#REDIRECT [[IR 05000148/1986001]]
{{Adams
| number = ML20207T446
| issue date = 03/19/1987
| title = Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-148/86-01.Careless Disregard for NRC Requirements Re Dismantling Activities Demonstrated
| author name = Martin R
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
| addressee name = Bearse R
| addressee affiliation = KANSAS, UNIV. OF, LAWRENCE, KS
| docket = 05000148
| license number =
| contact person =
| document report number = NUDOCS 8703240024
| title reference date = 01-13-1987
| document type = CORRESPONDENCE-LETTERS, NRC TO EDUCATIONAL INSTITUTION, OUTGOING CORRESPONDENCE
| page count = 2
}}
See also: [[see also::IR 05000148/1986001]]
 
=Text=
{{#Wiki_filter:,    _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _                            ___.
                                              ,                                  MAR I 91987
    +
      ~
    .                                      In Reply Refer To:
                                            Docket: 50-148/86-01
                                            University of Kansas
                                            ATTN: Mr. Robert C. Bearse, Associate
                                                      Vice Chancellor
                                            226 Strong Hall
                                            Lawrence, Kansas 66045-2300
                                            Gentlemen:
                                            Thank you for your letter of January 13, 1987, in response to our letter and
                                            Notice of Violation dated December 23, 1986. After reviewing your reply,
                                            it remains our position that you were provided guidance in late 1985 ragarding
                                            dismantling of the reactor and subsequent termination of the operating license,
                                            and that you demonstrated careless disregard for NRC requirements. Our
                                            position is based on the fact that you had telephone conversations with the
                                            NRC Project Manager concerning dismantling activities and, as a follow-up to
                                            these discussions, the Project Manager provided you a copy of NRC Regulatory
                                            Guide 1.86.
                                          We will review the implementation of your corrective actions during a future
                                            inspection to determine that full compliance has been achieved and will be
                                            maintained.
                                            Your January 13, 1987, letter contained a Safeguards Information attachment,
                                          which was properly marked. However, the letter itself was not marked
                                            " Safeguards Information" to indicate conspicuously the presence of protected
                                            information, as required by 10 CFR 73.21 (e). Please mark your copies of the
                                          January 13, 1987, letter appropriately.
                                                                                      Sincerely,
                                                                                      ORIGINAL SIGNfD gy
                                                                                      RO8ERT D. MAgry
                                                                                      Robert D. Martin
                                                                                      Regional Administrator
,                                          cc:
                                            Kansas Radiation Control Program Director
                                            bec: (see next page)
                                                                                                                      J
                                                                                              '
                                            RIV:FRP          C:FRPS          C:R&SPB      0:                  /    RA
                                            RWise/jt        BMurray        WLFisher      RL      rt    EGa liardo  gDo  tin
                                            ) /gp /87      3 /p /87      J /l3/87      $/l(/87( 3/ /87'            f/ /87
                                                                                                                                \
                                                                                            ENCLOSURE CONTAINS                    \
                                                                                            SAFEGUARDS INFORMATION.
                                                                                            UPON SEPARATION THIS
                                                                                                                                f
              l703240024870319
                          DR ADOCK 03000148                                                PAGE IS DECONTROLLED.
                                                                                                                              ly
              8                                              con
 
                                                            _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _
                                                                                                                        t
                                                                                                                    .
  .
  .. University of Kansas                    -2-
      bec w/ copy of licensee's response w/ safeguards:
              RIV Security File                                                                                        -
            G. McCorkle, NMSS
;            J. Gibson,.SSPD/NRR
                        ,
              IE File
;            Resident Inspector                                                                                        t
              R. D. Martin, RA                                                                                        '
              R. L. Bangart, DRS&S                                                                                      i
              Inspector                                                                                                '
            Chief EPSPS
            J. J. Dosa, Project Manager                                                                                i
;            H. N. Berkow                                                                                              i
<
            0. A. Powers
l            B. Murray
      bec w/ copy of licensee's response w/o safeguards:
      CMB IE-04
      RPB
!    D. Weiss, RM/ALF
      Section Chief (RPB/B)
      RIV File
      MIS
j'    RSTS Operator
      R&SPB                                                                                                          -;'
      W. L. Fisher, R&SPB
;    E. H. Johnson, DRS&P
      R. E. llall, DRS&P
i                                                                                                                      !
4
i                                                                                                                      !
'
                                                                                                                        t
                                                                                                                        i
i                                                                                                                      r
4
                                    ENCLOSUM CONTAINt
                                    SAFEGUARDS INFORMATION,                                                            !
                                    UPON SEPARATION THIS
                                                                                                                      I
                                    PAGE IS DECONTROLLED.
                                                                                                                        L
u
i
                                                                                                                      !
                                                                                                                        t
                                                                                                                        i
                                                                                                                      !
:                                                                                                                      !
                                                                                                                        i
 
