| | number = ML063490024 | | | number = ML063490024 |
| | issue date = 12/13/2006 | | | issue date = 12/13/2006 |
| | title = 12/13/2006 FENOC Slides from Perry Public Meeting to Discuss Results of NRC Confirmatory Action Letter Followup Inspections | | | title = FENOC Slides from Perry Public Meeting to Discuss Results of NRC Confirmatory Action Letter Followup Inspections |
| | author name = Pearce B | | | author name = Pearce B |
| | author affiliation = FirstEnergy Nuclear Operating Co | | | author affiliation = FirstEnergy Nuclear Operating Co |
Similar Documents at Perry |
---|
Category:Slides and Viewgraphs
MONTHYEARML24256A1672024-10-31031 October 2024 October 2024 Perry Plant License Renewal Draft Environmental Impact Statement Public Meeting Slides ML23291A0572023-10-25025 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant, Unit 1 License Renewal Application - Virtual Meeting Slides ML23291A0702023-10-18018 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant, Unit 1 License Renewal Application - In-person Meeting Slides ML23046A1682023-02-16016 February 2023 License Renewal Application - 2nd Safety Pre-Application Meeting, February 16, 2023 (Perry Slides) ML23044A2122023-02-14014 February 2023 February 14, 2023, Second Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - Energy Harbor Slides ML23044A2082023-02-14014 February 2023 February 14, 2023, Second Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - NRC Slides ML22200A2222022-07-21021 July 2022 License Renewal Application - Safety Pre-Application Meeting July 21, 2022 (Perry Slides) ML22199A0232022-07-21021 July 2022 July 21, 2022, Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - NRC Slides ML22199A0352022-07-21021 July 2022 July 21, 2022, Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - Energy Harbor Slides ML22201A0052022-07-19019 July 2022 License Renewal Application - Safety Pre-Application Meeting July 21, 2022 (NRC Slides) ML21176A1992021-06-25025 June 2021 Slideshow Presentation for 2020 End -of-Cycle Public Meeting for Davis-Besse and Perry ML21047A1522021-02-16016 February 2021 Slides - Perry Pre-Application Flooding 2/16/2021 Meeting Slides (L-2021-LRM-10016) ML20210M0712020-07-27027 July 2020 Combined End-of-Cycle 2019 Public Meeting Slide Presentation ML18054B6002018-02-21021 February 2018 Drywell General Area Heat Detectors License Amendment Request - Pre-Submittal Meeting, Perry Nuclear Power Plant, February 21, 2018 ML17205A0362017-07-19019 July 2017 Presentation for 2016 Perry EOC Open House ML16307A4052016-09-14014 September 2016 R-III Rug 15 Sep 16 Presentation ML16047A1332016-02-0909 February 2016 February 9, 2016, Public Meeting Slides for License Amendment Request for Drain Down of Upper Containment Pool in Mode 3 ML14079A0912014-03-18018 March 2014 NRC - Perry 2013 Annual Assessment Public Meeting Slides ML13294A5972013-10-21021 October 2013 FENOC Presentation Slides for Public Meeting September 24, 2013 ML13281A5302013-10-15015 October 2013 Meeting Slide for FENOC - NRC Pre-Submittal Meeting Request for Licensing Action ML13101A1432013-04-10010 April 2013 NRC 2012 Annual Assessment Presentation ML13101A1522013-04-10010 April 2013 2012 Annual Assessment Presentation ML12269A0612012-09-26026 September 2012 FENOC Presentation for 2012-09-26 Public Meeting ML12094A2932012-04-0303 April 2012 Licensee Slides for Annual Assessment Meeting ML12086A2002012-03-26026 March 2012 NRC Slides Regarding Perry Nuclear Plant EOC Meeting for Cy 2011 ML1122408232011-08-11011 August 2011 Annual Assessment Meeting, 2010 Reactor Oversight Program ML1122805732011-08-11011 August 2011 Licensee Presentation Slides from 2010 EOC Meeting 8/11/11 ML1117303602011-06-21021 June 2011 FENOC Licensee Slides for 6-21-11 All FENOC Meeting ML1021500852010-07-28028 July 2010 Licensee Slides for Perry; July 28, 2010; Annual Assessment Meeting ML1021500692010-07-28028 July 2010 NRC Slides for Perry, July 28, 2010; Annual Assessment Meeting ML1009102662010-03-31031 March 2010 Slides FENOC and NRC Senior Management Briefing, 3-31-10 ML0932101992009-11-12012 November 2009 NRC Slides from Public Meeting with Firstenergy Nuclear Operating Company ML0932005842009-11-12012 November 2009 FENOC Presentation for NRC Public Meeting ML0920900792009-07-21021 July 2009 Licensee Slides from End of Cycle - Public Meeting ML0920900682009-07-21021 July 2009 Slides for Perry Nuclear Power Plant Annual Assessment Meeting, Reactor Oversight Program - Cy 2008 ML0811506052008-04-24024 April 2008 Summary of Public Meeting with Firstenergy Nuclear Operating Co. to Discuss the 2007 Perry End-of-Cycle Performance Assessment ML0801604842008-01-0909 January 2008 Slides - FENOC Public Meeting, Senior Management Briefing, January 9, 2008 ML0708602302007-03-21021 March 2007 Slides, Perry Annual Assessment Meeting Reactor Oversight Process - Cy 2006. ML0708602352007-03-21021 March 2007 