Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML24025A159 | 25 January 2024 | NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - Rvi AMP and Inspection Plan (L-2023-LLL-0016) | |
ML23151A348 | 30 May 2023 | Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) | Incorporated by reference |
ML23142A273 | 22 May 2023 | Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) | Incorporated by reference |
ML23082A043 | 23 March 2023 | 002 Radiation Safety Baseline Inspection Information Request Final | High Radiation Area Locked High Radiation Area Process Control Program COVID-19 |
ML23020A125 | 23 January 2023 | Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) | Affidavit |
ML22115A141 | 25 April 2022 | NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information | Health Physics Network High winds |
ML21354A861 | 15 December 2021 | NRR E-mail Capture - Request for Additional Information - Duke Fleet Request RA-19-0352 - Alternative for RPV Closure Stud Exams (L-2020-LLR-0156) | Incorporated by reference Aging Management Stress corrosion cracking |
ML21258A365 | 15 September 2021 | Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2021011) and Request for Information (RFI) | Safe Shutdown Fitness for Duty Exemption Request Pandemic COVID-19 Fire Protection Program |
ML21172A243 | 21 June 2021 | NRR E-mail Capture - Request for Additional Information - Harris RA-20-0252 - LAR to Remove Extraneous Requirements from OL and TS (L-2021-LLA-0027) | |
ML21036A114 | 5 February 2021 | NRR E-mail Capture - Request for Additional Information - Harris - Relief Request RA-20-0312 - SW Pinhole Leak (L-2020-LLR-0143) | Through-Wall Leak |
ML21049A263 | 4 February 2021 | NRR E-mail Capture - Request for Additional Information - Duke Energy Fleet License Amendment Request to Revise Emergency Plan | FLEX Siren |
ML21032A049 | 1 February 2021 | NRR E-mail Capture - Request for Additional Information - Duke Fleet RA-20-0263 - Use of Later ASME B&Pv, XI for Repair - Replacement (L-2020-LLR-0124) | |
ML20323A407 | 18 November 2020 | NRR E-mail Capture - Request for Additional Information - Brunswick License Exemption Request from 10CFR73 Annual Force on Force Exercise Requirements (EPIC L-2020-LLE-0180) | Safeguards Contingency Plan Exemption Request Pandemic Coronavirus COVID-19 Grace period |
ML20297A307 | 13 October 2020 | NRR E-mail Capture - Request for Additional Information - Shearon Harris Nuclear Power Plant, Unit 1 - RCS Flowrate Reduction/Lbloca LAR | |
ML20274A046 | 29 September 2020 | Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2 | |
ML20247J382 | 3 September 2020 | Request for Additional Information - Shearon Harris Nuclear Power Plant, Unit 1 - Revise TS Related to Accident Monitoring and RFO Instrumentation | Anticipated operational occurrence |
ML19331A400 | 27 November 2019 | Request for Additional Information Regarding Licensing Action to Modify the Departure from Nucleate Boiling Ratio Safety Limit to Address Transition to New Fuel Type | |
ML19204A268 | 23 July 2019 | NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information for the Escw System TS AOT Extension and Removal of an Expired Note in TS Risk Informed LAR (L-2019-LLA-0025) | High winds Internal Flooding Probabilistic Risk Assessment Large early release frequency |
ML19136A271 | 28 May 2019 | Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding License Amendment Request to Modify the Departure from Nucleate Boiling Ratio Safety Limit to Address Transition to New Fuel Type | |
ML19060A091 | 18 March 2019 | Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors | Probabilistic Risk Assessment Large early release frequency |
ML19011A137 | 10 January 2019 | NRR E-mail Capture - Duke Energy Fleet RAIs - Relief Request 18-GO-001 - Proposed Alternative for Depth Sizing Qualification Examination of Welds (L-2018-LLR-0117) | |
ML19007A342 | 21 December 2018 | NRR E-mail Capture - Duke Energy Fleet Draft RAIs - Relief Request 18-GO-001 - Proposed Alternative for Depth Sizing Qualification Examination of Welds (L-2018-LLR-0117) | |
ML18332A439 | 28 November 2018 | NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information for EAL Scheme Changes | |
ML18337A127 | 28 November 2018 | NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information Regarding the Rts/Esfas Trip Setpoints Modification LAR | Anticipated operational occurrence Negative Flux Rate Trip |
ML18264A028 | 9 October 2018 | RAI Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk Informed Categorization Aad Treatment of Structures, Systems and Components for Nuclear Power Reactors | Internal Flooding Probabilistic Risk Assessment Very Early Warning Fire Detection |
ML18145A181 | 18 June 2018 | Request for Additional Information, License Amendment Request to Revise Updated Final Safety Analysis Report to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis | High winds Ultimate heat sink Tornado Missile Probabilistic Risk Assessment Tornado-Generated Missile Tornado Missile Protection Large early release frequency Tornado Missile Risk Evaluator |