      -                                                                                                                                          .
          '
    '
  ;
                                                                                                      SAFEGUARDS INFORMATION
*
                                                                              7$,6 #
                                                  Tile UNIVERSITY OF KANSAS
                            offico of the m Chano llnr for Hncan h. Gr.ninato stu. lies, an.1 Public service,
                                                              an.1 ihtan of the Grailuato s< hool
                                                    22th Strong llall.1.awrenu.. Kansas ca un2:"Hi
                                                                          (91.1) im 4 'I in 1
                                                                                                January 13, 1987
          U.S. Nuclear Regulatory Commission                                                                  ,    m,. .            K
          fogion IV
          611 Ryan Plaza Drive, Suite 1000
                                                                                                              ii,Q
                                                                                                                  i
                                                                                                                      C,. --~
                                                                                                                                          '
                                                                                                                    3                o    .
          Arlington, TX 76011                                                                                    b
                                                                                                                        m i g ggg7            ,
          Attn: Mr. Robert D. Martin, Regional Administrator
                                                                                                                '_
                                                                                                                L
                                                                                                                                    _j f      -
          Re        Docket No. $0-148, License No. R-78                                                                                      '
                    NRC Inspection ftoport 50-148/86-01
                    EA 86-186
          Dear Mr. Martin:
          The following are our responses to your Notice of Violation of December 23,
          1986.        .
                                                                  .
          A.      Failure to Apply for Authority to Dismantle a Facility.
                    (1) The removal [of the grid plato assembly], which we now understand
                          to be diamantlement, was done to empty the reactor tank of as much
                          activated material as casily possible so as to make an assessment
                          of the magnitude of future problems of decommission 1 sng. At the
                          time, we did not considor the action to be a dismantlement in the
                          sense implied by 10 CFR 50.82. We appreciate your not proposing a
                          civil penalty for this violation. At the same time, we do not                                                          l
                          understand and do not agree with the allegation that we                                                                !
                          " demonstrated careless disregard for this requirement by not
                          complying with 10 CFR 50.82 even af ter being informed of the
                          requirement by the project manager, Office of Nuclear Reactor
                          Regulation." The dismantlement took place on March 211, 1986, and
                          was called to our attention as being a possible violation no                                                            l
                                                                                                                                                  I
                          carlier than September or October, 1986. No subsequent
                          dismantlement has occurred. We are unaware of any specific
                          requirements communicated by the project manager which we                                                              i
                          disregarded.                                                                                                            l
                  (2) Corrective action has been taken to be certain by administrative
                          control that no further dismantlement of any kind will occur
                                                                              '
                          without proper authority.
                  (3) Correctivo action which will be taken is the same as (2) above.
                  (4)    In our opinion, we are now in full compliance. ENC 1.OSURE CONTAINS
                                                                                                                                        ,
                                                                                                        SAFEGUARDS INFORMATION.                  1
                              SAFEGUARDS INFORMATION                                                    ueOn sEeAnATioN TsiS                    !
                                                                                                        PAGE IS DECONTROLLEC-      0            l
                                                                  uain c.on
                                    c. ,il..... .., , ,... i,h s ...n. ... n. ,e n . . l u re n. o
                                                                                n...r.. u . - c" ~ ~ ""a                    k)
        --    ----
                                                                                                                    cd
 
