reviewed your supplemented information, specifically Section 11.2.2.40, "Mass and Energy Releases -FSAR [Final Safety Analysis Report] 6.2.1," of Enclosure 2 to your supplemented letter dated June 23, 2011, that discussed the EPITOME Code error. EPITOME is a code used by Westinghouse in the loss-of-coolant accident (LOCA) long-term mass and energy (M&E) calculation, which supplies input to the containment response.

Westinghouse discovered that the computer code (EPITOME) used to generate the M&E inputs for the containment peak pressure analysis contains an error which could result in an increase in the containment pressure and temperature for the double ended pump suction LOCA, including a maximum increase in the peak containment pressure of up to 5 psi and temperature of up to 5.5°F. The licensee states: HNP power uprate LOCA long-term mass and energy evaluation was predicated on no changes to the existing mass and energy release analysis of record due to the power uprate. Since the licensee used the EPITOME code in its existing M&E release analysis for HNP, provide information on how this code error affects HNP's containment response analysis for a LOCA, specifically regarding the calculated peak pressure and peak temperature.

Enclosure W. Jefferson Please feel free to contact me at 301-415-2020 or bye-mail at brenda.mozafari@nrc.gov if you have any questions on this issue or require additional time to submit your response.

Docket No.

Request for Additional cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC LPL2-2 R/F RidsNrrLACSola RidsNrrPMShearonHarris RidsRgn2MailCenter RidsAcrsAcnwMailCenter ADAMS A ccesslon N o. ML11214A079 Sincerely, IRA by FSaba fori Brenda Mozafari, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsNrrDorlLpl2-2 RidsNrrDssScvb RidsOgcRp RidsNrrDorlDpr BLee, NRR RLobel, NRR *B sy memo OFFICE LPL2-2/PM LPL2-21LA DSS/SCVB/BC LPL2-2BC LPL2-2/PM NAME BMozafari CSoia (BClayton for) RDennig DBroaddus (SLingam for) BMozafari (FSaba for) DATE 08/03/11 08/02/11 07/28/11 . 08/05/11 08/05111 OFFICIAL AGENCY RECORD