ML14365A094
ML14365A094 | |
Person / Time | |
---|---|
Site: | Indian Point, Holtec ![]() |
Issue date: | 12/16/2014 |
From: | Lawrence Coyle Entergy Nuclear Operations |
To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards |
References | |
NL-14-149 | |
Download: ML14365A094 (2) | |
Similar Documents at Indian Point, Holtec | |
---|---|
Category:Letter
MONTHYEARML24016A1902024-01-30030 January 2024
[Table view]International, Inc. - Notice of Violation; the U.S. Nuclear Regulatory Commission Inspection Report 07201014/2022201 ML24018A1992024-01-18018 January 2024 International, Administrative Change to HI-2200343-A ML24011A1982024-01-12012 January 2024 ISFSI, Notice of Organization Change for Site Vice President ML23342A1082024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23363A0312024-01-0404 January 2024 Application for HI-STORM 100 Cask System, Amendment No. 19 - Acknowledgement of Withdrawal and Notification of the U.S. Nuclear Regulatory Commission Staff Efforts Closure ML23355A0842023-12-21021 December 2023 International, Withdrawal of HI-STORM I00 Multipurpose Canister Storage System Amendment ML23353A1742023-12-19019 December 2023 ISFSI, Emergency Plan, Revision 23-04 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23324A0952023-12-0606 December 2023 Amendment No. 19 to Certificate of Compliance No. 1014 for the HI-STORM 100 Multi-purpose Canister Storage System - Request for Additional Information ML23328A0052023-12-0505 December 2023 Issuance of Renewed Certificate of Compliance No. 1014, Amendment No. 17 for the Hi-Storm 100 Cask System (Cac/Epid 001028/L-2021-LLA-0140) ML23339A0442023-12-0505 December 2023 Issuance of Amendment No. 68, 301 and 277 Regarding Changes to Implement the Independent Spent Fuel Storage Installation Physical Security Plan ML23326A1322023-12-0505 December 2023 Issuance of Amendment No. 67, 300 & 276 to Implement the Independent Spent Fuel Storage Installation Only Emergency Plan ML23338A3052023-12-0404 December 2023 International, Submittal of Supplement to RAI Responses on HI-STORM 100 Amendment 18 ML23338A2262023-12-0404 December 2023 Signed Amendment No. 27 to Indemnity Agreement No. B-19 ML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23334A1912023-11-30030 November 2023 International, Submittal of Topical Report HI-2210161-A Version ML23242A2772023-11-30030 November 2023 NRC Letter Issuance - IP LAR for Units 2 and 3 Renewed Facility Licenses and PDTS to Reflect Permanent Removal of Spent Fuel from SFPs ML23338A0482023-11-30030 November 2023 ISFSI, Report of Changes to Physical Security, Training and Qualification, Safeguards Contingency Plan, and ISFSI Security Program, Revision 28 ML22339A1572023-11-27027 November 2023 Letter - Indian Point - Ea/Fonsi Request for Exemptions from Certain Emergency Planning Requirements for 10 CFR 50.47 and 10 CFR Part 50, Appendix E IR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 ML23100A1172023-11-17017 November 2023 NRC Response - Indian Point Energy Center Generating Units 1, 2, and 3 Letter with Enclosures Regarding Changes to Remove the Cyber Security Plan License Condition ML23050A0032023-11-17017 November 2023 Letter - Issuance Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements Following Spent Fuel Transfer to Dry Storage ML23321A2172023-11-17017 November 2023 International, Responses to NRC Questions Form EA-23-044 Pre-Decisional Enforcement Conference ML23100A1252023-11-17017 November 2023 Letter and Enclosure 1 - Issuance Indian Point Energy Center Units 1, 2, and 3 Exemption for Offsite Primary and Secondary Liability Insurance Indemnity Agreement ML23100A1432023-11-16016 November 2023 Letter - Issuance Indian Point Energy Center Generating Units 1, 2, and 3 Exemption Concerning Onsite Property Damage Insurance (Docket Nos. 50-003, 50-247, 50-286) ML23064A0002023-11-13013 November 2023 NRC Issuance for Approval-Indian Point EC Units 1, 2 and 3 Emergency Plan and Emergency Action Level Scheme Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point JAFP-23-0063, Registration of Spent Fuel Cask Use2023-11-13013 