                                      - _ _ - _ _ _ _ _ _ .
                                                            .
                                                              .
                                9
                              .
                                                                B.  Failure to Post Required Regulatory Documents.
                                                                    (1) The violation occurred by socident during a clean-up when all
                                                                          documents were removed from the reactor bay bulletin board.
                                                                    (2) Corrective action has been to replace the required documents on
                                                                          the bulletin board.
                                                                    (3) Corrective action which will be taken is to insure by
                                                                          administrative control that the documents not be removed from the
                                                                          board in the future.
                                                                    (4)  In our opinion, we are now in full compliance.
                                                              C.  Failure to Identify Radioactive Material.
                                                                    (1) The fission monitor was normally in a sealed container under water
                                                                          in the reactor tank. After the container had been removed from
                                                                          the tank during fuel transfer operations, we neglected to label it
                                                                          properly.
                                                                    (2) This was pointed out to us during the inspection of September 11
                                                                          and 12, 1986, and the correct label was immediately applied.
                                                                          Subsequently, the monitor has been transferred to Kansas State
                                                                          University.
                                                                    (3) Future corrective action is moot.
                                                                    (4) In our opinion, we are now in full compliance.
                                                              D.    Response to Appendix D, Notice of Violation
                                                                    This response may include Safeguards Information and is appended as a
                                                                    separate document.
                                                              We hope that these responses are satisfactory and that no furter NRC
                                                              enforcement action will be necessary to ensure compliance with NRC
                                                              regulatory requirements.
                                                                                                                                                    Sincerely,
                                                                                                                                                    Robert C. Bearse
                                                                                                                                                    Associate Vice Chancellor
                                                              Enclosure marked " SAFEGUARDS INFORMATION"
                                                              Copies w/o enclosures Nuclear Reactor Committee
                                                                                      Carl E. Locke
                                                                      w/ enclosure Vickle Thomas
. - - - - - . - - - - - - - - - - - -                                                    - - - - - - . - - - - - - - - - - - . _ _ _ _ _ _ _ _ . -          . - - - ----__________________________---------_a
}}

Latest revision as of 12:41, 19 December 2021

Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-148/86-01.Careless Disregard for NRC Requirements Re Dismantling Activities Demonstrated
ML20207T446
Person / Time
Site: 05000148
Issue date: 03/19/1987
From: Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Bearse R
KANSAS, UNIV. OF, LAWRENCE, KS
References
NUDOCS 8703240024
Download: ML20207T446 (2)


See also: IR 05000148/1986001

Text

, _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ___.

, MAR I 91987

+

~

. In Reply Refer To:

Docket: 50-148/86-01

University of Kansas

ATTN: Mr. Robert C. Bearse, Associate

Vice Chancellor

226 Strong Hall

Lawrence, Kansas 66045-2300

Gentlemen:

Thank you for your letter of January 13, 1987, in response to our letter and

Notice of Violation dated December 23, 1986. After reviewing your reply,

it remains our position that you were provided guidance in late 1985 ragarding

dismantling of the reactor and subsequent termination of the operating license,

and that you demonstrated careless disregard for NRC requirements. Our

position is based on the fact that you had telephone conversations with the

NRC Project Manager concerning dismantling activities and, as a follow-up to

these discussions, the Project Manager provided you a copy of NRC Regulatory

Guide 1.86.

We will review the implementation of your corrective actions during a future

inspection to determine that full compliance has been achieved and will be

maintained.

Your January 13, 1987, letter contained a Safeguards Information attachment,

which was properly marked. However, the letter itself was not marked

" Safeguards Information" to indicate conspicuously the presence of protected

information, as required by 10 CFR 73.21 (e). Please mark your copies of the

January 13, 1987, letter appropriately.

Sincerely,

ORIGINAL SIGNfD gy

RO8ERT D. MAgry

Robert D. Martin

Regional Administrator

, cc:

Kansas Radiation Control Program Director

bec: (see next page)

J

'

RIV:FRP C:FRPS C:R&SPB 0: / RA

RWise/jt BMurray WLFisher RL rt EGa liardo gDo tin

) /gp /87 3 /p /87 J /l3/87 $/l(/87( 3/ /87' f/ /87

\

ENCLOSURE CONTAINS \

SAFEGUARDS INFORMATION.

UPON SEPARATION THIS

f

l703240024870319

DR ADOCK 03000148 PAGE IS DECONTROLLED.

ly

8 con

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _

t

.

.

.. University of Kansas -2-

bec w/ copy of licensee's response w/ safeguards:

RIV Security File -

G. McCorkle, NMSS

J. Gibson,.SSPD/NRR

,

IE File

Resident Inspector t

R. D. Martin, RA '

R. L. Bangart, DRS&S i

Inspector '

Chief EPSPS

J. J. Dosa, Project Manager i

H. N. Berkow i

<

0. A. Powers

l B. Murray

bec w/ copy of licensee's response w/o safeguards:

CMB IE-04

RPB

! D. Weiss, RM/ALF

Section Chief (RPB/B)

RIV File

MIS

j' RSTS Operator

R&SPB -;'

W. L. Fisher, R&SPB

E. H. Johnson, DRS&P

R. E. llall, DRS&P

i  !