RA-18-0011, Response to Request for Supplemental Information Regarding Duke Energy'S Response to GL 2016-01 Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools | 30 May 2018 | Response to Request for Supplemental Information Regarding Duke Energy'S Response to GL 2016-01 Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools | Aging Management License Renewal |
ML18116A105 | 25 April 2018 | NRR E-mail Capture - Harris/Robinson RAIs - Change Technical Specifications to Support Performance of Core Reload Design and Safety Analyses (L-2017-LLA-0356) | Shutdown Margin Anticipated operational occurrence |
ML18108A760 | 18 April 2018 | NRR E-mail Capture - Harris/Robinson Draft RAIs - Change Technical Specifications to Support Performance of Core Reload Design and Safety Analyses (L-2017-LLA-0356) | Shutdown Margin Anticipated operational occurrence |
ML18058B224 | 26 February 2018 | Emailed Radiation Safety RFI | High Radiation Area Locked High Radiation Area Process Control Program |
ML18005A548 | 8 January 2018 | Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses (CAC No. MF9996; EPID L-2017-LLA-0303) | |
ML17345A877 | 11 December 2017 | NRR E-mail Capture - Harris and Robinson Supplemental RAI - LAR to Adopt DPC-NE-3009-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis, (L-2016-LLA-0012) | Operator Manual Action |
ML17339A072 | 4 December 2017 | NRR E-mail Capture - Subject: Harris and Robinson Draft Supplemental RAIs - LAR to Adopt DPC-NE-3009-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis, (L-2016-LLA-0012) | Operator Manual Action |
ML17289A306 | 23 October 2017 | Shearon Harris Nuclear Plant, Unit 1 - Request for Additional Information Regarding License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements (CAC No. MF9828; EPID L-2017-LLA-0244) | |
ML17250B017 | 18 September 2017 | Shearon Harris, Unit 1 - Request for Additional Information Re: License Amendment Request Proposing New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods that Exceed the LHGR Limit Detailed in RG 1.183, Table 3 (CAC No. MF9740) | |
ML17241A018 | 30 August 2017 | Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Spent Fuel Storage Pool Criticality Analyses | |
ML17192A484 | 11 July 2017 | NRR E-mail Capture - Duke Energy Fleet RAIs Alternative for Reactor Pressure Vessel Flange Threads Examination (MF9513 to MF9521) | |
ML17123A133 | 9 May 2017 | Shearon Harris Nuclear Plant, Unit 1 - Request for Additional Information Re: License Amendment Request to Relocate Specific TS Parameters to the COLR, Remove Reference to a Plant Procedure as it Pertains to the COLR in TSs, etc. (CAC No. MF8894) | |
ML17109A291 | 19 April 2017 | NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Final Request for Additional Information Concerning LAR to Adopt TSTF-339, TSTF-5 and Other Administrative Changes | |
ML16363A011 | 27 December 2016 | Notification of Shearon Harris Nuclear Power Plant Design Basis Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2017007 | Probabilistic Risk Assessment Functionality Assessment Operability Determination |
ML16335A046 | 6 December 2016 | Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information Regarding License Amendment Request to Modify Diesel Fuel Oil Testing Surveillance Requirements (CAC No. MF7775) | |
ML16288A078 | 26 October 2016 | Shearon Harris Nuclear Power Plant, Unit 1, and H.B. Robinson Steam Electric Plant, Unit No. 2 - Redacted, Request for Additional Information Re: Request to Adopt DPC-NF-2010 and DPC-NF-2011 Nuclear Design Methodology (CAC Nos. MF7693 and MF7694) | |
ML16288A004 | 26 October 2016 | Shearon Harris Nuclear Plant, Unit 1 - Request For Additional Information Regarding License Amendment Request To Relocate The Explosive Gas Mixture And Liquid Holdup Tanks Technical Specifications Requirements (CAC No. MF8067) | |
ML16223A417 | 8 August 2016 | Notification of Inspection and Request for Information | Boric Acid Non-Destructive Examination Nondestructive Examination Incorporated by reference Flow Accelerated Corrosion Liquid penetrant |
ML16209A264 | 2 August 2016 | Shearon Harris Nuclear Plant, Unit 1 - Second Request For Additional Information Regarding License Amendment Request For A Temporary Change To Technical Specifications For The 'A' Emergency Service Water Pump Replacement (CAC No. MF7017) | |
ML16028A197 | 8 February 2016 | Request for Additional Information Regarding License Amendment Request for a Temporary Change to Technical Specifications for the 'A' Emergency Service Water Pump Replacement | Safe Shutdown Mission time Internal Flooding Large early release frequency Maintenance Rule Program |
ML15344A030 | 17 December 2015 | Request for Additional Information Application to Revise Technical Specifications for Methodology Report DPC-NE-2005-P, Revision 5, Thermal Hydraulic Statistical Core Design Methodology (MF5872/MF5873) | |
ML15320A386 | 19 November 2015 | RAI LAR to Adopt TSTF-523 | |
ML15314A359 | 10 November 2015 | Duke Energy Draft RAIs Request to Adopt TSTF-523 (CAC Nos. MF6413-MF6422) | |
ML15314A356 | 10 November 2015 | E-mail from J. Whited to A. Zaremba Duke Energy Draft RAIs License Amendment Request to Adopt TSTF-523 (CAC Nos. MF6413-MF6422) |