November 2023 Registration of Spent Fuel Cask Use ML23310A0362023-11-0909 November 2023 International, Inc. - U.S. Nuclear Regulatory Commission Inspection Report 07201014/2023201 ML23283A1262023-11-0202 November 2023 Letter - Second Request for Additional Information - HI-STORM 100 Amd 18 ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23063A1432023-11-0101 November 2023 Letter - Issuance Holtec Request for Indian Point Energy Center Generating Units 1, 2, and 3 Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47 and Part 50 ML23292A0262023-10-19019 October 2023 LTR-23-0211-RI Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report-RI ML23289A1582023-10-16016 October 2023 Decommissioning International - Registration of Spent Fuel Casks and Notification of Permanent Removal of All Indian Point Unit 3 Spent Fuel Assemblies from the Spent Fuel Pit ML23270A0082023-09-27027 September 2023 Registration of Spent Fuel Casks ML23237A5712023-09-22022 September 2023 09-22-2023 Letter to Dwaine Perry, Chief, Ramapo Munsee Nation, from Chair Hanson, Responds to Letter Regarding Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23263B1232023-09-20020 September 2023 HI-STORM 100 Amendment 16 Responses to Second Round Requests for Additional Information ML23234A1572023-09-14014 September 2023 Letter to Holtec International Final Safety Evaluation for Hi-2210161, Revision No. 4, Topical Report on the Radiological Fuel Qualification Methodology for Dry Storage Systems ML23145A1752023-09-12012 September 2023 NRC Choice Letter to Holtec International with Attached Safety Inspection Report, IR 72-1014/2022-201, December 12-15, 2022, Inspection of Holtec International in Camden, New Jersey (Docket Nos.: 72-1014, 72-1032) ML23242A2182023-09-12012 September 2023 IPEC NRC Response to the Town of New Windsor, Ny Board Certified Motion Letter Regarding Treated Water Release from IP Site (Dockets 50-003, 50-247, 50-286) ML23251A2512023-09-0808 September 2023 International, Submittal of Supplement to RAI Responses on HI-STORM 100 Amendment 18 ML23250A0812023-09-0707 September 2023 Registration of Spent Fuel Casks ML23255A0142023-08-31031 August 2023 LTR-23-0211 Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report 2024-01-09 Category:License-Dry Cask MONTHYEARML23328A0062023-12-0505 December 2023
[Table view]Renewed Certificate of Compliance No. 1014, Amendment No. 17 ML23328A0192023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix B ML23328A0232023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix D ML23328A0212023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix B-100U ML22175A0842023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014 Appendix B-100U, Technical Specifications for the HI-STORM 100 Cask System Amendment No. 17 ML22175A0822023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014 Appendix D, Technical Specifications for the HI-STORM 100 Cask System Amendment No. 17 ML22175A0852023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014, Amendment No. 17 ML23068A4402023-06-29029 June 2023 55. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix B ML23068A4552023-06-29029 June 2023 70. Final Safety Evaluation Report for Renewed Certificate of Compliance No. 1014, Amendment Nos. 0-15 ML23068A4542023-06-29029 June 2023 69. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix D ML23068A4532023-06-29029 June 2023 68. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix C ML23068A4522023-06-29029 June 2023 67. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix B-100U ML23068A4512023-06-29029 June 2023 66. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix A-100U ML23068A4502023-06-29029 June 2023 65. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix B ML23068A4492023-06-29029 June 2023 64. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix a ML23068A4482023-06-29029 June 2023 63. Renewed Certificate of Compliance No. 1014, Amendment No. 15 ML23068A4472023-06-29029 June 2023 62. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix B-100U ML23068A4462023-06-29029 June 2023 61. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix A-100U ML23068A4452023-06-29029 June 2023 60. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix B ML23068A4442023-06-29029 June 2023 59. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix a ML23068A4432023-06-29029 June 2023 58. Renewed Certificate of Compliance No. 1014, Amendment No. 14 ML23068A4422023-06-29029 June 2023 57. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix B-100U ML23068A4412023-06-29029 June 2023 56. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix A-100U ML23068A4392023-06-29029 June 2023 54. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix a ML23068A4382023-06-29029 June 2023 53. Renewed Certificate of Compliance No. 1014, Amendment No. 13 ML23068A4372023-06-29029 June 2023 52. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix B-100U ML23068A4362023-06-29029 June 2023 51. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix A-100U ML23068A4342023-06-29029 June 2023 49. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix a ML23068A4332023-06-29029 June 2023 48. Renewed Certificate of Compliance No. 1014, Amendment No. 12 ML23068A4322023-06-29029 June 2023 47. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix B-100U ML23068A4312023-06-29029 June 2023 46. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix A-100U ML23068A4292023-06-29029 June 2023 44. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix a ML23068A3892023-06-29029 June 2023 5. Renewed Certificate of Compliance No. 1014, Amendment No. 1 ML23068A3912023-06-29029 June 2023 7. Renewed Certificate of Compliance No. 1014, Amendment No. 1, Appendix B ML23068A3882023-06-29029 June 2023 4. Renewed Certificate of Compliance No. 1014, Amendment No. 0, Appendix B ML23068A3872023-06-29029 June 2023 3. Renewed Certificate of Compliance No. 1014, Amendment No. 0, Appendix a ML23068A3862023-06-29029 June 2023 2. Renewed Certificate of Compliance No. 1014, Amendment No. 0 ML23068A3902023-06-29029 June 2023 6. Renewed Certificate of Compliance No. 1014, Amendment No. 1, Appendix a ML23068A3922023-06-29029 June 2023 8. Renewed Certificate of Compliance No. 1014, Amendment No. 2 ML23068A3942023-06-29029 June 2023 10. Renewed Certificate of Compliance No. 1014, Amendment No. 2, Appendix B ML23068A3932023-06-29029 June 2023 9. Renewed Certificate of Compliance No. 1014, Amendment No. 2, Appendix a ML23068A3952023-06-29029 June 2023 11. Renewed Certificate of Compliance No. 1014, Amendment No. 3 ML23068A3962023-06-29029 June 2023 12. Renewed Certificate of Compliance No. 1014, Amendment No. 3, Appendix a ML23068A3972023-06-29029 June 2023 13. Renewed Certificate of Compliance No. 1014, Amendment No. 3, Appendix B ML23068A3982023-06-29029 June 2023 14. Renewed Certificate of Compliance No. 1014, Amendment No. 4 ML23068A4072023-06-29029 June 2023 23. Renewed Certificate of Compliance No. 1014, Amendment No. 7 ML23068A4172023-06-29029 June 2023 33. Renewed Certificate of Compliance No. 1014, Amendment No. 9, Rev. 1 ML23068A4232023-06-29029 June 2023 38. Renewed Certificate of Compliance No. 1014, Amendment No. 10 ML23068A4272023-06-29029 June 2023 42. Renewed Certificate of Compliance No. 1014, Amendment No. 10, Appendix B-100U ML23068A4282023-06-29029 June 2023 43. Renewed Certificate of Compliance No. 1014, Amendment No. 11 2023-06-29 Category:ISFSI MONTHYEARML23328A0062023-12-0505 December 2023
[Table view]Renewed Certificate of Compliance No. 1014, Amendment No. 17 ML23328A0192023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix B ML23328A0232023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix D ML23328A0212023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix B-100U ML22175A0842023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014 Appendix B-100U, Technical Specifications for the HI-STORM 100 Cask System Amendment No. 17 ML22175A0822023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014 Appendix D, Technical Specifications for the HI-STORM 100 Cask System Amendment No. 17 ML22175A0852023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014, Amendment No. 17 ML23068A4402023-06-29029 June 2023 55. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix B ML23068A4552023-06-29029 June 2023 70. Final Safety Evaluation Report for Renewed Certificate of Compliance No. 1014, Amendment Nos. 0-15 ML23068A4542023-06-29029 June 2023 69. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix D ML23068A4532023-06-29029 June 2023 68. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix C ML23068A4522023-06-29029 June 2023 67. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix B-100U ML23068A4512023-06-29029 June 2023 66. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix A-100U ML23068A4502023-06-29029 June 2023 65. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix B ML23068A4492023-06-29029 June 2023 64. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix a ML23068A4482023-06-29029 June 2023 63. Renewed Certificate of Compliance No. 1014, Amendment No. 15 ML23068A4472023-06-29029 June 2023 62. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix B-100U ML23068A4462023-06-29029 June 2023 61. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix A-100U ML23068A4452023-06-29029 June 2023 60. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix B ML23068A4442023-06-29029 June 2023 59. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix a ML23068A4432023-06-29029 June 2023 58. Renewed Certificate of Compliance No. 1014, Amendment No. 14 ML23068A4422023-06-29029 June 2023 57. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix B-100U ML23068A4412023-06-29029 June 2023 56. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix A-100U ML23068A4392023-06-29029 June 2023 54. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix a ML23068A4382023-06-29029 June 2023 53. Renewed Certificate of Compliance No. 1014, Amendment No. 13 ML23068A4372023-06-29029 June 2023 52. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix B-100U ML23068A4362023-06-29029 June 2023 51. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix A-100U ML23068A4342023-06-29029 June 2023 49. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix a ML23068A4332023-06-29029 June 2023 48. Renewed Certificate of Compliance No. 1014, Amendment No. 12 ML23068A4322023-06-29029 June 2023 47. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix B-100U ML23068A4312023-06-29029 June 2023 46. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix A-100U ML23068A4292023-06-29029 June 2023 44. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix a ML23068A3892023-06-29029 June 2023 5. Renewed Certificate of Compliance No. 1014, Amendment No. 1 ML23068A3912023-06-29029 June 2023 7. Renewed Certificate of Compliance No. 1014, Amendment No. 1, Appendix B ML23068A3882023-06-29029 June 2023 4. Renewed Certificate of Compliance No. 1014, Amendment No. 0, Appendix B ML23068A3872023-06-29029 June 2023 3. Renewed Certificate of Compliance No. 1014, Amendment No. 0, Appendix a ML23068A3862023-06-29029 June 2023 2. Renewed Certificate of Compliance No. 1014, Amendment No. 0 ML23068A3902023-06-29029 June 2023 6. Renewed Certificate of Compliance No. 1014, Amendment No. 1, Appendix a ML23068A3922023-06-29029 June 2023 8. Renewed Certificate of Compliance No. 1014, Amendment No. 2 ML23068A3942023-06-29029 June 2023 10. Renewed Certificate of Compliance No. 1014, Amendment No. 2, Appendix B ML23068A3932023-06-29029 June 2023 9. Renewed Certificate of Compliance No. 1014, Amendment No. 2, Appendix a ML23068A3952023-06-29029 June 2023 11. Renewed Certificate of Compliance No. 1014, Amendment No. 3 ML23068A3962023-06-29029 June 2023 12. Renewed Certificate of Compliance No. 1014, Amendment No. 3, Appendix a ML23068A3972023-06-29029 June 2023 13. Renewed Certificate of Compliance No. 1014, Amendment No. 3, Appendix B ML23068A3982023-06-29029 June 2023 14. Renewed Certificate of Compliance No. 1014, Amendment No. 4 ML23068A4072023-06-29029 June 2023 23. Renewed Certificate of Compliance No. 1014, Amendment No. 7 ML23068A4172023-06-29029 June 2023 33. Renewed Certificate of Compliance No. 1014, Amendment No. 9, Rev. 1 ML23068A4232023-06-29029 June 2023 38. Renewed Certificate of Compliance No. 1014, Amendment No. 10 ML23068A4272023-06-29029 June 2023 42. Renewed Certificate of Compliance No. 1014, Amendment No. 10, Appendix B-100U ML23068A4282023-06-29029 June 2023 43. Renewed Certificate of Compliance No. 1014, Amendment No. 11 2023-06-29 Category:(Amend) DKT 72 MONTHYEARML23328A0062023-12-0505 December 2023