4

i  !

'

t

i

i r

4

ENCLOSUM CONTAINt

SAFEGUARDS INFORMATION,  !

UPON SEPARATION THIS

I

PAGE IS DECONTROLLED.

L

u

i

!

t

i

!

!

i

- .

'

'

SAFEGUARDS INFORMATION

7$,6 #

Tile UNIVERSITY OF KANSAS

offico of the m Chano llnr for Hncan h. Gr.ninato stu. lies, an.1 Public service,

an.1 ihtan of the Grailuato s< hool

22th Strong llall.1.awrenu.. Kansas ca un2:"Hi

(91.1) im 4 'I in 1

January 13, 1987

U.S. Nuclear Regulatory Commission , m,. . K

fogion IV

611 Ryan Plaza Drive, Suite 1000

ii,Q

i

C,. --~

'

3 o .

Arlington, TX 76011 b

m i g ggg7 ,

Attn: Mr. Robert D. Martin, Regional Administrator

'_

L

_j f -

Re Docket No. $0-148, License No. R-78 '

NRC Inspection ftoport 50-148/86-01

EA 86-186

Dear Mr. Martin:

The following are our responses to your Notice of Violation of December 23,

1986. .

.

A. Failure to Apply for Authority to Dismantle a Facility.

(1) The removal [of the grid plato assembly], which we now understand

to be diamantlement, was done to empty the reactor tank of as much

activated material as casily possible so as to make an assessment

of the magnitude of future problems of decommission 1 sng. At the

time, we did not considor the action to be a dismantlement in the

sense implied by 10 CFR 50.82. We appreciate your not proposing a

civil penalty for this violation. At the same time, we do not l

understand and do not agree with the allegation that we  !

" demonstrated careless disregard for this requirement by not

complying with 10 CFR 50.82 even af ter being informed of the

requirement by the project manager, Office of Nuclear Reactor

Regulation." The dismantlement took place on March 211, 1986, and

was called to our attention as being a possible violation no l

I

carlier than September or October, 1986. No subsequent

dismantlement has occurred. We are unaware of any specific

requirements communicated by the project manager which we i

disregarded. l

(2) Corrective action has been taken to be certain by administrative

control that no further dismantlement of any kind will occur

'

without proper authority.

(3) Correctivo action which will be taken is the same as (2) above.

(4) In our opinion, we are now in full compliance. ENC 1.OSURE CONTAINS

,

SAFEGUARDS INFORMATION. 1

SAFEGUARDS INFORMATION ueOn sEeAnATioN TsiS  !

PAGE IS DECONTROLLEC- 0 l

uain c.on

c. ,il..... .., , ,... i,h s ...n. ... n. ,e n . . l u re n. o

n...r.. u . - c" ~ ~ ""a k)

-- ----

cd

- _ _ - _ _ _ _ _ _ .

.

.

9

.

B. Failure to Post Required Regulatory Documents.

(1) The violation occurred by socident during a clean-up when all

documents were removed from the reactor bay bulletin board.

(2) Corrective action has been to replace the required documents on

the bulletin board.

(3) Corrective action which will be taken is to insure by

administrative control that the documents not be removed from the

board in the future.

(4) In our opinion, we are now in full compliance.

C. Failure to Identify Radioactive Material.

(1) The fission monitor was normally in a sealed container under water

in the reactor tank. After the container had been removed from

the tank during fuel transfer operations, we neglected to label it

properly.

(2) This was pointed out to us during the inspection of September 11

and 12, 1986, and the correct label was immediately applied.

Subsequently, the monitor has been transferred to Kansas State

University.

(3) Future corrective action is moot.

(4) In our opinion, we are now in full compliance.

D. Response to Appendix D, Notice of Violation

This response may include Safeguards Information and is appended as a

separate document.

We hope that these responses are satisfactory and that no furter NRC

enforcement action will be necessary to ensure compliance with NRC

regulatory requirements.

Sincerely,

Robert C. Bearse

Associate Vice Chancellor

Enclosure marked " SAFEGUARDS INFORMATION"

Copies w/o enclosures Nuclear Reactor Committee

Carl E. Locke

w/ enclosure Vickle Thomas

. - - - - - . - - - - - - - - - - - - - - - - - - . - - - - - - - - - - - . _ _ _ _ _ _ _ _ . - . - - - ----__________________________---------_a