Slides, Perry Confirmatory Action Letter Closure Meeting. ML0708602382007-03-21021 March 2007 Perry EOC Cy 2006 Slides FENOC (EOC-Public Meeting) ML0708602462007-03-21021 March 2007 Perry EOC Cy 2006 Slides FENOC (CAL Closure - Public Meeting) ML0701205622007-01-10010 January 2007 Public Meeting - FENOC Meeting Slides ML0634900272006-12-13013 December 2006 NRC Slides from Public Meeting to Discuss Results of NRC Confirmatory Action Letter Follow-Up Inspections ML0634900242006-12-13013 December 2006 FENOC Slides from Perry Public Meeting to Discuss Results of NRC Confirmatory Action Letter Followup Inspections ML0623001242006-08-15015 August 2006 Licensee Public Meeting Slides ML0623001332006-08-15015 August 2006 NRC Perry 8-15-06 Public Meeting Slides ML0733408162006-07-14014 July 2006 Michael Johnson Ltr. Confirmatory Order (EA-01-082, EA-04-172) ML0619303972006-07-11011 July 2006 NRC CAL Followup Inspection Public Meeting Presentation Slides for Perry ML0619304062006-07-11011 July 2006 FENOC CAL Followup Inspection Public Meeting Presentation Slides ML0615106012006-05-23023 May 2006 EPRI HRA Users Group Review of Draft NUREG-1842 2024-10-31
[Table view] |
Text
Perry Nuclear Power Plant December 13, 2006 Public Meeting CAL Follow Up Inspections
Perry Nuclear Power Plant Bill Pearce Site Vice President CAL Follow Up Inspections 2
Introduction Q NRC Inspection Issues - Barry Allen and Mike Wayland Q Status of Performance Improvement Initiative (PII),
Status of Confirmatory Action Letter (CAL) Commitments and Key Actions Going Forward- Fred Cayia Q Closing Remarks CAL Follow Up Inspections 3
NRC Inspection Issues Barry Allen Director, Site Operations Mike Wayland Director, Maintenance CAL Follow Up Inspections 4
Fuse Removal Q October 23, 2006 - Additional fuse was pulled, making one of the two Division 1 Diesel Generator ventilation fans inoperable (CR 06-8702)
Q Apparent Causes
- Equipment labeling
- Clearance lacked sufficient detail
- Workers made incorrect assumptions CAL Follow Up Inspections 5
Fuse Removal Q Actions Taken
- Fuse reinstalled
- Job walked down with operations management and workers
- Interim action
- Night order issued to enhance expectations for fuse removal
- Workers re-trained, remediated, and prepared cause analysis
- Labels installed on wiring
- Lessons learned shared
- Section clock reset CAL Follow Up Inspections 6
Airlock Equalizer Valve Q Work performed to correct containment airlock equalizer valve mechanism without adequate work instructions (CR 06-10130)
Q Apparent Causes
- Weak supervisor oversight
- Supervisor did not recognize the need to stop work and revise work package before proceeding
- Lack of familiarity with the Fix-it Now (FIN) process CAL Follow Up Inspections 7
Airlock Equalizer Valve Q Actions
- Valve stem is replaced
- Stand-down to train FIN team members on FIN process restrictions
- Limits placed on who can authorize FIN work orders
- Workers not specifically trained in FIN process are not used for FIN work
- Section clock reset
- Training gap analysis to be performed to determine knowledge deficiency
- Evaluate a sample of FIN work orders for extent of condition CAL Follow Up Inspections 8
and Key Actions Going Forward Fred Cayia Director, Performance Improvement CAL Follow Up Inspections 9
Initiative (PII)
Q PII actions for each focus area completed
- Corrective Action Program Implementation Improvement
- Excellence in Human Performance
- Training to Improve Performance
- Effective Work Management
- Employee Engagement and Communication
- Operational Focused Organization Q PII Closure Reports for each focus area approved CAL Follow Up Inspections 10
Status of PII Q Demonstrated sustained improvement in Corrective Action Program and Human Performance Q Continuous improvement actions reflected in Excellence Plan Q Periodic performance assessments to ensure continuous improvement
- Oversight
- Metrics
- Benchmarking / Self-assessment CAL Follow Up Inspections 11
Status of CAL Commitments Q CAL Commitments completed
- Resolution of IP 95002 follow-up issues
- Corrective Action Program Implementation improvement
- Human Performance improvement
- Emergency Preparedness improvement Q Enhancements to key maintenance procedures on schedule for completion Q Letter requesting CAL Closure to be submitted CAL Follow Up Inspections 12
Key Actions Going Forward Q PII improved capability to perform critical self-assessments Q Self-assessments and benchmarking support continuous improvement in Corrective Action Program and Human Performance Q Plans for 2007
- Focused self-assessments
- Snapshot self-assessments
- Fleet-coordinated assessments Q The results of these assessments will be added to the excellence plans.
CAL Follow Up Inspections 13
Closing Remarks Bill Pearce Site Vice President CAL Follow Up Inspections 14
Perry Nuclear Power Plant December 13, 2006 Public Meeting CAL Follow Up Inspections