[Table view]Renewed Certificate of Compliance No. 1014, Amendment No. 17 ML23328A0192023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix B ML23328A0232023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix D ML23328A0212023-12-0505 December 2023 Renewed Certificate of Compliance No. 1014, Amendment No. 17, Appendix B-100U ML22175A0842023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014 Appendix B-100U, Technical Specifications for the HI-STORM 100 Cask System Amendment No. 17 ML22175A0822023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014 Appendix D, Technical Specifications for the HI-STORM 100 Cask System Amendment No. 17 ML22175A0852023-10-11011 October 2023 Proposed Certificate of Compliance No. 1014, Amendment No. 17 ML23068A4402023-06-29029 June 2023 55. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix B ML23068A4552023-06-29029 June 2023 70. Final Safety Evaluation Report for Renewed Certificate of Compliance No. 1014, Amendment Nos. 0-15 ML23068A4542023-06-29029 June 2023 69. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix D ML23068A4532023-06-29029 June 2023 68. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix C ML23068A4522023-06-29029 June 2023 67. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix B-100U ML23068A4512023-06-29029 June 2023 66. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix A-100U ML23068A4502023-06-29029 June 2023 65. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix B ML23068A4492023-06-29029 June 2023 64. Renewed Certificate of Compliance No. 1014, Amendment No. 15, Appendix a ML23068A4482023-06-29029 June 2023 63. Renewed Certificate of Compliance No. 1014, Amendment No. 15 ML23068A4472023-06-29029 June 2023 62. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix B-100U ML23068A4462023-06-29029 June 2023 61. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix A-100U ML23068A4452023-06-29029 June 2023 60. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix B ML23068A4442023-06-29029 June 2023 59. Renewed Certificate of Compliance No. 1014, Amendment No. 14, Appendix a ML23068A4432023-06-29029 June 2023 58. Renewed Certificate of Compliance No. 1014, Amendment No. 14 ML23068A4422023-06-29029 June 2023 57. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix B-100U ML23068A4412023-06-29029 June 2023 56. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix A-100U ML23068A4392023-06-29029 June 2023 54. Renewed Certificate of Compliance No. 1014, Amendment No. 13, Appendix a ML23068A4382023-06-29029 June 2023 53. Renewed Certificate of Compliance No. 1014, Amendment No. 13 ML23068A4372023-06-29029 June 2023 52. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix B-100U ML23068A4362023-06-29029 June 2023 51. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix A-100U ML23068A4342023-06-29029 June 2023 49. Renewed Certificate of Compliance No. 1014, Amendment No. 12, Appendix a ML23068A4332023-06-29029 June 2023 48. Renewed Certificate of Compliance No. 1014, Amendment No. 12 ML23068A4322023-06-29029 June 2023 47. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix B-100U ML23068A4312023-06-29029 June 2023 46. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix A-100U ML23068A4292023-06-29029 June 2023 44. Renewed Certificate of Compliance No. 1014, Amendment No. 11, Appendix a ML23068A3892023-06-29029 June 2023 5. Renewed Certificate of Compliance No. 1014, Amendment No. 1 ML23068A3912023-06-29029 June 2023 7. Renewed Certificate of Compliance No. 1014, Amendment No. 1, Appendix B ML23068A3902023-06-29029 June 2023 6. Renewed Certificate of Compliance No. 1014, Amendment No. 1, Appendix a ML23068A3882023-06-29029 June 2023 4. Renewed Certificate of Compliance No. 1014, Amendment No. 0, Appendix B ML23068A3872023-06-29029 June 2023 3. Renewed Certificate of Compliance No. 1014, Amendment No. 0, Appendix a ML23068A3862023-06-29029 June 2023 2. Renewed Certificate of Compliance No. 1014, Amendment No. 0 ML23068A3922023-06-29029 June 2023 8. Renewed Certificate of Compliance No. 1014, Amendment No. 2 ML23068A3942023-06-29029 June 2023 10. Renewed Certificate of Compliance No. 1014, Amendment No. 2, Appendix B ML23068A3932023-06-29029 June 2023 9. Renewed Certificate of Compliance No. 1014, Amendment No. 2, Appendix a ML23068A3952023-06-29029 June 2023 11. Renewed Certificate of Compliance No. 1014, Amendment No. 3 ML23068A3962023-06-29029 June 2023 12. Renewed Certificate of Compliance No. 1014, Amendment No. 3, Appendix a ML23068A3972023-06-29029 June 2023 13. Renewed Certificate of Compliance No. 1014, Amendment No. 3, Appendix B ML23068A3982023-06-29029 June 2023 14. Renewed Certificate of Compliance No. 1014, Amendment No. 4 ML23068A4072023-06-29029 June 2023 23. Renewed Certificate of Compliance No. 1014, Amendment No. 7 ML23068A4122023-06-29029 June 2023 28. Renewed Certificate of Compliance No. 1014, Amendment No. 8, Rev. 1 ML23068A4172023-06-29029 June 2023 33. Renewed Certificate of Compliance No. 1014, Amendment No. 9, Rev. 1 ML23068A4232023-06-29029 June 2023 38. Renewed Certificate of Compliance No. 1014, Amendment No. 10 ML23068A4272023-06-29029 June 2023 42. Renewed Certificate of Compliance No. 1014, Amendment No. 10, Appendix B-100U 2023-06-29 |
Text
Enterqy Nuclear Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel 914 254 6700 Lawrence Coyle Site Vice President NL-14-149 December 16, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11545 Rockville Pike, TWFN-2 F1 Rockville, MD 20852-2738
Subject:
Indian Point Energy Center Registration of Unit 3 Spent Fuel Cask Use Indian Point Nuclear Generating Unit No. 3 Docket Nos. 50-286 & 72-51 License Nos. DPR-64 & 72-0051
Dear Sir or Madam:
Entergy Nuclear Operations, Inc. (Entergy) operates the Indian Point Energy Center (IPEC) Independent Spent Fuel Storage Installation (ISFSI) in accordance with the general license provisions of 10 CFR 72.210. The conditions of 10 CFR 72.212(b)(2) include the registration of a spent fuel cask within 30 days of using a cask for the storage of spent nuclear fuel.Accordingly, this letter hereby registers the use on November 20, 2014 of the eighth (8th) IPEC Unit 3 dry fuel storage cask. The cask was loaded to Amendment 6 of the Holtec International CoC #1014 and the corresponding Holtec International HI-STORM 100 Cask System FSAR Revision 8. This cask is the twenty-eighth (28th) IPEC dry fuel storage cask to be added to the IPEC ISFSI pad.This letter also provides the following registration information associated with the twenty-eighth (28th) Holtec HI-STORM 100 spent fuel cask system that was placed into storage on the IPEC ISFSI pad [Docket No. 72-51]. The fuel contained in this cask is from IPEC Unit 3 Nuclear Power Plant, Reactor License No. DPR-64, Docket No. 50-286.[Eighth (8th) Unit 3 Spent Fuel Cask]Twenty-ei-ghth (28th) IPEC Spent Fuel Cask System: Date placed in use: November 20,2014 Licensee's Name: Entergy Nuclear Operations, Inc.Licensee's Address: Indian Point Energy Center 450 Broadway PO Box 249 Buchanan, NY 10511 k 4k <,<
NL-14-149 Docket Nos. 50-286 & 72-51 Page 2 of 2 Cask Model Number: Cask Certificate Number: MPC Serial Number: HI-STORM Overpack Serial Number: Number of Fuel Bundles: HI-STORM 100 1014 263 701 32 Total Cask Systems stored at the IPEC ISFSI pad [Docket No. 72-511: Twenty eight (28) HI-STORM 100 Cask Systems There are no new commitments made by Entergy contained in this letter. If you have any questions, please contact Mr. Timothy J. Salentino, Superintendent Dry Fuels Storage, at (914) 254-6773.Sincerely, cc: Mr. Daniel H. Dorman, Regional Administrator, NRC Region I Mr. Douglas V. Pickett, Senior Project Manager, NRC NRR DORL Ms. Bridget Frymire, New York State Department of Public Service Mr. Francis J. Murray, President and CEO, NYSERDA NRC Resident Inspectors